Tinker Air Force Base, through Air Force Sustainment Center, is soliciting proposals for renovation of restrooms in Building 117, with proposals due June 29, 2026. This Design-Bid-Build contract is restricted to Small Business MAC BOA (Multiple Award Contract Blanket Order Agreement) holders who attended the mandatory Initial Site Visit on May 14, 2026; only those attendees may continue toward award.

Place of performance is Building 117, Tinker Air Force Base, Oklahoma City, Oklahoma. The project involves complete demolition and replacement of all plumbing fixtures, domestic piping to isolation valves, and sanitary sewer in both men's and women's restrooms. Work includes new concrete slab-on-grade, metal-framed partition walls with tile finishes, six private shower/lavatory/water closet pods (three per facility), new LED lighting with occupancy sensors, new GFCI receptacles, new mechanical supply and exhaust systems, and new fire protection elements. The facility will remain occupied throughout construction; the contractor must provide four portable restrooms and four portable showers. Work must be conducted during normal duty hours (0700–1600 Monday–Friday) with completion within 625 calendar days of Notice to Proceed. A Fire Department amendment requires one door swing change from inswing to outswing; revised drawings were issued May 19, 2026.

The solicitation number is FA813726R0030 with project number WWYK190023. NAICS code is 236220 (Commercial and Institutional Building Construction) with size standard of $45 million in annual receipts. The government will evaluate proposals using Lowest Priced Technically Acceptable (LPTA) procedures, weighing technical acceptability (Capability and Management, Schedule and Planning) at pass/fail and price as the award determinant. A bid guarantee of 20 percent of bid price or $3 million (whichever is less) is required per amendment issued June 8, 2026. Performance and payment bonds within 10 calendar days of award are mandatory.

Recent updates include RFI confirmation (June 2 and 17) that 30 applicable specification sections from the SOW control compliance; 124 additional specification files are not applicable. Technical specifications cover divisions 00–28 with extensive requirements for safety, environmental compliance, Quality Control management, submittal procedures, and operations/maintenance documentation per Tinker AFB standards.

Notice text

8 versions

Update #8 · Latest ·

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 17 Jun 2026

Description of update>>>  Uploaded 190023 Renovate Restrooms B117 Pre Bid RFI Follow Up_COR_Signed

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 08 Jun 2026

Description of update>>>  Uploaded 190023 Renovate Restrooms B117 Solicitation Amendment FA813726R00300001

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 08 Jun 2026

Description of update>>>  Uploaded 190023 Renovate Restrooms B117 Technical Specifications

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 02 Jun 2026

Description of update>>>  Uploaded 190023 Renovate Restrooms B117 RFIs_ FINAL_COR_Signed

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 28 May 2026

Description of update>>>  Uploaded Model.zip file containg as-builts and TAFB_Tech_Reqs (Div 02-48).zip.  Contact the CO or CS listed in contact information if you are not able to access.

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 22 May 2026

Description of update>>>  Uploaded TAFB General Requirements (Div 00-01)

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 21 May 2026

Description of update>>>  Uploaded Initial Site Visit WWYK190023 and WWYK20190023_REV02_19MAY2026 Drawings.  After the site visit, the Fire Department advised they would like an inswing door changed to outswing to minimize response times.  Attached are the amended drawings.  The only change is the door swing.  No change in materials.

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

Project Solicitation Number:  FA813726R0030 

Project Title: WWYK190023 – Renovate Restrooms, B117
Project Location: Tinker AFB - B117

Renovate men’s and women’s restrooms at B117 via Design-Bid-Build contract. This involved complete demolition and replacement of all the existing plumbing fixtures, domestic piping to iso valves, and sanitary sewer in both the men’s and women’s restrooms.

The project is restricted to SB MAC BOA holders only.

Project specific documents are attached to this posting.

If you experience any difficulty at receiving or access to the project specific documents, send an email request to Contracting Points of Contact listed to have a DoD Safe document transmission.  In the email, please provide email addresses for Prime Contractor ONLY points of contact to have the DoD Safe link sent to.  Do not include any Sub-Contractor email addresses.

