This document is a federal contract specification section (Section 01 45 00.15 10) for the Resident Management System (RMS) Contractor Mode, specifically for a WVA Fire Station project. The specification outlines the mandatory requirements for contractors to use the U.S. Army Corps of Engineers' web-based RMS for contract administration, which includes comprehensive tracking and reporting across multiple areas such as administration, finances, quality control, submittal management, scheduling, and closeout.
Key requirements include entering and maintaining detailed contract data within the RMS system within seven calendar days of contract access, including contractor and subcontractor information, correspondence, equipment lists, daily reports, pay activities, schedules, and quality control documentation. The contractor must be prepared to transition from RMS to a new Construction Management Platform (CMP) at any time during the contract period, with no additional time or cost considerations. The system facilitates electronic information exchange between the government and contractor, and is considered an integral part of the contractor's quality control management.
View the file
Other files for this federal contract opportunity
Show all 46
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WVA Fire Station WVAFIRESTATION23 Amendment 009 September 10, 2025
SECTION 01 45 00.15 10
RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
11/23
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Health Requirements Manual
1.2 MEASUREMENT AND PAYMENT
The work of this section is not measured for payment. The Contractor is responsible for the work of this section, without any direct compensation other than the payment received for contract items.
1.3 CONTRACT ADMINISTRATION
The Government will use the Resident Management System (RMS) to assist in its monitoring and administration of this contract. The Government accesses the system using the Government Mode of RMS (RMS GM) and the Contractor accesses the system using the Contractor Mode (RMS CM). The term RMS will be used in the remainder of this section for both RMS GM and RMS CM. The joint Government-Contractor use of RMS facilitates electronic exchange of information and overall management of the contract. The Contractor accesses RMS to record, maintain, input, track, and electronically share information with the Government throughout the contract period in the following areas:
Administration Finances Quality Control Submittal Monitoring Scheduling Closeout Import/Export of Data
The Contractor must be prepared to transition from the Resident Management System (RMS) to the new Construction Management Platform (CMP) at any time during the period of performance of this contract, once the USACE enterprise implements this change. The Contractor's obligation to transition from RMS to the CMP system is a requirement of this contract.
Therefore, additional time or cost increase to complete this transition will not be considered. In the event of the transition, RMS project information will be migrated to CMP by the government and available in the CMP system. After the transition, the Contractor must utilize the CMP system to perform all contract administration functions previously required in RMS, including all areas listed above. After the transition, “RMS” and “CMP” will be synonymous for all “Resident Management System” and “RMS” references in this contract’s specification. To facilitate the
SECTION 01 45 00.15 10 Page 1 transition from RMS to CMP, online training for the CMP system will be made available to the Contractor with enough time to train staff, prior to the transition occurring.
1.3.1 Correspondence and Electronic Communications
For ease and speed of communications, exchange correspondence and other documents in electronic format to the maximum extent feasible. Some documents such as correspondence, including pay requests and payrolls, may be required in paper format with original signatures. Paper documents will govern in the event of discrepancy with the electronic version.
Contracting Officer will determine which documents require submission of paper copies.
1.3.2 Other Factors
Other portions of this document have a direct relationship to the reporting accomplished through RMS. Particular attention is directed to FAR 52.236-15 Schedules for Construction Contracts; FAR 52.232-27 Prompt Payment for Construction Contracts; FAR 52.232-5 Payments Under Fixed-Priced Construction Contracts; Section 01 32 01.00 10 PROJECT SCHEDULE; Section 01 33 00 SUBMITTAL PROCEDURES; Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS; and Section 01 45 00 QUALITY CONTROL.
1.4 RMS SOFTWARE
RMS is a web based application. Download, install and be able to utilize the latest version of RMS within 7 calendar days of receipt of the Notice to Proceed. RMS software, user manuals, access and installation instructions, program updates and training information are available from the RMS website ( https://rms.usace.army.mil ). The Government and the Contractor will have different access authorities to the same contract database through RMS. The common database will be updated automatically each time a user finalizes an entry or change.
1.5 CONTRACT DATABASE - GOVERNMENT
The Government will enter the basic contract award data in RMS prior to granting the Contractor access. The Government entries into RMS will generally be related to submittal reviews, correspondence status, and Quality Assurance(QA)comments, as well as other miscellaneous administrative information.
1.6 CONTRACT DATABASE - CONTRACTOR
Contractor entries into RMS establish, maintain, and update data throughout the duration of the contract. Contractor entries generally include prime and subcontractor information, daily reports, submittals, RFI's, schedule updates and payment requests. RMS includes the ability to import attachments and export reports in many of the modules, including submittals. The Contractor responsibilities for entries in RMS typically include the following items:
1.6.1 Administration
1.6.1.1 Contractor Information
Enter all current Contractor administrative data and information into RMS within 7 calendar days of receiving access to the contract in RMS. This
SECTION 01 45 00.15 10 Page 2 includes, but is not limited to, Contractor's name, address, telephone numbers, management staff, and other required items.
1.6.1.2 Subcontractor Information
Enter all missing subcontractor administrative data and information into RMS CM within seven calendar days of receiving access to the Contract in RMS or within seven calendar days of the signing of the subcontractor agreement for agreements signed at a later date. This includes name, trade, address, phone numbers, and other required information for all subcontractors. A subcontractor is listed separately for each trade to be performed.
1.6.1.3 Correspondence
Identify all Contractor correspondence to the Government with a serial number. Prefix correspondence initiated by the Contractor's site office with "S". Prefix letters initiated by the Contractor's home (main) office with "H". Letters are numbered starting from 0001. (e.g., H-0001 or S-0001). The Government's letters to the Contractor will be prefixed with "C" or "RFP".
1.6.1.4 Equipment
Enter and maintain a current list of equipment planned for use or being used on the jobsite, including the most recent and planned equipment inspection dates in accordance with Section 01 45 00 QUALITY CONTROL.
1.6.1.5 Reports
Track the status of the project using the reports available in RMS. The value of these reports reflects the quality of the data input. These reports include but are not limited to the Progress Payment Request worksheet, Quality Control (QC) comments, Deficiency Tracking Log, Submittal Register Status, and Three-Phase Control worksheets in accordance with Sections 01 20 00 PRICE AND PAYMENT PROCEDURES, Section 01 32 01.00 10 PROJECT SCHEDULE, 01 33 00 SUBMITTAL PROCEDURES, and
01 45 00 QUALITY CONTROL.
1.6.1.6 Request For Information (RFI)
Create and track all Requests For Information (RFI) in the RMS Administration Module for Government review and response. Provide status at weekly progress meeting in accordance with Section 01 32 01.00 10
PROJECT SCHEDULE.
1.6.2 Finances
1.6.2.1 Pay Activity Data
Develop and enter a list of pay activities in conjunction with the project schedule in accordance with Section 01 32 01.00 10 PROJECT SCHEDULE. The sum of pay activities equals the total Contract amount, including modifications. Each pay activity must be assigned to a Contract Line Item Number (CLIN). The sum of the activities assigned to a CLIN equals the amount of each CLIN.
SECTION 01 45 00.15 10 Page 3
1.6.2.2 Payment Requests
Prepare all progress payment requests using RMS. Update the work completed under the Contract at least monthly, measured as percent or as specific quantities. After the update, generate a payment request and prompt payment certification using RMS. Submit the signed prompt payment certification and payment request as well as supporting data, either electronically or by hard copy.
1.6.3 Quality Control (QC)
Enter and track implementation of the 3-phase QC Control System, QC testing, transferred and installed property and warranties in RMS. Link each deficiency and QC test to a pay activity. Prepare daily reports, identify and track deficiencies, document progress of work, and support other Contractor QC requirements in RMS. Maintain all data on a daily basis. Ensure that RMS reflects all quality control methods, tests and actions contained within the Contractor Quality Control (CQC) Plan and Government review comments. Provide within seven calendar days of Government acceptance of the CQC Plan.
1.6.3.1 Quality Control (QC) Reports
The Contractor's Quality Control (QC) Daily Report in RMS is the official report. The Contractor can use other supplemental formats to record QC data, but information from any supplemental formats are to be consolidated and entered into the RMS QC Daily Report. Any supplemental information may be entered into RMS as an attachment to the report. QC Daily Reports must be finalized and signed in RMS within 24 hours after the date covered by the report. Provide the Government a printed signed copy of the QC Daily Report, unless waived by the Contracting Officer.
1.6.3.2 Deficiency Tracking
Use the QC Daily Report Module to enter and track deficiencies.
Deficiencies identified and entered into RMS by the Contractor or the Government will be sequentially numbered with a QC or QA prefix for tracking purposes. Enter each deficiency into RMS the same day that the deficiency is identified. Monitor, track and resolve all QC and QA entered deficiencies. A deficiency is not considered to be corrected until the Government indicates concurrence in RMS.
1.6.3.3 Three-Phase Control Meetings
Maintain scheduled and actual dates and times of preparatory and initial control meetings in RMS, and upload meeting minutes of the meetings.
Worksheets for the three-phase control meetings are generated within RMS.
1.6.3.4 Labor and Equipment Hours
Enter labor and equipment exposure hours on a daily basis. Roll up the labor and equipment exposure data into a monthly exposure report.
1.6.3.5 Accident/Safety Reporting
Both the Contractor and the Government enter safety related comments in RMS as a deficiency. The Contractor must monitor, track and show resolution for safety issues in the QC Daily Report area of the RMS QC Module. In addition, follow all reporting requirements for accidents and
SECTION 01 45 00.15 10 Page 4 incidents as required in EM 385-1-1 , Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS and as required by any other applicable Federal, State or local agencies.
1.6.3.6 Definable Features of Work
Enter each feature of work, as defined in the approved CQC Plan, into the RMS QC Module. A feature of work may be associated with a single or multiple pay activities, however a pay activity is only to be linked to a single feature of work.
1.6.3.7 Activity Hazard Analysis
Import activity hazard analysis electronic document files into the RMS QC Module utilizing the document package manager. Prepare activity hazard analysis in accordance with Section 01 35 26 GOVERNMENT SAFETY
REQUIREMENTS.
1.6.4 Submittal Management
Enter all current submittal register data and information into RMS within seven calendar days of receiving access to the Contract in RMS.
Contractor is responsible for entering Activity Numbers for each submittal item corresponding to their Schedule. The Contractor will import the information shown in the submittal register following the specification Section 01 33 00 SUBMITTAL PROCEDURES unless otherwise directed by the Contracting Officer. Group electronic submittal documents into transmittal packages to send to the Government, except very large electronic files, samples, spare parts, mock ups, color boards, or where hard copies are specifically required. Track transmittals and update the submittal register in RMS on a daily basis throughout the duration of the Contract. Submit hard copies of all submittals unless waived by the Contracting Officer.
Contractor may request submittals to be added to RMS throughout the lifecycle of the project. Approval/disapproval of Contractor requests is at the discretion of the Contracting Officer. Submittals entry into RMS must be updated daily or as practical for performance of the Contract, as approved by the Contracting Officer.
1.6.5 Schedule
Enter and update the contract project schedule in RMS by either manually entering all schedule data or by importing the Standard Data Exchange Format (SDEF) file, based on the requirements in Section 01 32 01.00 13
PROJECT SCHEDULE.
1.6.6 Closeout
Closeout documents, processes and forms are managed and tracked in RMS by both the Contractor and the Government. Ensure that all closeout documents are entered, completed and documented within RMS.
1.7 IMPLEMENTATION
Use of RMS as described in the preceding paragraphs is mandatory. Ensure that sufficient resources are available to maintain contract data within the RMS system. RMS is an integral part of the Contractor's required management of quality control.
SECTION 01 45 00.15 10 Page 5
1.8 NOTIFICATION OF NONCOMPLIANCE
Take corrective action within seven calendar days after receipt of notice of RMS non-compliance by the Contracting Officer.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 45 00.15 10 Page 6
| 01 45 00.15 10 - RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE RMS CM |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 MEASUREMENT AND PAYMENT |
| 1.3 CONTRACT ADMINISTRATION |
| 1.3.1 Correspondence and Electronic Communications |
| 1.3.2 Other Factors |
| 1.4 RMS SOFTWARE |
| 1.5 CONTRACT DATABASE - GOVERNMENT |
| 1.6 CONTRACT DATABASE - CONTRACTOR |
| 1.6.1 Administration |
| 1.6.1.1 Contractor Information |
| 1.6.1.2 Subcontractor Information |
| 1.6.1.3 Correspondence |
| 1.6.1.4 Equipment |
| 1.6.1.5 Reports |
| 1.6.1.6 Request For Information RFI |
| 1.6.2 Finances |
| 1.6.2.1 Pay Activity Data |
| 1.6.2.2 Payment Requests |
| 1.6.3 Quality Control QC |
| 1.6.3.1 Quality Control QC Reports |
| 1.6.3.2 Deficiency Tracking |
| 1.6.3.3 Three-Phase Control Meetings |
| 1.6.3.4 Labor and Equipment Hours |
| 1.6.3.5 Accident/Safety Reporting |
| 1.6.3.6 Definable Features of Work |
| 1.6.3.7 Activity Hazard Analysis |
| 1.6.4 Submittal Management |
| 1.6.5 Schedule |
| 1.6.6 Closeout |
| 1.7 IMPLEMENTATION |
| 1.8 NOTIFICATION OF NONCOMPLIANCE |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |