This is an Amendment 0007 attachment containing Pre-Functional Checklists (PFC) and Functional Performance Tests (FPT) for HVAC equipment installations at the Huntington VAMC EHRM Upgrades project located in Huntington, West Virginia. The document serves as a template and verification tool for the mechanical contractor and construction manager to confirm proper installation, startup, and operational testing of cooling and heating equipment.
The PFC covers two primary equipment types: Computer Room Air Conditioner (CRAC) units and Variable Refrigerant Flow (VRF) units. For CRAC systems (CRAC-01 and CRAC-02 in Building 01S Data Center), the checklist verifies delivery, physical condition, piping integrity, electrical connections, and controls functionality, including refrigerant line sealing, proper insulation, pressure testing, thermostat operation, and completion of startup reports and training documentation. For VRF units deployed across multiple buildings (01S, 01W, Building 2, Building 5, Building 20, Building 23R, Building 25, Building 28, and Building TR1), the PFC examines similar installation requirements including indoor unit filters, air-cooled condensing unit specifications, refrigerant line protection and sealing, electrical wiring security, control sensor calibration, and operational manual compilation. The FPT procedures validate that CRAC and VRF systems achieve proper cooling and heating operation through temperature setpoint adjustments, damper positioning, airflow measurement, and sensor accuracy verification, with trending data collection at 15-minute intervals. All testing documentation requires contractor initials and construction manager sign-off, with sections for recording issues, corrective actions, and final system status (Pass/Fail/Partial with corrective actions).
View the file
Other files for this federal contract opportunity
Show all 50
EHRM Huntington VAMC 581-22-700 Construct Infrastructure Upgrades has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2207 Garnet Avenue Suite I
San Diego, CA 92109
Direct: (619) 770-8552
Contractor Initial VA CM Initial Date
Contractor Initial VA CM Initial Date
Contractor Initial VA CM Initial Date
Size (in)
Fan Power/Speed (hp/rpm)
Model
Yes, No, N/A
Voltage / Phase / Frequency (V/ph/Hz)
Equipment Location: Data Center
Manufacturer: Liebert
A. Model Verification (Note: 1. as specified, 2. as submitted, 3. as installed) Enter Note #
Manufacturer
Model #:
Serial #:
Service:
DS105
Comment/ Issues
1. Delivery Book
Building: 01S
Computer Room Air Conditioner (CRAC) Pre-Functional Checklist
Project: Huntington VAMC EHRM Upgrades Design Cx
Project Location:
Equipment ID: CRAC-01
Huntington , WV
Unit is free from physical damage
All components present
The refrigerant line openings are sealed
Serial Number
Start-up report is complete and has been provided to the GC for approval by the Owner
Training plan and instructor qualifications has been complete and provided to the GC for approval by the
Owner
Operation & Maintenance manual has been compiled and provided to the GC for approval by the Owner
B. Physical Checks
Airflow Max/Min (cfm)
Heating Capacity (MBH/gpm)
Filter drier is installed
Vacuum pulled on lineset
Lineset is strapped properly
A. Piping Yes, No, N/A
Unit tags affixed
2. Construction Checklist
Installation and startup manual provided
Comment/ Issues
Lineset is properly insulated
Refrigeration lineset pressure tested
Lineset insulation above roofline is UV protected
Comment/ Issues
Davenergy Project #: 61109
3/7/2024 1 CRAC-01 PFC
Direct: (619) 770-8552
Computer Room Air Conditioner (CRAC)Contractor Initial VA CM Initial Date
Contractor Initial VA CM Initial Date
Motors and compressors running in the right direction
System has correct refrigerant charge
Control wiring between fan coil and condensing unit installed
Comment/ Issues
Comment/ Issues
Controls contractor has status monitored
System graphics have been installed
Specified point-to-point checks have been completed and documentation record submitted for this system
Split system works off thermostat and reaches setpoint
C. Controls Yes, No, N/A
Thermostat mounted and wired if not remote controller
B. Electrical Yes, No, N/A
Power wiring connected, secure and grounded to both units
3/7/2024 2 CRAC-01 PFC
Direct: (619) 770-8552
Contractor Initial VA CM Initial Date
Contractor Initial VA CM Initial Date
Contractor Initial VA CM Initial Date
Lineset insulation above roofline is UV protected
Filter drier is installed
Lineset is strapped properly
Lineset is properly insulated
Refrigeration lineset pressure tested
Vacuum pulled on lineset
Unit tags affixed
2. Construction Checklist
A. Piping Yes, No, N/A Comment/ Issues
The refrigerant line openings are sealed
Installation and startup manual provided
Unit is free from physical damage
All components present
Training plan and instructor qualifications has been complete and provided to the GC for approval by the
Owner
B. Physical Checks Yes, No, N/A Comment/ Issues
Start-up report is complete and has been provided to the GC for approval by the Owner
Operation & Maintenance manual has been compiled and provided to the GC for approval by the Owner
Fan Power/Speed (hp/rpm)
Voltage / Phase / Frequency (V/ph/Hz)
Airflow Max/Min (cfm)
Heating Capacity (MBH/gpm)
Serial Number
Size (in)
Manufacturer
Model
Service:
1. Delivery Book
A. Model Verification (Note: 1. as specified, 2. as submitted, 3. as installed) Enter Note # Comment/ Issues
Manufacturer: Liebert
Model #: DS105
Serial #:
Project Location: Huntington , WV
Equipment ID: CRAC-02
Equipment Location: Data Center
Computer Room Air Conditioner (CRAC) Pre-Functional Checklist
Project: Huntington VAMC EHRM Upgrades Design Cx
Building: 01S
3/7/2024 3 CRAC-02 PFC
Direct: (619) 770-8552
Computer Room Air Conditioner (CRAC)Contractor Initial VA CM Initial Date
Contractor Initial VA CM Initial Date
8 System graphics have been installed
Split system works off thermostat and reaches setpoint
Specified point-to-point checks have been completed and documentation record submitted for this system
System has correct refrigerant charge
Motors and compressors running in the right direction
Control wiring between fan coil and condensing unit installed
Controls contractor has status monitored
C. Controls Yes, No, N/A Comment/ Issues
Thermostat mounted and wired if not remote controller
B. Electrical Yes, No, N/A Comment/ Issues
Power wiring connected, secure and grounded to both units
3/7/2024 4 CRAC-02 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Start-up report is complete and has been provided to the GC for approval by the owner
Operation & Maintenance manual has been compiled and provided to the GC for approval by the owner
Training plan and instructor qualifications has been complete and provided to the GC for approval by the owner
Equipment Location:
Manufacturer:
A. Model Verification (Note: 1. as specified, 2.
as submitted, 3. as installed) Enter Note #
Manufacturer
Model #:
Serial #:
Service:
Comment/ Issues
1. Delivery Book
Serial Number
B. Physical Checks
Size (in)
Fan Power/Speed (hp/rpm)
Model
Yes, No, N/A
Voltage / Phase / Frequency (V/ph/Hz)
Huntington, WV
Building: 01S
VRV Unit
Pre-Functional Checklist Project: Huntington VAMC EHRM Upgrades Cx
Project Location:
Equipment ID: CU-01
Airflow Max/Min (cfm)
Unit tags affixed
Installation and startup manual provided
Unit is free from physical damage
All components present
The refrigerant line openings are sealed
C. Other Yes, No, N/A Comment/Issues
TAB report is complete and has been provided to the GC for approval by the owner
Comment/ Issues
3/7/2024 1 B01S CU-01 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Minimum 20 gage sheet metal pan around refrigerant lines from bottom wall anchor to eave
20 gage sheet metal pan is painted to match building color of oil base paint
Seismic rated equipment stand for roof mounted units installed
Condensate drain pump installed
Legs for roof mounted support is sealed for water proof
B. Air-Cooled Condensing Unit Yes, No, N/A Comment/ Issues
Crank case heater installed
Factory wall mounting hardware used in installation
Minimum 3/4" condensate drain line
A. Indoor Unit Yes, No, N/A Comment/ Issues
Slide-in air filter installed
Low ambient temperature controls installed
System graphics have been installed
Split system works off thermostat and reaches setpoint
E. Controls Yes, No, N/A
Thermostat mounted and wired if not remote controller
Controls contractor has status monitored
Motors and compressors running in the right direction
System has correct refrigerant charge
Control wiring between fan coil and condensing unit installed
Specified point-to-point checks have been completed and documentation record submitted for this system
Device Calibration checks have been completed and documentation record submitted for this system
Vacuum pulled on lineset
Lineset is strapped properly
C. Piping Yes, No, N/A
2. Construction Checklist
Comment/ Issues
Comment/ Issues
Power wiring connected, secure and grounded to both units
Refrigeration lineset pressure tested
Minimum of 12" braided flexible refrigerant line
Lineset is properly insulated
D. Electrical Yes, No, N/A
Comment/ Issues
3/7/2024 2 B01S CU-01 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Training plan and instructor qualifications has been complete and provided to the GC for approval by the owner
TAB report is complete and has been provided to the GC for approval by the owner
Start-up report is complete and has been provided to the GC for approval by the owner
Operation & Maintenance manual has been compiled and provided to the GC for approval by the owner
Unit tags affixed
C. Other Yes, No, N/A Comment/Issues
The refrigerant line openings are sealed
Installation and startup manual provided
Unit is free from physical damage
All components present
Voltage / Phase / Frequency (V/ph/Hz)
B. Physical Checks Yes, No, N/A Comment/ Issues
Airflow Max/Min (cfm)
Fan Power/Speed (hp/rpm)
Serial Number
Size (in)
Manufacturer
Model
Service:
1. Delivery Book
A. Model Verification (Note: 1. as specified, 2.
as submitted, 3. as installed) Enter Note # Comment/ Issues
Manufacturer:
Model #:
Serial #:
Project Location: Huntington, WV
Equipment ID: CU-02
Equipment Location:
VRV Unit
Pre-Functional Checklist Project: Huntington VAMC EHRM Upgrades Cx
Building: 01S
3/7/2024 3 B01S CU-02 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Device Calibration checks have been completed and documentation record submitted for this system
System graphics have been installed
Split system works off thermostat and reaches setpoint
Specified point-to-point checks have been completed and documentation record submitted for this system
System has correct refrigerant charge
Motors and compressors running in the right direction
Control wiring between fan coil and condensing unit installed
Controls contractor has status monitored
E. Controls Yes, No, N/A Comment/ Issues
Thermostat mounted and wired if not remote controller
D. Electrical Yes, No, N/A Comment/ Issues
Power wiring connected, secure and grounded to both units
Lineset is properly insulated
Minimum of 12" braided flexible refrigerant line
Vacuum pulled on lineset
Lineset is strapped properly
C. Piping Yes, No, N/A Comment/ Issues
Refrigeration lineset pressure tested
Minimum 20 gage sheet metal pan around refrigerant lines from bottom wall anchor to eave
20 gage sheet metal pan is painted to match building color of oil base paint
Condensate drain pump installed
Legs for roof mounted support is sealed for water proof
Crank case heater installed
Seismic rated equipment stand for roof mounted units installed
Minimum 3/4" condensate drain line
B. Air-Cooled Condensing Unit Yes, No, N/A Comment/ Issues
Low ambient temperature controls installed
Factory wall mounting hardware used in installation
2. Construction Checklist
A. Indoor Unit Yes, No, N/A Comment/ Issues
Slide-in air filter installed
3/7/2024 4 B01S CU-02 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Training plan and instructor qualifications has been complete and provided to the GC for approval by the owner
TAB report is complete and has been provided to the GC for approval by the owner
Start-up report is complete and has been provided to the GC for approval by the owner
Operation & Maintenance manual has been compiled and provided to the GC for approval by the owner
Unit tags affixed
C. Other Yes, No, N/A Comment/Issues
The refrigerant line openings are sealed
Installation and startup manual provided
Unit is free from physical damage
All components present
Voltage / Phase / Frequency (V/ph/Hz)
B. Physical Checks Yes, No, N/A Comment/ Issues
Airflow Max/Min (cfm)
Fan Power/Speed (hp/rpm)
Serial Number
Size (in)
Manufacturer
Model
Service:
1. Delivery Book
A. Model Verification (Note: 1. as specified, 2.
as submitted, 3. as installed) Enter Note # Comment/ Issues
Manufacturer:
Model #:
Serial #:
Project Location: Huntington, WV
Equipment ID: CU-03
Equipment Location:
VRV Unit
Pre-Functional Checklist Project: Huntington VAMC EHRM Upgrades Cx
Building: 01S
3/7/2024 5 B01S CU-03 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Device Calibration checks have been completed and documentation record submitted for this system
System graphics have been installed
Split system works off thermostat and reaches setpoint
Specified point-to-point checks have been completed and documentation record submitted for this system
System has correct refrigerant charge
Motors and compressors running in the right direction
Control wiring between fan coil and condensing unit installed
Controls contractor has status monitored
E. Controls Yes, No, N/A Comment/ Issues
Thermostat mounted and wired if not remote controller
D. Electrical Yes, No, N/A Comment/ Issues
Power wiring connected, secure and grounded to both units
Lineset is properly insulated
Minimum of 12" braided flexible refrigerant line
Vacuum pulled on lineset
Lineset is strapped properly
C. Piping Yes, No, N/A Comment/ Issues
Refrigeration lineset pressure tested
Minimum 20 gage sheet metal pan around refrigerant lines from bottom wall anchor to eave
20 gage sheet metal pan is painted to match building color of oil base paint
Condensate drain pump installed
Legs for roof mounted support is sealed for water proof
Crank case heater installed
Seismic rated equipment stand for roof mounted units installed
Minimum 3/4" condensate drain line
B. Air-Cooled Condensing Unit Yes, No, N/A Comment/ Issues
Low ambient temperature controls installed
Factory wall mounting hardware used in installation
2. Construction Checklist
A. Indoor Unit Yes, No, N/A Comment/ Issues
Slide-in air filter installed
3/7/2024 6 B01S CU-03 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Training plan and instructor qualifications has been complete and provided to the GC for approval by the owner
TAB report is complete and has been provided to the GC for approval by the owner
Start-up report is complete and has been provided to the GC for approval by the owner
Operation & Maintenance manual has been compiled and provided to the GC for approval by the owner
Unit tags affixed
C. Other Yes, No, N/A Comment/Issues
The refrigerant line openings are sealed
Installation and startup manual provided
Unit is free from physical damage
All components present
Voltage / Phase / Frequency (V/ph/Hz)
B. Physical Checks Yes, No, N/A Comment/ Issues
Airflow Max/Min (cfm)
Fan Power/Speed (hp/rpm)
Serial Number
Size (in)
Manufacturer
Model
Service:
1. Delivery Book
A. Model Verification (Note: 1. as specified, 2.
as submitted, 3. as installed) Enter Note # Comment/ Issues
Manufacturer:
Model #:
Serial #:
Project Location: Huntington, WV
Equipment ID: CU-04
Equipment Location:
VRV Unit
Pre-Functional Checklist Project: Huntington VAMC EHRM Upgrades Cx
Building: 01S
3/7/2024 7 B01S CU-04 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Device Calibration checks have been completed and documentation record submitted for this system
System graphics have been installed
Split system works off thermostat and reaches setpoint
Specified point-to-point checks have been completed and documentation record submitted for this system
System has correct refrigerant charge
Motors and compressors running in the right direction
Control wiring between fan coil and condensing unit installed
Controls contractor has status monitored
E. Controls Yes, No, N/A Comment/ Issues
Thermostat mounted and wired if not remote controller
D. Electrical Yes, No, N/A Comment/ Issues
Power wiring connected, secure and grounded to both units
Lineset is properly insulated
Minimum of 12" braided flexible refrigerant line
Vacuum pulled on lineset
Lineset is strapped properly
C. Piping Yes, No, N/A Comment/ Issues
Refrigeration lineset pressure tested
Minimum 20 gage sheet metal pan around refrigerant lines from bottom wall anchor to eave
20 gage sheet metal pan is painted to match building color of oil base paint
Condensate drain pump installed
Legs for roof mounted support is sealed for water proof
Crank case heater installed
Seismic rated equipment stand for roof mounted units installed
Minimum 3/4" condensate drain line
B. Air-Cooled Condensing Unit Yes, No, N/A Comment/ Issues
Low ambient temperature controls installed
Factory wall mounting hardware used in installation
2. Construction Checklist
A. Indoor Unit Yes, No, N/A Comment/ Issues
Slide-in air filter installed
3/7/2024 8 B01S CU-04 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Training plan and instructor qualifications has been complete and provided to the GC for approval by the owner
TAB report is complete and has been provided to the GC for approval by the owner
Start-up report is complete and has been provided to the GC for approval by the owner
Operation & Maintenance manual has been compiled and provided to the GC for approval by the owner
Unit tags affixed
C. Other Yes, No, N/A Comment/Issues
The refrigerant line openings are sealed
Installation and startup manual provided
Unit is free from physical damage
All components present
Voltage / Phase / Frequency (V/ph/Hz)
B. Physical Checks Yes, No, N/A Comment/ Issues
Airflow Max/Min (cfm)
Fan Power/Speed (hp/rpm)
Serial Number
Size (in)
Manufacturer
Model
Service:
1. Delivery Book
A. Model Verification (Note: 1. as specified, 2.
as submitted, 3. as installed) Enter Note # Comment/ Issues
Manufacturer:
Model #:
Serial #:
Project Location: Huntington, WV
Equipment ID: CU-05
Equipment Location:
VRV Unit
Pre-Functional Checklist Project: Huntington VAMC EHRM Upgrades Cx
Building: 01S
3/7/2024 9 B01S CU-05 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Device Calibration checks have been completed and documentation record submitted for this system
System graphics have been installed
Split system works off thermostat and reaches setpoint
Specified point-to-point checks have been completed and documentation record submitted for this system
System has correct refrigerant charge
Motors and compressors running in the right direction
Control wiring between fan coil and condensing unit installed
Controls contractor has status monitored
E. Controls Yes, No, N/A Comment/ Issues
Thermostat mounted and wired if not remote controller
D. Electrical Yes, No, N/A Comment/ Issues
Power wiring connected, secure and grounded to both units
Lineset is properly insulated
Minimum of 12" braided flexible refrigerant line
Vacuum pulled on lineset
Lineset is strapped properly
C. Piping Yes, No, N/A Comment/ Issues
Refrigeration lineset pressure tested
Minimum 20 gage sheet metal pan around refrigerant lines from bottom wall anchor to eave
20 gage sheet metal pan is painted to match building color of oil base paint
Condensate drain pump installed
Legs for roof mounted support is sealed for water proof
Crank case heater installed
Seismic rated equipment stand for roof mounted units installed
Minimum 3/4" condensate drain line
B. Air-Cooled Condensing Unit Yes, No, N/A Comment/ Issues
Low ambient temperature controls installed
Factory wall mounting hardware used in installation
2. Construction Checklist
A. Indoor Unit Yes, No, N/A Comment/ Issues
Slide-in air filter installed
3/7/2024 10 B01S CU-05 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Training plan and instructor qualifications has been complete and provided to the GC for approval by the owner
TAB report is complete and has been provided to the GC for approval by the owner
Start-up report is complete and has been provided to the GC for approval by the owner
Operation & Maintenance manual has been compiled and provided to the GC for approval by the owner
Unit tags affixed
C. Other Yes, No, N/A Comment/Issues
The refrigerant line openings are sealed
Installation and startup manual provided
Unit is free from physical damage
All components present
Voltage / Phase / Frequency (V/ph/Hz)
B. Physical Checks Yes, No, N/A Comment/ Issues
Airflow Max/Min (cfm)
Fan Power/Speed (hp/rpm)
Serial Number
Size (in)
Manufacturer
Model
Service:
1. Delivery Book
A. Model Verification (Note: 1. as specified, 2.
as submitted, 3. as installed) Enter Note # Comment/ Issues
Manufacturer:
Model #:
Serial #:
Project Location: Huntington, WV
Equipment ID: CU-06
Equipment Location:
VRV Unit
Pre-Functional Checklist Project: Huntington VAMC EHRM Upgrades Cx
Building: 01S
3/7/2024 11 B01S CU-06 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Device Calibration checks have been completed and documentation record submitted for this system
System graphics have been installed
Split system works off thermostat and reaches setpoint
Specified point-to-point checks have been completed and documentation record submitted for this system
System has correct refrigerant charge
Motors and compressors running in the right direction
Control wiring between fan coil and condensing unit installed
Controls contractor has status monitored
E. Controls Yes, No, N/A Comment/ Issues
Thermostat mounted and wired if not remote controller
D. Electrical Yes, No, N/A Comment/ Issues
Power wiring connected, secure and grounded to both units
Lineset is properly insulated
Minimum of 12" braided flexible refrigerant line
Vacuum pulled on lineset
Lineset is strapped properly
C. Piping Yes, No, N/A Comment/ Issues
Refrigeration lineset pressure tested
Minimum 20 gage sheet metal pan around refrigerant lines from bottom wall anchor to eave
20 gage sheet metal pan is painted to match building color of oil base paint
Condensate drain pump installed
Legs for roof mounted support is sealed for water proof
Crank case heater installed
Seismic rated equipment stand for roof mounted units installed
Minimum 3/4" condensate drain line
B. Air-Cooled Condensing Unit Yes, No, N/A Comment/ Issues
Low ambient temperature controls installed
Factory wall mounting hardware used in installation
2. Construction Checklist
A. Indoor Unit Yes, No, N/A Comment/ Issues
Slide-in air filter installed
3/7/2024 12 B01S CU-06 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Training plan and instructor qualifications has been complete and provided to the GC for approval by the owner
TAB report is complete and has been provided to the GC for approval by the owner
Start-up report is complete and has been provided to the GC for approval by the owner
Operation & Maintenance manual has been compiled and provided to the GC for approval by the owner
Unit tags affixed
C. Other Yes, No, N/A Comment/Issues
The refrigerant line openings are sealed
Installation and startup manual provided
Unit is free from physical damage
All components present
Voltage / Phase / Frequency (V/ph/Hz)
B. Physical Checks Yes, No, N/A Comment/ Issues
Airflow Max/Min (cfm)
Fan Power/Speed (hp/rpm)
Serial Number
Size (in)
Manufacturer
Model
Service:
1. Delivery Book
A. Model Verification (Note: 1. as specified, 2.
as submitted, 3. as installed) Enter Note # Comment/ Issues
Manufacturer:
Model #:
Serial #:
Project Location: Huntington, WV
Equipment ID: CU-07
Equipment Location:
VRV Unit
Pre-Functional Checklist Project: Huntington VAMC EHRM Upgrades Cx
Building: 01S
3/7/2024 13 B01S CU-07 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Device Calibration checks have been completed and documentation record submitted for this system
System graphics have been installed
Split system works off thermostat and reaches setpoint
Specified point-to-point checks have been completed and documentation record submitted for this system
System has correct refrigerant charge
Motors and compressors running in the right direction
Control wiring between fan coil and condensing unit installed
Controls contractor has status monitored
E. Controls Yes, No, N/A Comment/ Issues
Thermostat mounted and wired if not remote controller
D. Electrical Yes, No, N/A Comment/ Issues
Power wiring connected, secure and grounded to both units
Lineset is properly insulated
Minimum of 12" braided flexible refrigerant line
Vacuum pulled on lineset
Lineset is strapped properly
C. Piping Yes, No, N/A Comment/ Issues
Refrigeration lineset pressure tested
Minimum 20 gage sheet metal pan around refrigerant lines from bottom wall anchor to eave
20 gage sheet metal pan is painted to match building color of oil base paint
Condensate drain pump installed
Legs for roof mounted support is sealed for water proof
Crank case heater installed
Seismic rated equipment stand for roof mounted units installed
Minimum 3/4" condensate drain line
B. Air-Cooled Condensing Unit Yes, No, N/A Comment/ Issues
Low ambient temperature controls installed
Factory wall mounting hardware used in installation
2. Construction Checklist
A. Indoor Unit Yes, No, N/A Comment/ Issues
Slide-in air filter installed
3/7/2024 14 B01S CU-07 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Training plan and instructor qualifications has been complete and provided to the GC for approval by the owner
TAB report is complete and has been provided to the GC for approval by the owner
Start-up report is complete and has been provided to the GC for approval by the owner
Operation & Maintenance manual has been compiled and provided to the GC for approval by the owner
Unit tags affixed
C. Other Yes, No, N/A Comment/Issues
The refrigerant line openings are sealed
Installation and startup manual provided
Unit is free from physical damage
All components present
Voltage / Phase / Frequency (V/ph/Hz)
B. Physical Checks Yes, No, N/A Comment/ Issues
Airflow Max/Min (cfm)
Fan Power/Speed (hp/rpm)
Serial Number
Size (in)
Manufacturer
Model
Service:
1. Delivery Book
A. Model Verification (Note: 1. as specified, 2.
as submitted, 3. as installed) Enter Note # Comment/ Issues
Manufacturer:
Model #:
Serial #:
Project Location: Huntington, WV
Equipment ID: CU-08
Equipment Location:
VRV Unit
Pre-Functional Checklist Project: Huntington VAMC EHRM Upgrades Cx
Building: 01S
3/7/2024 15 B01S CU-08 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Device Calibration checks have been completed and documentation record submitted for this system
System graphics have been installed
Split system works off thermostat and reaches setpoint
Specified point-to-point checks have been completed and documentation record submitted for this system
System has correct refrigerant charge
Motors and compressors running in the right direction
Control wiring between fan coil and condensing unit installed
Controls contractor has status monitored
E. Controls Yes, No, N/A Comment/ Issues
Thermostat mounted and wired if not remote controller
D. Electrical Yes, No, N/A Comment/ Issues
Power wiring connected, secure and grounded to both units
Lineset is properly insulated
Minimum of 12" braided flexible refrigerant line
Vacuum pulled on lineset
Lineset is strapped properly
C. Piping Yes, No, N/A Comment/ Issues
Refrigeration lineset pressure tested
Minimum 20 gage sheet metal pan around refrigerant lines from bottom wall anchor to eave
20 gage sheet metal pan is painted to match building color of oil base paint
Condensate drain pump installed
Legs for roof mounted support is sealed for water proof
Crank case heater installed
Seismic rated equipment stand for roof mounted units installed
Minimum 3/4" condensate drain line
B. Air-Cooled Condensing Unit Yes, No, N/A Comment/ Issues
Low ambient temperature controls installed
Factory wall mounting hardware used in installation
2. Construction Checklist
A. Indoor Unit Yes, No, N/A Comment/ Issues
Slide-in air filter installed
3/7/2024 16 B01S CU-08 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Training plan and instructor qualifications has been complete and provided to the GC for approval by the owner
TAB report is complete and has been provided to the GC for approval by the owner
Start-up report is complete and has been provided to the GC for approval by the owner
Operation & Maintenance manual has been compiled and provided to the GC for approval by the owner
Unit tags affixed
C. Other Yes, No, N/A Comment/Issues
The refrigerant line openings are sealed
Installation and startup manual provided
Unit is free from physical damage
All components present
Voltage / Phase / Frequency (V/ph/Hz)
B. Physical Checks Yes, No, N/A Comment/ Issues
Airflow Max/Min (cfm)
Fan Power/Speed (hp/rpm)
Serial Number
Size (in)
Manufacturer
Model
Service:
1. Delivery Book
A. Model Verification (Note: 1. as specified, 2.
as submitted, 3. as installed) Enter Note # Comment/ Issues
Manufacturer:
Model #:
Serial #:
Project Location: Huntington, WV
Equipment ID: CU-09
Equipment Location:
VRV Unit
Pre-Functional Checklist Project: Huntington VAMC EHRM Upgrades Cx
Building: 01S
3/7/2024 17 B01S CU-09 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Device Calibration checks have been completed and documentation record submitted for this system
System graphics have been installed
Split system works off thermostat and reaches setpoint
Specified point-to-point checks have been completed and documentation record submitted for this system
System has correct refrigerant charge
Motors and compressors running in the right direction
Control wiring between fan coil and condensing unit installed
Controls contractor has status monitored
E. Controls Yes, No, N/A Comment/ Issues
Thermostat mounted and wired if not remote controller
D. Electrical Yes, No, N/A Comment/ Issues
Power wiring connected, secure and grounded to both units
Lineset is properly insulated
Minimum of 12" braided flexible refrigerant line
Vacuum pulled on lineset
Lineset is strapped properly
C. Piping Yes, No, N/A Comment/ Issues
Refrigeration lineset pressure tested
Minimum 20 gage sheet metal pan around refrigerant lines from bottom wall anchor to eave
20 gage sheet metal pan is painted to match building color of oil base paint
Condensate drain pump installed
Legs for roof mounted support is sealed for water proof
Crank case heater installed
Seismic rated equipment stand for roof mounted units installed
Minimum 3/4" condensate drain line
B. Air-Cooled Condensing Unit Yes, No, N/A Comment/ Issues
Low ambient temperature controls installed
Factory wall mounting hardware used in installation
2. Construction Checklist
A. Indoor Unit Yes, No, N/A Comment/ Issues
Slide-in air filter installed
3/7/2024 18 B01S CU-09 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Training plan and instructor qualifications has been complete and provided to the GC for approval by the owner
TAB report is complete and has been provided to the GC for approval by the owner
Start-up report is complete and has been provided to the GC for approval by the owner
Operation & Maintenance manual has been compiled and provided to the GC for approval by the owner
Unit tags affixed
C. Other Yes, No, N/A Comment/Issues
The refrigerant line openings are sealed
Installation and startup manual provided
Unit is free from physical damage
All components present
Voltage / Phase / Frequency (V/ph/Hz)
B. Physical Checks Yes, No, N/A Comment/ Issues
Airflow Max/Min (cfm)
Fan Power/Speed (hp/rpm)
Serial Number
Size (in)
Manufacturer
Model
Service:
1. Delivery Book
A. Model Verification (Note: 1. as specified, 2.
as submitted, 3. as installed) Enter Note # Comment/ Issues
Manufacturer:
Model #:
Serial #:
Project Location: Huntington, WV
Equipment ID: CU-10
Equipment Location:
VRV Unit
Pre-Functional Checklist Project: Huntington VAMC EHRM Upgrades Cx
Building: 01S
3/7/2024 19 B01S CU-10 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Device Calibration checks have been completed and documentation record submitted for this system
System graphics have been installed
Split system works off thermostat and reaches setpoint
Specified point-to-point checks have been completed and documentation record submitted for this system
System has correct refrigerant charge
Motors and compressors running in the right direction
Control wiring between fan coil and condensing unit installed
Controls contractor has status monitored
E. Controls Yes, No, N/A Comment/ Issues
Thermostat mounted and wired if not remote controller
D. Electrical Yes, No, N/A Comment/ Issues
Power wiring connected, secure and grounded to both units
Lineset is properly insulated
Minimum of 12" braided flexible refrigerant line
Vacuum pulled on lineset
Lineset is strapped properly
C. Piping Yes, No, N/A Comment/ Issues
Refrigeration lineset pressure tested
Minimum 20 gage sheet metal pan around refrigerant lines from bottom wall anchor to eave
20 gage sheet metal pan is painted to match building color of oil base paint
Condensate drain pump installed
Legs for roof mounted support is sealed for water proof
Crank case heater installed
Seismic rated equipment stand for roof mounted units installed
Minimum 3/4" condensate drain line
B. Air-Cooled Condensing Unit Yes, No, N/A Comment/ Issues
Low ambient temperature controls installed
Factory wall mounting hardware used in installation
2. Construction Checklist
A. Indoor Unit Yes, No, N/A Comment/ Issues
Slide-in air filter installed
3/7/2024 20 B01S CU-10 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Training plan and instructor qualifications has been complete and provided to the GC for approval by the owner
TAB report is complete and has been provided to the GC for approval by the owner
Start-up report is complete and has been provided to the GC for approval by the owner
Operation & Maintenance manual has been compiled and provided to the GC for approval by the owner
Unit tags affixed
C. Other Yes, No, N/A Comment/Issues
The refrigerant line openings are sealed
Installation and startup manual provided
Unit is free from physical damage
All components present
Voltage / Phase / Frequency (V/ph/Hz)
B. Physical Checks Yes, No, N/A Comment/ Issues
Airflow Max/Min (cfm)
Fan Power/Speed (hp/rpm)
Serial Number
Size (in)
Manufacturer
Model
Service:
1. Delivery Book
A. Model Verification (Note: 1. as specified, 2.
as submitted, 3. as installed) Enter Note # Comment/ Issues
Manufacturer:
Model #:
Serial #:
Project Location: Huntington, WV
Equipment ID: CU-06
Equipment Location:
VRV Unit
Pre-Functional Checklist Project: Huntington VAMC EHRM Upgrades Cx
Building: 01S
3/7/2024 21 B01S CU-11 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Device Calibration checks have been completed and documentation record submitted for this system
System graphics have been installed
Split system works off thermostat and reaches setpoint
Specified point-to-point checks have been completed and documentation record submitted for this system
System has correct refrigerant charge
Motors and compressors running in the right direction
Control wiring between fan coil and condensing unit installed
Controls contractor has status monitored
E. Controls Yes, No, N/A Comment/ Issues
Thermostat mounted and wired if not remote controller
D. Electrical Yes, No, N/A Comment/ Issues
Power wiring connected, secure and grounded to both units
Lineset is properly insulated
Minimum of 12" braided flexible refrigerant line
Vacuum pulled on lineset
Lineset is strapped properly
C. Piping Yes, No, N/A Comment/ Issues
Refrigeration lineset pressure tested
Minimum 20 gage sheet metal pan around refrigerant lines from bottom wall anchor to eave
20 gage sheet metal pan is painted to match building color of oil base paint
Condensate drain pump installed
Legs for roof mounted support is sealed for water proof
Crank case heater installed
Seismic rated equipment stand for roof mounted units installed
Minimum 3/4" condensate drain line
B. Air-Cooled Condensing Unit Yes, No, N/A Comment/ Issues
Low ambient temperature controls installed
Factory wall mounting hardware used in installation
2. Construction Checklist
A. Indoor Unit Yes, No, N/A Comment/ Issues
Slide-in air filter installed
3/7/2024 22 B01S CU-11 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Training plan and instructor qualifications has been complete and provided to the GC for approval by the owner
TAB report is complete and has been provided to the GC for approval by the owner
Start-up report is complete and has been provided to the GC for approval by the owner
Operation & Maintenance manual has been compiled and provided to the GC for approval by the owner
Unit tags affixed
C. Other Yes, No, N/A Comment/Issues
The refrigerant line openings are sealed
Installation and startup manual provided
Unit is free from physical damage
All components present
Voltage / Phase / Frequency (V/ph/Hz)
B. Physical Checks Yes, No, N/A Comment/ Issues
Airflow Max/Min (cfm)
Fan Power/Speed (hp/rpm)
Serial Number
Size (in)
Manufacturer
Model
Service:
1. Delivery Book
A. Model Verification (Note: 1. as specified, 2.
as submitted, 3. as installed) Enter Note # Comment/ Issues
Manufacturer:
Model #:
Serial #:
Project Location: Huntington, WV
Equipment ID: CU-12
Equipment Location:
VRV Unit
Pre-Functional Checklist Project: Huntington VAMC EHRM Upgrades Cx
Building: 01S
3/7/2024 23 B01S CU-12 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Device Calibration checks have been completed and documentation record submitted for this system
System graphics have been installed
Split system works off thermostat and reaches setpoint
Specified point-to-point checks have been completed and documentation record submitted for this system
System has correct refrigerant charge
Motors and compressors running in the right direction
Control wiring between fan coil and condensing unit installed
Controls contractor has status monitored
E. Controls Yes, No, N/A Comment/ Issues
Thermostat mounted and wired if not remote controller
D. Electrical Yes, No, N/A Comment/ Issues
Power wiring connected, secure and grounded to both units
Lineset is properly insulated
Minimum of 12" braided flexible refrigerant line
Vacuum pulled on lineset
Lineset is strapped properly
C. Piping Yes, No, N/A Comment/ Issues
Refrigeration lineset pressure tested
Minimum 20 gage sheet metal pan around refrigerant lines from bottom wall anchor to eave
20 gage sheet metal pan is painted to match building color of oil base paint
Condensate drain pump installed
Legs for roof mounted support is sealed for water proof
Crank case heater installed
Seismic rated equipment stand for roof mounted units installed
Minimum 3/4" condensate drain line
B. Air-Cooled Condensing Unit Yes, No, N/A Comment/ Issues
Low ambient temperature controls installed
Factory wall mounting hardware used in installation
2. Construction Checklist
A. Indoor Unit Yes, No, N/A Comment/ Issues
Slide-in air filter installed
3/7/2024 24 B01S CU-12 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Training plan and instructor qualifications has been complete and provided to the GC for approval by the owner
TAB report is complete and has been provided to the GC for approval by the owner
Start-up report is complete and has been provided to the GC for approval by the owner
Operation & Maintenance manual has been compiled and provided to the GC for approval by the owner
Unit tags affixed
C. Other Yes, No, N/A Comment/Issues
The refrigerant line openings are sealed
Installation and startup manual provided
Unit is free from physical damage
All components present
Voltage / Phase / Frequency (V/ph/Hz)
B. Physical Checks Yes, No, N/A Comment/ Issues
Airflow Max/Min (cfm)
Fan Power/Speed (hp/rpm)
Serial Number
Size (in)
Manufacturer
Model
Service:
1. Delivery Book
A. Model Verification (Note: 1. as specified, 2.
as submitted, 3. as installed) Enter Note # Comment/ Issues
Manufacturer:
Model #:
Serial #:
Project Location: Huntington, WV
Equipment ID: CU-13
Equipment Location:
VRV Unit
Pre-Functional Checklist Project: Huntington VAMC EHRM Upgrades Cx
Building: 01S
3/7/2024 25 B01S CU-13 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Device Calibration checks have been completed and documentation record submitted for this system
System graphics have been installed
Split system works off thermostat and reaches setpoint
Specified point-to-point checks have been completed and documentation record submitted for this system
System has correct refrigerant charge
Motors and compressors running in the right direction
Control wiring between fan coil and condensing unit installed
Controls contractor has status monitored
E. Controls Yes, No, N/A Comment/ Issues
Thermostat mounted and wired if not remote controller
D. Electrical Yes, No, N/A Comment/ Issues
Power wiring connected, secure and grounded to both units
Lineset is properly insulated
Minimum of 12" braided flexible refrigerant line
Vacuum pulled on lineset
Lineset is strapped properly
C. Piping Yes, No, N/A Comment/ Issues
Refrigeration lineset pressure tested
Minimum 20 gage sheet metal pan around refrigerant lines from bottom wall anchor to eave
20 gage sheet metal pan is painted to match building color of oil base paint
Condensate drain pump installed
Legs for roof mounted support is sealed for water proof
Crank case heater installed
Seismic rated equipment stand for roof mounted units installed
Minimum 3/4" condensate drain line
B. Air-Cooled Condensing Unit Yes, No, N/A Comment/ Issues
Low ambient temperature controls installed
Factory wall mounting hardware used in installation
2. Construction Checklist
A. Indoor Unit Yes, No, N/A Comment/ Issues
Slide-in air filter installed
3/7/2024 26 B01S CU-13 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Training plan and instructor qualifications has been complete and provided to the GC for approval by the owner
TAB report is complete and has been provided to the GC for approval by the owner
Start-up report is complete and has been provided to the GC for approval by the owner
Operation & Maintenance manual has been compiled and provided to the GC for approval by the owner
Unit tags affixed
C. Other Yes, No, N/A Comment/Issues
The refrigerant line openings are sealed
Installation and startup manual provided
Unit is free from physical damage
All components present
Voltage / Phase / Frequency (V/ph/Hz)
B. Physical Checks Yes, No, N/A Comment/ Issues
Airflow Max/Min (cfm)
Fan Power/Speed (hp/rpm)
Serial Number
Size (in)
Manufacturer
Model
Service:
1. Delivery Book
A. Model Verification (Note: 1. as specified, 2.
as submitted, 3. as installed) Enter Note # Comment/ Issues
Manufacturer:
Model #:
Serial #:
Project Location: Huntington, WV
Equipment ID: CU-01
Equipment Location:
VRV Unit
Pre-Functional Checklist Project: Huntington VAMC EHRM Upgrades Cx
Building: 01W
3/7/2024 27 B01W CU-01 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Device Calibration checks have been completed and documentation record submitted for this system
System graphics have been installed
Split system works off thermostat and reaches setpoint
Specified point-to-point checks have been completed and documentation record submitted for this system
System has correct refrigerant charge
Motors and compressors running in the right direction
Control wiring between fan coil and condensing unit installed
Controls contractor has status monitored
E. Controls Yes, No, N/A Comment/ Issues
Thermostat mounted and wired if not remote controller
D. Electrical Yes, No, N/A Comment/ Issues
Power wiring connected, secure and grounded to both units
Lineset is properly insulated
Minimum of 12" braided flexible refrigerant line
Vacuum pulled on lineset
Lineset is strapped properly
C. Piping Yes, No, N/A Comment/ Issues
Refrigeration lineset pressure tested
Minimum 20 gage sheet metal pan around refrigerant lines from bottom wall anchor to eave
20 gage sheet metal pan is painted to match building color of oil base paint
Condensate drain pump installed
Legs for roof mounted support is sealed for water proof
Crank case heater installed
Seismic rated equipment stand for roof mounted units installed
Minimum 3/4" condensate drain line
B. Air-Cooled Condensing Unit Yes, No, N/A Comment/ Issues
Low ambient temperature controls installed
Factory wall mounting hardware used in installation
2. Construction Checklist
A. Indoor Unit Yes, No, N/A Comment/ Issues
Slide-in air filter installed
3/7/2024 28 B01W CU-01 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Training plan and instructor qualifications has been complete and provided to the GC for approval by the owner
TAB report is complete and has been provided to the GC for approval by the owner
Start-up report is complete and has been provided to the GC for approval by the owner
Operation & Maintenance manual has been compiled and provided to the GC for approval by the owner
Unit tags affixed
C. Other Yes, No, N/A Comment/Issues
The refrigerant line openings are sealed
Installation and startup manual provided
Unit is free from physical damage
All components present
Voltage / Phase / Frequency (V/ph/Hz)
B. Physical Checks Yes, No, N/A Comment/ Issues
Airflow Max/Min (cfm)
Fan Power/Speed (hp/rpm)
Serial Number
Size (in)
Manufacturer
Model
Service:
1. Delivery Book
A. Model Verification (Note: 1. as specified, 2.
as submitted, 3. as installed) Enter Note # Comment/ Issues
Manufacturer:
Model #:
Serial #:
Project Location: Huntington, WV
Equipment ID: CU-02
Equipment Location:
VRV Unit
Pre-Functional Checklist Project: Huntington VAMC EHRM Upgrades Cx
Building: 01W
3/7/2024 29 B01W CU-02 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Device Calibration checks have been completed and documentation record submitted for this system
System graphics have been installed
Split system works off thermostat and reaches setpoint
Specified point-to-point checks have been completed and documentation record submitted for this system
System has correct refrigerant charge
Motors and compressors running in the right direction
Control wiring between fan coil and condensing unit installed
Controls contractor has status monitored
E. Controls Yes, No, N/A Comment/ Issues
Thermostat mounted and wired if not remote controller
D. Electrical Yes, No, N/A Comment/ Issues
Power wiring connected, secure and grounded to both units
Lineset is properly insulated
Minimum of 12" braided flexible refrigerant line
Vacuum pulled on lineset
Lineset is strapped properly
C. Piping Yes, No, N/A Comment/ Issues
Refrigeration lineset pressure tested
Minimum 20 gage sheet metal pan around refrigerant lines from bottom wall anchor to eave
20 gage sheet metal pan is painted to match building color of oil base paint
Condensate drain pump installed
Legs for roof mounted support is sealed for water proof
Crank case heater installed
Seismic rated equipment stand for roof mounted units installed
Minimum 3/4" condensate drain line
B. Air-Cooled Condensing Unit Yes, No, N/A Comment/ Issues
Low ambient temperature controls installed
Factory wall mounting hardware used in installation
2. Construction Checklist
A. Indoor Unit Yes, No, N/A Comment/ Issues
Slide-in air filter installed
3/7/2024 30 B01W CU-02 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Training plan and instructor qualifications has been complete and provided to the GC for approval by the owner
TAB report is complete and has been provided to the GC for approval by the owner
Start-up report is complete and has been provided to the GC for approval by the owner
Operation & Maintenance manual has been compiled and provided to the GC for approval by the owner
Unit tags affixed
C. Other Yes, No, N/A Comment/Issues
The refrigerant line openings are sealed
Installation and startup manual provided
Unit is free from physical damage
All components present
Voltage / Phase / Frequency (V/ph/Hz)
B. Physical Checks Yes, No, N/A Comment/ Issues
Airflow Max/Min (cfm)
Fan Power/Speed (hp/rpm)
Serial Number
Size (in)
Manufacturer
Model
Service:
1. Delivery Book
A. Model Verification (Note: 1. as specified, 2.
as submitted, 3. as installed) Enter Note # Comment/ Issues
Manufacturer:
Model #:
Serial #:
Project Location: Huntington, WV
Equipment ID: CU-03
Equipment Location:
VRV Unit
Pre-Functional Checklist Project: Huntington VAMC EHRM Upgrades Cx
Building: 01W
3/7/2024 31 B01W CU-03 PFC
Direct: (619) 770-8552
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Contractor
Initial
CM
Initial Date
Device Calibration checks have been completed and documentation record submitted for this system
System graphics have been installed
Split system works off thermostat and reaches setpoint
Specified point-to-point checks have been completed and documentation record submitted for this system
System has correct refrigerant charge
Motors and compressors running in the right direction
Control wiring between fan coil and condensing unit installed
Controls contractor has status monitored
E. Controls Yes, No, N/A Comment/ Issues
Thermostat mounted and wired if not remote controller
D. Electrical Yes, No, N/A Comment/ Issues
Power wiring connected, secure and grounded to both units
Lineset is properly insulated
Minimum of 12" braided flexible refrigerant line
Vacuum pulled on lineset
Lineset is strapped properly
C. Piping Yes, No, N/A Comment/ Issues
Refrigeration lineset pressure tested
Minimum 20 gage sheet metal pan around refrigerant lines from bottom wall anchor to eave
20 gage sheet metal pan is painted…