S06 - Amendment 0007 - ATT 6 - Crane lift Info.pdf

PDF 33 KB Posted

Attached to
EHRM Huntington VAMC 581-22-700 Construct Infrastructure Upgrades Federal contract opportunity
Solicitation number
36C77626R0025
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This document is a crane operations safety requirements specification for construction work at a VA (Veterans Affairs) facility.

All crane work must comply with 29 CFR 1926 Subpart CC and EM 385-1-1 standards. Crane operators must be licensed, qualified, or certified prior to operating equipment, with no phase-in period allowed. A detailed lift plan must be submitted to the Resident Engineer 14 days before each scheduled lift, including truck route, crane load analysis, crane positioning, swing path, and other critical lift elements. Critical lifts require comprehensive planning to minimize crane failure and catastrophic loss risks. The General Contractor must review and accept the lift plan before VA submission, and the Facility Safety Manager or Contracting Officer Representative (COR) must approve it before work proceeds.

Crane operators are prohibited from carrying loads over general public or VAMC personnel. Loads cannot be carried over occupied buildings unless one of three conditions is met: (1) the top two or more floors are vacated and Professional Engineer analysis demonstrates adequate overhead protection from roof and vacated floors, or minimum 300 psf protection; (2) Professional Engineer-designed overhead protection is installed over the roof by the contractor with sufficient protection against load loss or minimum 300 psf; or (3) formal documentation is submitted to the Contracting Officer showing the building roof was previously designed with reinforced concrete or equivalent means to provide overhead protection from construction activities, supported by Professional Engineer analysis demonstrating adequate protection or minimum 300 psf protection.

View the file

Other files for this federal contract opportunity

Other files attached to EHRM Huntington VAMC 581-22-700 Construct Infrastructure Upgrades, newest first.
File Type Posted
S06 - 36C77626R0025 0008.pdf PDF
S06 - Amendment 0008 - ATT 3 - Civil OSP Redesign-signed.pdf PDF
S06 - Amendment 0008 - ATT 7 - 02EP100B - ELECTRICAL 20260413.pdf PDF
S06 - Amendment 0008 - ATT 8 - 260508 - Sheet 01S-AE452 TR Tower 4 Wall sections update.pdf PDF
S06 - Amendment 0008 - ATT 12 - Environmental Report Huntington WV.pdf PDF
S06 - Amendment 0008 - ATT 13 - Hot Tapping Permit.pdf PDF
S06 - Amendment 0008 - ATT 1 - TechQuestionsVAresponses Final Set - Huntington EHRM IU.pdf PDF
S06 - Amendment 0008 - ATT 10 - 260508 - Sheet AD103-1B Data Center Phase 1B Demo Roof update.pdf PDF
S06 - Amendment 0008 - ATT 11 - Burn Permit.pdf PDF
S06 - Amendment 0008 - ATT 14 - Energized Electrical Work Permit.pdf PDF
S06 - 36C77626R0025 0007.pdf PDF
S06 - Amendment 0007 - ATT 1 - TechQuestionsVAresponses Partial 4 - Huntington EHRM IU.pdf PDF
S06 - Amendment 0007 - ATT 5 - Appendix A - PFC FPT.pdf PDF
S06 - 36C77626R0025 0006.pdf PDF
S06 - Amendment 0006 - ATT 1 - TechQuestionsVAresponses Partial 3 - Huntington EHRM IU.pdf PDF
S06 - 36C77626R0025 0005.pdf PDF
S06 - Amendment 0004 - ATT 2 - FAR 52.222-90 ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS - APR 2026.pdf PDF
S06 - Amendment 0004 - ATT 1 - TechQuestionsVAresponses Partial 2 - Huntington EHRM IU.pdf PDF
S06 - 36C77626R0025 0004.pdf PDF
S06 - Amendment 0003 - ATT 2 - TechQuestionsVAresponses Partial - Huntington EHRM IU.pdf PDF
S06 - 36C77626R0025 0003.pdf PDF
S06 - 36C77626R0025 0002.pdf PDF
S06 - Amendment 0001 - ATT 1 - Site Visit In-Sheet - Huntington EHRM IU.pdf PDF
S06 - 36C77626R0025 0001.pdf PDF
S02 - ATT 10 - 581-22-700 - 100 Drawings Part-8 of 24.pdf PDF
S02 - ATT 14 - 581-22-700 - 100 Drawings Part-12 of 24.pdf PDF
S02 - ATT 27 - 581-22-700 - Asbestos locations.xlsx XLSX spreadsheet
S02 - ATT 28 - 581-22-700 - FLS Compliance Letter.pdf PDF
S02 - 36C77626R0025.pdf PDF
S02 - ATT 1 - 581-22-700 - 100 Specifications Part-1 of 2.pdf PDF
S02 - ATT 2 - 581-22-700 - 100 Specifications Part-2 of 2.pdf PDF
S02 - ATT 9 - 581-22-700 - 100 Drawings Part-7 of 24.pdf PDF
S02 - ATT 11 - 581-22-700 - 100 Drawings Part-9 of 24.pdf PDF
S02 - ATT 15 - 581-22-700 - 100 Drawings Part-13 of 24.pdf PDF
S02 - ATT 18 - 581-22-700 - 100 Drawings Part-16 of 24.pdf PDF
S02 - ATT 20 - 581-22-700 - 100 Drawings Part-18 of 24.pdf PDF
S02 - ATT 23 - 581-22-700 - 100 Drawings Part-21 of 24.pdf PDF
S02 - ATT 24 - 581-22-700 - 100 Drawings Part-22 of 24.pdf PDF
S02 - ATT 30 - 581-22-700 - 100 Commissioning Plan.pdf PDF
S02 - ATT 3 - 581-22-700 - 100 Drawings Part-1 of 24.pdf PDF
S02 - ATT 4 - 581-22-700 - 100 Drawings Part-2 of 24.pdf PDF
S02 - ATT 5 - 581-22-700 - 100 Drawings Part-3 of 24.pdf PDF
S02 - ATT 6 - 581-22-700 - 100 Drawings Part-4 of 24.pdf PDF
S02 - ATT 7 - 581-22-700 - 100 Drawings Part-5 of 24.pdf PDF
S02 - ATT 17 - 581-22-700 - 100 Drawings Part-15 of 24.pdf PDF
S02 - ATT 19 - 581-22-700 - 100 Drawings Part-17 of 24.pdf PDF
S02 - ATT 22 - 581-22-700 - 100 Drawings Part-20 of 24.pdf PDF
S02 - ATT 26 - 581-22-700 - 100 Drawings Part-24 of 24.pdf PDF
S02 - ATT 33 - WD - WV20260048 - 01-02-2026.pdf PDF
S02 - ATT 35 - Site Visit Information - Huntington EHRM IU.pdf PDF
Show all 50

EHRM Huntington VAMC 581-22-700 Construct Infrastructure Upgrades has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .