This is a Technical Questions and Responses Tracking Sheet for federal solicitation 36C77626R0025 for the EHRM Construct Infrastructure Upgrade in Huntington, West Virginia. The document consists of 85 substantive questions from contractors and corresponding answers from the VA, with questions numbered 86-150 left blank.
The responses address critical design and construction requirements across multiple disciplines. Key technical clarifications include: deep foundations using micropiles for all three telecom tower structures (T1, T2, T3); shallow foundations for the MCR addition; blast exemption for towers; firestopping by UL or FM Global certified contractors only; Category 6A cabling installation with specific fiber route separation requirements (50 feet minimum between A and B side fibers when entering patient-serving buildings, 10 feet inside buildings); EMT conduit for horizontal fiber runs with J-hooks as acceptable alternate when EMT is not achievable; and a 10 percent allowance of 2-port work area outlets for VA discretionary use. Contractor responsibilities include complete NFPA fire sprinkler design with hydraulic calculations and flow testing for both data center and telecom room modifications, independent testing and balancing by certified TAB contractors, seismic delegated design with engineer-stamped calculations submitted for approval, and integration of new HVAC and security systems into existing campus infrastructure. The responses confirm contractor furnishing and installation of all mechanical equipment including UPS systems, precision cooling units, and rack power distribution units, with specific electrical requirements referenced on detailed drawings (EP500 and EP400 series). Notable scope exclusions include post-tension slab penetration restrictions (none identified in existing structures) and additional waterproof membrane at mud slab (not required). The document serves as clarification of contract requirements for bidding purposes on this healthcare facility infrastructure project.
View the file
Other files
Show 40 more
Latest 50 of 68 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL QUESTIONS AND SOLICITATION #: 36C77626R0025
RESPONSES TRACKING SHEET PROJECT TITLE: EHRM Construct Infrastructure Upgrade – Huntington, WV
# CONTRACTOR QUESTION VA RESPONSE
1 IBC Chapter 14, does not provide provisions for LRFD loads. Table 1810.3.2.6 provides capacities based on allowable stresses for materials used in deep foundation elements, please provide the ASD loads.
We will provide ASD loads
2 Please confirm all EHRM blast requirements of been incorporated into the new data center and TR tower designs.
Towers have not been designed for blast and it was determined they are except from blast loads.
3 Specification: 07 84 00 Topic: Firestopping Confirm that all firestopping shall be done by a UL or FM Global certified contractor.
Confirmed - All firestopping shall be done by a UL or FM Global certified contractor.
4 Sheet: A-603 Specification: 09 22 16 Topic: Non-structural wall types Please provide stud & top/bottom track thickness/gauge as well as spacing for all wall types shown on A-603.
5 Sheet: N/A Specification:
10 26 00 Topic: Wall protection Architectural plans do not indicate wall protection scope (corner guards, handrails, etc.) Please confirm that this specification can be omitted.
AE clarifies that this spec cannot be omitted, TR towers require wall protection scope
6 Sheet: TNG001 Specification: 27 15 13 Topic: Allowance WAOs General note 38 states that we are to include an additional 10% of the total number of WAOs, to be used an allowance.
Please confirm these allowance WAOs are to be 2-port outlets.
These are to be 2 port WAOs.
7 Sheet: TNG001 Specification: 27 15 13 Topic: Allowance WAOs For allowance WAOs, please confirm that these will not be replacing existing WAOs and that new conduit and backboxes will be required.
The Contractor needs to include in their bid an additional 10% of the total of all WAOs in the project. These will be used at the discretion of the VA. That will include new WAO locations as well as existing WAO locations.
8 Sheet: S-002 Specification: 01 45 35 Topic: Special inspections Please confirm that an SIOR will be required to oversee the inspections indicated in section 01 45 35.
Confirmed
9 Sheet: N/A Specification:
10 26 00 Topic: Wall protection Architectural plans do not indicate wall protection scope (corner guards, handrails, etc.) Please confirm that this specification can be omitted.
AE clarifies that this spec cannot be omitted, TR towers require wall protection scope
10 A-side and B-side fiber route diversity criteria:
Please define the minimum acceptable physical separation and route independence between A-side and B-side fiber pathways, including whether shared corridors, sleeves, pull points, rooms, trays, or risers are permitted, so the contractor has a clear design and pricing basis for compliance.
The A and B side fibers when entering a Patient serving Building, must be separated by a minimum of 50 feet. Once inside the Building, a separation of at least 10 feet must be maintained. If that separation within the Building is not feasible, the A and B sides must be separated as much as possible. In a non Patient servind Building, The A and B sdie fibers can reside within the same ductbank but NOT within the same conduit. The Contractor shall verify that these are geodiverse in non Patient serving buildings, other wise a separate duct bank will be required.