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

After review of the project specific documents, if you are a Tinker AFB – MAC BOA Holder, please send an email to the Contracting Points of Contact as an RSVP stating you are interested in attending the Initial Site Visit.  Your RSVP email must be received within 5 calendar days from the posting of this project.  In your RSVP, please let us know if all personnel that will be attending the Initial Site Visit have base access.  If anyone requires base access, you must forward with your RSVP the Entry Access List (EAL) so that we can know how many personnel require base access.   ***** ONLY MAC BOA Prime Contractors are to RSVP, Subcontractors are to inform at least one Prime Contractor of their intention to attend and if a Subcontractor requires base access, they must be sponsored by a Prime Contractor.

After receipt of your RSVP and EAL if required, an Initial Site Visit will be coordinated.  Initial Site Visit is set for May 14, 2026 – 1:30 PM – B117

You must attend the Initial Site Visit for the project to be considered eligible to propose.

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

Update #7 ·

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 08 Jun 2026

Description of update>>>  Uploaded 190023 Renovate Restrooms B117 Solicitation Amendment FA813726R00300001

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 08 Jun 2026

Description of update>>>  Uploaded 190023 Renovate Restrooms B117 Technical Specifications

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 02 Jun 2026

Description of update>>>  Uploaded 190023 Renovate Restrooms B117 RFIs_ FINAL_COR_Signed

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 28 May 2026

Description of update>>>  Uploaded Model.zip file containg as-builts and TAFB_Tech_Reqs (Div 02-48).zip.  Contact the CO or CS listed in contact information if you are not able to access.

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 22 May 2026

Description of update>>>  Uploaded TAFB General Requirements (Div 00-01)

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 21 May 2026

Description of update>>>  Uploaded Initial Site Visit WWYK190023 and WWYK20190023_REV02_19MAY2026 Drawings.  After the site visit, the Fire Department advised they would like an inswing door changed to outswing to minimize response times.  Attached are the amended drawings.  The only change is the door swing.  No change in materials.

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

Project Solicitation Number:  FA813726R0030 

Project Title: WWYK190023 – Renovate Restrooms, B117
Project Location: Tinker AFB - B117

Renovate men’s and women’s restrooms at B117 via Design-Bid-Build contract. This involved complete demolition and replacement of all the existing plumbing fixtures, domestic piping to iso valves, and sanitary sewer in both the men’s and women’s restrooms.

The project is restricted to SB MAC BOA holders only.

Project specific documents are attached to this posting.

If you experience any difficulty at receiving or access to the project specific documents, send an email request to Contracting Points of Contact listed to have a DoD Safe document transmission.  In the email, please provide email addresses for Prime Contractor ONLY points of contact to have the DoD Safe link sent to.  Do not include any Sub-Contractor email addresses.

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

After review of the project specific documents, if you are a Tinker AFB – MAC BOA Holder, please send an email to the Contracting Points of Contact as an RSVP stating you are interested in attending the Initial Site Visit.  Your RSVP email must be received within 5 calendar days from the posting of this project.  In your RSVP, please let us know if all personnel that will be attending the Initial Site Visit have base access.  If anyone requires base access, you must forward with your RSVP the Entry Access List (EAL) so that we can know how many personnel require base access.   ***** ONLY MAC BOA Prime Contractors are to RSVP, Subcontractors are to inform at least one Prime Contractor of their intention to attend and if a Subcontractor requires base access, they must be sponsored by a Prime Contractor.

After receipt of your RSVP and EAL if required, an Initial Site Visit will be coordinated.  Initial Site Visit is set for May 14, 2026 – 1:30 PM – B117

You must attend the Initial Site Visit for the project to be considered eligible to propose.

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

Update #6 ·

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 08 Jun 2026

Description of update>>>  Uploaded 190023 Renovate Restrooms B117 Technical Specifications

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 02 Jun 2026

Description of update>>>  Uploaded 190023 Renovate Restrooms B117 RFIs_ FINAL_COR_Signed

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 28 May 2026

Description of update>>>  Uploaded Model.zip file containg as-builts and TAFB_Tech_Reqs (Div 02-48).zip.  Contact the CO or CS listed in contact information if you are not able to access.

