WVA-FIRESTATION_RTA_SPEC_07-11-2025.pdf

PDF 14 MB Posted

Attached to
WVA Fire Station Construction Acquisition Federal contract opportunity
Solicitation number
W912DS25RA009
Issued by
Department of the Army Corps of Engineers Engineering District New York

About this file

This file is a comprehensive project specification document for the construction of a new three-company fire station at the Watervliet Arsenal in Watervliet, NY, prepared by the US Army Corps of Engineers New York District. The project is a Design-Bid-Build construction contract with an anticipated project completion date of 730 calendar days from the Notice to Proceed, scheduled for April 2025.

The specification document provides extensive technical details across 33 divisions, covering everything from site preparation and structural elements to mechanical, electrical, and communications systems. Key project characteristics include a Design-Bid-Build delivery method, construction of a standard Army fire station headquarters, and compliance with various sustainability and environmental requirements. The project is registered for LEED v4 BD+C Silver certification and will follow strict quality control, safety, and environmental management protocols. The total project is estimated to cost between $25 million and $100 million, with specific attention to seismic design, energy efficiency, and building performance standards.

View the file

Other files for this federal contract opportunity

Other files attached to WVA Fire Station Construction Acquisition, newest first.
File Type Posted
ET601 - TELECOMM RISER DIAGRAM.pdf PDF
Solicitation Amendment W912DS25RA009_0009(final).pdf PDF
01 45 00.15 10.pdf PDF
Solicitation Amendment W912DS25RA009_0008 (final).pdf PDF
Amendment W912DS25RA0090007.pdf PDF
Solicitation Amendment W912DS25RA009 0006.pdf PDF
01 50 00.pdf PDF
Solicitation Amendment W912DS25RA0090005.pdf PDF
FINAL_GeotechnicalReport_WatervlietArsenal_Rev1 8-7-23.pdf PDF
WVA Fire Station A-604 20250814.pdf PDF
25-08-11_I-601 and I-602.pdf PDF
09 51 00.pdf PDF
Solicitation Amendment W912DS25RA0090004 SF 30.pdf PDF
MI703.pdf PDF
ET-601 - TELECOMM RISER DIAGRAM.pdf PDF
ES103 - ELECTRICAL - SITE PLAN - POWER -TELECOMMUNICATIONS.pdf PDF
12 24 13.pdf PDF
WVA Fire Station A-602 20250814.pdf PDF
FINAL_GeotechnicalReport_WatervlietArsenal_Rev1 8-7-23.pdf PDF
08 71 00.pdf PDF
06 41 16.00 10.pdf PDF
01 45 00.pdf PDF
WVA Fire Station A-121 20250730.pdf PDF
WVA Fire Station A-603 20250801.pdf PDF
WVA Fire Station A-511 20250730.pdf PDF
WVA Fire Station A-510 20250730.pdf PDF
WVA Fire Station A-310 20250730.pdf PDF
WVA Fire Station A-123 20250730.pdf PDF
AHJ Interpretation - FP Quals.pdf PDF
07 21 16.pdf PDF
07 21 13.pdf PDF
WVA Fire Station A-503 20250730.pdf PDF
WVA Fire Station A-122 20250730.pdf PDF
WVA Fire Station A-602 20250801.pdf PDF
WVA Fire Station A-507 20250730.pdf PDF
WVA Fire Station A-501 20250730.pdf PDF
Solicitation Amendment W912DS25RA009 0003.pdf PDF
WVA Fire Station JA Simplex Fire Alarm System_sOAS.pdf PDF
WVA Fire Station JA Plymovent Vehicle Exhaust System_sOAS.pdf PDF
Solicitation Amendment W912DS25RA009 0002.pdf PDF
Site Visit Photos.pdf PDF
Attendance List 21 July 2025.pdf PDF
W912DS25RA009 Amendment 0001.pdf PDF
WVA Fire Station - Drawings - RTA 20250624.pdf PDF
CID PACKAGE.pdf PDF
Solicitation - W912DS25RA009(4).pdf PDF
Show all 46

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Army Corps of Engineers

New York District

3 Company Fire Station

Watervliet Arsenal

PN 81503

Watervliet, NY

Design Bid Build

RTA

Project Specifications

APRIL 2025

THIS PAGE INTENTIONALLY LEFT BLANK

WVA Fire Station WVAFIRESTATION23 RTA April 29, 2025

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK

01 14 00 11/22 WORK RESTRICTIONS

01 20 00 11/20, CHG 2: 08/21 PRICE AND PAYMENT PROCEDURES

01 30 00 11/20, CHG 2: 05/22 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 08/23 PROJECT SCHEDULE

01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES

01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND

REPORTING

01 35 26 05/24 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 08/23, CHG 1: 05/24 QUALITY CONTROL

01 45 00.15 10 11/23 RESIDENT MANAGEMENT SYSTEM CONTRACTOR

MODE (RMS CM)

01 45 35 11/20 SPECIAL INSPECTIONS

01 50 00 11/20, CHG 2: 08/22 TEMPORARY CONSTRUCTION FACILITIES AND

CONTROLS

01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS

01 58 00 08/19, CHG 5: 08/22 PROJECT IDENTIFICATION

01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND

DISPOSAL

01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS

01 78 23 08/15, CHG 2: 08/21 OPERATION AND MAINTENANCE DATA

01 78 24.00 10 05/18, CHG 1: 11/21 FACILITY DATA REQUIREMENTS

01 91 00.15 03/24 TOTAL BUILDING COMMISSIONING

01 91 19 05/23 BUILDING ENCLOSURE COMMISSIONING

DIVISION 02 - EXISTING CONDITIONS

02 41 00 08/22 DEMOLITION

DIVISION 03 - CONCRETE

03 30 00 02/19, CHG 4: 08/22 CAST-IN-PLACE CONCRETE

DIVISION 04 - MASONRY

04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY

DIVISION 05 - METALS

05 05 20 05/22 POST-INSTALLED CONCRETE AND MASONRY

ANCHORS

05 05 23.16 08/18 STRUCTURAL WELDING

05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL

05 21 00 05/15, CHG 1: 08/18 STEEL JOIST FRAMING

05 30 00 05/15, CHG 2: 08/18 STEEL DECKS

05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING

05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS

05 51 00 02/17, CHG 1: 05/17 METAL STAIRS

05 52 00 02/18, CHG 1: 02/20 METAL RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY

06 41 16.00 10 08/10, CHG 1: 11/18 PLASTIC-LAMINATE-CLAD ARCHITECTURAL

PROJECT TABLE OF CONTENTS Page 1

CABINETS

06 61 16 08/20 SOLID SURFACING FABRICATIONS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 11 13 08/11, CHG 1: 05/17 BITUMINOUS DAMPPROOFING

07 21 13 02/16, CHG 2: 08/20 BOARD AND BLOCK INSULATION

07 21 16 08/23 MINERAL FIBER BLANKET INSULATION

07 22 00 02/16, CHG 3: 11/18 ROOF AND DECK INSULATION

07 27 10 08/23 BUILDING AIR BARRIER SYSTEM

07 27 19.01 05/17, CHG 2: 08/20 SELF-ADHERING AIR BARRIERS

07 27 26 08/23 FLUID-APPLIED MEMBRANE AIR BARRIERS

07 27 36 08/23 SPRAY FOAM AIR BARRIERS

07 54 19 08/23 POLYVINYL-CHLORIDE ROOFING

07 60 00 05/17, CHG 2: 11/18 FLASHING AND SHEET METAL

07 81 00 02/11 SPRAY-APPLIED FIREPROOFING

07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING

07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 08/20 STEEL DOORS AND FRAMES

08 11 16 05/17, CHG 2: 11/18 ALUMINUM DOORS AND FRAMES

08 14 00 08/16, CHG 1: 08/18 WOOD DOORS

08 22 20 11/19 FIBERGLASS REINFORCED PLASTIC (FRP)

DOORS AND FRAMES

08 36 13 08/20 SECTIONAL FOUR FOLD OVERHEAD DOORS

08 41 13 08/18, CHG 1: 08/18 ALUMINUM-FRAMED ENTRANCES AND

STOREFRONTS

08 51 13 05/19 ALUMINUM WINDOWS

08 60 45 08/20 TRANSLUCENT PANELS

08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE

08 81 00 05/19 GLAZING

08 91 00 08/20 METAL WALL AND DOOR LOUVERS

DIVISION 09 - FINISHES

09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD

09 30 10 08/20 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 08/20 ACOUSTICAL CEILINGS

09 62 38 08/17, CHG 1: 08/18 STATIC-CONTROL FLOORING

09 65 00 08/10, CHG 3: 08/18 RESILIENT FLOORING

09 65 66 08/16, CHG 1: 08/18 RESILIENT ATHLETIC FLOORING

09 68 00 11/17, CHG 2: 08/20 CARPETING

09 90 00 02/21 PAINTS AND COATINGS

DIVISION 10 - SPECIALTIES

10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE

10 14 00.20 08/20 INTERIOR SIGNAGE

10 21 13 08/20 TOILET COMPARTMENTS

10 22 39 08/20 FOLDING PANEL PARTITIONS

10 26 00 08/20 WALL AND DOOR PROTECTION

10 28 13 08/20 TOILET ACCESSORIES

10 44 16 11/19 FIRE EXTINGUISHERS

10 56 13 04/06 STEEL SHELVING

DIVISION 11 - EQUIPMENT

PROJECT TABLE OF CONTENTS Page 2

11 11 37 11/18 ELECTRIC VEHICLE SUPPLY EQUIPMENT

11 31 13 08/17, CHG 1: 08/18 ELECTRIC KITCHEN EQUIPMENT

11 44 00 08/17, CHG 1: 08/18 FOOD COOKING EQUIPMENT

DIVISION 12 - FURNISHINGS

12 24 13 08/20 ROLLER WINDOW SHADES

12 48 13 08/23 ENTRANCE FLOOR MATS AND FRAMES

DIVISION 21 - FIRE SUPPRESSION

21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE

PROTECTION

21 23 00 05/24 WET CHEMICAL FIRE EXTINGUISHING SYSTEMS

DIVISION 22 - PLUMBING

22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE

22 15 26.00 20 04/06 HIGH AND MEDIUM PRESSURE COMPRESSED

AIR PIPING

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 05 15 05/22 COMMON PIPING FOR HVAC

23 05 48.19 05/18, CHG 2: 08/20 SEISMIC BRACING FOR HVAC

23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR

HVAC

23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL

SYSTEMS

23 08 00 05/23 COMMISSIONING OF MECHANICAL AND

PLUMBING SYSTEMS

23 09 00 02/19, CHG 3: 05/21 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES

FOR HVAC

23 09 23.02 02/19, CHG 1: 02/20 BACNET DIRECT DIGITAL CONTROL FOR HVAC

AND OTHER BUILDING CONTROL SYSTEMS

23 11 20 05/20 FACILITY GAS PIPING

23 21 23 08/17 HYDRONIC PUMPS

23 23 00 08/21 REFRIGERANT PIPING

23 30 00 05/20, CHG 1: 02/22 HVAC AIR DISTRIBUTION

23 35 16.17 10 05/20 MECHANICAL ENGINE EXHAUST SYSTEMS

23 52 00 04/08, CHG 5: 11/19 HEATING BOILERS

23 54 19 08/21 BUILDING HEATING SYSTEMS, WARM AIR

23 81 00 05/18, CHG 1: 02/21 DECENTRALIZED UNITARY HVAC EQUIPMENT

DIVISION 25 - INTEGRATED AUTOMATION

25 05 11.01 05/21 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS - UTILITY MONITORING

AND CONTROL SYSTEM (UMCS)

25 05 11.02 05/21 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS - FIRE ALARM / MASS

NOTIFICATION SYSTEM (FA/MNS)

25 05 11.03 05/21 CYBERSECURITY FOR FACILITY-RELATED

CONTROL SYSTEMS - PUBLIC ADDRESS

SYSTEMS (PA)

DIVISION 26 - ELECTRICAL

PROJECT TABLE OF CONTENTS Page 3

26 05 48 11/23 SEISMIC PROTECTION FOR ELECTRICAL

EQUIPMENT

26 05 73 08/23 POWER SYSTEM STUDIES

26 08 00 11/22 APPARATUS INSPECTION AND TESTING

26 11 16 11/21 SECONDARY UNIT SUBSTATIONS

26 13 14 11/21 SUBSTATION HOUSE

26 20 00 08/23 INTERIOR DISTRIBUTION SYSTEM

26 24 13 08/21 SWITCHBOARDS

26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS

UNDER 600 VOLTS

26 32 15.00 05/20 ENGINE-GENERATOR SET STATIONARY

15-2500 KW, WITH AUXILIARIES

26 33 53 05/19 STATIC UNINTERRUPTIBLE POWER SUPPLY

(UPS)

26 41 00 08/23 LIGHTNING PROTECTION SYSTEM

26 42 13 05/21 GALVANIC (SACRIFICIAL) ANODE CATHODIC

PROTECTION (GACP) SYSTEM

26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING

26 56 00 08/21 EXTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING

SYSTEM

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 76 08/20 INTERIOR FIRE ALARM AND MASS

NOTIFICATION SYSTEM, ADDRESSABLE

DIVISION 31 - EARTHWORK

31 00 00 08/23 EARTHWORK

31 05 19.13 02/21 GEOTEXTILES FOR EARTHWORK

31 10 00 02/21 SITE CLEARING

31 11 00 11/18 CLEARING AND GRUBBING

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 05 33 08/17 LANDSCAPE ESTABLISHMENT

32 11 13.16 05/20 BITUMINOUS-STABILIZED SUBGRADE

32 11 20 05/22 BASE COURSE FOR RIGID AND

SELECT-MATERIAL FOR FLEXIBLE PAVING

32 11 23 05/22 AGGREGATE BASE COURSE FOR FLEXIBLE

PAVING

32 11 26 05/20 HOT-MIX BITUMINOUS BASE COURSE FOR

ROADS AND STREETS

32 11 26.19 05/20 BITUMINOUS-STABILIZED BASE AND SUBBASE

COURSES

32 12 13 05/24 BITUMINOUS TACK AND PRIME COATS

32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING

32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS

32 31 13 11/21 CHAIN LINK FENCES AND GATES

32 92 19 08/17, CHG 1: 08/21 SEEDING

32 93 00 08/17, CHG 1: 08/21 EXTERIOR PLANTS

DIVISION 33 - UTILITIES

PROJECT TABLE OF CONTENTS Page 4

33 11 00 02/18, CHG 1: 02/22 WATER UTILITY DISTRIBUTION PIPING

33 11 23 11/09, CHG 1: 08/17 NATURAL GAS AND LIQUID PETROLEUM PIPING

33 30 00 05/18 SANITARY SEWERAGE

33 40 00 11/21 STORMWATER UTILITIES

33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 5

SECTION 01 11 00

SUMMARY OF WORK

08/15, CHG 2: 08/21

PART 1 GENERAL

1.1 FAR 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK

a. The Contractor is required to (i) commence work under this contract within five (5) calendar days after the date the Contractor receives the Notice to Proceed, (ii) prosecute the work diligently, and (iii) complete the entire work ready for use, not later than 730 calendar days after the date the Contractor receives the notice to proceed. The time stated for completion must include final cleanup of the premises.

b. The Contractor must furnish all labor, materials, equipment, and services for the following work: shown in the plans and specifications.

c. All work must be in accordance with the drawings and specifications or instructions attached hereto and made a part thereof, or to be furnished hereafter by the Contracting Officer and subject, in every detail, to his supervision, direction, and instructions.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes construction of an Army standard design of the Three Company Fire Station headquarters.

1.2.2 Location

The work is located at the Watervliet Arsenal, New York, approximately as indicated in drawing plan. The site of the work is on a military reservation and all rules and regulations issued by the Commanding Officer covering general safety, security, and sanitary requirements, etc., must be observed by the Contractor. The exact location will be shown by the Contracting Officer.

1.3 DFARS 236.204, DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS

This project is estimated between $25,000,000.00 and $100,000,000.00

1.4 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

SECTION 01 11 00 Page 1

c. At Contractor's own expense, immediately restore to service and repair any damage caused by Contractor's workmen to the existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone).

Provide immediate notification of the Contracting Officer and verbal procedures to restore. Immediately assemble personnel, equipment and material necessary to restore. Compliance with Contract Documents for quality installation must be included. The work must proceed at 24-hours per day until satisfactorily restored service is achieved.

Fixing loose ends requires Contracting Officer approval to perform during normal working hours. The request to perform repairs during normal working hours requires Contractor's written approval. The write up of procedures to repair must be submitted to the Contracting officer.

d. Repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

1.5 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.No excavation whether minor or major including trenching, sidewalk replacement, etc. will be permitted without an approved digging permit. Contractor shall apply for renewal of work permits as required if the work continues beyond the original permit expiration date. Contact local utility locating service a minimum of 72 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.

Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the groundor paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.5.1 Notification Prior to Excavation

Notify the Contracting Officer at least 15 days prior to starting excavation work.

SECTION 01 11 00 Page 2

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 3

SECTION 01 14 00

WORK RESTRICTIONS

11/22

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 13 (2024) Standard for the Installation of Sprinkler Systems

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2024) Safety -- Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel

Digging Permit ; G

1.3 SPECIAL SCHEDULING REQUIREMENTS

a. Contractor must be ready for operation as approved by Contracting Officer before work is started which would interfere with normal operation.

b. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.

1.4 CONTRACTOR ACCESS AND USE OF PREMISES

1.4.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, SECTION 01 14 00 Page 1 include delivery vehicles, are clearly identified with their company name.

1.4.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.4.1.2 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.4.2 Working Hours

Regular working hours will consist of an 8 1/2 hour period , between 7 a.m. and 3:30 p.m.,Monday through Friday, excluding Government holidays.

1.4.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.

1.4.4 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS.Such interruptions are further limited to 4 hours. This time limit includes time for deactivation and reactivation.

d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.

SECTION 01 14 00 Page 2

1.5 DIGGING PERMIT

The Contractor is responsible for obtaining a digging permit prior to commencing excavations. No excavation whether minor or major including trenching, side-walk replacement, etc. will be permitted without an approved digging permit. Carefully avoid contact or damage with known or identified underground utilities. Work on or near roadways must be flagged in accordance with EM 385-1-1 , which forms a part of these specifications. Work located along the alert force route cannot cause blockage, and the Contractor must maintain un-obstructed access for alert force traffic at all times.

Locate and verify all underground utilities and thereafter maintain those locations on the ground and/or on the contract drawings for use through out the project by all interested.

Dig safe permit must be submitted to the contracting officer's representative a minimum of 30 days prior to the commencement of any work requiring.

1.6 CONTRACTOR'S PROJECT WORK ATTENDANCE

Inform the COR and/or Project Inspector of their presence on post at all times. At the beginning and end of each workday, notify the COR and/or Project Inspector of location(s) on post where work is being performed or has been completed for the day.

1.7 SUBCONTRACTORS

It is the responsibility of the Contractor to inform all their subcontractors of all the instructions contained in this information sheet. Subcontractors are responsible to report project work attendance through the Prime Contractor to the COR whenever they are on post.

1.8 ELEVATED THREAT LEVEL FORCE PROTECTION CONDITION (FPCON) AT WATERVLIET

ARSENAL

Impact on Contractor performance during increased FPCON during periods of increased threat. During FPCONs Charlie and Delta, services may be discontinued/postponed due to higher threat. Services will resume when FPCON level is reduced to level Bravo or lower.

1.9 RANDOM ANTITERRORISM MEASURES PROGRAM (RAMP) AT THE WATERVLIET ARSENAL

In accordance with AR 525-13, Contractor personnel working on an installation are subject to participation in installation RAMP security program (e.g., vehicles, wearing of ID badges, etc.) and installation security program.

1.9.1 Badges

All personnel will report to the Visitors Center daily to be issued a pass. They must return the pass when they leave for the day by dropping it off in the drop box by the Visitors Center attached to the barrier to the left prior to entering the exit lane of the south gate. All personnel must show a driver's license or state identification card (picture ID) to the security guard in order to get the pass. If the personnel will be working on the arsenal for over 90 days, they may be authorized a WVA

SECTION 01 14 00 Page 3 picture badge, which will allow them access during normal work hours without getting a daily pass.

1.9.2 Picture Badges

The Contractor may request through the Contracting Officer a picture badge if the term of the contract warrants. Requests must be made in writing on company letterhead to the Contracting Officer listing the following:

a. Contract Number.

b. Indicate that the individual(s) work for said company.

c. Project name and location of work site (i.e., Bldg. #).

d. Duration of performance (start and stop dates).

e. All personnel being issued a picture badge shall present a passport or original birth certificate (with a raised seal) and driver's license.

(A social security card is not an acceptable form of identification).

f. During performance of the contract, the Contractor is responsible for prompt return of badges for any employee who no longer requires access to the work site.

g. Upon completion or termination of the contract or expiration of badge(s), the Contractor shall ensure that they are returned to the issuing office.

h. Final payment on the contract will be held until all badges are properly returned.

i. Possession of a picture badge does not relieve the badge holder from the responsibility to notify the COR of project work attendance.

1.10 ACCESS POLICY

a. All Contractor personnel entering the installation and requiring unescorted access must have a valid purpose to enter and be sponsored by a U.S. Government organization or a Contractor providing support on the installation. They must have their identity proofed and vetted through the National Crime Information Center (NCIC) database, and be issued, or in possession of an authorized and valid access credential from the Watervliet Arsenal installation.

b. At the discretion of the Commander, US Army Watervliet Arsenal, any individual known to have a criminal background involving violence or meets the disqualifying standards in the Final Credentialing Standards for Issuing Personal Identity Verification Cards under HSPD-12 (31 JUL 2008) and local command guidance, may be denied access to the Watervliet Arsenal. Fingerprinting of employees and any other security procedures deemed necessary for the security of Watervliet Arsenal (vehicle searches or x-raying packages, bags, briefcases) may be required based on the Force Protection Condition level at the time of access and whether the installation or building location is identified as a restricted area or Mission Essential Vulnerable Area

(MEVA).

SECTION 01 14 00 Page 4

1.11 NON-CITIZENS

Non-citizens of the U.S. may not be approved for access.

1.12 CAMERAS

a. The Security Office and Public Affairs Officer must approve all cameras use prior to any pictures being taken, to include using a photographic-capable cell phone as a photographic device. Requests must be submitted to the WVA COR then routed to Security and then to the Public Affairs Officer. Violations may result in the camera and film being confiscated and a citation being issued for an appearance before the U.S. Magistrate in Albany, NY.

b. For any photos that have been approved by the Security Office and Public Affairs Officer be advised that the photos contain military imagery that is owned by the US Government: US Army Watervliet Arsenal. It is not to be used for any purpose other than the purpose for which it is furnished nor distributed or reproduced for any purpose to persons other than the individuals specified to receive it, or their employees, without written consent of the US Army Watervliet Arsenal.

c. All photos must be reviewed by the security office before the photo capture system (i.e., camera, cell phone, etc.) has left the arsenal.

1.13 TRAFFIC CONTROL

Post Speed Limit is 15 mph. Parking is allowed in valid spaces only. All valid spaces are clearly marked with white lines on both sides of the space. Vehicles parked in other than valid spaces are subject to being issued traffic citations requiring a monetary fine and/or an appearance before the U.S. Magistrate in Albany, N.Y. Motorists within the confines of WVA are subject to all New York State Vehicle and Traffic Laws. Any moving or nonmoving violation may result in a traffic citation being issued. Loading and unloading of vehicles will be allowed only for the amount of time required to perform the function. Vehicles cannot be left unattended in other than valid parking spaces. If a patrol officer can approach a vehicle, write a traffic citation, affix that citation to the vehicle, and depart the area with no one present at the vehicle, that vehicle is considered to be unattended. Both the Fire Department and Security Department must be notified prior to blocking of streets. The Contractor must coordinate through the COR for approval to block or close streets.

1.14 DELIVERIES

Deliveries to Contractors shall enter the post through the South Gate.

Contractors expecting deliveries should notify the South Gate (266-5821) prior to the arrival of the delivery. The Contractor's representative must accept deliveries. Materials, which are delivered to the site, are the responsibility of the Contractor. Storage and special conditions must be coordinated with the COR for approval to block or close streets.

1.15 CONTRABAND

Alcohol, illegal drugs, and any firearms are prohibited. Violations may result in the items being confiscated and a citation being issued for an appearance before the U.S. Magistrate in Albany, NY.

SECTION 01 14 00 Page 5

1.16 RESTRICTION OF WVA PROVIDED DOCUMENTS

Documents provided by WVA contain proprietary information and are to be used only in support of their current authorized release. Other requests for documents must be referred to the Contracting Officer, Army Contracting Command - Warren (ACC-WRN) (WVA), 1 Buffington Street, Watervliet, NY 12189. Documents shall be destroyed to prevent disclosure and reconstruction of the contents upon completion of contracted work.

1.17 SECURITY OF EQUIPMENT

Contractors are responsible for securing all of their equipment. WVA is not responsible for stolen or lost items.

1.18 VEHICLES IN BUILDINGS

Contractors' vehicles and equipment using fuel shall receive clearance from the Fire Chief before entering the building. Refueling of vehicles in a building requires Fire Department standby.

1.19 STORAGE SHED/TRAILERS/TEMPORARY OFFICES

The placement of all storage shed/trailers/temporary offices are subject to the approval of the Public Works Division, the Watervliet Arsenal Fire department, and the Watervliet Arsenal Security Department. The Contractor shall submit their placement request in writing 10 business days in advance to the project COR or technical POC for request evaluation and approval. (Note: Request approval is not guaranteed.) All temporary sheds, trailers or offices within thirty feet of any Arsenal structure must be equipped with a temporary sprinkler system as required by NFPA 13 .

The Fire Inspection Staff will assist Contractors in determining sprinkler requirements on site, upon request. Call extension 5990 for fire inspector assistance.

1.20 EQUIPMENT, DUMPSTER, STORAGE CONTAINER/SHED, TRAILER, and OFFICE

IDENTIFICATION

Contractor shall prominently display the following information on all Contractor and subcontractor, owned, leased or rented motorized and wheeled equipment, dumpsters, storage containers/sheds, trailers, and offices:

a. Contractor Company Name.

b. Project Number/Contract Number or Equivalent (information will be provided to Contractor by the Watervliet Arsenal, the Arsenal Partnership (AP), or the AP's Construction Manager).

c. Contractor Project Point of Contact (POC) with phone number or Arsenal/AP Project POC with phone number (information will be provided to Contractor by the Watervliet Arsenal, the AP, or the AP's Construction Manager).

1.21 GASOLINE CONTAINERS AND FLAMMABLES

Gasoline will be stored in safety containers equipped with self closing lids and other features as certified by the Underwriters' Laboratories.

Flammable liquids will be kept in National Fire Protection Association or

SECTION 01 14 00 Page 6

UL approved containers; Fire Department (extension 5990) will be called in event of a question. If gasoline or any other type fuel is kept in a portable tank it must have secondary containment or the tank be double walled and the product labeled on the side of the tank (i.e., flammable).

1.22 FIRE HYDRANTS

Fire hydrants shall not be used without the permission of Facilities Engineering and notification of the Fire Department (extension 5990). If permission is granted to use hydrants, the Contractor will provide adapters, valves and hoses. A backflow preventer will also be required of the Contractor. It is the responsibility of the Contractor to ensure the hydrants are shut off and have drained properly. The Fire Department must be notified when finished.

1.23 DISCHARGES

Unless granted prior written approval, there shall be no discharge to the sanitary sewer, the storm sewer, the industrial sewer system, or the Industrial Waste Treatment Plant (IWTP). Except when WVA has established with the Contractor a prior written agreement regarding discharge of "purge water" originating from groundwater monitoring wells and/or "decontamination water" originating from activities associated with groundwater monitoring wells, there shall be no dumping of oil or chemicals or fluids to the ground.

1.24 DOCUMENTATION OF DISPOSITION OF MATERIALS AND ITEMS REMOVED FROM

WATERVLIET ARSENAL

The Contractor shall furnish documentation of the final disposition of all materials and items leaving Watervliet Arsenal. If an item is resold intact, indicate such action for the item and the name and address of purchaser. If oil is drained from an item, provide documentation for both the oil and the item by identifying final disposition location and management method for each (e.g., recycled, incinerated, land filled).

All materials and items leaving Watervliet Arsenal shall be managed strictly in accordance with all applicable environmental regulations. The Contractor shall indicate intentions for all such materials and items at the pre-construction meeting, for approval by Watervliet Arsenal.

1.25 WASTE DISPOSAL

All hazardous waste shall be disposed of by the Contractor. The Contractor is responsible for management and disposal of all hazardous waste in accordance with applicable regulations, WVA's Hazardous Waste Management Plan, Section 01 57 19 - 3.4.3.1 and the Contractor's Approved Environmental Protection Plan. Hazardous waste shall be moved to Building 145 for 90 day storage in accordance with the RCRA "three day" rule.

Drums of hazardous waste shall not remain outdoors overnight. Other wastes include any spent material such as garbage, packaging, residues, construction and demolition debris, excavated soils and earthen materials not designated for immediate reuse, etc., which is known by WVA and/or demonstrated by the Contractor via appropriate sampling and analysis to not be hazardous waste (such demonstration shall be to the satisfaction of WVA). The Contractor is responsible for disposal of other wastes, unless noted otherwise. Disposal of wastes at private sites such as sites advertising clean fill wanted, etc., is prohibited. The Contractor shall comply with 6 NYCRR Part 364 for all waste hauling activities. The Contractor shall furnish copies of documents for each waste shipment, such

SECTION 01 14 00 Page 7 as Bills of Lading, etc., (Including "light weight" upon entering WVA, and "heavy weight" upon exiting WVA) through the COR to Facilities Engineering. Contractor shall furnish and properly label new, unused, appropriate drums and/or containers (including, but not limited to, compliance with DOT's Performance Oriented Packaging Standards (POPS)) for containerizing waste. Contractor supplied dumpsters shall be covered with water proof covers to prevent precipitation from entering the dumpster.

Covers shall be secured in place whenever the Contractor leaves the job site, and whenever precipitation is possible or occurring. Scrap metals that are recycled at an approved scrap metal facility do not required testing and waste characterization. Proper cleaning (triple rinse) is still required.

1.26 INDUSTRIAL WASTE TREATMENT PLANT (IWTP)

Due to OSHA Process Safety Management rule requirements, the Contractor shall coordinate with the IWTP Leader regarding IWTP-specific requirements when work is to be performed in and/or around the IWTP.

Requirements will include:

a. Hazard awareness of chemicals used at the facility to include sulfur dioxide (so2), chromic acid, and sulfuric acid.

b. Hazmin system-access by IWTP leader for all chemicals/sds upon request.

c. Proper PPE to be used when working with chemicals. This shall include protective suites (Tyvek), hardhats, chemical resistant gloves, respiratory protection, and hearing protection.

d. Building evacuation procedures when so2 alarm activates.

e. Must sign in/out of IWTP roster as acknowledgment this procedure.

1.27 UTILITY CLEARANCE PERMIT (UCP)

All contracted work is subject to the WVA Regulation on utility clearance permits, WVAR 420-02. The Contractor will assist the COR in preparing the UCP. The Contractor shall review the project site, project documents and utility record plans to determine the presence of concealed utilities within the area(s) of the project work. The Contractor is required to sign the UCP and concur / non-concur with the project UCP.

1.28 MARKING UNDER GROUND UTILITIES

All contract work, which involves the installation or unearthing of underground utilities, shall include the marking of these utilities as part of the required project work. The tape shall be detectable by a metal detector when buried up to 3 feet deep. The tape shall be of a type specifically manufactured for marking and locating underground utilities.

The metallic core of the tape shall be encased in a protective jacket or provided with other means to protect it from corrosion. Tape color shall be as specified below and shall bear a continuous printed inscription describing the specific utility.

RED: ELECTRIC

BLUE: WATER SYSTEM

GREEN: SEWER SYSTEM

YELLOW: GAS LINE OR PIPELINE (FOR NATURAL GAS, OIL,

SECTION 01 14 00 Page 8

STEAM/CONDENSATE OR OTHER DANGEROUS MATERIALS)

ORANGE: FIBER OPTIC (TELEPHONE, TELEVISION, SECURITY OR FIRE ALARM)

1.29 SULFUR DIOXIDE (SO2) AWARENESS

Due to the presence of highly hazardous chemicals located in the Industrial Waste Treatment Plant, always follow the instructions of WVA officials quickly and completely in the event of any emergency. This is especially important when working in or near the Industrial Waste Treatment Plant (IWTP).

Because of the requirements of OSHA's Process Safety Management (PSM) standard (For specific requirements see Title 29 of the Code of Federal Regulations, Part 1910.119 on the OSHA website) safe work practices have been developed that provide for the control of hazards during operations such as lockout/tag out; confined space entry; line breaking of process associated piping; control over IWTP facility entry. These safe work practices apply to all employees and Contractors equally. Contractors must follow all safe work practices while working on the installation and provide training to employees on PSM before working within the IWTP.

For Contractors performing maintenance or repair, turnaround, major renovation, or specialty work on or adjacent to a covered process, contact the Contracting Officer's Representative (COR) for more instructions on special provisions of the PSM standard that applies to this work.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 14 00 Page 9

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

11/20, CHG 2: 08/21

PART 1 GENERAL

1.1 CONTRACT COST BREAKDOWN

The Contractor must furnish within 30 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This Contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.

1.2 SINGLE JOB PAYMENT ITEMS

Payment items for the work of this Contract for which Contract job payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 20 00 Page 1

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

11/20, CHG 2: 05/22

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2024) Safety -- Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map

Progress and Completion Pictures

SD-04 Samples

Color Boards ; G, RO

1.3 COLOR BOARDS

Submit five sets of color boards within 90 calendar days after Contract Award. Each set of boards must include samples of colors and finishes of interior surfaces, such as walls, floors, and ceilings. Present the samples on 8 by 10-1/2 inches boards (modules) with a maximum spread of 24 by 31-1/2 inches for foldouts. Design modules to fit in a standard loose-leaf, three-ring binder. Where special finishes such as architectural concrete, carpet, or prefinished textured metal panels are required, submit samples not less than 12 inches square with the board.

If more space is needed, more than one board per set may be submitted.

Certify that the color samples have been reviewed in detail, and that the color samples are in strict accordance with contract drawings and specifications, except as may be otherwise explicitly stated. Submittal of color samples does not relieve the Contractor of the responsibility to submit samples required elsewhere herein.

1.4 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as

SECTION 01 30 00 Page 1 required if the locations are moved.

1.5 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit the monthly invoice two sets of digital photographs, cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.

Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch as a digital file. Include a date designator in file names. Photographs provided are for unrestricted use by the Government.

Refer to section 01 33 00 SUBMITTAL PROCEDURES, Electronic File Format paragraph for information on electronic file format for submission .

1.6 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by the New York State law and 52.228-5 - Insurance - Work on a Government Installation..

a. Before commencing work under this contract, the Contractor must notify the Contracting Officer in writing that the required insurance has been obtained. The policies evidencing required insurance must contain an endorsement to the effect that cancellation or material change adversely affecting the Government's interest cannot be effective for such a period as may be prescribed by the laws of the State in which this contract is to be performed and in no event less than 30 days after written notice thereof to the Contracting Officer.

b. The Contractor must insert the substance of this clause, including this paragraph (b), in subcontracts under this contract that require work on a Government installation and must require subcontractors to provide and maintain the insurance required in the Schedule or elsewhere in the contract. The Contractor must maintain a copy of all subcontractors' proofs of required insurance, and must make copies available to the Contracting Officer upon request.

c. This insurance will be included at no additional cost to the government.

1.7 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS

In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS

222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) Contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or

SECTION 01 30 00 Page 2 incentive applies to the solicitation or performance under the resultant contract, USACE Contractors are encouraged to seek out highly qualified veterans to perform services under this contract.

The following resources are available to assist USACE Contractors in their outreach efforts:

Federal Veteran employment information at http://www.fedshirevets.gov/index.aspx Department of Labor Veterans Employment Assistance https://www.dol.gov/vets/ Department of Veterans Affairs-VOW to Hire Heroes Act http://benefits.va.gov/vow/ Army Wounded Warrior Program-http://wtc.army.mil/modules/employers/index.html U.S. Chamber of Commerce Foundation-Hiring Our Heroes http://www.hiringourheroes.org /

1.8 PROJECT MANAGER

Provide a Project Manager with minimum of 15 years of construction experience in similar size project as a project manager. Project manager will serve as the Governments' sole point of contact in all matters relating to work including, but not limited to, contract compliance, progress of work, overall project scheduling, financial matters, and change orders. Performs all project management duties of the project and attend all job meetings. Individual must be on site a minimum of one days per week and authorized to negotiate changes. The Contracting Officer may request proof of the project manager's qualifications at any point in the project if the performance of the superintendent is in question.

Project manager must be capable of reading, writing, and conversing fluently in the English language.

1.9 SUPERVISION

1.9.1 Superintendent Qualifications

Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

1.9.2 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work.In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.

SECTION 01 30 00 Page 3

1.9.3 Duties

The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.9.4 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.10 SUPERINTENDENCE OF SUBCONTRACTORS

a. The Contractor shall be required to furnish the following, in addition to the superintendence required by the Contract Clause titled, "SUPERINTENDENCE BY THE CONTRACTOR".

(1) If more than 50% and less than 70% of the value of the contract work is subcontracted, one superintendent shall be provided at the site and on the Contractor's payroll to be responsible for coordinating, directing, inspecting and expediting the subcontract work.

(2) If 70% or more of the value of the work is subcontracted, the Contractor shall be required to furnish two such superintendents to be responsible for coordinating, directing, inspecting and expediting the subcontract work.

b. If the Contracting Officer, at any time after 50% of the subcontracted work has been completed, finds that satisfactory progress is being made, he may waive all or part of the above requirement for additional superintendence subject to the right of the Contracting Officer to reinstate such requirement if at any time during the progress of the remaining work he finds that satisfactory progress is not being made.

1.11 PRECONSTRUCTION CONFERENCE

Prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Conference . The conference must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this conference is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required

SECTION 01 30 00 Page 4 phasing.

The Contractor must provide at this conference the following items as indicated:

a. Initial Project Schedule; Section 01 32 01.00 10 PROJECT SCHEDULE.

b. Accident Prevention Plan (APP); Section 01 35 26 GOVERNMENTAL SAFETY

REQUIREMENTS.

c. Contractor Quality Control (CQC) Plan; Section 01 45 00 QUALITY

CONTROL.

d. List of Contact Personnel; Section 01 14 00 WORK RESTRICTIONS.

e. Letter appointing Superintendent.

f. Detailed Concept of Operations Plan.

1.11.1 Attendees

Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.

1.12 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)

Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning the turnover process at the Pre-Construction Conference meeting with a discussion of the Red Zone process and convene at regularly scheduled NRZ Meetings beginning at approximately 75 percent of project completion.

Include the following in the facility Turnover effort:

1.12.1 Red Zone Checklist

a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the Red Zone Checklist template.

b. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting…