This is a Solicitation (Standard Form 1442) for the Watervliet Arsenal Fire Station Construction Acquisition project located in Watervliet, New York. The U.S. Army Corps of Engineers is seeking a contractor to construct a 32,480 square foot, two-story fire station with three company bays, 21 dormitory rooms, administrative offices, dispatch areas, training rooms, fitness facilities, and associated infrastructure. The project will include vehicle apparatus bays, utilities, access roads, parking, and information systems.
The solicitation is a single-step best value trade-off procurement with 100% unrestricted full and open competition and a HUBZone preference. The contract is firm-fixed-price with a total contract duration of 730 calendar days, and the estimated project cost range is between $35 million and $75 million. Proposals are due by 2:00 PM EST on August 11, 2025, and all offerors must submit a Project Labor Agreement with their proposals. The contract will be awarded using a best value source selection process that evaluates technical factors and price, with technical factors being approximately equal in importance to price.
View the file
Other files for this federal contract opportunity
Show all 46
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR
INFORMATION CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF PAGES
AWARD (To be completed by Government)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES
CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Section 00 00 00 - Procurement and Contracting Requirements
WVA Fire Station Construction Acquisition
W912DS25RA009
Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN) Schedule
Additional Information/Notes
Item Supplies/Service Quantity Unit Unit Price Amount
3 CO FIRE STATION: All work (includes all plant, labor, and material) associated with the construction of the facility as described in the plans and specifications except for work included in items below.
Pricing Arrangement: Firm Fixed Price
1 Job
3 CO FIRE STATION: All work for the Final Record Drawing Submission (See Section 01 78 00).
Pricing Arrangement: Firm Fixed Price
1 Job
Option Line Item
3 CO FIRE STATION: All work associated with the construction of the Training Mezzanine above the slab, as listed on sheets S-107, S-108, S-201 and S-503. (Base bid will cover work associated with training mezzanines footing and foundation).
CLIN 0003 may be exercised at any time within 240 calendar days after notice to proceed (NTP).
Pricing Arrangement: Firm Fixed Price
1 Job
Option Line Item
3 CO FIRE STATION: All work (includes all plant, labor, and material) for the landscape plans as indicated in sheet L-101.
CLIN
0004 may be exercised at any time within 240 calendar days after notice to proceed (NTP).
Pricing Arrangement: Firm Fixed Price
1 Job
W912DS25RA009
$40,000.00
Section 00 20 00 - Instructions for Procurements
TOTAL BASE BID (SUM of CLINs 0001 through 0002)
TOTALOPTIONAL ITEMS (SUM of CLINs 0003 through 0004)
TOTAL BASE BID PLUS OPTIONAL ITEMS (SUM OF CLINs 0001 through0004)
NOTES:
(1) Total Offer shall include all costs associated with each item number including all overhead, bonding, and profit.
(2) Offerors must submit a price for every CLIN. Failure to do so may result in an Offer being unacceptable.
(3) Contract duration is 730 calendar days.
(4) CLIN 0002 is pre-priced at $40,000.00 and this price shown may not be changed. See Section 01 78 00 for Final Record Drawing definition and requirement.
(5) CLIN 0003-0004: may be exercised at any time within 240 calendar days after notice to proceed (NTP). The Contracting Officer may exercise the Optional Item(s) by written notice to the Contractor within the time period specified above. The period of performance of the contract will not be extended with the exercise of the Optional Item.
(6) Offer Acceptance Period: Offers are to be valid for 120 days.
IMPORTANT: A PROJECT LABOR AGREEMENT MUST BE SUBMITTED BY ALL OFFERORS WITH THEIR PROPOSALS! This project is subject to the Project Labor Agreement (PLA) requirements of Executive Order 14063. See FAR provision 52.222-33, Notice of Requirement for Project Labor Agreement, and clause 52.222-34, Project Labor Agreement, for definitions and requirements pertaining to the use of a PLA for this contract.
Section 00 21 00 - Instructions
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) - ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for Monday, 21 July, 2025 at 1000.
Participants will meet at:
Watervliet Arsenal Watervliet, New York 12189 At the corner of Dalleba St. and Farley Dr. (see map).
All requests must be in NLT 1000 EST Thursday, 17 Jul 2025 to be approved in time for the visit. Please anticipate up to two (2) hours on day of site visit to clear the WVA security background check at the South Gate Visitor's center. Also, all visitors will need to bring proper ID and PPE (hard hat, eyeglasses, safety shoes) to access the project area. Due to WVA security requirements, no photographic documentation will be permitted.
Photographs may be taken by the Government as per request during the site visit. Site visit photos taken by the Government and the sign in sheet will be posted as a solicitation amendment to the original solicitation announcement.
Email all requests to both Odile Accilien-Sorger and Kaitlyn Hughes, site visit POCs listed on the form.
POC: Odile Accilien-Sorger, Project Manager Email: odile.accilien-sorger@usace.army.mil Office Phone: (518) 266-6376 Mobile Phone: (845) 293-7983
POC: Katie Hughes, Technical Manager Email: kaitlin.t.hughes@usace.army.mil Office Phone: (917) 790-8293
(End of provision)
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
52.204-7 System for Award Management. Nov 2024 52.204-16 Commercial and Government Entity Code Reporting. Aug 2020 52.204-22 Alternative Line Item Proposal. Jan 2017 52.214-34 Submission of Offers in the English Language. Apr 1991 52.214-35 Submission of Offers in U.S. Currency. Apr 1991 52.215-1 Instructions to Offerors-Competitive Acquisition. Nov 2021
52.215-20 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data.
Nov 2021
52.222-5 Construction Wage Rate Requirements-Secondary Site of the Work. May 2014 52.225-12 Notice of Buy American Requirement-Construction Materials Under Trade Agreements. May 2014 52.232-28 Invitation to Propose Performance-Based Payments. Mar 2000
DFARS Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
252.204-7019 Notice of NIST SP 800-171 DoD Assessment Requirements. Nov 2023 252.204-7024 Notice on the Use of the Supplier Performance Risk System. Mar 2023 252.215-7013 Supplies and Services Provided by Nontraditional Defense Contractors. Jan 2023 252.215-7016 Notification to Offerors-Postaward Debriefings. Dec 2022
FAR Clauses Incorporated by Full Text
52.216-1 Type of Contract. (Apr 1984)
Type of Contract (Apr 1984)
The Government contemplates award of a contract resulting from this solicitation.Firm Fixed Price
(End of provision)
52.233-2 Service of Protest. (Sep 2006)
Service of Protest (Sept 2006)
Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that (a) are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from District Contracting Chief, New York District Directorate of Contracting U.S. Army Corps of Engineers
. Nicholas.P.Emanuel@usace.army.mil
The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.(b)
(End of provision)
52.252-1 Solicitation Provisions Incorporated by Reference. (Feb 1998)
Solicitation Provisions Incorporated by Reference (Feb 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
https://www.acquisition.gov.far
(End of provision)
52.252-3 Alterations in Solicitation. (Apr 1984)
Alterations in Solicitation (Apr 1984)
Portions of this solicitation are altered as follows:
(End of clause)
52.252-5 Authorized Deviations in Provisions. (Nov 2020)
Authorized Deviations in Provisions (Nov 2020)
The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the (a) addition of "(DEVIATION)" after the date of the provision.
The use in this solicitation of any Defense Federal Acquisition Regulation Supplement (48 CFR Chapter ) provision with an authorized deviation (b) 1 is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of provision)
DFARS Clauses Incorporated by Full Text
252.215-7008 Only One Offer. (Dec 2022)
ONLY ONE OFFER (DEC 2022)
(a) Cost or pricing data requirements. After initial submission of offers, if the Contracting Officer notifies the Offeror that only one offer was
W912DS25RA009
https://www.acquisition.gov.far received, the Offeror agrees to-
(1) Submit any additional cost or pricing data that is required in order to determine whether the price is fair and reasonable (10 U.S.C. 3705) or to comply with the statutory requirement for certified cost or pricing data (10 U.S.C. 3702 and FAR 15.403-3); and
(2) Except as provided in paragraph (b) of this provision, if the acquisition exceeds the certified cost or pricing data threshold and an exception to the requirement for certified cost or pricing data at FAR 15.403-1(b)(2) through (5) does not apply, certify all cost or pricing data in accordance with paragraph (c) of DFARS provision 252.215-7010, Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data, of this solicitation.
(b) Canadian Commercial Corporation. If the Offeror is the Canadian Commercial Corporation, certified cost or pricing data are not required. If the Contracting Officer notifies the Canadian Commercial Corporation that additional data other than certified cost or pricing data are required in accordance with DFARS 225.870-4(c), the Canadian Commercial Corporation shall obtain and provide the following:
(1) Profit rate or fee (as applicable).
(2) Analysis provided by Public Works and Government Services Canada to the Canadian Commercial Corporation to determine a fair and reasonable price (comparable to the analysis required at FAR 15.404-1).
(3) Data other than certified cost or pricing data necessary to permit a determination by the U.S. Contracting Officer that the proposed price is fair and reasonable ____[U.S. Contracting Officer to provide description of the data required in accordance with FAR 15.403-3(a)(1) with the notification].
(4) As specified in FAR 15.403-3(a)(4), an offeror who does not comply with a requirement to submit data that the U.S. Contracting Officer has deemed necessary to determine price reasonableness or cost realism is ineligible for award unless the head of the contracting activity determines that it is in the best interest of the Government to make the award to that offeror.
(c) Subcontracts. Unless the Offeror is the Canadian Commercial Corporation, the Offeror shall insert the substance of this provision, including this paragraph (c), in all subcontracts exceeding the simplified acquisition threshold defined in FAR part 2.
(End of provision)
1.
2.
Section 00 21 16 - Instructions to Proposers
CPARS
The Federal Acquisition Regulation (FAR) requires that Past Performance Information (PPI) be collected on DoD contracts. The Contractor Performance Assessment Reporting System (CPARS) is a web-enabled application that supports the completion, distribution, and retrieval of all contract performance evaluations. Contractor Representatives are responsible for reviewing and commenting on evaluations submitted on the Contractor Performance Assessment Reporting System (CPARS) website at https://www.cpars.gov/
AT/OPSEC
1. AT Level I Training.
This provision/contract text is for contractor employees with an area of performance within an Army-controlled installation, facility, or area. All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, or controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever applies. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee to the COR (or to the contracting officer, if a COR is not assigned) within 30 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at https://jkodirect.jten.mil
19. AT Level 1 training (general).
21b. For contractor not eligible for CAC, but requires access to a DoD facility or installation.
E VERIFY
The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/everify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award." *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative.
This Form will be provided to the Contracting Officer and shall become part of the official contract file.
IWATCH (See Something, Say Something) training.
25. Impact of FPCON changes on contract performance or implementation during periods of increased threat.
26. Random Antiterrorism Measures Program or participation in All Hazards/Annual AT/Force Protection Exercise.
INSTRUCTIONS TO OFFERORS
NOTICE REGARDING BID BONDS, PEFORMANCE BONDS, AND PAYMENT BONDS
The Standard Forms (SF24, SF25, and SF25A) for these bonds have been revised and can be found using the search at https://www.gsa.gov /reference/forms#
When including your bid/offer, contractors/sureties shall use the revised versions. No other version will be valid and thus may render your bid /offer non-compliant.
Past Performance Information
Please answer the following questions:
- In the past 3 years, have you:
Ever received a cure notice?
W912DS25RA009
https://www.cpars.gov/ https://jkodirect.jten.mil
2.
3.
4.
5.
Had LDs assessed?
Received show cause notice?
Had a non-responsibility determination?
If so, please provide the name of the project, the client, and date of action.
