This is a Work Sequence specification document for the Skytop Lodge Sewage Treatment Plant Improvements Project (005153.0436) in Canadensis, Pennsylvania. The project involves the construction and installation of a comprehensive sewage treatment system upgrade including an influent screening system, equalization tank, chemical feed system, two secondary clarifiers, post-aeration tank, UV disinfection system, and associated yard piping, electrical improvements, and structural components. The contractor must maintain operations of the existing facility during construction and is responsible for coordinating all work to meet substantial completion and final completion milestones. A pre-bid conference is scheduled for August 25, 2026 at 10:30 AM at the Skytop Lodge STP facility in Falls Road, Canadensis, Pennsylvania, with bid submission deadline of Friday, September 18, 2026 at 10:00 AM via PennBid.

The work sequence outlines 20 sequential phases beginning with mobilization and erosion/sediment control installation, progressing through site preparation, construction of primary treatment components, installation of sanitary manholes, chemical building improvements, equipment startup and training, and concluding with final grading, seeding, fence installation, demolition of existing equipment, paving restoration, removal of erosion controls, and demobilization. Bid security of not less than 10 percent in the form of a certified check or bid bond is required. All bidding documents are available through the PennBid website at https://pennbid.bonfirehub.com/, with official notifications and addenda provided exclusively through this designated platform.

View the file

Other files

File Type Posted
33 05 97 - Identification And Signage For Utilities.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
26 05 10 - Basic Electrical Materials & Methods.pdf PDF
01 78 36 - Warranties.pdf PDF
26 12 19.01 - Liquid Filled Medium Voltage Pad Mounted Transformers.pdf PDF
01 61 00 - Product Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
43 26 13 - Submersible Sewage Pumps.pdf PDF
33 05 77 Packaged Metering Manhole.pdf PDF
01 10 00 - Project Summary.pdf PDF
26 05 73 - Power System Study and Testing.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
02 41 19.13 - SELECTIVE BUILDING DEMOLITION.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
40 05 51 - Common Requirements For Process Valves.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
40 05 62 - Plug Valves.pdf PDF
26 24 16 - Panelboards.pdf PDF
00 45 36 EEO Certificate.pdf PDF
46 66 16 - Trojan Open Channel UV Disinfection System.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
40 23 23 - Potable Water Process Piping.pdf PDF
31 23 19 - Dewatering.pdf PDF
40 95 34 a- IOList Table.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 31 32 - Geotechnical Data.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
31 05 16 - Aggregate for Earthwork.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 60 00 - Project Forms.pdf PDF
01 22 00 - Unit Prices.pdf PDF
06 10 00 - Rough Carpentry.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
06 17 53 - Shop-Fabricated Wood Trusses.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
40 05 23 - Stainless Steel Process Pipe And Tubing.pdf PDF
26 05 33.16 - Boxes.pdf PDF
26 05 29 - Electrical Supports, Anchors and Fasteners.pdf PDF
41 22 23.16 - Portable Hoists.pdf PDF
26 32 13 - Packaged Engine Generator Systems.pdf PDF
31 23 16.13 - Trenching.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
46 43 21 Packaged Wastewater Treatment Plant Equipment.pdf PDF
13 34 00 - Pre-engineered Post Frame Structures.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
Show 40 more

Latest 50 of 157 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 12 16 – WORK SEQUENCE

Herbert, Rowland & Grubic, Inc. 01 12 16-1 005153.0436

SECTION 01 12 16 – WORK SEQUENCE

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Site Conditions.

2. Construction Constraints.

3. Suggested Construction Sequence

B. Related Requirements:

1. Section 01 50 00 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1.2 CONSTRUCTION CONSTRAINTS.

A. The following is a list of constraints that the Contractor shall include in developing the overall plan of construction. This list is not intended to release the Contractor from the responsibility to coordinate the Work in any manner which will ensure Project completion within the Substantial Completion and Final Completion milestones:

1. Contractor must maintain the operations of the existing facility during construction.

1.3 SUGGESTED CONSTRUCTION SEQUENCE

A. The following areas are not necessarily listed in their required sequence of construction.

A suggested sequence within each area, where necessary, is included. This sequence is not intended to release the Contractor from the responsibility to coordinate all Work in a safe manner which will ensure the Substantial Completion and Final Completion milestones are met. The Contractor is ultimately responsible for the sequence and execution of the Work:

1. Mobilization.

2. Installation of Erosion and Sediment Control Measures.

3. Site Grading.

4. Site Excavation.

5. Construction of Secondary Clarifiers, Post-Aeration Tank, UV Disinfection and

Blower Accessory Shelter. Construction shall include all yard piping, electrical improvements, structural improvements, and appurtenances required for systems to operate as show in the Technical Specifications and Drawings.

6. Installation of San MH-4 and MH-5.

7. Chemical Building Improvements and installation of chemical feed equipment and feed lines.

8. Bypass Pumping from Recirculation Pump Station to existing Settling Basin for

Installation of San MH-4 and work within the Recirculation Pump Station and Bypass Pumping from Settling Tanks to existing outfall gravity sewer for installation of San MH-6.

01 12 16 – WORK SEQUENCE

Herbert, Rowland & Grubic, Inc. 01 12 16-2 005153.0436

9. Connection of flow to San MH-4, San MH-5, Secondary Clarifiers, UV Disinfection, and new San MH-6 after equipment start-up and training has been completed.

10. Bypassing Pumping from Influent Manhole to Imhoff Tank.

11. Installation of Equalization Tanks, Influent Screening System, and associated

Electrical Improvements, Structural Improvements, site piping, and all items show in the associated Technical Specifications and Drawings. Removal of existing screening system will be completed during this to allow for installation of the new Influent Screening System.

12. Equalization Tank and Influent Screening System Equipment Start Up/Training.

13. Transfer of flow to new Equalization Tank and Influent Screening System.

14. Operation of New Facility.

15. Final Grading and Seeding.

16. Fence Installation.

17. Removal of existing settling tank and associated piping and any miscellaneous demolition that has not yet been completed per the Technical Specifications and Drawings.

18. Final Paving/restoration.

19. Removal of Erosion and Sediment Control Measures.

20. Demobilization.

PART 2 - PRODUCTS - NOT USED.

PART 3 - EXECUTION - NOT USED.

END OF SECTION