01 50 00.pdf
PDF 54 KB Posted
- Attached to
- WVA Fire Station Construction Acquisition Federal contract opportunity
- Solicitation number
- W912DS25RA009
About this file
This document is a Section 01 50 00 specification for Temporary Construction Facilities and Controls for a WVA Fire Station project, Amendment 006, dated August 26, 2025. The specification provides comprehensive requirements for contractors regarding temporary site facilities, including detailed guidelines for site access, safety, utility usage, traffic control, fencing, storage areas, and cybersecurity during construction.
Key requirements include establishing a secure construction site with 6-foot high chain link fencing, maintaining temporary safety fencing, controlling dust and traffic, implementing cybersecurity protocols for contractor computers and networks, providing temporary utilities, maintaining proper sanitation facilities, and ensuring daily cleanup. The document mandates specific provisions such as changing default passwords, using anti-malware software, testing backflow preventers, and protecting stored materials. Contractors must also follow strict guidelines for trailer placement, appearance, and removal, with an emphasis on maintaining a clean, organized, and secure construction environment.
View the file
Other files for this federal contract opportunity
Show all 46
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WVA Fire Station WVAFIRESTATION23 Amendment 006 August 26, 2025
SECTION 01 50 00
TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
11/20, CHG 2: 08/22
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C511 (2017; R 2021) Reduced-Pressure Principle Backflow Prevention Assembly
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2020; TIA 22-1; ERTA 1 2022) National Electrical Code
NFPA 241 (2022) Standard for Safeguarding Construction, Alteration, and Demolition Operations
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual
U.S. FEDERAL HIGHWAY ADMINISTRATION (FHWA)
MUTCD (2009; Rev 2012) Manual on Uniform Traffic Control Devices
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Construction Site Plan ; G, RO
Traffic Control Plan ; G, RO
Haul Road Plan ; G, RO
Contractor Computer Cybersecurity Compliance Statements ; G, RO
Contractor Temporary Network Cybersecurity Compliance Statements ; G, SECTION 01 50 00 Page 1
RO
SD-06 Test Reports
Backflow Preventer Tests
SD-07 Certificates
Backflow Tester Certification
Backflow Preventers Certificate of Full Approval
1.3 CONSTRUCTION SITE PLAN
Prior to the start of work, submit for Government approval a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation. Identify any areas which may have to be graveled to prevent the tracking of mud. Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.
1.4 BACKFLOW PREVENTERS CERTIFICATE
1.4.1 Backflow Tester Certificate
Prior to testing, submit to the Contracting Officer certification issued by the State or local regulatory agency attesting that the backflow tester has successfully completed a certification course sponsored by the regulatory agency. Tester must not be affiliated with a company participating in other phases of this Contract.
1.4.2 Backflow Prevention Training Certificate
Submit a certificate recognized by the State or local authority that states the Contractor has completed at least 10 hours of training in backflow preventer installations. The certificate must be current.
1.5 DOD CONDITION OF READINESS (COR)
DOD will set the Condition of Readiness (COR) based on the weather forecast for sustained winds 50 knots ( 58 mph ) or greater. Contact the Contracting Officer for the current COR setting.
Monitor weather conditions a minimum of twice a day and take appropriate actions according to the approved Emergency Plan in the accepted Accident Prevention Plan, EM 385-1-1 Section 01 Emergency Planning and the instructions below.
Unless otherwise directed by the Contracting Officer, comply with:
a. Condition FOUR (Sustained winds of 58 mph or greater expected within 72 hours): Normal daily jobsite cleanup and good housekeeping practices. Collect and store in piles or containers scrap lumber, waste material, and rubbish for removal and disposal at the close of
SECTION 01 50 00 Page 2 each work day. Maintain the construction site including storage areas, free of accumulation of debris. Stack form lumber in neat piles less than 3.3 feet high. Remove all debris, trash, or objects that could become missile hazards. Review requirements pertaining to "Condition THREE" and continue action as necessary to attain "Condition FOUR" readiness. Contact Contracting Officer for weather and COR updates and completion of required actions.
b. Condition THREE (Sustained winds of 58 mph or greater expected within 48 hours): Maintain "Condition FOUR" requirements and commence securing operations necessary for "Condition ONE" which cannot be completed within 18 hours. Cease all routine activities which might interfere with securing operations. Commence securing and stow all gear and portable equipment. Make preparations for securing buildings. Reinforce or remove formwork and scaffolding. Secure machinery, tools, equipment, materials, or remove from the jobsite.
Expend every effort to clear all missile hazards and loose equipment from general base areas. Contact Contracting Officer for weather and COR updates and completion of required actions. Review requirements pertaining to "Condition TWO" and continue action as necessary to attain "Condition THREE" readiness.
c. Condition TWO (Sustained winds of 58 mph or greater expected within 24 hours): Secure the jobsite, and leave Government premises.
d. Condition ONE. (Sustained winds of 58 mph or greater expected within 12 hours): Contractor access to the jobsite and Government premises is prohibited.
1.6 CYBERSECURITY DURING CONSTRUCTION
{For Reference Only: This subpart (and its subparts) relates to AC-18, SA-3, CCI-00258.} Meet the following requirements throughout the construction process.
1.6.1 Contractor Computer Equipment
Contractor owned computers may be used for construction. When used, contractor computers must meet the following requirements:
1.6.1.1 Operating System
The operating system must be an operating system currently supported by the manufacturer of the operating system. The operating system must be current on security patches and operating system manufacturer required updates.
1.6.1.2 Anti-Malware Software
The computer must run anti-malware software from a reputable software manufacturer. Anti-malware software must be a version currently supported by the software manufacturer, must be current on all patches and updates, and must use the latest definitions file. All computers used on this project must be scanned using the installed software at least once per day.
1.6.1.3 Passwords and Passphrases
The passwords and passphrases for all computers must be changed from their
SECTION 01 50 00 Page 3 default values. Passwords must be a minimum of eight characters with a minimum of one uppercase letter, one lowercase letter, one number and one special character.
1.6.1.4 Contractor Computer Cybersecurity Compliance Statements
Provide a single submittal containing completed Contractor Computer Cybersecurity Compliance Statements for each company using contractor owned computers. Contractor Computer Cybersecurity Compliance Statements must use the template published at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs/forms-graphics-tables . Each Statement must be signed by a cybersecurity representative for the relevant company.
1.6.2 Temporary IP Networks
Temporary contractor-installed IP networks may be used during construction.
Provide Government access to Contractor furnished temporary IP networks during construction. When used, temporary contractor-installed IP networks must meet the following requirements:
1.6.2.1 Network Boundaries and Connections
The network must not extend outside the project site and must not connect to any IP network other than IP networks provided under this project or Government furnished IP networks provided for this purpose. Any and all network access from outside the project site is prohibited.
1.6.3 Government Access to Network
Government personnel, as defined, prescribed, and identified by the Contracting Officer, must be allowed to have complete and immediate access to the network at any time in order to verify compliance with this specification. Or if there is a Government agency that's responsible, identify that agency.
1.6.4 Temporary Wireless IP Networks
In addition to the other requirements on temporary IP networks, temporary wireless IP (WiFi) networks must not interfere with existing wireless network and must use WPA2 security. Network names (SSID) for wireless networks must be changed from their default values.
1.6.5 Passwords and Passphrases
The passwords and passphrases for all network devices and network access must be changed from their default values. Passwords must be a minimum 8 characters with a minimum of one uppercase letter, one lowercase letter, one number and one special character.
1.6.6 Contractor Temporary Network Cybersecurity Compliance Statements
Provide a single submittal containing completed Contractor Temporary Network Cybersecurity Compliance Statements for each company implementing a temporary IP network. Contractor Temporary Network Cybersecurity Compliance Statements must use the template published at http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs/ forms-graphics-tables . Each Statement must be signed by a cybersecurity representative for the relevant company. If no temporary IP networks will
SECTION 01 50 00 Page 4 be used, provide a single copy of the Statement indicating this.
PART 2 PRODUCTS
2.1 TEMPORARY SIGNAGE
2.1.1 Bulletin Board
Prior to the commencement of work activities, provide a clear weatherproof covered bulletin board not less than 36 by 48 inches in size for displaying the Equal Employment Opportunity poster, a copy of the wage decision contained in the Contract, Wage Rate Information poster, Safety and Health Information as required by EM 385-1-1 Section 01 and other information approved by the Contracting Officer. Coordinate requirements herein with 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS. Locate the bulletin board at the project site in a conspicuous place easily accessible to all employees, and in location as approved by the Contracting Officer.
2.1.2 Project Identification Signs
The requirements for the signs, their content, and location are as specified in Section 01 58 00 PROJECT IDENTIFICATION. Erect signs within 15 days after receipt of the notice to proceed. Correct the data required by the safety sign daily, with light colored metallic or non-metallic numerals.
2.1.3 Warning Signs
Post temporary signs, tags, and labels to give workers and the public adequate warning and caution of construction hazards according to the EM 385-1-1 Section 04. Attach signs to the perimeter fencing every 150 feet warning the public of the presence of construction hazards. Signs must require unauthorized persons to keep out of the construction site.
Correct the data required by safety signs daily. Post signs at all points of entry designating the construction site as a hard hat area.
2.2 TEMPORARY TRAFFIC CONTROL
2.2.1 Haul Roads
Construct access and haul roads necessary for proper prosecution of the work under this Contract in accordance with EM 385-1-1 Section 04.
Construct with suitable grades and widths; avoid sharp curves, blind corners, and dangerous cross traffic. Submit haul road plan for approval. Provide necessary lighting, signs, barricades, and distinctive markings for the safe movement of traffic. The method of dust control, although optional, must be adequate to ensure safe operation at all times. Location, grade, width, and alignment of construction and haul roads are subject to approval by the Contracting Officer. Lighting must be adequate to assure full and clear visibility for full width of haul road and work areas during any night work operations.
2.2.2 Barricades
Erect and maintain temporary barricades to limit public access to hazardous areas. Barricades are required whenever safe public access to paved areas such as roads, parking areas or sidewalks is prevented by construction activities or as otherwise necessary to ensure the safety of
SECTION 01 50 00 Page 5 both pedestrian and vehicular traffic. Securely place barricades clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night.
2.3 FENCING
Provide fencing along the construction site and at all open excavations and tunnels to control access by unauthorized personnel. Safety fencing must be highly visible to be seen by pedestrians and vehicular traffic.
All fencing must meet the requirements of EM 385-1-1 . Remove the fence upon completion and acceptance of the work.
2.3.1 Polyethylene Mesh Safety Fencing
Temporary safety fencing must be a high visibility orange colored, high density polyethylene grid, a minimum of 48 inches high and maximum mesh size of 2 inches . Fencing must extend from the grade to a minimum of 48 inches above the grade and be tightly secured to T-posts spaced as necessary to maintain a rigid and taut fence. Fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection.
2.3.2 Chain Link Panel Fencing
Temporary panel fencing must be galvanized steel chain link panels 6 feet high. Multiple fencing panels may be linked together at the bases to form long spans as needed. Each panel base must be weighted down using sand bags or other suitable materials in order for the fencing to withstand anticipated winds while remaining upright. Fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection.
2.3.3 Post-Driven Chain Link Fencing
Temporary post-driven fencing must be galvanized chain link fencing 6 feet high supported by an tightly secured to galvanized steel posts driven below grade. Fence posts must be located on minimum 10 foot centers.
Posts may be set in various surfaces such as sand, soil, asphalt or concrete as necessary. Chain link fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection. Completely remove fencing and posts at the completion of construction and restore surfaces disturbed or damaged to its original condition. Locate and identify underground utilities prior to setting fence posts. Equip fence with a lockable gate. Gate must remain locked when construction personnel are not present.
2.4 TEMPORARY WIRING
Provide temporary wiring in accordance with EM 385-1-1 Section 11, NFPA 241 and NFPA 70 . Include monthly inspection and testing of all equipment and apparatus.
2.5 BACKFLOW PREVENTERS
Reduced pressure principle type conforming to the applicable requirements AWWA C511. Provide backflow preventers as required by the local water department and as required by the local water departments hydrant connection permit.
SECTION 01 50 00 Page 6
PART 3 EXECUTION
3.1 EXISTING PARKING
The existing parking for visitors and Government employees cannot be used by the Contractor. No contractor or subcontractor employee parking is available near the immediate facility and no parking on the shoulders of the roads is allowed.
3.2 EMPLOYEE PARKING
Construction Contract employees must park privately owned vehicles in an area designated by the Contracting Officer. Employee parking must not interfere with existing and established parking requirements of the Government installation.
3.3 AVAILABILITY AND USE OF UTILITY SERVICES
3.3.1 Temporary Utilities
Provide temporary utilities required for construction. Materials may be new or used, must be adequate for the required usage, not create unsafe conditions, and not violate applicable codes and standards.
Utilities are available to the Contractor without charge from existing outlets and supplies available to the Government on military installations. Otherwise the contractor shall make arrangements with local utility companies for connection, metering and payment for utilities at its expense. The Contractor shall carefully conserve any utilities furnished without charge. If the use of utilities is abused the Contractor will be required to meter and pay for utilities.
b. The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters where required. The Contractor shall furnish to the Contracting Officer Representative a complete system layout drawing showing type of materials to be used and method of installation for all temporary electrical systems. Telephone service is the responsibility of the Contractor. The Contractor shall maintain all temporary lines in a workmanlike manner satisfactory to the Contracting Officer Representative. Before final acceptance of the work by the Government, the Contractor shall remove all temporary connections, distribution lines, meters and associated paraphernalia. (FAR 52.236-14).
c. Utility Service Interruptions. The Contractor shall submit written notification not less than 15 calendar days in advance of each interruption of each utility and communication service to or within existing buildings and facilities being used by others. No single outage will exceed 4 hours unless approved in writing. The time and duration of all outages will be coordinated with the Using Agency by the Contracting Officer Representative. All outages or interruptions shall be scheduled during weekends, unless specifically approved by the Contracting Officers Representative.
SECTION 01 50 00 Page 7
3.3.2 Sanitation
Provide and maintain within the construction area minimum field-type sanitary facilities in accordance with EM 385-1-1 Section 02. Locate the facilities behind the construction fence or out of the public view. Clean units and empty wastes at least once a week or more frequently into a municipal, district, or Watervliet Arsenal sanitary sewage system, or remove waste to a commercial facility. Keep such places clean and free from flies and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean. Contractor must keep such places clean and be responsible for damages done thereto by Contractor's workmen. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use them.
Obtain approval from the system owner prior to discharge into a municipal, district, or commercial sanitary sewer system. Penalties or fines associated with improper discharge will be the responsibility of the Contractor. Coordinate with the Contracting Officer and follow Watervliet Arsenal regulations and procedures when discharging into the Watervliet Arsenal sanitary sewer system. Maintain these conveniences at all times.
Include provisions for pest control and elimination of odors. Government toilet facilities will not be available to Contractor's personnel.
3.3.3 Telephone
Make arrangements and pay all costs for telephone facilities desired.
3.3.4 Fire Protection
Provide temporary fire protection equipment for the protection of personnel and property during construction in accordance with Section 9 of EM 385-1-1 . The Contractor's means of providing such protection will be included in his safety plan as required by the contract. The plan must include fire exits and access routes during construction and during partial acceptance of the facilities, if required. Remove debris and flammable materials daily to minimize potential hazards.
3.4 TRAFFIC PROVISIONS
3.4.1 Maintenance of Traffic
a. Conduct operations in a manner that will not close a thoroughfare or interfere with traffic on railways or highways except with written permission of the Contracting Officer at least 15 calendar days prior to the proposed modification date, and provide a Traffic Control Plan for Government approval detailing the proposed controls to traffic movement for approval. The plan must be in accordance with State and local regulations and the MUTCD, Part VI. Make all notifications and obtain all permits required for modification to traffic movements outside Watervliet Arsenal's jurisdiction. Contractor may move oversized and slow-moving vehicles to the worksite provided requirements of the highway authority have been met.
b. Conduct work so as to minimize obstruction of traffic, and maintain traffic on at least half of the roadway width at all times. Obtain approval from the Contracting Officer prior to starting any activity that will obstruct traffic.