11 Assumption for project cabling removal:
For bidding purposes, please confirm that all existing Category 6 and lower cabling identified for replacement under this project shall be completely removed, including all associated abandoned devices, terminations, and cabling within the affected rooms, pathways, ceilings, and telecommunications spaces. Please confirm that this removal scope shall be used as the basis for bidder pricing.
The Contractor is required to remove all unused cabling below category 6 back to source. This includes termination points, cable support, abandoned cable tray and conduits. Exception is that the conduits going from above the ACT to the outlet box are to remain and a blank plate shall be placed over the Box for future use. Devices such as telephones, computers, WAPs etc. are NOT to be removed.
12 Reuse of vacated pathway capacity:
For bidding purposes, please confirm whether bidders may rely on reuse of pathway capacity created by removal of existing project cabling.
If reuse is not permitted, or if pathway fill conditions cannot be verified prior to demolition, please confirm whether new raceway is required.
The Contractor shall reuse raceways where existing cabling is to be or has been removed such as cable tray and conduits. The Contractor cannot exceed the 40% fill ratio in any new or existing pathways. J hooks are an acceptable cable support method.
13 Division ownership of communications outlet backboxes and raceway from outlet to accessible ceiling space:
Section 26 05 33 requires complete raceway systems for all wiring, Section 27 05 33 states that all conduit, fittings, and boxes to form raceway systems for communications cabling will be provided by the contractor, and the telecommunications drawings require a new 1- 1/4 inch conduit from new backbox to accessible ceiling space where an existing data outlet does not exist. Please confirm which specification division is intended to furnish and install the communications outlet backbox, outlet box/device ring, conduit stub, and raceway from the communications outlet to accessible ceiling space for new or relocated Division 27 outlets.
Division 27 05 33.
14 Division ownership of communications pull boxes, conduit bodies, and sleeves required solely for Division 27 pathway routing:
The telecommunications drawings require pull boxes at 100-foot intervals and require conduits and sleeves as needed for routing and installation of horizontal and backbone cabling. Please confirm which specification division is intended to furnish and install pull boxes, conduit bodies, horizontal sleeves, vertical sleeves, and similar pathway appurtenances required solely to route Division 27 horizontal and backbone communications cabling between work area outlets, telecommunications rooms, entrance rooms, TDU spaces, and MDA spaces.
Sheet TNG001 note 19 establishes the pull boxes and requirements for the Division 27 category 6A cabling.
15 Division ownership of fire-stop sleeves and firestopping associated only with communications penetrations:
The telecommunications drawings require fire-stop sleeves, require A-side and B-side sleeves to be separated by at least 10 feet, and require fire-stop materials in and around conduit for communications pathway penetrations. Please confirm which specification division is intended to furnish and install the fire-stop sleeves and associated firestopping for penetrations made solely for Division 27 communications raceways and cabling.
Division 27 05 33 Conduits and Backboxes for Communications Systems shall be used for Fire stop sleeves. Also please see sheet 01STN400Ba detail 4 as an example. Further, Specificatin Section 07 84 00 Firestopping shall provide guidance for the requirements of firestopping around any penetrations.
16 Division ownership of communications cable tray, ladder rack, tray dividers, and segregation hardware:
The telecommunications drawings require wire basket cable tray, fiber backbone cable tray above the horizontal distribution tray, and tray dividers as needed to segregate data cabling from security, fire alarm, nurse call, and other special systems. Please confirm which specification division is intended to furnish and install communications cable tray, ladder rack, tray supports, tray dividers, and other pathway segregation hardware serving Division 27 cabling within telecommunications rooms, entrance rooms, MDA/TDU spaces, and the data center.
Specification Section 27 05 33 and 27 05 36 both govern the requirements for this project.
17 Division ownership of rack-mounted telecom power protection equipment:
Section 27 11 26 states that all power distribution and interconnections supporting equipment deployed in telecommunications spaces will be provided by the contractor and includes zone PDUs, rack-mounted UPS units, and rack PDUs.
Please confirm whether Division 27 is intended to furnish and install all zone PDUs, rack-mounted UPS units, rack PDUs, interconnecting cords, and other rack-level power protection devices within telecommunications rooms and the data center, with Division 26 limited to building power infrastructure upstream of that equipment unless otherwise noted.
Specification section 27 11 26 applies to all TR locations. Division 26 33 53 applies to UPS support systems for the
MCR.
18 Division ownership of access control panels and ESS equipment located inside telecommunications rooms and data center spaces:
The telecommunications room drawings and data center drawings show access control panels located within telecom spaces, and certain room keynotes require a complete access control panel system including required connections, programming, power supplies, and components. Please confirm whether Division 28 is intended to furnish, install, program, test, and commission all access control panels, ESS control equipment, and associated low-voltage cabling located inside telecommunications rooms and the data center, even where those items are shown on Division 27 telecommunications drawings.
These locations are reflected on the TN sheets for clarity. Division 28 Specifications provide requirements for the provision and install of the equipment.
19 Division ownership of telecommunications and
ESS
bonding interfaces in telecom rooms and the data center:
The grounding plans show secondary bonding busbars, relocated SBBs, SBCs, bonds to overhead cable tray, and a bond to electro-static discharge flooring in the data center, while communications and ESS specifications separately address grounding and bonding. Please confirm which specification division is intended to furnish, install, and test telecommunications bonding busbars, secondary bonding busbars, telecommunications grounding conductors, bonds to cable tray, ESS equipment bonds, relocated SBBs, SBCs, and the bond to the electrostatic discharge flooring in the telecommunications rooms and the data center
Division 27 05 26 and 28 05 26 govern the gronding and bonding for inside the TRs. The grounding of the Antistatic flooring is the responsibility of the flooring Contractor.
20 Acceptable manufacturers and equivalency criteria:
Please identify all acceptable manufacturers for rack power distribution units and provide the specific equivalency criteria required for approval of products other than the named APC basis of design. Please also identify any required performance characteristics, features, certifications, or compatibility requirements that must be met for an alternate manufacturer to be considered acceptable.
Any rack PDU manufacturer as long as it meets the contract document requirements. APC RPDU AP8861 or equivalent is noted as basis of design.
21 Basis of bid and approval of alternate manufacturers:
Please confirm whether bidders may include rack power distribution units from manufacturers other than the named APC basis of design in the base bid without prior approval. If prior approval is required, please identify the required pre-bid approval process and timing.
Any rack PDU manufacturer as long as it meets the contract document requirements. APC RPDU AP8861 or equivalent is noted as basis of design.
22 A-side and B-side receptacle requirements:
Please define the exact required quantity of A-side and B- side source receptacles, branch circuits, and rack-mounted power devices per rack or enclosure for each room type. Please clarify whether these quantities are required per rack, per cabinet, or per room, and identify any required redundancy, diversity, or spare capacity that must be included in the design.
Reference electrical details (EP500 series) for rack configuration and power requirements. Reference enlarged electrical floor plans (EP400 series) for quantity of racks.
23 Basis of bid for rack power distribution:
Please confirm the bid basis bidders are to use for rack power distribution, including the assumed number of A-side and B-side receptacles, branch circuits, and rack power devices per rack or enclosure.
Reference electrical details (EP500 series) for rack configuration and power requirements. Reference enlarged electrical floor plans (EP400 series) for quantity of racks.
24 TR Tower 2 pressure relationship:
Please confirm the required pressure relationship for the TR Tower 2 construction zone relative to the adjacent occupied spaces and identify any required monitoring, alarms, or daily documentation associated with maintaining that pressure relationship.
During Constructruction, the TR Tower 2 construction zone shall be negatively pressurized. A/E recommends -0.01
in. wc relative to the adjacent occupied spaces. See specification section 01 35 26 for specific requirements.
25 TR Tower 2 exhaust discharge location:
Please confirm the permitted temporary exhaust discharge location for TR Tower 2 construction and identify whether any temporary ducting, weather protection, filtration, or relocation of the exhaust point is required during the work.
The Contractor is responsible to coordinate an acceptable exhaust discharge location for TR Tower 2 with VA COR.
See specification section 01 35 26 for specific requirements.
26 TR Tower 2 restoration scope:
Please clarify the full restoration scope required after removal of temporary ICRA barriers, doors, tacky mats, exhaust setups, and related temporary conditions at TR Tower 2, including finishes, patching, repainting, and adjacent-area repairs.
AE clarifies that all repairs, finishing, patching after removal of ICRA Barriers, doors, tacky mats, exhaust setups, and related temporary conditions are to match exisiting.
27 TR Tower 3 temporary barrier and door rating:
Please confirm whether the temporary ICRA barrier and temporary door assembly at TR Tower 3 must match the adjacent permanent fireresistance requirements or only the temporary ratings explicitly noted on the architectural sheets.
AE confirms only the tempoary ratings explicitly noted on the architectural sheets
28 TR Tower 3 restoration scope:
Please clarify the full restoration scope required after removal of temporary barriers, doors, tacky mats, temporary finishes, and related temporary construction elements at TR Tower 3, including repairs to adjacent occupied areas.
AE clarifies that all repairs, finishing, patching after removal of ICRA Barriers, doors, tacky mats, exhaust setups, and related temporary conditions are to match exisiting.
29 Warranty preservation requirements for roof work:
Please identify all warranty preservation requirements for roof penetrations and patches, including whether the work must be performed by the existing roofing installer, a manufacturer-authorized subcontractor, or another approved specialty installer.
Defer to VA Station for roof manufacturer and warranty information
30 Restoration responsibility for temporary access Alterations:
If temporary access alterations are permitted, please identify the full restoration responsibility, including architectural, structural, waterproofing, security, and finish restoration required to return the altered conditions to final contract requirements.
AE identifies 100% responsibility to return the altered conditions to final contract requirements
31 Weather protection requirements for temporary access alterations:
If temporary access alterations are permitted, please identify all required temporary weather protection, water protection, thermal protection, and temporary enclosure requirements during construction
AE identifies 100% responsibility to return the altered conditions to final contract requirements
32 Infection-control requirements for temporary access alterations:
If temporary access alterations are permitted, please identify all infection-control, containment, pressure relationship, cleaning, and monitoring requirements that apply to those access modifications and the adjacent occupied areas.
AE identifies 100% responsibility to return the altered conditions to final contract requirements
33 Foundation type bid basis
— MCR addition:
Please confirm the required bid basis foundation system for the MCR building addition. The current geotechnical report states the MCR addition is expected to use shallow spread foundations bearing on bedrock. Please confirm whether shallow spread footings bearing on bedrock is the governing foundation type bidders are to carry for the MCR structure, identify the required minimum bearing elevation, and clarify whether any condition not explicitly covered in the geotechnical report is to be priced by analogy or by another stated basis. Please also confirm that any foundation type change directed after award, or any subsurface condition that requires a different foundation system than the stated bid basis, will be treated as a change to the contract reviewed and confirmed by the structural engineer of record, entitling the contractor to an equitable adjustment under FAR 52.243-4 Changes for
Structural confirms the use of shallow foundations.
all resulting cost and schedule impacts.
34 Foundation type bid basis
— telecom tower Structures:
Please confirm the required bid basis foundation system for each telecom tower structure. The current geotechnical report states that deep foundations, with micropiles and drilled shafts identified as options, are planned for TR1 and TR2, and that TR3 is also recommended for deep foundations due to lack of subsurface information at the final structure location.
Please identify the governing foundation type bidders are to carry for each tower structure, and clarify whether any tower structure not explicitly covered in the geotechnical report is to be priced by analogy or by another stated basis.
Please also confirm that any subsurface or geotechnical conditions encountered during construction at any tower location that materially differ from those depicted in the geotechnical report will be treated as Type I or Type II differing site conditions under FAR 52.236-2 Differing Site Conditions, entitling the contractor to an equitable adjustment for all resulting cost and schedule impacts, Structural confirms T1, T2, And T3 are to be supported on Micropiles.
and that any foundation type change directed by the geotechnical engineer of record or structural engineer of record during construction will be treated as a change to the contract.
35 Indoor vertical fiber risers inside buildings:
Please confirm whether all new vertical fiber risers inside existing buildings, outside of TR, ER, and data center footprints, are required to be installed in conduit for this project.
The use of vertical placed ladder rack is the method of support for vertical fiber optic cables. See sheet TN504 detail 4.
36 Innerduct or Maxcell in indoor fiber riser conduits:
If indoor vertical fiber risers are required to be installed in conduit, please confirm whether Maxcell, innerduct, or any other conduit partitioning product is required inside those conduits.
Please see response to item above.
37 Horizontal indoor fiber support method in accessible ceilings and corridors:
Please confirm whether new horizontal indoor fiber runs inside buildings are permitted to be routed on J-hooks or cable tray where not otherwise shown, or whether those runs are required to be installed in conduit.
All horizontal fiber runs are to be enclosed in EMT conduit. If use of EMT is not achievable then J Hooks are acceptable.
38 Armored fiber in lieu of conduit for horizontal indoor runs:
If new horizontal indoor fiber runs are not required to be installed in conduit, please confirm whether plenum-armored or riser-armored fiber may be used on J-hooks in lieu of conduit for those horizontal indoor runs.
All horizontal fiber runs are to be enclosed in EMT conduit. If use of EMT is not achievable then armored fiber in J hooks is acceptable.
39 Fiber routing through crawl spaces, utility spaces, and other exposed indoor areas:
Please confirm whether fiber routes that pass through building crawl spaces, utility spaces, interstitial spaces, or other exposed but indoor areas are required to be installed in conduit for the full route, or whether armored fiber supported on J-hooks or other cable supports is acceptable in those areas.
Please see response to item 38.
40 Fiber routing above hard lids and inaccessible Ceilings:
Please confirm whether new indoor fiber routed above hard lids or through inaccessible ceilings is required to be installed in conduit for the full route.
Please see response to item 38.
41 Head-end fiber between TR, ER, MCR, and data center spaces:
Please confirm whether fiber runs between TRs, ERs, MCR spaces, and the new data center within buildings are required to be 100 percent in conduit, or whether horizontal segments may be routed on J-hooks or cable tray where not otherwise shown on the contract documents.
Please see response to item 38.
42 Required cable type if armored fiber on J-hooks is Permitted:
If armored fiber on J-hooks is permitted for any indoor horizontal fiber runs, please confirm the required cable type and rating for those runs, including whether the Government requires CMP armored cable in plenums, CMR armored cable in riser or non-plenum spaces, or inside/outside armored OS2 cable where routes pass through mixed environments.
Any cable that is placed in a space shall be rated for that space per NFPA requirements.
43 Basis of bid where existing pathway is unavailable or unusable for fiber routing:
Where the contract documents direct reuse of existing pathway as conduit fill allows, please confirm the basis of bid if existing pathway is found to be unavailable, inaccessible, overfilled, or unsuitable for new fiber routing. Specifically, please confirm whether bidders are to assume new conduit, cable tray, or J-hook routing will be required in those locations.
The existing pathways are to be reused as much as possible. Spare capacity is expected to be achieved with the removal of cables rated category 6 and below. If too little capacity is found in these pathways then J hooks are an acceptable method of cable support.
44 Corridor fiber support method where cable tray is not shown:
Please confirm whether fiber routed in building corridors, where cable tray is not specifically shown, may be supported on J-hooks, or whether conduit is required in those corridor conditions.
Conduit is the preferred method. If that is not achievable J hooks are acceptable.
45 Fire sprinkler quantity basis for TR and data center Scope:
Please confirm the fire sprinkler scope bidders are required to include for the new data center and all new or expanded telecommunications rooms, including whether bidders are to assume all sprinkler heads, branch piping revisions, and related work necessary to achieve final NFPA-compliant light hazard coverage for floorplan changes and new obstructions created by ductwork, cable trays, conduits, equipment, and room reconfiguration are included in the base bid.
Contractor is responsible for providing complete NFPA working drawings with final sprinkler layout and branch piping revisions. Contractor is further responsible for providing complete NFPA 13 compliant installation and any other required work.
46 Fire sprinkler hydraulic calculations and flow-test Basis:
Please confirm whether bidders are required to perform a new fire hydrant flow test and prepare hydraulic calculations for the new data center sprinkler system, and please separately confirm whether any hydraulic calculations or new flow testing are required for telecommunications room sprinkler modifications and expansions under this contract, since the sprinkler specification identifies light hazard coverage for telecommunications rooms and the data center but leaves the water supply location blank.
Contractor is responsible to perform new fire hydrant flow test and prepare hydraulic calculations for the new data center.
Additionally, contractor is responsible to preform fire hydrant flow tests, and prepare calculations for telecommunication room fire sprinkler revisions and additions.
47 Seismic delegated design scope:
Please confirm which project systems, assemblies, supports, anchors, restraints, and attachments the Government expects bidders to include as delegated seismic design items requiring engineer-stamped calculations, coordinated seismic submittals, and any required special seismic certification under Section 13 05 41 and the project Seismic Design Category C requirements.
The non-structural systems are listed in the specification. 13 05 41
48 Temporary shoring engineering basis:
Please confirm whether all temporary shoring, sheeting, bracing, and associated engineering required to perform the work shown on the structural documents and otherwise required by excavation or construction conditions are to be designed by the Contractor and included in the base bid.
Yes to contractor should include it.
49 Waterproof membrane requirement at top of mud Slab:
Structural Note 4 calls for waterproof membrane at the top of mud slab “as required.” Please confirm whether bidders are required to include a waterproof membrane at the top of mud slab for this project.
An additional waterproof membrance is not required on top of the mud slab.
50 Waterproof membrane specification at top of mud Slab:
If a waterproof membrane at the top of mud slab is required for this project, please provide the governing specification, product type, performance requirement, and installation basis bidders are to carry.
An additional waterproof membrance is not required on top of the mud slab.
51 Temporary 1-hour rated doors at phasing and ICRA Openings:
Please confirm whether bidders are required to include temporary 1-hour rated self-closing doors at all phasing and ICRA openings where a temporary 1-hour separation is required, or only at the specific locations explicitly shown on the drawings.
AE confirms that this is only for specific locations esplicitly shown and taged with Keynote 10
52 Low-voltage segregation bid basis:
Please confirm the required bid basis for segregating data cabling from security, fire alarm, nurse call, and other special systems, including whether bidders are to assume separate raceways throughout, or whether bundling by like systems with tray dividers in common specialsystems cable tray is the intended basis where common tray is used.
Bidders shall assume that cable tray dividers will be necessary for the spearation of the category 6A cables from other system cables.
53 TNG003 indoor A and B fiber EMT pathway Requirement:
Please confirm that bidders are required to include 2-inch indoor EMT conduit pathways for A-side and B-side fiber routes between the building point-of-entry indoor enclosure and the associated TR or TE rooms as described on TNG003.
That is correct.
54 Alternate pathway materials for indoor A and B fiber routes:
If 2-inch indoor EMT is not required for all indoor A-side and B-side fiber pathway segments described on TNG003, please identify the alternate pathway materials, sizes, and protection methods bidders may use as the bid basis.
2 inch EMT is required to be provided in all routes. Should this not be achievable the use of J hooks is permittable.
55 Identification of post-tension slab locations:
Please identify each building, floor, and area within the project scope where existing post-tension slabs, tendons, or PT anchor heads are present and where the post-tension slab penetration restrictions shown on the structural details apply.
The structural asbuilts do not show any post tension in the strucutres Towers 1,2 and 4 are attached to. We do not have structural as-builts for building 2 that tower 3 is next to.
56 Snow-event bid basis for 18-inch accumulation Note:
Please clarify the intended bid basis for the structural note referencing snow accumulation of 18 inches or greater, including whether bidders are expected to include any temporary support, snow removal, protection, or weather-response scope specifically tied to that threshold.
This is a bidding question, but structurally the snow should not be allowed to accumulate higher than 18"
57 Grounding conductor raceway requirement in ceilings, risers, tunnels, and crawl spaces:
Please confirm whether grounding and bonding conductors routed above ceilings, through risers, through interstitial spaces, through crawl spaces, or through tunnels are required to be installed in raceway unless specifically noted otherwise on the contract documents.
Per contract drawings, where conductor is subject to physical damage, conductor shall be routed through RMC.
58 Existing cable tray capacity verification:
Please confirm whether the Government or design team has verified that existing cable tray systems and supports in the affected buildings have sufficient fill capacity and structural capacity to accommodate the new communications cabling required under this project.
Existing cable trays have not been verified as to current capacity. With the removal of category 6 cables and below, additional capacity should be available. If this capacity is still not enough, the use of J Hooks is an acceptable means of support for category 6A cableing.
59 Basis of bid for overfilled or inaccessible cable tray:
If existing cable tray sections are found to be overfilled, inaccessible, unusable, or structurally inadequate for new communications cabling, please confirm the basis of bid and whether bidders are to include new supplemental cable tray, new raceway, or other new pathway work in the base bid where such conditions are not specifically shown.
Existing cable trays have not been verified as to current capacity. With the removal of category 6 cables and below, additional capacity should be available. If this capacity is still not enough, the use of J Hooks is an acceptable means of support for category 6A cableing.
60 Basis of bid for telecommunications outlet replacement scope:
Please confirm that the telecommunications outlet replacement scope for this project is a one-for-one replacement of existing outlets and associated cabling unless otherwise specifically shown on the drawings or directed in writing by the VA COR.
This is NOT a 1 for 1 replacement. See the TN 100 series sheets for all locations ot be recabled.
61 Full room and above-ceiling survey requirement for outlet quantities:
Please confirm whether bidders are required to perform a full room-by-room and above-ceiling survey to establish final outlet quantities, cable counts, and pathway requirements, or whether bidders may rely on the quantities and locations shown in the contract documents as the basis of bid.
NO the Contracor should bid based on the WAOs shown on the TN 100 series sheets.
62 Drop-count matrix and governing quantity Document:
Please provide a drop-count matrix by TR, building, floor, or coverage zone for all telecommunications outlets and cable quantities, or identify the specific drawing, schedule, or bid document that bidders are to rely upon as the sole governing quantity basis for pricing outlet and cable counts.
The TN 100 series sheets show ALL known cable locations to be recabled. Additionally, the sheet TN701 provides a matrix of the WAO count per TR and per Building.
63 Extra Cat6A cabling, extra data rough-in, and unforeseen telecom pathway allowance:
Please confirm whether bidders are expected to include any allowance or contingency in the base bid for additional Category 6A cabling, additional 1-inch data rough-in, or unforeseen telecommunications pathway work beyond the quantities and pathway scope specifically shown in the contract documents.
The ony allowance is for 2 port WAOs. The Contractor shall include an additional 10% of the total of WAOs in this project that will be used by the VA at their disrection.
64 Station-end patch-cord responsibility:
Specification Section 27 16 19 states the contractor will supply patch cords, station cords, and cross-connect wire, while the Huntington technology notes specifically define extensive TR and MCR patch-cord requirements. Please confirm whether the contractor is required to furnish only closet-end/TR/MCR patch cords, or whether station-end/user-end patch cords at the work area outlets are also included in the contractor’s base bid scope
Please see sheet TNG001 notes 25 and 26 for the patch cord amounts to be provided by the Contractor.
65 Removal of replaced legacy fiber and copper after Cutover:
Please confirm whether all replaced legacy copper and fiber cabling associated with this project is to be removed after successful cutover and not abandoned in place, unless specifically noted otherwise in the contract documents.
All copper legacy copper cabling category 6 and below is to be removed. Any copper backbone cables must be verified that no circuits are still in use prior to removal. Legacy fiber optic cables are to be verified with the VA before removal.
66 Service-provider fiber building-entry conduit Requirement:
Please confirm whether service-provider fiber and other backbone fiber entering a building outside of a secured TR, ER, or similar telecom space is required to be installed in conduit from the building penetration or entry facility to the inside of the secured telecom space, and whether bidders are to carry that conduit as the base bid.
Yes all fiber is to be placed in EMT as much as practable.
67 Responsibility for discovered existing rated walls and fire safing beyond shown work:
Please confirm that the contractor is required to maintain and restore the fire rating of walls and penetrations affected by the work shown in the contract documents, but is not required to upgrade unrelated existing rated wall assemblies, fire safing, or discovered legacy conditions beyond the depicted project scope unless specifically directed after award.
AE confirms that the contractor is required to maintain and restore the fire rating of walls and penetrations affected by the work shown in the contract documents.
68 Static dissipative floor sealer locations:
Section 09 66 00 requires static dissipative sealer for concrete substrates. Please confirm all rooms and areas within the project scope where static dissipative floor sealer is required, including building number and room number, and confirm whether this sealer is in addition to or in lieu of any ESD flooring system or raised-floor system referenced elsewhere in the contract documents for those locations.
AE confirms that any room with keynote 7 is to have anti static coating
69 Finish schedule completeness and governing status:
Section 09 06 00 provides a schedule of finishes. Please confirm that the finish schedule issued with the contract documents is complete and governing for all rooms and areas within the project scope, including new MCR and tower rooms, corridor areas restored after ICRA barrier removal, incidental rooms impacted by phased construction, and any area where finishes are disturbed during demolition or installation.
AE confirms that the schedule issued with the contract documents is complete
70 Finish schedule completeness and governing status:
Please also confirm whether any room or area not shown on the finish schedule is to receive finishes matching adjacent existing conditions or is to be left unfinished.
AE confirms that corridor and similar spaces are not included in the finish scheudle and are to receive finishes that match existing conditions
71 Seismic restraint delegated design basis by trade:
Please confirm whether delegated seismic design responsibility rests with the contractor's engineer of record or with each individual trade subcontractor, and confirm whether engineer-stamped seismic restraint calculations must be submitted for Government approval before installation of any restrained.
The GC should coordinate this. Yes it should be submitted for approval
72 Plumbing scope in new tower rooms and data Center:
Please confirm the complete plumbing scope required in the new TR towers, data center, and MCR addition, including floor drains, condensate drains, domestic water connections, emergency eyewash or safety fixtures, and any other plumbing rough-in or fixture work required by code or the contract documents in those spaces, so bidders have a complete and accurate plumbing bid basis
Contractor to see floor plans for plumbing scope.
73 Testing, Adjusting, and Balancing requirements:
Section 23 05 93 requires testing, adjusting, and balancing for HVAC systems. Please confirm whether an independent TAB contractor separate from the mechanical installer is required, identify all HVAC systems in the new data center, MCR, and TR towers subject to TAB, and confirm whether certified TAB reports must be reviewed and accepted by the Government's Commissioning Agent before final acceptance of mechanical systems in those spaces.
An independent TAB contractor is required. See specifications for TAB requirements.
74 BAS tie-in requirements for new HVAC systems:
Section 23 09 23 requires DDC for HVAC. Please confirm whether the new data center and tower HVAC systems are required to be tied into the existing campus Building Automation System, identify the existing BAS manufacturer and platform, and confirm whether the contractor is responsible for programming new points, developing graphics, and performing integrated BAS testing as part of the base bid or whether BAS programming and graphics are owner-furnished.
The new data center and TR towers are required to be tied into the existing campu Building Automation systems.
Contractor is responsible for programming new points, developing graphics, and performing integrated BAS testing.
See response to RFI 13 for existing manufacturer and platform.
75 Precision cooling unit type and configuration for new data center:
Please confirm the required type, quantity, capacity, and configuration of precision cooling units or computer room air conditioning units for the new data center, including the source of chilled water or refrigerant, the required redundancy configuration, and whether the precision cooling equipment is owner-furnished and contractor-installed, or contractor-furnished and contractor-installed.
See mechanical drawings and specifications.
All mechanical equipment included in this contract is contractor-furnished, contractor-installed.
76 HVAC subcontractor licensing — refrigerant, TAB, and DDC contractors:
Please confirm whether any West Virginia licensure or certification requirements applicable to HVAC work on this project also apply to refrigerant-handling technicians, TAB contractors, and DDC or building-controls contractors performing work under Divisions 23 and 25. For each specialty, please identify the required credential type, whether the requirement applies to the firm, individual personnel, or both, and when proof of compliance must be submitted.
See specifications for all licensure and certification requirements.
77 UPS system configuration for new data center:
Section 26 33 53 requires static uninterruptible power supply systems. Please confirm the required UPS capacity, battery runtime, redundancy configuration, and physical arrangement for the new data center UPS system. Please also confirm whether the UPS is ownerfurnished and contractor-installed or contractor-furnished and contractor-installed, and identify whether a maintenance bypass switch and static bypass are required as part of the base bid.
UPS is contractor furnished and contractor installed. UPS capacity, runtime, configuration, and arrangement shall be as shown in the contract drawings and specification 26 33 53.
78 Surge protective device locations and ratings:
Section 26 43 13 requires surge protective devices.
Please confirm all required SPD locations associated with the new data center, MCR, and all new or modified distribution panels under this project, including the required surge protection category, surge current rating, and nominal discharge current rating at each location, so bidders can accurately price the complete SPD scope.
Reference electrical one-lines and panel schedule sheets for panelboards requiring SPDs.
79 Interior and exterior lighting scope:
Sections 26 51 00 and 26 56 00 require interior and exterior lighting. Please confirm the complete lighting scope for all new rooms, ICRA restoration areas, and exterior areas affected by the data center addition and tower construction, including whether existing lighting fixtures in all areas disturbed by construction must be replaced, relamped, or restored to match original conditions as part of the base bid. Please also confirm the required lighting levels for new data center, MCR, and telecom tower rooms.
Reference electrical plans for lighting requirements.
80 Security access detection scope:
Section 28 13 53 requires security access detection.
Please confirm the complete scope of security detection devices required in the new data center and all new telecom tower rooms, including motion detectors, door position contacts, glass break sensors, and duress stations.
The drawings and specs do include the complete scope for this section. Please see the TN sheets for ceiling mounted motion detectors in all TRs and the MCR. NO glass break sensors or duress staions are required for this project.
81 Security access detection scope:
Please also confirm whether these systems tie into the existing campus intrusion detection system or operate as standalone systems, and identify the responsible trade for furnishing, installing, programming, and testing all detection devices.
These motion sensors are to be tied into the eisting access control system.
82 Division 28 commissioning scope and contractor Deliverables:
Section 28 08 00 requires commissioning of electronic safety and security systems.
Please confirm whether all Division 28 systems, including PACS, video surveillance, intrusion detection, and fire alarm, are subject to formal commissioning under Section 28 08 00 on this project.
Please identify all contractor commissioning deliverables required before Government final acceptance of Division 28 systems, including prefunctional checklists, functional performance test procedures, integrated systems test procedures, training documentation, and commissioning reports.
Specification Section 28 08 00 does apply to all systems in the division 28 section. All commissioning requirements are contained in that Specification Section.
83 Micropile contractor qualifications and licensure Requirements:
Please confirm whether the micropile specialty contractor must be pre-qualified or submit documented experience on comparable federal, VA, or healthcare projects prior to award or prior to beginning micropile work, identify the minimum qualification requirements, and confirm the required state licensure for the Micropile PE of Record for this West Virginia project.
Contractor does not need to be pre-qualified., but must submit prior experience per the specs. Confirmed PE of record should be for West Virginia
84 Emergency generator capacity and load bank testing obligations for new telecom rooms:
Please confirm whether the existing campus emergency generator system has sufficient capacity to serve all new telecommunications rooms, the new data center, and all associated UPS, precision cooling, and life safety loads required under this contract in addition to existing emergency loads.
Please also confirm whether load bank testing of the emergency generator is required, the required duration and load percentage, and who is responsible for providing the load bank and coordinating the test.
Reference generator capacity and load information schedule on sheet EP701 for generator loading information.
Load bank testing is not required for this project. Contractor shall coordinate with the VA to determine if load bank testing is desired.
85 Legacy 110V telecom rooms:
Please identify each telecommunications room or space that requires legacy 110V distribution in addition to the standard 208V rack power arrangement so bidders can correctly size feeders, transformers, branch circuits, and device counts
Reference electrical details (EP500 series) for rack configuration and power requirements. Reference enlarged electrical floor plans (EP400 series) for quantity of racks.