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 22 May 2026

Description of update>>>  Uploaded TAFB General Requirements (Div 00-01)

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 21 May 2026

Description of update>>>  Uploaded Initial Site Visit WWYK190023 and WWYK20190023_REV02_19MAY2026 Drawings.  After the site visit, the Fire Department advised they would like an inswing door changed to outswing to minimize response times.  Attached are the amended drawings.  The only change is the door swing.  No change in materials.

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

Project Solicitation Number:  FA813726R0030 

Project Title: WWYK190023 – Renovate Restrooms, B117
Project Location: Tinker AFB - B117

Renovate men’s and women’s restrooms at B117 via Design-Bid-Build contract. This involved complete demolition and replacement of all the existing plumbing fixtures, domestic piping to iso valves, and sanitary sewer in both the men’s and women’s restrooms.

The project is restricted to SB MAC BOA holders only.

Project specific documents are attached to this posting.

If you experience any difficulty at receiving or access to the project specific documents, send an email request to Contracting Points of Contact listed to have a DoD Safe document transmission.  In the email, please provide email addresses for Prime Contractor ONLY points of contact to have the DoD Safe link sent to.  Do not include any Sub-Contractor email addresses.

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

After review of the project specific documents, if you are a Tinker AFB – MAC BOA Holder, please send an email to the Contracting Points of Contact as an RSVP stating you are interested in attending the Initial Site Visit.  Your RSVP email must be received within 5 calendar days from the posting of this project.  In your RSVP, please let us know if all personnel that will be attending the Initial Site Visit have base access.  If anyone requires base access, you must forward with your RSVP the Entry Access List (EAL) so that we can know how many personnel require base access.   ***** ONLY MAC BOA Prime Contractors are to RSVP, Subcontractors are to inform at least one Prime Contractor of their intention to attend and if a Subcontractor requires base access, they must be sponsored by a Prime Contractor.

After receipt of your RSVP and EAL if required, an Initial Site Visit will be coordinated.  Initial Site Visit is set for May 14, 2026 – 1:30 PM – B117

You must attend the Initial Site Visit for the project to be considered eligible to propose.

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

Update #5 ·

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 02 Jun 2026

Description of update>>>  Uploaded 190023 Renovate Restrooms B117 RFIs_ FINAL_COR_Signed

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 28 May 2026

Description of update>>>  Uploaded Model.zip file containg as-builts and TAFB_Tech_Reqs (Div 02-48).zip.  Contact the CO or CS listed in contact information if you are not able to access.

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 22 May 2026

Description of update>>>  Uploaded TAFB General Requirements (Div 00-01)

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 21 May 2026

Description of update>>>  Uploaded Initial Site Visit WWYK190023 and WWYK20190023_REV02_19MAY2026 Drawings.  After the site visit, the Fire Department advised they would like an inswing door changed to outswing to minimize response times.  Attached are the amended drawings.  The only change is the door swing.  No change in materials.

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

Project Solicitation Number:  FA813726R0030 

Project Title: WWYK190023 – Renovate Restrooms, B117
Project Location: Tinker AFB - B117

Renovate men’s and women’s restrooms at B117 via Design-Bid-Build contract. This involved complete demolition and replacement of all the existing plumbing fixtures, domestic piping to iso valves, and sanitary sewer in both the men’s and women’s restrooms.

The project is restricted to SB MAC BOA holders only.

Project specific documents are attached to this posting.

If you experience any difficulty at receiving or access to the project specific documents, send an email request to Contracting Points of Contact listed to have a DoD Safe document transmission.  In the email, please provide email addresses for Prime Contractor ONLY points of contact to have the DoD Safe link sent to.  Do not include any Sub-Contractor email addresses.

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

After review of the project specific documents, if you are a Tinker AFB – MAC BOA Holder, please send an email to the Contracting Points of Contact as an RSVP stating you are interested in attending the Initial Site Visit.  Your RSVP email must be received within 5 calendar days from the posting of this project.  In your RSVP, please let us know if all personnel that will be attending the Initial Site Visit have base access.  If anyone requires base access, you must forward with your RSVP the Entry Access List (EAL) so that we can know how many personnel require base access.   ***** ONLY MAC BOA Prime Contractors are to RSVP, Subcontractors are to inform at least one Prime Contractor of their intention to attend and if a Subcontractor requires base access, they must be sponsored by a Prime Contractor.

After receipt of your RSVP and EAL if required, an Initial Site Visit will be coordinated.  Initial Site Visit is set for May 14, 2026 – 1:30 PM – B117

You must attend the Initial Site Visit for the project to be considered eligible to propose.

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

Update #4 ·

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 28 May 2026

Description of update>>>  Uploaded Model.zip file containg as-builts and TAFB_Tech_Reqs (Div 02-48).zip.  Contact the CO or CS listed in contact information if you are not able to access.

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 22 May 2026

Description of update>>>  Uploaded TAFB General Requirements (Div 00-01)

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 21 May 2026

Description of update>>>  Uploaded Initial Site Visit WWYK190023 and WWYK20190023_REV02_19MAY2026 Drawings.  After the site visit, the Fire Department advised they would like an inswing door changed to outswing to minimize response times.  Attached are the amended drawings.  The only change is the door swing.  No change in materials.

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

Project Solicitation Number:  FA813726R0030 

Project Title: WWYK190023 – Renovate Restrooms, B117
Project Location: Tinker AFB - B117

Renovate men’s and women’s restrooms at B117 via Design-Bid-Build contract. This involved complete demolition and replacement of all the existing plumbing fixtures, domestic piping to iso valves, and sanitary sewer in both the men’s and women’s restrooms.

The project is restricted to SB MAC BOA holders only.

Project specific documents are attached to this posting.

If you experience any difficulty at receiving or access to the project specific documents, send an email request to Contracting Points of Contact listed to have a DoD Safe document transmission.  In the email, please provide email addresses for Prime Contractor ONLY points of contact to have the DoD Safe link sent to.  Do not include any Sub-Contractor email addresses.

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

After review of the project specific documents, if you are a Tinker AFB – MAC BOA Holder, please send an email to the Contracting Points of Contact as an RSVP stating you are interested in attending the Initial Site Visit.  Your RSVP email must be received within 5 calendar days from the posting of this project.  In your RSVP, please let us know if all personnel that will be attending the Initial Site Visit have base access.  If anyone requires base access, you must forward with your RSVP the Entry Access List (EAL) so that we can know how many personnel require base access.   ***** ONLY MAC BOA Prime Contractors are to RSVP, Subcontractors are to inform at least one Prime Contractor of their intention to attend and if a Subcontractor requires base access, they must be sponsored by a Prime Contractor.

After receipt of your RSVP and EAL if required, an Initial Site Visit will be coordinated.  Initial Site Visit is set for May 14, 2026 – 1:30 PM – B117

You must attend the Initial Site Visit for the project to be considered eligible to propose.

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

Update #3 ·

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 22 May 2026

Description of update>>>  Uploaded TAFB General Requirements (Div 00-01)

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 21 May 2026

Description of update>>>  Uploaded Initial Site Visit WWYK190023 and WWYK20190023_REV02_19MAY2026 Drawings.  After the site visit, the Fire Department advised they would like an inswing door changed to outswing to minimize response times.  Attached are the amended drawings.  The only change is the door swing.  No change in materials.

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

Project Solicitation Number:  FA813726R0030 

Project Title: WWYK190023 – Renovate Restrooms, B117
Project Location: Tinker AFB - B117

Renovate men’s and women’s restrooms at B117 via Design-Bid-Build contract. This involved complete demolition and replacement of all the existing plumbing fixtures, domestic piping to iso valves, and sanitary sewer in both the men’s and women’s restrooms.

The project is restricted to SB MAC BOA holders only.

Project specific documents are attached to this posting.

If you experience any difficulty at receiving or access to the project specific documents, send an email request to Contracting Points of Contact listed to have a DoD Safe document transmission.  In the email, please provide email addresses for Prime Contractor ONLY points of contact to have the DoD Safe link sent to.  Do not include any Sub-Contractor email addresses.

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

After review of the project specific documents, if you are a Tinker AFB – MAC BOA Holder, please send an email to the Contracting Points of Contact as an RSVP stating you are interested in attending the Initial Site Visit.  Your RSVP email must be received within 5 calendar days from the posting of this project.  In your RSVP, please let us know if all personnel that will be attending the Initial Site Visit have base access.  If anyone requires base access, you must forward with your RSVP the Entry Access List (EAL) so that we can know how many personnel require base access.   ***** ONLY MAC BOA Prime Contractors are to RSVP, Subcontractors are to inform at least one Prime Contractor of their intention to attend and if a Subcontractor requires base access, they must be sponsored by a Prime Contractor.

After receipt of your RSVP and EAL if required, an Initial Site Visit will be coordinated.  Initial Site Visit is set for May 14, 2026 – 1:30 PM – B117

You must attend the Initial Site Visit for the project to be considered eligible to propose.

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

Update #2 ·

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

Updated 21 May 2026

Description of update>>>  Uploaded Initial Site Visit WWYK190023 and WWYK20190023_REV02_19MAY2026 Drawings.  After the site visit, the Fire Department advised they would like an inswing door changed to outswing to minimize response times.  Attached are the amended drawings.  The only change is the door swing.  No change in materials.

Proposals due 29 Jun 2026

Only the MAC BOA Holder GCs that attended Site Visit on 14 May 2026 will be able to continue forward toward the award.

==========================================================================================

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

Project Solicitation Number:  FA813726R0030 

Project Title: WWYK190023 – Renovate Restrooms, B117
Project Location: Tinker AFB - B117

Renovate men’s and women’s restrooms at B117 via Design-Bid-Build contract. This involved complete demolition and replacement of all the existing plumbing fixtures, domestic piping to iso valves, and sanitary sewer in both the men’s and women’s restrooms.

The project is restricted to SB MAC BOA holders only.

Project specific documents are attached to this posting.

If you experience any difficulty at receiving or access to the project specific documents, send an email request to Contracting Points of Contact listed to have a DoD Safe document transmission.  In the email, please provide email addresses for Prime Contractor ONLY points of contact to have the DoD Safe link sent to.  Do not include any Sub-Contractor email addresses.

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

After review of the project specific documents, if you are a Tinker AFB – MAC BOA Holder, please send an email to the Contracting Points of Contact as an RSVP stating you are interested in attending the Initial Site Visit.  Your RSVP email must be received within 5 calendar days from the posting of this project.  In your RSVP, please let us know if all personnel that will be attending the Initial Site Visit have base access.  If anyone requires base access, you must forward with your RSVP the Entry Access List (EAL) so that we can know how many personnel require base access.   ***** ONLY MAC BOA Prime Contractors are to RSVP, Subcontractors are to inform at least one Prime Contractor of their intention to attend and if a Subcontractor requires base access, they must be sponsored by a Prime Contractor.

After receipt of your RSVP and EAL if required, an Initial Site Visit will be coordinated.  Initial Site Visit is set for May 14, 2026 – 1:30 PM – B117

You must attend the Initial Site Visit for the project to be considered eligible to propose.

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

Update #1 ·

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

Project Solicitation Number:  FA813726R0030 

Project Title: WWYK190023 – Renovate Restrooms, B117
Project Location: Tinker AFB - B117

Renovate men’s and women’s restrooms at B117 via Design-Bid-Build contract. This involved complete demolition and replacement of all the existing plumbing fixtures, domestic piping to iso valves, and sanitary sewer in both the men’s and women’s restrooms.

The project is restricted to SB MAC BOA holders only.

Project specific documents are attached to this posting.

If you experience any difficulty at receiving or access to the project specific documents, send an email request to Contracting Points of Contact listed to have a DoD Safe document transmission.  In the email, please provide email addresses for Prime Contractor ONLY points of contact to have the DoD Safe link sent to.  Do not include any Sub-Contractor email addresses.

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

After review of the project specific documents, if you are a Tinker AFB – MAC BOA Holder, please send an email to the Contracting Points of Contact as an RSVP stating you are interested in attending the Initial Site Visit.  Your RSVP email must be received within 5 calendar days from the posting of this project.  In your RSVP, please let us know if all personnel that will be attending the Initial Site Visit have base access.  If anyone requires base access, you must forward with your RSVP the Entry Access List (EAL) so that we can know how many personnel require base access.   ***** ONLY MAC BOA Prime Contractors are to RSVP, Subcontractors are to inform at least one Prime Contractor of their intention to attend and if a Subcontractor requires base access, they must be sponsored by a Prime Contractor.

After receipt of your RSVP and EAL if required, an Initial Site Visit will be coordinated.  Initial Site Visit is set for May 14, 2026 – 1:30 PM – B117

You must attend the Initial Site Visit for the project to be considered eligible to propose.

This posting is for Tinker AFB - MAC BOA Holders ONLY.  

Files

File Type Posted
190023 Reno Restrooms B117 Pre Bid RFI Follow Up_COR_Signed.pdf PDF
Solicitation Amendment FA813726R00300001 SF 30.pdf PDF
26 00 00.00 20.pdf PDF
02 41 00.pdf PDF
09 22 00.pdf PDF
32 11 29.pdf PDF
06 10 00.pdf PDF
26 05 00.00 40.pdf PDF
08 34 01.pdf PDF
07 12 00.pdf PDF
28 31 64.00 10.pdf PDF
23 34 23.00 40.pdf PDF
07 42 13.pdf PDF
23 31 13.00 40.pdf PDF
10 21 13.pdf PDF
07 42 63.pdf PDF
08 14 00.pdf PDF
07 22 00.pdf PDF
07 53 23.pdf PDF
26 28 01.00 10.pdf PDF
31 23 15.pdf PDF
07 54 19.pdf PDF
05 30 00.pdf PDF
07 72 20.pdf PDF
07 62 13.pdf PDF
05 50 13.pdf PDF
32 13 73.pdf PDF
08 41 13.pdf PDF
32 11 23.pdf PDF
03 11 13.00 10.pdf PDF
08 51 13.pdf PDF
10 14 00.10.pdf PDF
23 07 00.pdf PDF
08 51 23.pdf PDF
23 23 00.pdf PDF
13 34 19.pdf PDF
09 51 00.pdf PDF
07 51 13.pdf PDF
07 19 00.pdf PDF
09 65 00.pdf PDF
23 81 23.pdf PDF
23 65 00.pdf PDF
10 14 00.20.pdf PDF
05 05 23.16.pdf PDF
08 34 19.10 20.pdf PDF
22 05 48.00 20.pdf PDF
26 20 00.pdf PDF
26 29 23.pdf PDF
23 01 30.41.pdf PDF
08 56 53.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

Similar open opportunities

Opportunity Agency Set-aside Responses due
WWYK260004 - repair structural integrity, B1134, post 34 & north wall Tinker AFB, Oklahoma 73145, United States · NAICS 238190 Air Force Sustainment Center Total Small Business
2-STEP SEALED BID - TINKER AFB WWYK250019 Remove and Replace Fire Sprinkler in Plasma Booth Dust Collectors and Replace the Building F/A System, B3221 Tinker AFB, Oklahoma 73145, United States · NAICS 236220 Air Force Sustainment Center Total Small Business
WWYK250063 - install react VII facility, B9001, post V19 Tinker AFB, Oklahoma 73145, United States · NAICS 236220 Air Force Sustainment Center Woman-Owned Small Business
WWYK240015 - Rehab Tanks 62501E & 62501W Tinker AFB, Oklahoma 73145, United States · NAICS 236220 Air Force Sustainment Center No set-aside
WWYK100209-Repair Perimeter Dr and Industrial Blvd Tinker AFB, Oklahoma 73145, United States · NAICS 237310 Air Force Sustainment Center Woman-Owned Small Business Sole Source

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors