This document is an electrical plan for Building 01W, Level 00G, part of the EHRM Infrastructure Upgrades project at the VA Huntington facility located at 1540 Spring Valley Drive, Huntington, West Virginia. The drawing (01WEP100G) is dated 100% Construction Documents as of September 3, 2025, and was prepared by SPEES Design Build under the U.S. Department of Veterans Affairs, Office of Construction and Facilities Management.

The electrical plan shows the ground floor layout of Building 01W with detailed depictions of power distribution systems, including A-side and B-side power sourcing (both concealed and underground/underfloor routing), transformers (XFMR-1W-TWR2A and XFMR-1W-TWR2B), enclosed circuit breakers, humidifier units, and connections to various building zones including medical offices, nursing areas, volunteer spaces, employee union areas, and telecommunications equipment rooms. Key construction requirements include: coordination with the VA regarding electrical system shutdowns and essential equipment backup power; demolition of equipment and raceways associated with removed walls; sealing of wall and ceiling penetrations to maintain fire ratings; pull box placement for feeders exceeding 250 feet or having more than 270 degrees of total bend; conduit expansion couplings at building expansion joints; bonding of tower structural steel to existing building steel with #3/0 copper conductors; and provision of updated circuit panel directories for all impacted panels. The contractor must field-verify all existing power, lighting, and associated circuitry and coordinate all work with architectural, structural, and trade drawings.

View the file

Other files for this federal contract opportunity

Other files attached to EHRM Huntington VAMC 581-22-700 Construct Infrastructure Upgrades, newest first.
File Type Posted
S06 - 36C77626R0025 0008.pdf PDF
S06 - Amendment 0008 - ATT 3 - Civil OSP Redesign-signed.pdf PDF
S06 - Amendment 0008 - ATT 7 - 02EP100B - ELECTRICAL 20260413.pdf PDF
S06 - Amendment 0008 - ATT 8 - 260508 - Sheet 01S-AE452 TR Tower 4 Wall sections update.pdf PDF
S06 - Amendment 0008 - ATT 12 - Environmental Report Huntington WV.pdf PDF
S06 - Amendment 0008 - ATT 13 - Hot Tapping Permit.pdf PDF
S06 - Amendment 0008 - ATT 1 - TechQuestionsVAresponses Final Set - Huntington EHRM IU.pdf PDF
S06 - Amendment 0008 - ATT 10 - 260508 - Sheet AD103-1B Data Center Phase 1B Demo Roof update.pdf PDF
S06 - Amendment 0008 - ATT 11 - Burn Permit.pdf PDF
S06 - Amendment 0008 - ATT 14 - Energized Electrical Work Permit.pdf PDF
S06 - 36C77626R0025 0007.pdf PDF
S06 - Amendment 0007 - ATT 1 - TechQuestionsVAresponses Partial 4 - Huntington EHRM IU.pdf PDF
S06 - Amendment 0007 - ATT 5 - Appendix A - PFC FPT.pdf PDF
S06 - 36C77626R0025 0006.pdf PDF
S06 - Amendment 0006 - ATT 1 - TechQuestionsVAresponses Partial 3 - Huntington EHRM IU.pdf PDF
S06 - 36C77626R0025 0005.pdf PDF
S06 - Amendment 0004 - ATT 2 - FAR 52.222-90 ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS - APR 2026.pdf PDF
S06 - Amendment 0004 - ATT 1 - TechQuestionsVAresponses Partial 2 - Huntington EHRM IU.pdf PDF
S06 - 36C77626R0025 0004.pdf PDF
S06 - Amendment 0003 - ATT 2 - TechQuestionsVAresponses Partial - Huntington EHRM IU.pdf PDF
S06 - 36C77626R0025 0003.pdf PDF
S06 - 36C77626R0025 0002.pdf PDF
S06 - Amendment 0001 - ATT 1 - Site Visit In-Sheet - Huntington EHRM IU.pdf PDF
S06 - 36C77626R0025 0001.pdf PDF
S02 - ATT 10 - 581-22-700 - 100 Drawings Part-8 of 24.pdf PDF
S02 - ATT 14 - 581-22-700 - 100 Drawings Part-12 of 24.pdf PDF
S02 - ATT 27 - 581-22-700 - Asbestos locations.xlsx XLSX spreadsheet
S02 - ATT 28 - 581-22-700 - FLS Compliance Letter.pdf PDF
S02 - 36C77626R0025.pdf PDF
S02 - ATT 1 - 581-22-700 - 100 Specifications Part-1 of 2.pdf PDF
S02 - ATT 2 - 581-22-700 - 100 Specifications Part-2 of 2.pdf PDF
S02 - ATT 9 - 581-22-700 - 100 Drawings Part-7 of 24.pdf PDF
S02 - ATT 11 - 581-22-700 - 100 Drawings Part-9 of 24.pdf PDF
S02 - ATT 15 - 581-22-700 - 100 Drawings Part-13 of 24.pdf PDF
S02 - ATT 18 - 581-22-700 - 100 Drawings Part-16 of 24.pdf PDF
S02 - ATT 20 - 581-22-700 - 100 Drawings Part-18 of 24.pdf PDF
S02 - ATT 23 - 581-22-700 - 100 Drawings Part-21 of 24.pdf PDF
S02 - ATT 24 - 581-22-700 - 100 Drawings Part-22 of 24.pdf PDF
S02 - ATT 30 - 581-22-700 - 100 Commissioning Plan.pdf PDF
S02 - ATT 3 - 581-22-700 - 100 Drawings Part-1 of 24.pdf PDF
S02 - ATT 4 - 581-22-700 - 100 Drawings Part-2 of 24.pdf PDF
S02 - ATT 5 - 581-22-700 - 100 Drawings Part-3 of 24.pdf PDF
S02 - ATT 6 - 581-22-700 - 100 Drawings Part-4 of 24.pdf PDF
S02 - ATT 7 - 581-22-700 - 100 Drawings Part-5 of 24.pdf PDF
S02 - ATT 17 - 581-22-700 - 100 Drawings Part-15 of 24.pdf PDF
S02 - ATT 19 - 581-22-700 - 100 Drawings Part-17 of 24.pdf PDF
S02 - ATT 22 - 581-22-700 - 100 Drawings Part-20 of 24.pdf PDF
S02 - ATT 26 - 581-22-700 - 100 Drawings Part-24 of 24.pdf PDF
S02 - ATT 33 - WD - WV20260048 - 01-02-2026.pdf PDF
S02 - ATT 35 - Site Visit Information - Huntington EHRM IU.pdf PDF
Show all 50

EHRM Huntington VAMC 581-22-700 Construct Infrastructure Upgrades has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PB

BB

BBBBBBBBB

B

B

B

B

B

B

B

B

BB

BB

A

A

A

A

A

A

A

A

A

A

A

A

A

A

AA

AA

BBBBBBB

BB

BB

B

B

B

BBB

B

AAAAAAA

AAAAAAA

A A

B B

A A

B B

AREA SHOWN

1W-6

1W-5

B L D

G

S E

E S

H E

E T

E

P G

B L D

G

W

REF02

01WEP400Ga

ELEC. EQUIP.

GC149

IRM

GC150

ELEC.

GC151a

HBPC

GC151

HBPC

GC152

ISO OFFICE

GC153

MID SOUTH CPAC

GC157

MID SOUTH CPAC

GC158

HAC

GC159MY HLTH VET

GC165

VOLUNTEER

GC164

VOLUNTEER

GC163A

VOLUNTEER

GC163

EMPLOYEE UNION

GC145

LRC

GC145A

LRC

GC154

MIDSOUTH CPAC

GC155

NURSING

GC156

NURSING

GC160

TELEHEALTH

GC161

TELEHEALTH

GC162

EMPLOYEE UNION

GC146

M FOSTER HM OFFICE

GC143

HBPC OFFICE

GC144

HBPC OFFICE

HBPC PHARM OFFICE

GC142

HBPC OFFICE

GC140

HBPC OFFICE

GC139

HBPC DIETICIAN OFFICE

GC138

STOR

GC135

EMPLOYEE UNION

GC141A

NURSING

GC166

STOR

GC141B

ELEV

W-1

ELEV

W-2

MECH. EQUIP

GC148

STAIR 12

GC148

STAFF RESTROOM

GC137

STAFF RESTROOM

GC136

VESTIBULE

GC167

OBVER.ROOM

GC150

SIMULATION LAB

GC169

GC128h

GC128i

GC128f

GC128g

PRIVACY

GC134

TR TOWER 2

T2-00G

T2-A

T2-B

T2-1

01W-P-10A

01W-P-11A

01W-P-02A

01WEP400Ga

EXISTING HOUSEKEEPING PAD

HOUSEKEEPING PAD

1W-LSGA

1W-CPGA SEC.1

1W-CPGA SEC.2

XFMR '1W-CPGA'

DISCONNECT

HUMIDIFIER UNIT 01W-P-01A

01WEP400Gb

01WEP400Gb

01W-P-01B

ENCLOSED CIRCUIT BREAKER

"ECB-XFMR-1W-TWR2B"

TRANSFORMER 'XFMR-1W-TWR2A'

TRANSFORMER 'XFMR-1W-TWR2B'

EXISTING

HOUSEKEEPING PAD

5 PB-1

01W-P-10B

ENCLOSED CIRCUIT BREAKER

"ECB-XFMR-1W-TWR2A"

BLDG 01

BLDG 02

BLDG 01W

BLDG 01SBLDG 23R

BLDG 23

BLDG 01A

BLDG 12

A SIDE POWER, CONCEALED WHERE POSSIBLE

B SIDE POWER, CONCEALED WHERE POSSIBLE

A SIDE POWER, UNDERGROUND / UNDERFLOOR

B SIDE POWER, UNDERGROUND / UNDERFLOOR

PROVIDED TO INDICATE 'A' AND 'B' SIDE SOURCED POWER FEEDERS.

REFERENCE GENERAL SYMBOL LEGEND FOR ADDITIONAL

INFORMATION.

LEGEND

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of

Construction and Facilities

Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ENGINEERING DISCIPLINE:

SPEES DESIGN BUILD

23830 PACIFIC HIGHWAY S. SUITE 300

KENT, WA 98032

/0

/2

:4

:2 a m

B

IM

/5

-2

-7

V A

H u n t i n g to n E

H R

M /E

E

B L D

G

G R

O U

N D

F L

O O

R .r v t

01WEP100G

BLDG 01W - LEVEL 00G - ELECTRICAL PLAN

01W

DCW/NVP RTS/JNV

100% CONSTRUCTION

DOCUMENTS

09/03/2025

581-22-700EHRM INFRASTRUCTURE

UPGRADES - HUNTINGTON

VA HUNTINGTON

1540 SPRING VALLEY DRIVE, HUNTINGTON, WV 25704-9300

PROJECT

NORTH

1" = 10'-0"

BLDG 01W - LEVEL 00G - ELECTRICAL PLAN

ES101

1 8'0 16' 32'

PROJECT

NORTH

CONDUIT CONTINUES TO BUS DUCT CONNECTION BOX. BUS DUCT EXTENDS

VERTICALLY THROUGH STACKED TRS. REFERENCE SHEET 01WEP400G AND

ENLARGED ELECTRCIAL PLANS 01WEP401, 01WEP402, AND 01WEP403 FOR

ADDITIONAL INFORMATION.

PROVIDE TBB AS INDICATED; WHERE CONDUCTOR IS SUBJECT TO PHYSICAL DAMAGE,

CONDUCTOR SHALL BE ROUTED THROUGH RMC. REFERENCE TELECOMMUNICATIONS

BONDING RISER DIAGRAM ON SHEET EG602 FOR ADDITIONAL INFORMATION.

REFERENCE PHOTO DETAIL '1' ON SHEET EP501 FOR ADDITIONAL INFORMATION.

REFERENCE PHOTO DETAIL '2' ON SHEET EP501 FOR ADDITIONAL INFORMATION.

PROVIDE PULL BOX AND MOUNTING HARDWARE FOR CONDUCTOR PULLING MEANS.

LABEL PULL BOX WITH EQUIPMENT NAME IT IS SERVING. REFERENCE TYPICAL PULL

BOX SCHEDULE ON SHEET EP701 FOR ADDITIONAL INFORMATION.

GENERAL NOTES

KEY PLAN

KEY NOTES

1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR SHALL

FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS REQUIRED. ALL

RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT TO BE DEMOLISHED

SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS OTHERWISE NOTED.

2. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS, AND

RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND, IN ALL LOCATIONS,

WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER INSTALLATION,

UNLESS OTHERWISE NOTED.

3. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM

SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED

EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY POWER

AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT. POWER TO

ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND SHALL REMAIN

ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN SHALL CONFORM WITH

VA STANDARDS.

4. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE

RATING OR NEW FIRE RATING; PROVIDE CORE DRILLING AS REQUIRED. COORDINATE

WITH ARCHITECTURAL AND STRUCTURAL DRAWINGS AS REQUIRED.

5. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL INFORMATION.

6. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL

PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.

7. CONTRACTOR SHALL PROVIDE PULL BOXES FOR ALL FEEDERS WHERE FEEDER RUNS

EXCEED 250FT OR HAVE MORE THAN 270 DEGREES OF TOTAL BEND. PULL BOX

PLACEMENT AND SIZING BY CONTRACTOR. COORDINATE PULL BOX LOCATIONS WITH

ALL OBSTRUCTIONS, TRADES, AND VA AS REQUIRED.

8. CONDUIT EXPANSION COUPLINGS ARE REQUIRED WHEN CONDUIT IS ROUTED

ACROSS BUILDING EXPANSION JOINTS. REFERENCE DETAIL '1' ON SHEET EP509 FOR

ADDITIONAL INFORMATION.

9. ALL RACEWAYS SHALL BE ROUTED ABOVE ACCESSIBLE CEILING, WHERE PRESENT,

UNLESS OTHERWISE NOTED.

Revisions: Date:

Addendum 1: Pre Bid RFIs 4/13/2026

PROVIDE UFER CONDUCTOR AND BONDING OF TOWER STRUCTURAL STEEL TO EXISTING

BUILDING STRUCTURAL STEEL WITH #3/0 COPPER; ALL CONNECTION POINTS SHALL BE

ACCESSIBLE. WHERE EXISTING BUILDING GROUND RING EXISTS, CONTRACTOR SHALL

MATCH EXISTING CONDUCTOR SIZE AND EXTEND RING AROUND TOWER FOOTING.

File details come from the government source that posted it. Updated .