BIDDER INQUIRIES
INQUIRIES
Submission of inquiries will open on 11 July 2025. Please submit technical inquiries and questions relating to this solicitation via email to denisse.m.
soto@usace.army.mil and Nicholas.P.Emanuel@usace.army.mil. Submission of inquires will close 28 July 2025 11:59AM EDT. The Government reserves the right to decline addressing questions received after this date. If an Offeror believes that the requirement in this solicitation contains an error, omission, or are otherwise unsound; immediately notify the Contract Specialist in writing with supporting rationale. The Government reserves the right to award this contract based on the initial bid, as received, without discussions. A prospective vendor who submits a comment or question will receive an acknowledgement via e-mail, followed by an answer after it has been processed by our technical team. All timely questions and approved answers will be made available through an amendment which will be posted on sam.gov as soon as the comment/question entering period is over and answers are all finalized.
ELECTRONIC BID SUBMISSION
ELECTRONIC PROPOSALS
(a) Definition.
Electronic proposal, as used in this provision, means a proposal, revision or modification of a proposal, or withdrawal of a proposal that is transmitted to and received by the Government via electronic commerce (see FAR Subpart 4.5 -- Electronic Commerce in Contracting).
(b) Offerors may submit electronic proposals as responses to this solicitation. Electronic proposals are subject to the same rules as paper proposals.
(c) The format for electronic proposals in this solicitation is: PDF documents sent via email, ONLY to the Contract Specialist and Contracting Officer, as listed below:
Denisse Soto: Email Address: Denisse.M.Soto@usace.army.mil
Nicholas Emanuel: Email Address: nicholas.p.emanuel@usace.army.mil
(d) If any portion of an electronic proposal received by the Contracting Officer is unreadable to the degree that conformance to the essential requirements of the solicitation cannot be ascertained from the document --
(1) The Contracting Officer immediately shall notify the offeror and permit the offeror to resubmit the proposal;
(2) The method and time for resubmission shall be prescribed by the Contracting Officer after consultation with the offeror; and
(3) The resubmission shall be considered as if it were received at the date and time of the original unreadable submission for the purpose of determining timeliness, provided the offeror complies with the time and format requirements for resubmission prescribed by the Contracting Officer.
(e) The Government reserves the right to make award solely on the electronic proposal. However, if requested to do so by the Contracting Officer, the apparently successful offeror promptly shall submit the complete original signed proposal.
ELECTRONIC PROPOSAL SUBMISSION
Submit proposals no later than 2:00PM EST on 11 August 2025 via e-mail to:
Denisse.M.Soto@usace.army.mil nicholas.p.emanuel@usace.army.mil
File size is limited to 25MB per email. It is advised to submit e-mail 2 hours in advance to ensure the proposal is submitted timely.
(End of Provision)
Section 00 22 00 - Supplementary Instructions
BASIS OF AWARD
Please see the attached document titled "Basis of award - W912DS25RA009"
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
52.217-4 Evaluation of Options Exercised at Time of Contract Award. Jun 1988
Section 00 45 00 - Representations and Certifications
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment.
Nov 2021
52.204-29 Federal Acquisition Supply Chain Security Act Orders-Representation and Disclosures. Dec 2023 52.209-7 Information Regarding Responsibility Matters. Oct 2018 52.209-13 Violation of Arms Control Treaties or Agreements-Certification. Nov 2021 52.229-12 Tax on Certain Foreign Procurements. Feb 2021 52.236-28 Preparation of Proposals-Construction. Oct 1997
DFARS Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
252.203-7005 Representation Relating to Compensation of Former DoD Officials. Sep 2022 252.204-7008 Compliance with Safeguarding Covered Defense Information Controls. Oct 2016
252.204-7017 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services-Representation.
May 2021
252.225-7055 Representation Regarding Business Operations with the Maduro Regime. May 2022
252.225-7057 Preaward Disclosure of Employment of Individuals Who Work in the People's Republic of China.
Aug 2022
252.225-7059 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region- Representation.
Jun 2023
DFARS Clauses Incorporated by Full Text
252.204-7007 Alternate A, Annual Representations and Certifications. (Oct 2024) Alternate A (Oct 2024)
ALTERNATE A, ANNUAL REPRESENTATIONS AND CERTIFICATIONS (OCT 2024)
Substitute the following paragraphs (b), (d), and (e) for paragraphs (b) and (d) of the provision at FAR 52.204-8:
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (e) of this provision applies.
(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (e) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
[ ] (i) Paragraph (e) applies.
[ ] (ii) Paragraph (e) does not apply and the Offeror has completed the individual representations and certifications in the solicitation.
(d)(1) The following representations or certifications in the SAM database are applicable to this solicitation as indicated:
(i) 252.204-7016, Covered Defense Telecommunications Equipment or Services-Representation. Applies to all solicitations.
(ii) 252.216-7008, Economic Price Adjustment-Wage Rates or Material Prices Controlled by a Foreign Government. Applies to solicitations for fixed-price supply and service contracts when the contract is to be performed wholly or in part in a foreign country, and a foreign government controls wage rates or material prices and may during contract performance impose a mandatory change in wages or prices of materials.
(iii) 252.225-7042, Authorization to Perform. Applies to all solicitations when performance will be wholly or in part in a foreign country.
(iv) 252.225-7049, Prohibition on Acquisition of Certain Foreign Commercial Satellite Services-Representations. Applies to solicitations for the acquisition of commercial satellite services.
(v) 252.225-7050, Disclosure of Ownership or Control by the Government of a Country that is a State Sponsor of Terrorism. Applies to all solicitations expected to result in contracts of $150,000 or more.
(vi) 252.229-7012, Tax Exemptions (Italy)-Representation. Applies to solicitations and contracts when contract performance will be in Italy.
(vii) 252.229-7013, Tax Exemptions (Spain)-Representation. Applies to solicitations and contracts when contract performance will be in Spain.
(2) The following representations or certifications in SAM are applicable to this solicitation as indicated by the Contracting Officer: [Contracting Officer check as appropriate.]
[ ](i) 252.209-7002, Disclosure of Ownership or Control by a Foreign Government.
[ ](ii) 252.225-7000, Buy American-Balance of Payments Program Certificate.
[ ](iii) 252.225-7020, Trade Agreements Certificate.
[ ] Use with Alternate I.
[ ](iv) 252.225-7031, Secondary Arab Boycott of Israel.
[ ](v) 252.225-7035, Buy American-Free Trade Agreements-Balance of Payments Program Certificate.
[ ] Use with Alternate I.
[ ] Use with Alternate II.
[ ] Use with Alternate III.
[ ] Use with Alternate IV.
[ ] Use with Alternate V.
[ ](vi) 252.226-7002, Representation for Demonstration Project for Contractors Employing Persons with Disabilities.
[ ](vii) 252.232-7015, Performance-Based Payments-Representation.
(e) The Offeror has completed the annual representations and certifications electronically via the SAM website at https://www.sam.gov. After reviewing the SAM database information, the Offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in FAR 52.204-8(c) and paragraph (d) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer, and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [Offeror to insert changes, identifying change by provision number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.
FAR/DFARS Provision # Title Date Change
Any changes provided by the Offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications located in the SAM database.
(End of provision)
Section 00 70 00 - Conditions of the Contract
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
52.215-1 Instructions to Offerors-Competitive Acquisition. (Alternate I) Nov 2021 Alternate I Oct 1997 52.219-9 Small Business Subcontracting Plan. (Alternate II) Jan 2025 Alternate II Nov 2016 52.222-3 Convict Labor. Jun 2003 52.222-7 Withholding of Funds. May 2014 52.232-27 Prompt Payment for Construction Contracts. Jan 2017 52.232-39 Unenforceability of Unauthorized Obligations. Jun 2013 52.233-1 Disputes. May 2014 52.233-3 Protest after Award. Aug 1996 52.233-4 Applicable Law for Breach of Contract Claim. Oct 2004 52.236-2 Differing Site Conditions. Apr 1984 52.236-3 Site Investigation and Conditions Affecting the Work. Apr 1984 52.236-5 Material and Workmanship. Apr 1984 52.236-6 Superintendence by the Contractor. Apr 1984 52.236-7 Permits and Responsibilities. Nov 1991 52.236-8 Other Contracts. Apr 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. Apr 1984 52.236-10 Operations and Storage Areas. Apr 1984 52.236-11 Use and Possession Prior to Completion. Apr 1984 52.236-12 Cleaning Up. Apr 1984 52.236-13 Accident Prevention. Nov 1991 52.236-15 Schedules for Construction Contracts. Apr 1984 52.236-17 Layout of Work. Apr 1984 52.236-21 Specifications and Drawings for Construction. Feb 1997 52.236-26 Preconstruction Conference. Feb 1995
52.240-1 Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American Security Drone Act-Covered Foreign Entities.
Nov 2024
52.242-13 Bankruptcy. Jul 1995 52.242-14 Suspension of Work. Apr 1984 52.243-4 Changes. Jun 2007 52.247-68 Report of Shipment (REPSHIP). Feb 2006 52.249-2 Termination for Convenience of the Government (Fixed-Price). Apr 2012 52.249-10 Default (Fixed-Price Construction). Apr 1984
DFARS Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
252.226-7003 Drug-Free Work Force. Aug 2024 252.235-7003 Frequency Authorization. (Alternate I) Mar 2014 Alternate I Mar 2014
FAR Clauses Incorporated by Full Text
52.232-5 Payments under Fixed-Price Construction Contracts. (May 2014)
Payments under Fixed-Price Construction Contracts (May 2014)
(a) Payment of price. The Government shall pay the Contractor the contract price as provided in this contract.
(b) Progress payments. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.
(1) The Contractor's request for progress payments shall include the following substantiation:
(i) An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.
(ii) A listing of the amount included for work performed by each subcontractor under the contract.
(iii) A listing of the total amount of each subcontract under the contract.
(iv) A listing of the amounts previously paid to each such subcontractor under the contract.
(v) Additional supporting data in a form and detail required by the Contracting Officer.
(2) In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be taken into consideration. Material delivered to the Contractor at locations other than the site also may be taken into consideration if-
(i) Consideration is specifically authorized by this contract; and
(ii) The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract.
(c) Contractor certification. Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made: (However, if the Contractor elects to delete paragraph (c)(4) from the certification, the certification is still acceptable.)
I hereby certify, to the best of my knowledge and belief, that-
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;
(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
(4) This certification is not to be construed as final acceptance of a subcontractor's performance.
____ (Name)
____ (Title)
____ (Date)
(d) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall-
(1) Notify the Contracting Officer of such performance deficiency; and
(2) Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8 thday after the date of receipt of the unearned amount until-
(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or
(ii) The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.
(e) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.
(f) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as-
(1) Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or
(2) Waiving the right of the Government to require the fulfillment of all of the terms of the contract.
(g) Reimbursement for bond premiums. In making these progress payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (e) of this clause shall not apply to that portion of progress payments attributable to bond premiums.
(h) Final payment. The Government shall pay the amount due the Contractor under this contract after-
(1) Completion and acceptance of all work;
(2) Presentation of a properly executed voucher; and
(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor's claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of1940 (31 U.S.C.3727 and 41 U.S.C.6305).
(i) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A "contract action" is any action resulting in a contract, as defined in FAR subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.
(j) Interest computation on unearned amounts. In accordance with 31 U.S.C.3903(c)(1), the amount payable under paragraph (d)(2) of this clause shall be-
(1) Computed at the rate of average bond equivalent rates of 91-day Treasury bills auctioned at the most recent auction of such bills prior to the date the Contractor receives the unearned amount; and
(2) Deducted from the next available payment to the Contractor.
(End of clause)
52.236-1 Performance of Work by the Contractor. (Apr 1984)
Performance of Work by the Contractor (Apr 1984)
The Contractor shall perform on the site, and with its own organization, work equivalent to at least percent of the total amount 20% (twenty percent) of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.
(End of clause)
52.248-3 Value Engineering-Construction. (Oct 2020)
Value Engineering-Construction (Oct 2020)
(a) General. The Contractor is encouraged to develop, prepare, and submit value engineering change proposals (VECP's) voluntarily. The Contractor shall share in any instant contract savings realized from accepted VECP's, in accordance with paragraph (f) of this clause.
(b) Definitions. "Collateral costs," as used in this clause, means agency costs of operation, maintenance, logistic support, or Government-furnished property.
Collateral savings, as used in this clause, means those measurable net reductions resulting from a VECP in the agency's overall projected collateral costs, exclusive of acquisition savings, whether or not the acquisition cost changes.
Contractor's development and implementation costs, as used in this clause, means those costs the Contractor incurs on a VECP specifically in developing, testing, preparing, and submitting the VECP, as well as those costs the Contractor incurs to make the contractual changes required by Government acceptance of a VECP.
Government costs, as used in this clause, means those agency costs that result directly from developing and implementing the VECP, such as any net increases in the cost of testing, operations, maintenance, and logistic support. The term does not include the normal administrative costs of processing the VECP.
Instant contract savings, as used in this clause, means the estimated reduction in Contractor cost of performance resulting from acceptance of the VECP, minus allowable Contractor's development and implementation costs, including subcontractors' development and implementation costs (see paragraph (h) of this clause).
Value engineering change proposal (VECP) means a proposal that-
(1) Requires a change to this, the instant contract, to implement; and
(2) Results in reducing the contract price or estimated cost without impairing essential functions or characteristics; provided, that it does not involve a change-
(i) In deliverable end item quantities only; or
(ii) To the contract type only.
(c) VECP preparation. As a minimum, the Contractor shall include in each VECP the information described in paragraphs (c)(1) through (7) of this clause. If the proposed change is affected by contractually required configuration management or similar procedures, the instructions in those procedures relating to format, identification, and priority assignment shall govern VECP preparation. The VECP shall include the following:
(1) A description of the difference between the existing contract requirement and that proposed, the comparative advantages and disadvantages of each, a justification when an item's function or characteristics are being altered, and the effect of the change on the end item's performance.
(2) A list and analysis of the contract requirements that must be changed if the VECP is accepted, including any suggested specification revisions.
(3) A separate, detailed cost estimate for (i) the affected portions of the existing contract requirement and (ii) the VECP. The cost reduction associated with the VECP shall take into account the Contractor's allowable development and implementation costs, including any amount attributable to subcontracts under paragraph (h) of this clause.
(4) A description and estimate of costs the Government may incur in implementing the VECP, such as test and evaluation and operating and support costs.
(5) A prediction of any effects the proposed change would have on collateral costs to the agency.
(6) A statement of the time by which a contract modification accepting the VECP must be issued in order to achieve the maximum cost reduction, noting any effect on the contract completion time or delivery schedule.
(7) Identification of any previous submissions of the VECP, including the dates submitted, the agencies and contract numbers involved, and previous Government actions, if known.
(d) Submission. The Contractor shall submit VECP's to the Resident Engineer at the worksite, with a copy to the Contracting Officer.
(e) Government action.
(1) The Contracting Officer will notify the Contractor of the status of the VECP within 45 calendar days after the contracting office receives it. If additional time is required, the Contracting Officer will notify the Contractor within the 45-day period and provide the reason for the delay and the expected date of the decision. The Government will process VECP's expeditiously; however, it will not be liable for any delay in acting upon a VECP.
(2) If the VECP is not accepted, the Contracting Officer will notify the Contractor in writing, explaining the reasons for rejection. The Contractor may withdraw any VECP, in whole or in part, at any time before it is accepted by the Government. The Contracting Officer may require that the Contractor provide written notification before undertaking significant expenditures for VECP effort.
(3) Any VECP may be accepted, in whole or in part, by the Contracting Officer's award of a modification to this contract citing this clause. The Contracting Officer may accept the VECP, even though an agreement on price reduction has not been reached, by issuing the Contractor a notice to proceed with the change. Until a notice to proceed is issued or a contract modification applies a VECP to this contract, the Contractor shall perform in accordance with the existing contract. The decision to accept or reject all or part of any VECP is a unilateral decision made solely at the discretion of the Contracting Officer.
(f) Sharing-
(1) Rates. The Government's share of savings is determined by subtracting Government costs from instant contract savings and multiplying the result by-
(i) 45 percent for fixed-price contracts; or
(ii) 75 percent for cost-reimbursement contracts.
(2) Payment. Payment of any share due the Contractor for use of a VECP on this contract shall be authorized by a modification to this contract to-
(i) Accept the VECP;
(ii) Reduce the contract price or estimated cost by the amount of instant contract savings; and
(iii) Provide the Contractor's share of savings by adding the amount calculated to the contract price or fee.
(g) Collateral savings. If a VECP is accepted, the Contracting Officer will increase the instant contract amount by 20 percent of any projected collateral savings determined to be realized in a typical year of use after subtracting any Government costs not previously offset. However, the Contractor's share of collateral savings will not exceed the contract's firm-fixed-price or estimated cost, at the time the VECP is accepted, or $100,000, whichever is greater. The Contracting Officer is the sole determiner of the amount of collateral savings.
(h) Subcontracts. The Contractor shall include an appropriate value engineering clause in any subcontract of $75,000 or more and may include one in subcontracts of lesser value. In computing any adjustment in this contract's price under paragraph (f) of this clause, the Contractor's allowable development and implementation costs shall include any subcontractor's allowable development and implementation costs clearly resulting from a VECP accepted by the Government under this contract, but shall exclude any value engineering incentive payments to a subcontractor. The Contractor may choose any arrangement for subcontractor value engineering incentive payments; provided, that these payments shall not reduce the
Government's share of the savings resulting from the VECP.
(i) Data. The Contractor may restrict the Government's right to use any part of a VECP or the supporting data by marking the following legend on the affected parts:
These data, furnished under the Value Engineering-Construction clause of contract ____, shall not be disclosed outside the Government or duplicated, used, or disclosed, in whole or in part, for any purpose other than to evaluate a value engineering change proposal submitted under the clause. This restriction does not limit the Government's right to use information contained in these data if it has been obtained or is otherwise available from the Contractor or from another source without limitations.
If a VECP is accepted, the Contractor hereby grants the Government unlimited rights in the VECP and supporting data, except that, with respect to data qualifying and submitted as limited rights technical data, the Government shall have the rights specified in the contract modification implementing the VECP and shall appropriately mark the data. (The terms "unlimited rights" and "limited rights" are defined in part 27 of the Federal Acquisition Regulation.)
(End of clause)
52.252-2 Clauses Incorporated by Reference. (Feb 1998)
Clauses Incorporated By Reference (Feb 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
https://www.acquisition.gov.far
(End of clause)
52.252-4 Alterations in Contract. (Apr 1984)
Alterations in Contract (Apr 1984)
Portions of this contract are altered as follows:
(End of clause)
52.252-6 Authorized Deviations in Clauses. (Nov 2020)
Authorized Deviations in Clauses (Nov 2020)
The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated(a) by the addition of "(DEVIATION)" after the date of the clause.
The use in this solicitation or contract of any Defense Federal Acquisition Regulation (48 CFR ) clause with an authorized deviation is(b) _ _201 indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of clause)
W912DS25RA009
https://www.acquisition.gov.far
Section 00 72 00 - General Conditions
WAGE RATES
SEE ATTACHED PDF
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may because for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000.00, whichever is less.-
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of provision)
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
52.202-1 Definitions. Jun 2020 52.203-3 Gratuities. Apr 1984 52.203-5 Covenant Against Contingent Fees. May 2014 52.203-6 Restrictions on Subcontractor Sales to the Government. Jun 2020 52.203-7 Anti-Kickback Procedures. Jun 2020 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity. May 2014 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .