S06 - Amendment 0008 - ATT 5 - ELECTRICAL 2026.04.13.pdf
PDF 1 MB Posted
- Attached to
- EHRM Huntington VAMC 581-22-700 Construct Infrastructure Upgrades Federal contract opportunity
- Solicitation number
- 36C77626R0025
About this file
This is an electrical plan drawing for Building 01S, Level 00G (ground floor) at the VA Huntington facility located at 1540 Spring Valley Drive, Huntington, WV 25704. The drawing is part of the EHRM Infrastructure Upgrades project (IM 360://581-22-700) and was issued at 100% construction document phase on September 3, 2025. The plan depicts the electrical distribution system for the ground floor of Building 01S, including power routing, panel locations, and equipment connections serving medical and administrative spaces such as examination rooms, audiology facilities, geriatric patient care units, pharmacy, walk-in clinics, and various support functions.
Key construction requirements include: contractor field verification of all existing power, lighting, and circuitry; demolition of equipment and raceways associated with removed walls; coordination with VA prior to electrical system shutdowns; provision of backup emergency power to maintain uninterrupted service to essential equipment; sealing of all interior penetrations to match fire ratings; and provision of updated circuit panel directories. The contractor must provide pull boxes for feeders exceeding 250 feet or with more than 270 degrees of total bend, route raceways above accessible ceilings where present, and provide UFER grounding and bonding of tower structural steel to existing building steel using #3/0 copper conductors. The plan references corresponding one-line diagrams, typical pull box schedules, and detailed sheets for TR Tower routing and expansion joint details. The project involves both A-side and B-side power sourcing distributed through concealed raceways and underground/underfloor feeders as indicated in the legend.
View the file
Other files for this federal contract opportunity
Show all 50
EHRM Huntington VAMC 581-22-700 Construct Infrastructure Upgrades has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PB
PB
PB
A A
AA
A A A A A A A A
A
A
B
B
B
B
B
B
B
B
A A A A A AB B
B B B
B B B B
A A
B B
A A
B B
AREA SHOWN
J K L M N O P Q R S T U V W X Y
01SEP400Ga
01SEP400Ga
B L D
G
A
B L D
G
B L D
G
S
B L D
G
S E
E S
H E
E T
E
P G
BLDG 01S
BLDG 12
B L D
G
01SEP400Gb
01SEP400Gb
GB160
PUBLIC ELEV.
P3
PUBLIC ELEV.
P2
PUBLIC ELEV.
P1
MEN
GB174
STAIR 1
LINEN
GB169
HAC
GB170
GB173
PUBLIC LOBBY
CG19
TELE.
GB171
ELEC.
GB172
SERVICE ELEV.
S1
SERVICE ELEV.
S2
SERVICE LOBBY
CG17
GB168g
BVA
GB168c
IRM
GB168a
EXAM
GB168k
FEE CLAIMS
GB168b
BOOTH
EXAMINER
GB168j
GB168l
GB168
GB168i
GB168h
MEDICAL RECORDS
GB168d
GB168f
GB168e
STAIR 4
MECH RM
GB167
HEALTH TECH
GB149c
HEALTH TECH
GB149d
EXAM
GB149e
EXAM
GB149fEXAM
GB149g
AUDIOLOGY ROOM
GB149
RECEP
GB148
OFFICE
GB148a
OFFICE
GB148b
OFFICE
GB146
TLT
GB145
CERUMEN MGMT
GB147b
TLT
GB144
GB143
HAC
GB142
GERI PACT
GB151
GERI PACT
GB152
GB140
GB141
STORAGE
GB141a
CLEAN SUPPLY
GB139
PALL CARE
GB138
PALL CARE
GB137
GERI PACT
GB153
GERI PACT
GB154
EXAM 8
GB136
PHARM
GB135
AMCARE ADMIN
GB150
AMCARE
GB150A
AMCARE ADMIN
GB168rr
GERI PACT
GB155H
CORRIDOR
CG11
CORRIDOR
CG13
CORRIDOR
CG10
EXAM 7
GB134
EXAM 6
GB133
WALK IN CLINIC
GB156
EXAM 15
EXAM 4
GB132
LOUNGE
GB129
WALK IN CLINIC
GB158
GB127
GB130
EXAM 5
GB131
CORRIDOR
CG16
AMCARE ADMIN
GB155b
AMCARE
GB155G
EXAM 5
GB155F
VAPD
GB155c
VAPD
GB165
AMCARE ADMIN
CG24
VAPD
GB164
GB159
GB161
EXAMINER
GB149h
EXAMINER
GB149i
BOOTH
BOOTH
BOOTH
ELEC.
GB166b
TEL
GB166a
EXAMINER
GB149j
POSTIOGRAPHY & LAB
GA121
CORRIDOR
CG14
CORRIDOR
CG15
STAIR 3
STAIR 2
MECH
GB166
BLDG 01A: SEE SHEET 01AEP100G
WOMEN
GB175
PANEL 'RPN-GC'
PANEL 'LPN-GC1'
TR TOWER 4
T4-00G
TR TOWER 1
T1-00G
FROM SHEET 01SEP100B
01S-P-DCA
01S-P-DCB
FROM SHEET 01SEP100B
TE
1S_RPN-GA
1S_LPN-GA
1S_RCP-GA
1S_MCC-NGA
1S_LPC-GB
1S_LPN-GB
1S_LPS-GB
1S_RPN-GB
1S_RPC-GB
1S_RPS-GB
XFMR'S (ABOVE)
01-FA-01
PB-1
PB-13
TO SHEET
01AEP100G
3 PB-2
BLDG 01
BLDG 02
BLDG 01W
BLDG 01SBLDG 23R
BLDG 23
BLDG 01A
BLDG 12
A SIDE POWER, CONCEALED WHERE POSSIBLE
B SIDE POWER, CONCEALED WHERE POSSIBLE
A SIDE POWER, UNDERGROUND / UNDERFLOOR
B SIDE POWER, UNDERGROUND / UNDERFLOOR
PROVIDED TO INDICATE 'A' AND 'B' SIDE SOURCED POWER FEEDERS.
REFERENCE GENERAL SYMBOL LEGEND FOR ADDITIONAL
INFORMATION.
LEGEND
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of
Construction and Facilities
Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
SPEES DESIGN BUILD
23830 PACIFIC HIGHWAY S. SUITE 300
KENT, WA 98032
/0
/2
:4
:0 a m
B
IM
/5
-2
-7
V A
H u n t i n g to n E
H R
M /E
E
B L D
G
G R
O U
N D
F L
O O
R .r v t
01SEP100G
BLDG 01S - LEVEL 00G - ELECTRICAL PLAN
01S
DCW/NVP RTS/JNV
100% CONSTRUCTION
DOCUMENTS
09/03/2025
581-22-700EHRM INFRASTRUCTURE
UPGRADES - HUNTINGTON
VA HUNTINGTON
1540 SPRING VALLEY DRIVE, HUNTINGTON, WV 25704-9300
PROJECT
NORTH
3/32" = 1'-0"
BLDG 01S - LEVEL 00G - ELECTRICAL PLAN
ES101
1 0 20' 40'10'
PROJECT
NORTH
GENERAL NOTES
KEY PLAN
KEY NOTES
1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR SHALL
FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS REQUIRED. ALL
RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT TO BE DEMOLISHED
SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS OTHERWISE NOTED.
2. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS, AND
RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND, IN ALL LOCATIONS,
WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER INSTALLATION,
UNLESS OTHERWISE NOTED.
3. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM
SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED
EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY POWER
AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT. POWER TO
ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND SHALL REMAIN
ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN SHALL CONFORM WITH
VA STANDARDS.
4. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE
RATING OR NEW FIRE RATING; PROVIDE CORE DRILLING AS REQUIRED. COORDINATE
WITH ARCHITECTURAL AND STRUCTURAL DRAWINGS AS REQUIRED.
5. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL INFORMATION.
6. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL
PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.
7. CONTRACTOR SHALL PROVIDE PULL BOXES FOR ALL FEEDERS WHERE FEEDER RUNS
EXCEED 250FT OR HAVE MORE THAN 270 DEGREES OF TOTAL BEND. PULL BOX
PLACEMENT AND SIZING BY CONTRACTOR. COORDINATE PULL BOX LOCATIONS WITH
ALL OBSTRUCTIONS, TRADES, AND VA AS REQUIRED.
8. CONDUIT EXPANSION COUPLINGS ARE REQUIRED WHEN CONDUIT IS ROUTED
ACROSS BUILDING EXPANSION JOINTS. REFERENCE DETAIL '1' ON SHEET EP509 FOR
ADDITIONAL INFORMATION.
9. ALL RACEWAYS SHALL BE ROUTED ABOVE ACCESSIBLE CEILING, WHERE PRESENT,
UNLESS OTHERWISE NOTED.
1 TR TOWER 1: FEEDERS ROUTE THROUGH VERTICALLY STACKED TR TOWER.
REFERENCE SHEET 01SEP401a AND ENLARGED PLANS 01SEP402a, 01SEP403a, 01SEP404a, 01SEP405a FOR ADDITIONAL INFORMATION.
TR TOWER 4: FEEDERS ROUTE THROUGH VERTICALLY STACKED TR TOWER.
REFERENCE SHEET 01SEP401b AND ENLARGED PLANS 01SEP402b, 01SEP403b, 01SEP404b, 01SEP405b FOR ADDITIONAL INFORMATION.
PROVIDE PULL BOX AND MOUNTING HARDWARE FOR CONDUCTOR PULLING MEANS.
LABEL PULL BOX WITH EQUIPMENT NAME IT IS SERVING. REFERENCE TYPICAL PULL
BOX SCHEDULE ON SHEET EP701 FOR ADDITIONAL INFORMATION.
REFERENCE GENERAL NOTE '7' ON THIS SHEET FOR PULL BOX REQUIREMENTS.
Revisions: Date:
Addendum 1: Pre Bid RFIs 4/13/2026
PROVIDE UFER CONDUCTOR AND BONDING OF TOWER STRUCTURAL STEEL TO EXISTING
BUILDING STRUCTURAL STEEL WITH #3/0 COPPER; ALL CONNECTION POINTS SHALL BE
ACCESSIBLE. WHERE EXISTING BUILDING GROUND RING EXISTS, CONTRACTOR SHALL
MATCH EXISTING CONDUCTOR SIZE AND EXTEND RING AROUND TOWER FOOTING.
File details come from the government source that posted it. Updated .