This is a Request for Information (RFI) issued by the U.S. Air Force for solicitation FA8137-26-R-0030 concerning the renovation of men's and women's restrooms/showers in Building 117 at Tinker Air Force Base. The RFI, dated June 11, 2026, addresses a discrepancy between the number of technical specification sections identified as applicable to the project and those actually included in the specification package.

The Government identified thirty (30) applicable technical specification sections listed in Statement of Work (SOW) Appendix B; however, the specification package contains one hundred fifty-four (154) technical specification files. The Contractor submitted three questions requesting confirmation that one hundred twenty-four (124) specification sections—covering divisions such as Concrete, Masonry, Metals, Wood/Plastics, Thermal/Moisture Protection, Openings, Finishes, Specialties, Special Construction, Fire Suppression, Plumbing, HVAC, Electrical, Electronic Safety and Security, Earthwork, Exterior Improvements, and Utilities—are not applicable to the restroom renovation project and should be excluded from compliance requirements. The Government, through the Contracting Officer Representative (COR), confirmed that the listed specifications are not applicable and that the thirty (30) sections in SOW Appendix B constitute the complete and controlling set of applicable specifications. The Contractor also reserved the right to submit additional RFIs upon receipt and review of the applicable specification sections, noting that project specifications were not available in the initial bid files.

View the file

Other files

File Type Posted
Solicitation Amendment FA813726R00300001 SF 30.pdf PDF
23 08 00.pdf PDF
23 35 00.pdf PDF
07 60 00.pdf PDF
03 39 00.00 10.pdf PDF
32 01 14.pdf PDF
32 12 15.pdf PDF
07 42 13.pdf PDF
26 51 00.pdf PDF
33 11 00.pdf PDF
26 00 00.00 20.pdf PDF
10 21 13.pdf PDF
23 82 16.00 40.pdf PDF
32 13 14.pdf PDF
09 51 00.pdf PDF
08 41 13.pdf PDF
32 12 10.1.pdf PDF
07 14 00.pdf PDF
23 52 00.pdf PDF
08 34 19.10 20.pdf PDF
08 51 23.pdf PDF
07 41 13.pdf PDF
07 24 00.pdf PDF
05 50 13.pdf PDF
26 20 00.pdf PDF
26 23 00.pdf PDF
23 05 15.pdf PDF
23 64 26.pdf PDF
23 00 00.pdf PDF
07 61 14.00 20.pdf PDF
03 62 16.pdf PDF
32 92 23.pdf PDF
10 14 00.10.pdf PDF
32 01 16.pdf PDF
09 90 00.pdf PDF
06 41 16.00 10.pdf PDF
23 31 13.00 40.pdf PDF
26 41 00.pdf PDF
09 72 00.pdf PDF
05 40 00.pdf PDF
000_TABLE OF CONTENTS Technical.pdf PDF
10 44 16.pdf PDF
32 11 23.pdf PDF
08 11 13.pdf PDF
07 31 13.pdf PDF
03 20 00.00 10.pdf PDF
09 29 00.pdf PDF
08 34 01.pdf PDF
08 52 00.pdf PDF
23 70 03.pdf PDF
Show 40 more

Latest 50 of 184 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI

WWYK190023 11 June 2026 Solicitation FA8137-26-R-0030

Per SOW Section 5.2 and Appendix B, the Government identified thirty (30) technical specification sections developed by the Government and applicable to the work of this project. The Government’s specification package, however, contains one hundred fifty-four (154) technical specification files — substantially more than the thirty (30) sections listed in Appendix B.

The following one hundred twenty-four (124) technical specification sections were furnished in the specification package but are not listed in SOW Appendix B. Based on the Contractor’s review of the SOW and the project drawings, these sections do not appear to be within the scope of work for this project (an interior renovation of the men’s and women’s restrooms/showers in B117).

Question 1: Please confirm that the specification sections listed below are NOT applicable to this project and are not part of the scope of work, and that the thirty (30) specification sections listed in SOW Appendix B are the complete and controlling set of applicable specifications for this project.

Confirmed. -DBS

Question 2: This is a bid-build project with no design responsibility assigned to the Contractor other than delegated design outlined in SOW, paragraph 3.5, Working Documents. Accordingly, the Contractor requests that the Government affirmatively identify the complete and definitive list of specification sections the Contractor is required to comply with. Determination of specification applicability is a design/Government function and should not be left to the Contractor’s interpretation. If the Government considers any section below to be applicable, please identify the section and the associated scope so the Contractor may price the work accordingly. All spec requirements are listed on the SOW. -DBS

Question 3. Spec Section 33 11 00 – a specification file for this section was furnished in the package, but the section does not appear on the Government Table of Contents (Tinker AFB Technical Specifications, April 2019) and is not listed in Appendix B. As a result, the package contains 154 specification files while the Table of Contents lists 153 sections. Please confirm this section is not applicable, and please confirm whether any additional specification sections exist that were not indexed on the Table of Contents. -Below listed specs are N/A. -DBS

Specification sections requested to be confirmed NOT applicable:

Division 03 - CONCRETE

1. 03 11 13.00 10 Structural Cast-in-Place Concrete Forming

2. 03 20 00.00 10 Concrete Reinforcing

3. 03 39 00.00 10 Concrete Curing

4. 03 62 16 Metallic Non-Shrink Grouting Division 04 - MASONRY

5. 04 20 00 Unit Masonry

Division 05 - METALS

6. 05 05 23.16 Structural Welding

7. 05 12 00 Structural Steel

8. 05 21 00 Steel Joist Framing

9. 05 30 00 Steel Decks

10. 05 40 00 Cold-Formed Metal Framing

11. 05 50 13 Miscellaneous Metal Fabrications

Division 06 - WOOD, PLASTICS, AND COMPOSITES

28. 06 41 16.00 10 Plastic-Laminate-Clad Architectural Cabinets

29. 06 61 16 Solid Surfacing Fabrications

Division 07 - THERMAL AND MOISTURE PROTECTION

14. 07 12 00 Built-Up Bituminous Waterproofing

15. 07 14 00 Fluid-Applied Waterproofing

Solicitation FA8137-26-R-0030

16. 07 19 00 Water Repellants

17. 07 22 00 Roof and Deck Insulation

18. 07 24 00 Exterior Insulation and Finish Systems

19. 07 31 13 Asphalt Shingles

20. 07 41 13 Metal Roof Panels

21. 07 42 13 Metal Wall Panels

22. 07 42 63 Fabricated Wall Panel Assemblies

23. 07 51 13 Built-Up Asphalt Roofing

24. 07 52 00 Modified Bituminous Membrane Roofing

25. 07 53 23 Ethylene-Propylene-Diene-Monomer Roofing

26. 07 54 19 Polyvinyl-Chloride Roofing

27. 07 60 00 Flashing and Sheet Metal

45. 07 61 14.00 20 Steel Standing Seam Roofing

46. 07 72 20 Gravity-Type Roof Ventilators

47. 07 62 13 Copper Sheet Metal Flashing and Trim

Division 08 - OPENINGS

31. 08 11 16 Aluminum Doors and Frames

32. 08 33 23 Overhead Coiling Doors

33. 08 34 01 Forced Entry Resistant Components

34. 08 34 19.10 20 Rolling Service and Fire Doors

35. 08 36 13 Sectional Overhead Doors

36. 08 41 13 Aluminum-Framed Entrances and Storefronts

37. 08 51 13 Aluminum Windows

38. 08 51 23 Steel Windows

39. 08 52 00 Wood Windows

40. 08 56 53 Blast Resistant Tempered Glass Windows

41. 08 81 00 Glazing

Division 09 - FINISHES

42. 09 65 00 Resilient Flooring

43. 09 68 00 Carpeting

44. 09 72 00 Wallcoverings

Division 10 - SPECIALTIES

49. 10 14 00.10 Exterior Signage

50. 10 21 13 Toilet Compartments

51. 10 22 13 Wire Mesh Partitions

52. 10 22 39 Folding Panel Partitions

Division 13 - SPECIAL CONSTRUCTION

53. 13 34 19 Metal Building Systems

54. 13 48 00 Seismic Protection for Miscellaneous Equipment

Division 21 - FIRE SUPPRESSION

WWYK190023 – Renovate Restrooms, B117 | Page 2 of 4

51. 21 13 17 Dry Pipe Sprinkler System, Fire Protection

Division 22 - PLUMBING

52. 22 05 48.00 20 Mechanical Sound, Vibration, and Seismic Control

Solicitation FA8137-26-R-0030

Division 23 - HVAC

53. 23 01 30.41 HVAC System Cleaning

54. 23 03 00 Basic Mechanical Materials and Methods

55. 23 05 15 Common Piping for HVAC

56. 23 05 48.00 40 Vibration and Seismic Controls for HVAC Piping and Equipment

57. 23 08 01.00 20 Testing Industrial Ventilation Systems

58. 23 09 23.01 LonWorks Direct Digital Control for HVAC and Other Building Control Systems

59. 23 11 25 Facility Gas Piping

60. 23 23 00 Refrigerant Piping

61. 23 25 00 Chemical Treatment of Water for Mechanical Systems

62. 23 31 13.00 40 Metal Ducts

63. 23 34 23.00 40 HVAC Power Ventilators

64. 23 35 00 Overhead Vehicle Tailpipe and Welding Fume Exhaust Removal System(s)

65. 23 36 00.00 40 Air Terminal Units

66. 23 52 00 Heating Boilers

67. 23 54 16 Heating System; Gas-Fired Heaters

68. 23 57 10 Forced Hot Water Heating Systems Using Water and Steam Heat Exchangers

69. 23 64 10 Water Chillers, Vapor Compression Type

70. 23 64 26 Chilled, Chilled-Hot, and Condenser Water Piping Systems

71. 23 65 00 Cooling Towers and Remote Evaporatively-Cooled Condensers

72. 23 70 03 Heating and Utilities Systems, Central Steam

73. 23 81 00 Unitary Air Conditioning Equipment

74. 23 81 23 Computer Room Air Conditioning Units

75. 23 82 01 Warm Air Heating Systems

76. 23 82 16.00 40 Air Coils

77. 23 82 23.00 40 Unit Ventilators

78. 23 82 43.00 40 Electric Duct Heaters

79. 23 82 46.00 40 Electric Unit Heaters

Division 26 - ELECTRICAL

80. 26 05 48.00 10 Seismic Protection for Electrical Equipment

81. 26 08 00 Apparatus Inspection and Testing

82. 26 23 00 Low-Voltage Switchgear

83. 26 28 01.00 10 Coordinated Power System Protection

84. 26 29 23 Variable Frequency Drive Systems Under 600 Volts

85. 26 32 14.00 10 Diesel-Generator Set, Stationary 15-300 KW, Standby Applications

86. 26 36 00.00 10 Automatic Transfer Switch and By-Pass/Isolation Switch

87. 26 41 00 Lightning Protection System

88. 26 42 14.00 10 Cathodic Protection System (Sacrificial Anode)

89. 26 56 00 Exterior Lighting

90. 26 56 20.00 10 Airfield and Heliport Lighting and Visual Navigation Aids

Division 28 - ELECTRONIC SAFETY AND SECURITY

91. 28 31 00.00 10 Fire Detection and Alarm System, Direct Current Loop

92. 28 31 33.00 10 Fire Alarm Reporting System, Radio Type

Division 31 - EARTHWORK

WWYK190023 – Renovate Restrooms, B117 | Page 3 of 4 WWYK190023 – Renovate Restrooms, B117 | Page 4 of 4

93. 31 00 00 Earthwork

Solicitation FA8137-26-R-0030

94. 31 23 06 Excavation, Embankment, and Preparation of Subgrade for Roadways and Parking Lots

95. 31 23 15 Excavation, Filling and Backfilling for Buildings

96. 31 23 16 Excavation, Trenching, and Backfilling for Utilities

Division 32 - EXTERIOR IMPROVEMENTS

Division 33 - UTILITIES

121. 33 11 00 Water Utility Distribution Piping (title per CSI MasterFormat; section not shown on the

Government Table of Contents)

1. 33 40 00 Storm Drainage Utilities

2. 33 71 02 Underground Electrical Distribution Division 40 - PROCESS INTERCONNECTIONS

3. 40 17 26.00 20 Welding Pressure Piping

Total sections requiring confirmation: 124.

The Contractor respectfully notes that the project specifications were not included in the bid files made available prior to the RFI deadline. The Contractor reserves the right to submit additional RFIs upon receipt and review of the applicable specification sections.

97. 32 01 13 Spray Applications, Seal Coats, and Surface Treatments

98. 32 01 14 Asphalt Pavement Sealer

99. 32 01 16 Cold Milling; Asphaltic Concrete

100. 32 01 17 Crack Sealing in Asphalt Concrete Pavements

101. 32 01 17.62 Fabric Reinforcement for Asphalt Concrete Pavements

102. 32 01 18 Joints in Concrete Flatwork

103. 32 01 19 Field Molded Sealants for Sealing Joints in Rigid Pavements

104. 32 01 22 Bituminous Rejuvenation

105. 32 11 11 Asphalt Treated Permeable Base (ATPB) (Drainage Layer)

106. 32 11 23 Aggregate Base Course

107. 32 11 29 Lime-Stabilized Subgrade

108. 32 12 10.1 Bituminous Tack Coat

109. 32 12 10.2 Bituminous Prime Coat

110. 32 12 15 Airfield Pavement, Hot-Mix Asphalt

111. 32 13 11 Airfield Pavement, Portland Cement Concrete

112. 32 13 14 Pavement, Non-Airfield

113. 32 13 73 Joint Sealing in Concrete Pavement Jet-Fuel-Resistant

114. 32 13 74 Joint Sealing in Concrete Pavement Non-Jet-Fuel-Resistant

115. 32 16 13 Concrete Sidewalks and Curbs and Gutters

116. 32 17 23 Pavement Markings

117. 32 31 13 Chain Link Fences and Gates

118. 32 84 24 Irrigation Sprinkler Systems

119. 32 92 19 Seeding

120. 32 92 23 Sodding

S. James Potter -COR

Specification sections requested to be confirmed NOT applicable: Division 03 - CONCRETE
Division 04 - MASONRY
Division 05 - METALS
Division 06 - WOOD, PLASTICS, AND COMPOSITES
Division 07 - THERMAL AND MOISTURE PROTECTION
Division 08 - OPENINGS
Division 13 - SPECIAL CONSTRUCTION
Division 21 - FIRE SUPPRESSION
Division 22 - PLUMBING
Division 23 - HVAC
Division 26 - ELECTRICAL
Division 28 - ELECTRONIC SAFETY AND SECURITY
Division 31 - EARTHWORK
Division 32 - EXTERIOR IMPROVEMENTS
Division 40 - PROCESS INTERCONNECTIONS
Total sections requiring confirmation: 124.