SECTION 01 50 00 Page 8
c. Provide, erect, and maintain, at Contractor's expense, lights, barriers, signals, passageways, detours, and other items, that may be required by the Life Safety Signage, overhead protection authority having jurisdiction.
d. Provide cones, signs, barricades, lights, or other traffic control devices and personnel required to control traffic. Do not use foil-backed material for temporary pavement marking because of its potential to conduct electricity during accidents involving downed power lines.
3.4.2 Protection of Traffic
Maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer. Measures for the protection and diversion of traffic, including the provision of watchmen and flagmen, erection of barricades, placing of lights around and in front of equipment the work, and the erection and maintenance of adequate warning, danger, and direction signs, will be as required by the State and local authorities having jurisdiction. Provide self-illuminated (lighted) barricades during hours of darkness.
Brightly-colored (orange) vests are required for all personnel working in roadways. Provide self-illuminated (lighted) barricades during hours of darkness. Brightly-colored (orange) vests are required for all personnel working in roadways. Protect the traveling public from damage to person and property. Minimize the interference with public traffic on roads selected for hauling material to and from the site. Investigate the adequacy of existing roads and their allowable load limit. Contractor is responsible for the repair of damage to roads caused by construction operations. When materials are transported in prosecuting the work, vehicles must not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by Federal, State, or local law or regulations. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage.
3.4.3 Rush Hour Restrictions
Do not interfere with the peak traffic flows preceding and during normal operations without notification to and approval by the Contracting Officer.
3.4.4 Dust Control
Dust control methods and procedures must be approved by the Contracting Officer. Coordinate dust control methods with 01 57 19 TEMPORARY
ENVIRONMENTAL CONTROLS.
3.5 REDUCED PRESSURE BACKFLOW PREVENTERS
Provide an approved reduced pressure backflow prevention assembly at each location where the Contractor taps into the Government potable water supply.
Perform backflow preventer tests using test equipment, procedures, and certification forms conforming to those outlined in the latest edition of the Manual of Cross-Connection Control published by the FCCCHR Manual.
Test and tag each reduced pressure backflow preventer upon initial installation (prior to continued water use) and quarterly thereafter. Tag
SECTION 01 50 00 Page 9 must contain the following information: make, model, serial number, dates of tests, results, maintenance performed, and signature of tester.
Record test results on certification forms conforming to requirements cited earlier in this paragraph.
3.6 ACCESS ROADS
3.6.1 Maintenance of Access Roads
a. The Contractor shall be responsible for the maintenance of access roads at the construction site. Maintenance of access roads shall include snow removal. The Contractor shall remove snow piles and rows when they affect safety, hamper emergency and fire vehicles, or block proper drainage.
b. The Contractor shall provide and allow full access to the project site to all traffic, except as noted, to other contractors and authorized personnel as designated by the Contracting Officer.
c. The Contractor shall not inflict damage upon land properties, roads outside the authorized construction areas by unwarranted entry upon, driving over curbs, passage through, damage to or disposal of, material on such land or property, or overloading of roads. The Contractor may make a separate agreement with other parties, regarding the use of, or right to, land or facilities. If such an agreement is made, it shall be in writing and a copy shall be furnished to the Contracting Officer.
The Contractor shall hold and save the Government, its officers and agents free from liability of any nature or kind arising from any trespassing or damage occasioned by Contractor operations.
3.7 CONTRACTOR'S TEMPORARY FACILITIES
Contractor-owned or -leased trailers must be identified by Government assigned numbers. Size and location of the number will comply with installation's guidelines. Contractor shall affix a weather proof card on equipment which states owner's contact phone number and contractor's name. Apply the number to the trailer within 14 calendar days of notification, or sooner, if directed by the Government. Temporary facilities must meet requirements as identified in EM 385-1-1 Section 04.
Contractor is responsible for security of their property. Provide adequate outside security lighting at the temporary facilities. Trailers must be anchored to resist high winds and meet applicable state or local standards for anchoring mobile trailers. Coordinate anchoring with EM 385-1-1 Section 04. The Contract Clause entitled "FAR 52.236-10, Operations and Storage Areas" and the following apply:
3.7.1 Administrative Field Offices
Provide and maintain administrative field office facilities within the construction area at the designated site. Government office and warehouse facilities will not be available to the Contractor's personnel.
3.7.2 Storage Area
Construct a temporary 6 foot high chain link fence around trailers and
SECTION 01 50 00 Page 10 materials. Include plastic strip inserts, colored brown, so that visibility through the fence is obstructed. Fence posts may be driven, in lieu of concrete bases, where soil conditions permit. Do not place or store trailers, materials, or equipment outside the fenced area unless such trailers, materials, or equipment are assigned a separate and distinct storage area by the Contracting Officer away from the vicinity of the construction site but within the installation boundaries. Trailers, equipment, or materials must not be open to public view with the exception of those items which are in support of ongoing work on the current day.
Do not stockpile materials outside the fence in preparation for the next day's work. Park mobile equipment, such as tractors, wheeled lifting equipment, cranes, trucks, and like equipment within the fenced area at the end of each work day.
Keep fencing in a state of good repair and proper alignment. If the Contractor elects to traverse grassed or unpaved areas which are not established roadways with construction equipment or other vehicles, cover the grassed or unpaved areas with a layer of gravel as necessary to prevent rutting and the tracking of mud onto paved or established roadways; gravel gradation must be at the Contractor's discretion.. Mow and maintain grass located within the boundaries of the construction site for the duration of the project. Grass and vegetation along fences, structures, under trailers, and in areas not accessible to mowers must be edged or trimmed neatly.
3.7.3 Supplemental Storage Area
Upon request, and pending availability, the Contracting Officer will designate another or supplemental area for the use and storage of trailers, equipment, and materials. This area may not be in close proximity of the construction site but will be within the installation boundaries. Maintain the area in a clean and orderly fashion and secured if needed to protect supplies and equipment. Utilities will not be provided to this area by the Government.
3.7.4 Appearance of Trailers
a. Trailers must be roadworthy and comply with all appropriate state and local vehicle requirements. Trailers which are rusted, have peeling paint or are otherwise in need of repair will not be allowed on Installation property. Trailers must present a clean and neat exterior appearance and be in a state of good repair.
b. Maintain the temporary facilities. Failure to do so will be sufficient reason to require their removal at the Contractor's expense.
3.7.5 Safety Systems
Protect the integrity of all installed safety systems or personnel safety devices. Obtain prior approval from the Contracting Officer if entrance into systems serving safety devices is required. If it is temporarily necessary to remove or disable personnel safety devices in order to accomplish Contract requirements, provide alternative means of protection prior to removing or disabling any permanently installed safety devices or equipment and obtain approval from the Contracting Officer.
3.7.6 Weather Protection of Temporary Facilities and Stored Materials
Take necessary precautions to ensure that roof openings and other critical
SECTION 01 50 00 Page 11 openings in the building are monitored carefully. Take immediate actions required to seal off such openings when rain or other detrimental weather is imminent, and at the end of each workday. Ensure that the openings are completely sealed off to protect materials and equipment in the building from damage.
3.7.6.1 Building and Site Storm Protection
When a warning of gale force winds is issued, take precautions to minimize danger to persons, and protect the work and nearby Government property.
Precautions must include, but are not limited to, closing openings;
removing loose materials, tools and equipment from exposed locations; and removing or securing scaffolding and other temporary work. Close openings in the work when storms of lesser intensity pose a threat to the work or any nearby Government property.
3.8 GOVERNMENT FIELD OFFICE
3.8.1 Resident Engineer's Office
The Contractor is not required to provide a field office for Government employees.
3.9 PLANT COMMUNICATIONS
Whenever the individual elements of the plant are located so that operation by normal voice between these elements is not satisfactory, install a satisfactory means of communication, such as telephone or other suitable devices and make available for use by Government personnel.
3.10 TEMPORARY PROJECT SAFETY FENCING
As soon as practicable, but not later than 15 days after the date established for commencement of work, furnish and erect temporary project safety fencing at the work site. Maintain the safety fencing during the life of the Contract and, upon completion and acceptance of the work, remove from the work site.
3.11 CLEANUP
Remove construction debris, waste materials, packaging material and the like from the work site daily. Any dirt or mud which is tracked onto paved or surfaced roadways must be cleaned away. Store all salvageable materials resulting from demolition activities within the fenced area described above or at the supplemental storage area. Neatly stack stored materials not in trailers, whether new or salvaged.
3.12 RESTORATION OF STORAGE AREA
Upon completion of the project remove the bulletin board, signs, barricades, haul roads, and all other temporary products from the site.
After removal of trailers, materials, and equipment from within the fenced area, remove the fence. Restore areas used during the performance of the Contract to the original or better condition. Remove gravel used to traverse grassed areas and restore the area to its original condition, including top soil and seeding as necessary.
-- End of Section --
SECTION 01 50 00 Page 12
| 01 50 00 - TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 SUBMITTALS |
| 1.3 CONSTRUCTION SITE PLAN |
| 1.4 BACKFLOW PREVENTERS CERTIFICATE |
| 1.4.1 Backflow Tester Certificate |
| 1.4.2 Backflow Prevention Training Certificate |
| 1.5 DOD CONDITION OF READINESS COR |
| 1.6 CYBERSECURITY DURING CONSTRUCTION |
| 1.6.1 Contractor Computer Equipment |
| 1.6.1.1 Operating System |
| 1.6.1.2 Anti-Malware Software |
| 1.6.1.3 Passwords and Passphrases |
| 1.6.1.4 Contractor Computer Cybersecurity Compliance Statements |
| 1.6.2 Temporary IP Networks |
| 1.6.2.1 Network Boundaries and Connections |
| 1.6.3 Government Access to Network |
| 1.6.4 Temporary Wireless IP Networks |
| 1.6.5 Passwords and Passphrases |
| 1.6.6 Contractor Temporary Network Cybersecurity Compliance Statements |
| PART 2 PRODUCTS |
| 2.1 TEMPORARY SIGNAGE |
| 2.1.1 Bulletin Board |
| 2.1.2 Project Identification Signs |
| 2.1.3 Warning Signs |
| 2.2 TEMPORARY TRAFFIC CONTROL |
| 2.2.1 Haul Roads |
| 2.2.2 Barricades |
| 2.3 FENCING |
| 2.3.1 Polyethylene Mesh Safety Fencing |
| 2.3.2 Chain Link Panel Fencing |
| 2.3.3 Post-Driven Chain Link Fencing |
| 2.4 TEMPORARY WIRING |
| 2.5 BACKFLOW PREVENTERS |
| PART 3 EXECUTION |
| 3.1 EXISTING PARKING |
| 3.2 EMPLOYEE PARKING |
| 3.3 AVAILABILITY AND USE OF UTILITY SERVICES |
| 3.3.1 Temporary Utilities |
| 3.3.2 Sanitation |
| 3.3.3 Telephone |
| 3.3.4 Fire Protection |
| 3.4 TRAFFIC PROVISIONS |
| 3.4.1 Maintenance of Traffic |
| 3.4.2 Protection of Traffic |
| 3.4.3 Rush Hour Restrictions |
| 3.4.4 Dust Control |
| 3.5 REDUCED PRESSURE BACKFLOW PREVENTERS |
| 3.6 ACCESS ROADS |
| 3.6.1 Maintenance of Access Roads |
| 3.7 CONTRACTOR'S TEMPORARY FACILITIES |
| 3.7.1 Administrative Field Offices |
| 3.7.2 Storage Area |
| 3.7.3 Supplemental Storage Area |
| 3.7.4 Appearance of Trailers |
| 3.7.5 Safety Systems |
| 3.7.6 Weather Protection of Temporary Facilities and Stored Materials |
| 3.7.6.1 Building and Site Storm Protection |
| 3.8 GOVERNMENT FIELD OFFICE |
| 3.8.1 Resident Engineer's Office |
| 3.9 PLANT COMMUNICATIONS |
| 3.10 TEMPORARY PROJECT SAFETY FENCING |
| 3.11 CLEANUP |
| 3.12 RESTORATION OF STORAGE AREA |
File details come from the government source that posted it. Updated .