TABLE OF CONTENTS.pdf
PDF 190 KB Posted
- Solicitation number
- W50S8T25BA011
- Issued by
-
Department of the Army National Guard
About this file
This is a Table of Contents document for the 137th SOW Oklahoma ANG B-3 100% Repair Building 1040 project, dated September 12, 2024, with Addendum #1 dated February 17, 2025.
The document outlines 33 construction divisions covering comprehensive building renovation work including general requirements, existing conditions (demolition, asbestos and lead remediation), concrete, masonry, metals, wood/plastics/composites, thermal and moisture protection, openings, finishes, specialties, equipment, furnishings, fire suppression, plumbing, HVAC, integrated automation (including cybersecurity systems), electrical systems, communications, electronic safety and security, earthwork, exterior improvements, and utilities. Notable specialized components include BACnet digital control systems, engine-generator sets, interior fire alarm and mass notification systems, and telecommunications infrastructure. The scope suggests a major facility renovation project requiring coordination across multiple construction trades and technical disciplines.
View the file
Other files
Show all 50
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
137TH SOW OKLAHOMA ANG B-3 100% REPAIR BUILDING 1040
OKLAHOMA CITY, OK 12 SEPTEMBER, 2024
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 20 00 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 35 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 91 00.15 10 TOTAL BUILDING COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 82 00 ASBESTOS REMEDIATION
02 83 00 LEAD REMEDIATION
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 20 00 MASONRY
DIVISION 05 - METALS
05 12 00 STRUCTURAL STEEL
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 20 00 FINISH CARPENTRY
06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
06 61 16 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 BOARD AND BLOCK INSULATION
07 21 16 MINERAL FIBER BLANKET INSULATION
07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 27 36 SPRAY FOAM AIR BARRIERS
07 60 00 FLASHING AND SHEET METAL
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
PROJECT TABLE OF CONTENTS Page 1
Gallagher, Brad K.
Text Box
ADDENDUM #1 - 02-17-2025
Gallagher, Brad K.
Cloud
08 11 13 STEEL DOORS AND FRAMES
08 11 16 ALUMINUM DOORS AND FRAMES
08 14 00 WOOD DOORS
08 31 00 ACCESS DOORS AND PANELS
08 34 73 SOUND CONTROL DOOR ASSEMBLIES
08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 87 23.13 SAFETY FILMS
08 91 00 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 ACOUSTICAL CEILINGS
09 62 38 STATIC-CONTROL FLOORING
09 65 00 RESILIENT FLOORING
09 68 00 CARPETING
09 69 13 RIGID GRID ACCESS FLOORING
09 72 00 WALLCOVERINGS
09 90 00 PAINTS AND COATINGS
09 96 00 HIGH-PERFORMANCE COATINGS
DIVISION 10 - SPECIALTIES
10 11 00 VISUAL DISPLAY UNITS
10 14 00.20 INTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 22 39 FOLDING PANEL PARTITIONS
10 26 00 WALL AND DOOR PROTECTION
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
10 51 13 LOCKERS
10 51 16 CELL PHONE LOCKERS
DIVISION 11 - EQUIPMENT
11 94 10 ROOFTOP FALL PROTECTION ANCHORS
DIVISION 12 - FURNISHINGS
12 21 00 WINDOW BLINDS
DIVISION 21 - FIRE SUPPRESSION
21 13 13 WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
PROJECT TABLE OF CONTENTS Page 2
Gallagher, Brad K.
Text Box
ADDENDUM #1 - 02-17-2025
Gallagher, Brad K.
Cloud
Gallagher, Brad K.
Line
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC
23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING
CONTROL SYSTEMS
23 11 20 FACILITY GAS PIPING
23 21 23 HYDRONIC PUMPS
23 23 00 REFRIGERANT PIPING
23 30 00 HVAC AIR DISTRIBUTION
23 52 00 HEATING BOILERS
23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING SYSTEMS
23 80 20.00 10 GAS-FIRED HEATING EQUIPMENT
23 81 00 DECENTRALIZED UNITARY HVAC EQUIPMENT
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.01 CYBERSECURITY FOR FACILITY-RELATED CONTROL SYSTEMS -
BUILDING CONTROL SYSTEMS (BCS)
25 05 11.04 CYBERSECURITY FOR MODERATE IMPACT FIRE PROTECTION CONTROL
SYSTEMS
25 08 10 UTILITY MONITORING AND CONTROL SYSTEM TESTING
DIVISION 26 - ELECTRICAL
26 05 26.00 40 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 05 71.00 40 LOW VOLTAGE OVERCURRENT PROTECTIVE DEVICES
2626 05 73 POWER SYSTEM STUDIES
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 32 15 ENGINE-GENERATOR SET STATIONARY 15-2500 KW, WITH
AUXILIARIES
26 36 23 AUTOMATIC TRANSFER SWITCHES AND BY-PASS/ISOLATION SWITCH
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
26 53 00.00 40 EXIT SIGNS
DIVISION 27 - COMMUNICATIONS
27 05 13.43 TELEVISION DISTRIBUTION SYSTEM
27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
27 13 23.00 40 COMMUNICATIONS OPTICAL BACKBONE CABLING
27 51 16 PUBLIC ADDRESS SYSTEMS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM,
ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19.61 SEALING OF JOINTS IN RIGID PAVEMENT
32 11 20 BASE COURSE FOR RIGID PAVING
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE
FACILITIES
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 PAVEMENT MARKINGS
PROJECT TABLE OF CONTENTS Page 3
26 09 23.00 40 LIGHTING CONTROL DEVICES
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 32 15 ENGINE-GENERATOR SET STATIONARY 15-2500 KW, WITH
AUXILIARIES
26 36 23 AUTOMATIC TRANSFER SWITCHES AND BY-PASS/ISOLATION SWITCH
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
26 53 00.00 40 EXIT SIGNS
DIVISION 27 - COMMUNICATIONS
27 05 13.43 TELEVISION DISTRIBUTION SYSTEM
27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
27 13 23.00 40 COMMUNICATIONS OPTICAL BACKBONE CABLING
27 51 16 PUBLIC ADDRESS SYSTEMS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM,
ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19.61 SEALING OF JOINTS IN RIGID PAVEMENT
32 11 20 BASE COURSE FOR RIGID PAVING
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE
FACILITIES
32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 PAVEMENT MARKINGS
nmorrell Cloud nmorrell Text Box
ADDENDUM #1 - 02-17-2025
DIVISION 33 - UTILITIES
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 4
| OK B1040 Cover - Vol1 |
| Sign n Seal Page OK ANG |
| TABLE OF CONTENTS |
| SECTION 28 3176 - INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM |
| This Page Intentionally Left Blank |
| SECTION 33 1615 - WATER STORAGE STEEL TANKS | |
| SECTION 33 1615 - WATER STORAGE STEEL TANKS | |
| PART 1 - GENERAL | |
| 1.1 REFERENCES | |
| A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only. | |
| B. AMERICAN WATER WORKS ASSOCIATION (AWWA) | |
| 1. AWWA C104/A21.4 | (2016) Cement-Mortar Lining for Ductile-Iron Pipe and Fittings for Water |
| 2. AWWA C105/A21.5 | (2010) Polyethylene Encasement for Ductile-Iron Pipe Systems |
| 3. AWWA C110/A21.10 | (2012) Ductile-Iron and Gray-Iron Fittings for Water |
| 4. AWWA C111/A21.11 | (2017) Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and Fittings |
| 5. AWWA C115/A21.15 | (2011) Flanged Ductile-Iron Pipe with Ductile-Iron or Gray-Iron Threaded Flanges |
| 6. AWWA C150/A21.50 | (2014) Thickness Design of Ductile-Iron Pipe |
| 7. AWWA C151/A21.51 | (2017) Ductile-Iron Pipe, Centrifugally Cast |
| 8. AWWA C500 | (2009) Metal-Seated Gate Valves for Water Supply Service |
| 9. AWWA C600 | (2017) Installation of Ductile-Iron Mains and Their Appurtenances |
| 10. AWWA D100 | (2011) Welded Steel Tanks for Water Storage |
| 11. AWWA D103 | (2009; Errata 2010; Addenda 2014) Factory-Coated Bolted Steel Tanks for Water Storage |
| C. ASME INTERNATIONAL (ASME) | |
| 1. ASME B16.3 | (2016) Malleable Iron Threaded Fittings, Classes 150 and 300 |
| 2. ASME B40.100 | (2013) Pressure Gauges and Gauge Attachments |
| D. ASTM INTERNATIONAL (ASTM) | |
| 1. ASTM A48/A48M | (2003; R 2012) Standard Specification for Gray Iron Castings |
| 2. ASTM A53/A53M | (2018) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless |
| 3. ASTM A197/A197M | (2000; R 2015) Standard Specification for Cupola Malleable Iron |
| E. AMERICAN SOCIETY OF SANITARY ENGINEERS (ASSE) |
| 1. (2011) Performance Requirements for Double Check Backflow Prevention Assemblies and Double Check Fire Protection Backflow Prevention Assemblies - (ANSI approved) |
| F. MANUFACTURERS STANDARDIZATION SOCIETY OF THE VALVE AND FITTINGS INDUSTRY (MSS) | |
| 1. MSS SP-80 | (2013) Bronze Gate, Globe, Angle and Check Valves |
| G. NATIONAL FIRE PROTECTION ASSOCIATION (NFPA) | |
| 1. NFPA 22 | (2018) Standard for Water Tanks for Private Fire Protection |
| H. SOCIETY FOR PROTECTIVE COATINGS (SSPC) | |
| 1. SSPC PS 4.04 | (1982; E 2004) Four-Coat White or Colored Vinyl Painting System (For Fresh Water, Chemical, and Corrosive Atmospheres) |
| 2. SSPC PS Guide 17.00 | (1982; E 2004) Guide for Selecting Urethane Painting Systems |
| 3. SSPC Paint 21 | (1982; E 2004) White or Colored Silicone Alkyd Paint (Type I, High Gloss and Type II, Medium Gloss) |
| 4. SSPC Paint 25 | (1997; E 2004) Zinc Oxide, Alkyd, Linseed Oil Primer for Use Over Hand Cleaned Steel, Type I and Type II |
| 5. SSPC Paint 104 | (1982; E 2004) White or Tinted Alkyd Paint |
| I. U.S. DEPARTMENT OF DEFENSE (DOD) | |
| 1. MIL-DTL-24441 | (2009; Rev D) Paint, Epoxy-Polyamide, General Specification for |
| 2. MIL-PRF-23236 | (2009; Rev D) Coating Systems for Ship Structures |
| J. U.S. FEDERAL AVIATION ADMINISTRATION (FAA) | |
| 1. FAA AC 150/5345-43 | (2016; Rev H2019; Rev J) Specification for Obstruction Lighting Equipment |
| 1.2 SUBMITTALS |
| A. Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 3329 SUSTAINABILITY REPORTING. The Fire Protection Engineer identified in Section 21 1313 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION shall approve all submittals before submitting to the Authorities having Jurisdiction, and shall provide all services defined in Section 21 1313 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION. Submit the following in accordance with Section 01 3300 SUBMITTAL PROCEDURES: |
| 1. SD-02 Shop Drawings |
| a. Tank Installation; G |
| 2. SD-03 Product Data |
| a. System Description |
| b. Foundations |
| c. Altitude Valve |
| d. Exterior Tank Level Gauge |
| 3. SD-06 Test Reports |
| a. Tank Installation |
| b. Testing of Valves and Piping |
| 4. SD-07 Certificates |
| a. System Description |
| b. Foundations |
| 1.3 QUALIFICATIONS |
| A. Fire Protection Engineer |
| 1. Fire Protection Engineer shall be the same person as submitted in Section 21 1313 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION and shall have the same duties. Fire Protection Engineer shall approve all submittals and certify the installation meets the requirements or the contract documents and referenced criteria. |
| 1.4 DELIVERY, STORAGE, AND HANDLING |
| A. Deliver paint in unopened containers with unbroken seals and labels showing designated name, specification number, color, directions for use, manufacturer, and date of manufacture, legible and intact at time of use. Handle and store water storage tank systems, components, and parts to prevent distortions and other damage that could affect their structural, mechanical, or electrical integrity. Replace damaged items that cannot be restored to original condition. Store items subject to deterioration by exposure to elements, in a well-drained location, protected from weather, and accessible for inspection and handling. |
| PART 2 - PRODUCTS |
| 2.1 SYSTEM DESCRIPTION |
| A. The water storage tank is intended to be a suction tank used for fire protection water supply, and shall comply with all NFPA requirements, specifically NFPA 22. It is the Contractor's responsibility to produce a complete and working system, including, but not limited to items and components referenced on the drawings. |
| B. Submit a certificate signed by a registered professional engineer, providing the following information: |
| 1. Description of the structural design loading conditions used for the design of entire tank including the foundation. |
| 2. Description of the structural design method and codes used in establishing the allowable stresses and safety factors applied in the design. |
| 3. A statement verifying that the structural design has been checked by experienced engineers specializing in hydraulic structures. |
| 4. A statement verifying that the detail drawings have been checked by experienced engineers specializing in hydraulic structures to determine that they agree with the design calculations in member sizes, dimensions, and fabricating process as prescribed by applicable ACI and AWWA standards. |
| C. Design and Construction Standards |
| 1. The design, fabrication, and erection of the reservoir shall be in accordance with the applicable requirements of AWWA D100 or AWWA D103 except as modified herein. Earthquake design shall be. Submit Design Analyses and Calculations. No additional thickness for corrosion allowance will be required. Design metal temperature shall be per manufacturer's recommendation. The reservoir shall be designed for a peak wind speed and snow load per manufacturer's recommendations. |
| D. Welding |
| 1. Qualification of welding procedures, welders, and welding operators shall be in accordance with Section 8.2 of AWWA D100. |
| E. Sizing and Design |
| 1. Sizing and design of tank shall be in accordance with Section 4 of AWWA D100. Submit a certificate signed by a registered professional engineer providing: (1) description of the entire tank and foundation structural design loading conditions, (2) description of structural design methods and codes used in establishing allowable stresses and safety factors, (3) statement that the structural design has been checked by experienced engineers specializing in hydraulic structures to ensure that design calculations for member sizes, dimensions, and fabrication processes are as prescribed by ACI and AWWA standards, and (4) certification that the completed work was inspected in accordance with AWWA D100 or AWWA D103 as applicable. |
| F. Reservoir |
| 1. The reservoir must be able to provide a 45 minute discharge of the combined hangar sprinkler and foam system while the altitude valve is simultaneously filling the tank from the domestic water supply based on the Contractor performed hydrant flow test while also flowing 500 gpm from the nearest hydrant. |
| 2. The Fire Protection Engineer shall calculate the required water storage tank levels as follows: |
| a. Determine fire suppression demand for 45 minutes duration. |
| b. Determine tank empty level: The tank empty level shall be calculated as the minimum available level with positive suction pressure at the fire pump after a full tank discharge with a discharge rate of 150% of the fire pump rated capacity. |
| c. Determine the available simultaneous refill capacity based on the water supply piping, backflow preventer and altitude valve provided, with the nearest hydrant flowing 500 gpm. Maintain minimum 25 psi in the domestic water system for this calculation. Target simultaneous fill rate is 1000 gpm. Do not exceed 1400 gpm simultaneous fill. |
| d. Determine net usable tank capacity in accordance with UFC 4-211-01 based on 1.2 times the fire suppression system demand flow rate less the simultaneous fill for the 45 minutes duration. |
| e. Tank low level alarm shall occur when the tank falls 1" (or more) below the level of the tank empty level plus the net usable capacity (the tank full level). |
| f. Altitude valve shall open when the level drops to the tank full level, before the tank low level arlarm is activated. |
| g. Altitude shall close as quickly as possible after the level reaches 12" above the tank full level. A typical altitude valve requires approximately 18" between open and close setpoints. |
| h. Tank overflow level is set at 1" (or more) above altitude close level. |
| i. Allow 6" or greater air gap above tank overflow inlet to discharge of tank fill piping. |
| j. Allow 10" or greater above tank fill piping discharge for fill piping elbow and clearance. |
| 3. Tank shall have a storage capacity of a minimum 60,000 gallons net usable capacity, while simultaneously refilling the tank at 1000 gpm. Increase capacity accordingly if hangar fire protection system flow rate exceeds 1970 gpm. |
| 4. The reservoir shall have such standard shell height and such diameter as will meet the requirements for the selected standard capacity and for the high-water level specified above. The reservoir may have supported cone roof, as approved. The reservoir shall be of welded or bolted construction. Calculations indicating levels shall be prepared by the Fire Protection Engineer and submitted for review. |
| G. Sizing of Reservoir |
| 1. Section 6 of AWWA D100 or Section 4 of AWWA D103. Minimum nominal capacity of the tank shall be 66,000 gallons, with 1'0" freeboard. Minimum sidewall height shall be 20 feet, based on 24'-7" diameter tank, 1250 gpm altitude valve concurrent fill rate and 1970 gpm demand. For 1000 gpm concurrent altitude valve fill rate and 1970 gpm demand, provide 24'7" diameter tank with minimum nominal capacity of 73,000 gallons, 22' sidewall. Capacity shall not be less than 120% of the design hangar fire protection demand. Capacity shall not have less than the net usable capacity described above. For tank diameters between 23'-6" and 25'-0", adjust sidewall height accordingly. |
| H. Coatings Certification |
| 1. Coating materials for interior applications and all other materials which will be in normal contact with potable water shall conform to NSF/ANSI 61. |
| 2.2 MATERIALS |
| A. Provide materials conforming to the following requirements: |
| 1. Steel |
| a. Schedule 40 steel. Section 2 of AWWA D100 or Section 2 of AWWA D103. |
| 2. Shop Fabrication |
| a. Section 9 of AWWA D100 or Section 7 of AWWA D103. |
| 3. Ductile-Iron Pipe |
| a. Pipe for fluid conductors, except for overflow pipe, shall be ductile-iron pipe or steel and shall be either of the following: |
| 1) Bell-and-Plain End Pipe |
| a) AWWA C150/A21.50 and AWWA C151/A21.51, for not less than 150 psi working pressure, unless otherwise shown or specified. Joints shall be push-on or mechanical-joint conforming to AWWA C111/A21.11. Pipe shall be cement mortar lined in accordance with AWWA C104/A21.4. Linings shall be standard thickness. |
| 2) Flanged Pipe |
| a) Flanged pipes shall conform to the applicable portions of AWWA C110/A21.10, AWWA C115/A21.15 and AWWA C151/A21.51, for not less than 150 psi working pressure, unless otherwise shown or specified. Pipe shall have flanged ends in accordance with AWWA C115/A21.15. Pipe shall be cement mortar lined in accordance with AWWA C104/A21.4. Linings shall be standard thickness. |
| 4. Specials and Fittings (except for overflow pipe) |
| a. Ductile-Iron with Bell-and-Plain End |
| 1) AWWA C110/A21.10 and AWWA C151/A21.51 for not less than 150 psi working pressure, unless otherwise shown or specified. Specials and fittings shall be cement mortar lined in accordance with AWWA C104/A21.4. Linings shall be standard thickness. |
| b. Ductile-Iron with Flanged Ends |
| 1) AWWA C110/A21.10 and AWWA C151/A21.51 for not less than 150 psi working pressure unless otherwise shown or specified. Fittings shall have flanged ends in accordance with AWWA C110/A21.10. Specials and fittings shall be cement mortar lined in accordance with AWWA C104/A21.4. Linings shall be standard thickness. |
| c. Fittings for Screw-Joint Pipe |
| 1) Malleable-iron, galvanized, 150 psi, ASTM A197/A197M, threaded ends, ASME B16.3. |
| d. Joints Inside Valve Chamber |
| 1) All joints inside the valve chamber shall be flanged. |
| 5. Valves |
| a. Gate Valves |
| 1) Gate valves shall be opened by turning counterclockwise. Valves 3 inches and larger shall be iron body, brass mounted, conforming to AWWA C500. Valves smaller than 3 inches shall be all bronze and shall conform to MSS SP-80, Type 1, class 150. Valves 3 inches or larger located in valve chambers shall be equipped with hand-operating wheels and shall be flanged. |
| b. Butterfly Valves |
| 1) Butterfly valves shall be opened by turning counterclockwise. Valves shall conform to AWWA C504. Body and disc shall be cast iron, conforming to ASTM A48/A48M. Shaft shall be 18-8 stainless steel. Resilient seat shall be bonded to the valve body. Butterfly valves shall be stainless steel to rubber seated, tight closing type. |
| c. Check Valves |
| 1) Check valves shall be of the horizontal swing-check type, suitable for the purpose and the operating conditions. The body shall be iron and shall have a removable gate assembly and a cover removable for inspection. The gate, gate seat, shaft, gate studs, and nuts shall be bronze or other suitable alloy. Valves shall conform to AWWA C508. |
| d. Altitude Valve |
| 1) The supply to the reservoir shall be controlled by a minimum 6 inch altitude valve, automatic in operation and accurately set to prevent overflow of the reservoir. The valve shall have flanged ends and a heavy cast iron body, shall be bronze fitted with renewable cups and seats, and shall be designed without metal-to-metal seats. The valve shall be cushioned when opening and closing to prevent water hammer or shock. Valves shall be provided with a travel indicator. |
| 2) Hydraulically operated valve shall be pilot controlled, one-way flow, with pressure sustaining feature to maintain minimum 25 psi in the domestic water system. Pressure sensing line shall be installed per manufacturer's instructions and protected from freezing. |
| 3) Valve shall be provided with on/off level, on at -12 inches from normal, and off at normal. Coordinate and provide valve start and stop setpoints, tank full and tank low level elevations, etc. |
| 6. Pressure Gauge |
| a. Pressure gauge of the direct-reading type, equipped with a shutoff cock, shall be provided in the valve chamber on the tank side and on the discharge side of the altitude valve. Gauges shall have 6 inch dials, shall be stem mounted, and shall conform to ASME B40.100. Accuracy of gauges shall be Grade A or better. Gauges shall be calibrated in psi in not more than 2 psi increments from 0 to 50 psi in excess of the normal operating pressure at the tank. |
| b. |
| 7. Backflow Preventer |
| a. Double-check backflow prevention assembly shall comply with ASSE 1015. The assembly shall have a bronze, cast-iron or stainless steel body with flanged ends. The assembly shall include pressure gauge test ports and OS&Y shutoff valves on the inlet and outlet, 2-positive-seating check valve for continuous pressure application, and four test cocks. Assemblies shall be rated for working pressure of 175 psi The maximum pressure loss shall be 8 psi at a flow rate equal to the tank fill or sprinkler water demand, at the location of the assembly. A test port and a pressure gauge with valve shall be provided both upstream and downstream of the double check backflow prevention assembly valves. Provide tamper (supervisory) switch at each control valve. |
| b. |
| 8. Exterior Tank Level Gauge |
| a. Provide visible exterior tank water level gauge readily available and viewable from the road for each tank in accordance with NFPA 22 and manufacturer's recommendations and requirements. |
| 9. Appurtenances |
| a. Automatic controls for maintaining water level in tank, with valves, piping and audible and visual alarms to indicate the following: High and low water levels. Water level off-normal. (+/- 3") Water level returned to normal. Provide nozzle on wall of tank for each device in approved location. |
| 2.3 ASSEMBLIES |
| A. Tank Accessories |
| 1. Section 7 of AWWA D100 or Section 5 of AWWA D103 and as specified. Additional requirements for accessories are as follows: |
| a. Manholes and Pipe Connections |
| 1) Section 7 of AWWA D100 and Section 5 of AWWA D103 represent the minimum requirements. Number, type, location, and size of manholes and pipe connections shall be per NFPA 22 and as recommended by tank manufacturer.Inlet pipe connections shall be provided with deflectors and routed inside the tank to the remote half of the tank. Outlet pipe connections shall be provided with vortex breakers per NFPA 22. |
| b. Overflow |
| 1) The overflow for the tank shall consist of an overflow weir and stub overflow or outside drop pipe, adequately supported and capable of discharging at a rate of 1250 gpm. The top of the weir shall be 6 inches minimum below the turned down 90 degree fill pipe. The weir shall be located per manufacturers recommendation. The stub overflow shall be steel, ASTM A53/A53M or equal, and shall be fitted with a screen and the overflow pipe shall be steel, ASTM A53/A53M or equal, and shall terminate 1 to 2 feet above grade and shall be fitted with a flapper valve or screen to prevent ingress of animals and insects. Overflow pipe shall be at least one size larger than fill pipe. |
| c. Vent |
| 1) Vent shall be welded to the cover plate of the center manhole on the roof. Vent will be tank manufacturer's standard type mushroom vent with aluminum bird screen. The free area of the vent shall be sized 50 percent in excess of the 1,000 gpm pump-in rate and 3,000 gpm pump-out rate. Screening for vent shall conform to Section 5.7.2 of AWWA D100 or Section 5.7.2 of AWWA D103which ensures fail-safe operation in the event that screen frosts over and the bottom of the screen shall be sufficiently elevated for snow consideration in the area. |
| d. Ladders and Safety Devices |
| 1) Ladders and safety devices shall be provided in accordance with Sections 7.4 and 7.5 of AWWA D100 or Sections 5.4 and 5.5 of AWWA D103. Location of ladders shall be as shown on the drawings. Sections 7.4 and 7.5 of AWWA D100 and Sections 5.4 and 5.5 of AWWA D103 represent the minimum requirement. In addition, safety cage, rest platforms, roof ladder handrails, and other safety devices shall be provided as required by federal or local laws or regulations. |
| e. Scaffold Cable Support |
| 1) Provision shall be made for the attachment of a scaffold cable support at the top of the roof on welded tanks. |
| f. Balconies |
| 1) Provide a balcony a minimum of 2 feet wide with a standard guard railing. Provide a structural steel railing with a top rail 42 inches above balcony platform with an intermediate rail halfway between. Guard rail shall be capable of withstanding a force of 200 pounds applied in any direction. Install a steel toe board with minimum height of 4 inches. Bottom of toe board shall be a maximum 1/4 inch from platform top. Extend guard rail and toe board entire length of balcony except where access openings are required. For balcony floors use diamond plates a minimum of 1/4 inch thick, punched or drilled for drainage. Hatches through balcony floor shall be counterbalanced or otherwise arranged to open from below. |
| g. Coating for Welded Tanks |
| 1) Provide exterior coating systems conforming to Section 09 9113, "Exterior Painting," and interior coating systems conforming to NFPA 22, AWWA D103, manufacturer's recommendations and Section 09 9123, "Interior Painting." |
| h. Coating for Bolted Tanks |
| 1) As supplied by the manufacturer. |
| B. Valve Enclosure |
| 1. Valve enclosure shall be sufficiently large to house all control valves and fittings. Pipes, valves, and fittings shall be supported from the floor of the enclosure. The valve enclosure shall be constructed to provide not less than 6 feet of clearance over the pipes and shall connect directly to the fire pump enclosure. The valve enclosure shall be insulated and constructed of the same material as the fire pump enclosure, with hinged and latching access doors on opposite ends to access valves, and shall connect seamlessly to the tank and fire pump house. Enclosure shall be provided with heat, weatherproof receptacle and light as well as drainage to concrete at a safe location exterior of the enclosure where discharge will not cause ponding or other damage. |
| C. Anchors for Reservoirs |
| 1. The following requirements shall be met: |
| a. An adequate number of anchors designed to prevent overturning of the reservoir when empty shall be installed. If anchor bolts are used, the nominal diameter shall not be less than one inch, plus a corrosion allowance of at least 1/4 inch on the diameter. If anchor straps are used, they shall be pre-tensioned before welding to the tank shell. |
| b. The anchor bolts shall be a right angle bend, hook, or plate washer, while anchor straps shall have only a plate welded to the bottom. The anchors shall be inserted into the foundation to resist the computed uplift. |
| c. Attachment of anchors to the shell shall not add significant localized stresses to the shell. The method of attachment shall consider the effects of deflection and rotation of the tank shell. Anchors shall not be attached to the tank bottom. Attachment of the anchor bolts to the shell shall be through stiffened chair-type assemblies or anchor rings of adequate size and height. |
| 2.4 CONCRETE WORK |
| A. Concrete work shall conform to Section 03 3000 CAST-IN-PLACE CONCRETE. |
| PART 3 - EXECUTION |
| 3.1 FOUNDATIONS |
| A. Foundations for the reservoir and for the valve chamber shall be constructed of concrete, reinforced where necessary, and designed in accordance with Section 12 of AWWA D100 or Sections 11 and 8.5 of AWWA D103 for earth, and constructed in conformance with the applicable requirements of Section 03 3000 CAST-IN-PLACE CONCRETE, except as shown or specified herein. An AWWA D100 Type 1 or an AWWA D103 Type 1 or Type 2 foundation shall be provided for the reservoir. Factor of safety on overturning of reservoir under design wind load shall be 1.33 minimum. |
| 3.2 EXCAVATING, FILLING, AND GRADING |
| A. Excavating, filling, and grading shall conform to the applicable requirements of Section 31 0000 EARTHWORK. |
| 3.3 CATHODIC PROTECTION |
| A. Cathodic protection shall be provided, conforming to NFPA 22 requirements. |
| 3.4 OBSTRUCTION LIGHTING |
| A. Obstruction lighting shall be provided and shall conform to Division 26 or FAA AC 150/5345-43. |
| 3.5 BEACON |
| A. Beacon shall be provided and shall conform to Division 26. |
| 3.6 TANK INSTALLATION |
| A. Submit detail and erection drawings, before proceeding with any fabrication. Complete drawings with details of steel, pipe, and concrete work, and of the assembling of items required for the total installation. Use standard welding symbols as recommended by the American Welding Society. Details of welded joints referenced on the drawings shall be included. Tank installation shall be in accordance with the following requirements: |
| 1. Welding |
| a. Section 8 of AWWA D100 or Section 6 of AWWA D103. |
| 2. Erection |
| a. Section 10 of AWWA D100 or Section 8 of AWWA D103. |
| 3. Inspections and Testing |
| a. Tank inspection and testing shall be in accordance with Section 11 of AWWA D100 or Section 9 of AWWA D103. Mill and shop inspectionsare not required. Perform the radiographic inspections of the welded tank shell, the hydrostatic test and the vacuum box leak test of the tank bottom. Final hydrostatic and leak tests shall be performed before painting of welded tanks. |
| 3.7 PIPING INSTALLATION (EXCEPT FOR OVERFLOW PIPING) |
| A. General Guidelines |
| 1. Where details of fabrication or installation are not shown on the drawings, installation shall conform to Section 1 and 3 of AWWA C600. |
| B. Testing of Valves and Piping |
| 1. After the reservoir has been erected and the valves and piping installed, and before field painting is begun, the valves and piping shall be hydrostatically tested in accordance with Section 4 of AWWA C600 and in accordance with NFPA 22. Submit each coating manufacturer's technical data, application instructions, Safety Data Sheets (SDS), and certificate for compliance for VOC content. Submit copies of the following test results: |
| a. Manufacturer's mill test reports for plate material. |
| b. Mill and shop inspections by a commercial inspection agency. |
| c. After acceptance of the structure, the radiographic film and test segments. |
| d. At the conclusion of the work, a written report covering the hydrostatic test and certifying that the work was inspected in accordance with Section 11.2.1 of AWWA D100. |
2. Replace with sound material any defective material disclosed by the pressure test; the test shall be repeated until the test results are satisfactory.
| C. Polyethylene Encasement of Underground Ductile-Iron Piping |
| 1. Polyethylene encasement of underground ductile-iron piping shall be provided in addition to asphaltic coating in accordance with AWWA C105/A21.5. |
| D. Plugging Ends |
| 1. Cap or plug pipe ends left for future connections as directed. |
| 3.8 3.8 PAINTING AND COATING OF TANK |
| A. Each coating manufacturer's technical data, application instructions, SDS, and certificate for compliance for VOC content must be submitted to the Contracting Officer. Application, curing time, mixing and thinning of the coating materials must be in strict accordance with the manufacturer¢s instructions. The use of thinners must not alter the required minimum dry thickness or adversely affect the VOC content. |
| B. Exterior Surfaces (Welded Tanks) |
| 1. |
| 2. A gray vinyl prime coat a minimum of 1.5 mil thick followed by two coats of light gray vinyl paint, each a minimum of 1.5 mil thick shall be applied. The primer and paint shall be VR-3 in accordance with SSPC PS 4.04, or a two-component catalyzed epoxy prime and intermediate coat, each a minimum of 3.0 mil thick, followed by a two-component catalyzed aliphatic polyurethane finish coat, a minimum of 1.5 mil thick, conforming to Type V of SSPC PS Guide 17.00 shall be applied. The prime coat shall be a green primer, Formula 150 in accordance with MIL-DTL-24441. The intermediate coat shall be white Formula 152 in accordance with MIL-DTL-24441 and may be tinted with pigment color. The finish coat shall be [light gray. |
| C. Interior Surfaces (Welded Tanks) |
| 1. A prime coat at least 3.0 mil thick and a [gray final coat at least 5.0 mil thick shall be applied. Each coat shall be a two-component catalyzed epoxy in accordance with MIL-PRF-23236. The primer shall contrast with the color of the finish coat. Color shall be submitted for approval. |
| D. Bolted Tanks |
| 1. The tanks shall have a coating applied to both the interior and exterior surfaces in accordance with Section 10 of AWWA D103. Color shall be as approved. |
| 3.9 INSPECTION AND REPAIR |
| A. Prior to tank repair job, perform a detailed inspection of the structure and submit report by a certified inspector. |
This Page Intentionally Left Blank
| TOC |
| PROJECT TABLE OF CONTENTS |
| 01 11 00 |
| 01 11 00 - SUMMARY OF WORK |
| PART 1 GENERAL |
| 1.1 SUBMITTALS |
| 1.2 WORK COVERED BY CONTRACT DOCUMENTS |
| 1.2.1 Project Description |
| 1.2.2 Location |
| 1.3 CONTRACT DRAWINGS |
| 1.4 OCCUPANCY OF PREMISES |
| 1.5 ON-SITE PERMITS |
| 1.5.1 Utility Outage Requests and Utility Connection Requests |
| 1.5.2 Excavation Permits |
| 1.6 LOCATION OF UNDERGROUND UTILITIES |
| 1.6.1 Notification Prior to Excavation |
1.7 SALVAGE MATERIAL AND EQUIPMENT
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 01 14 00 |
| 01 14 00 - WORK RESTRICTIONS |
| PART 1 GENERAL |
| 1.1 DEFINITIONS |
| 1.1.1 State |
| 1.2 SUBMITTALS |
| 1.3 CONTRACTOR ACCESS AND USE OF PREMISES |
| 1.3.1 Activity Regulations |
| 1.3.1.1 Subcontractors and Personnel Contacts |
| 1.3.1.2 No Smoking Policy |
| 1.3.2 Working Hours |
| 1.3.3 Work Outside Regular Hours |
| 1.3.4 Occupied and Existing Buildings |
| 1.3.5 Utility Cutovers and Interruptions |
| 1.4 SECURITY REQUIREMENTS AND RESTRICTIONS |
| 1.4.1 Building Entrance Restrictions |
| 1.4.2 Public Release of Information |
| 1.4.3 Responsibility for Physical Security |
| 1.4.4 Employment |
| 1.4.5 Compliance |
| 1.4.6 Cultural Resources |
| 1.4.7 Unexploded Ordnance |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 01 20 00 |
| 01 20 00 - PRICE AND PAYMENT PROCEDURES |
| PART 1 GENERAL |
| 1.1 SUBMITTALS |
| 1.2 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT |
| 1.2.1 Final Invoice |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 01 30 00 |
| 01 30 00 - ADMINISTRATIVE REQUIREMENTS |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 SUBMITTALS |
| 1.3 COLOR BOARDS FOR AIR FORCE PROJECTS |
| 1.4 VIEW LOCATION MAP |
| 1.5 PROGRESS AND COMPLETION PICTURES |
| 1.6 MINIMUM INSURANCE REQUIREMENTS |
| 1.7 SUPERVISION |
| 1.7.1 Superintendent Qualifications |
| 1.7.2 Minimum Communication Requirements |
| 1.7.3 Duties |
| 1.7.4 Non-Compliance Actions |
| 1.8 PRECONSTRUCTION CONFERENCE |
| 1.8.1 Attendees |
| 1.9 FACILITY TURNOVER PLANNING MEETINGS Red Zone Meetings |
| 1.9.1 Red Zone Checklist |
| 1.9.2 Meetings |
| 1.10 PARTNERING |
| 1.11 PERFORMANCE ASSESSMENT PLAN PAP |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 01 32 01.00 10 |
| 01 32 01.00 10 - PROJECT SCHEDULE |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 SUBMITTALS |
| 1.3 PROJECT SCHEDULER QUALIFICATIONS |
| PART 2 PRODUCTS |
| 2.1 SOFTWARE |
| 2.1.1 Government Default Software |
| 2.1.2 Contractor Software |
| 2.1.2.1 Primavera |
| 2.1.2.2 Other Than Primavera |
| PART 3 EXECUTION |
| 3.1 GENERAL REQUIREMENTS |
| 3.2 BASIS FOR PAYMENT AND COST LOADING |
| 3.2.1 Activity Cost Loading |
| 3.2.2 Withholdings / Payment Rejection |
| 3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS |
| 3.3.1 Level of Detail Required |
| 3.3.2 Activity Durations |
| 3.3.3 Design and Permit Activities |
| 3.3.4 Procurement Activities |
| 3.3.5 Mandatory Tasks |
| 3.3.6 Government Activities |
| 3.3.7 Standard Activity Coding Dictionary |
| 3.3.7.1 Workers Per Day WRKP |
| 3.3.7.2 Responsible Party Coding RESP |
| 3.3.7.3 Area of Work Coding AREA |
| 3.3.7.4 Modification Number MODF |
| 3.3.7.5 Bid Item Coding BIDI |
| 3.3.7.6 Phase of Work Coding PHAS |
| 3.3.7.7 Category of Work Coding CATW |
| 3.3.7.8 Feature of Work Coding FOW |
| 3.3.8 Contract Milestones and Constraints |
| 3.3.8.1 Project Start Date Milestone and Constraint |
| 3.3.8.2 End Project Finish Milestone and Constraint |
| 3.3.8.3 Interim Completion Dates and Constraints |
| 3.3.8.3.1 Start Phase |
| 3.3.8.3.2 End Phase |
| 3.3.9 Calendars |
| 3.3.10 Open Ended Logic |
| 3.3.11 Default Progress Data Disallowed |
| 3.3.12 Out-of-Sequence Progress |
| 3.3.13 Added and Deleted Activities |
| 3.3.14 Original Durations |
| 3.3.15 Leads, Lags, and Start to Finish Relationships |
| 3.3.16 Retained Logic |
| 3.3.17 Percent Complete |
| 3.3.18 Remaining Duration |
| 3.3.19 Cost Loading of Closeout Activities |
| 3.3.19.1 As-Built Drawings |
| 3.3.19.2 O & M Manuals |
3.3.20 Early Completion Schedule and the Right to Finish Early
| 3.4 PROJECT SCHEDULE SUBMISSIONS |
| 3.4.1 Preliminary Project Schedule Submission |
| 3.4.2 Initial Project Schedule Submission |
| 3.4.3 Periodic Schedule Updates |
| 3.5 SUBMISSION REQUIREMENTS |
| 3.5.1 Data CD/DVDs |
| 3.5.2 Narrative Report |
| 3.5.3 Schedule Reports |
| 3.5.3.1 Activity Report |
| 3.5.3.2 Logic Report |
| 3.5.3.3 Total Float Report |
| 3.5.3.4 Earnings Report by CLIN |
| 3.5.3.5 Schedule Log |
| 3.5.4 Network Diagram |
| 3.5.4.1 Continuous Flow |
| 3.5.4.2 Project Milestone Dates |
| 3.5.4.3 Critical Path |
| 3.5.4.4 Banding |
| 3.5.4.5 Cash Flow Schedule Variance Control SVC Diagram |
| 3.6 PERIODIC SCHEDULE UPDATE |
| 3.6.1 Periodic Schedule Update Meetings |
| 3.6.2 Update Submission Following Progress Meeting |
| 3.7 WEEKLY PROGRESS MEETINGS |
| 3.8 REQUESTS FOR TIME EXTENSIONS |
| 3.8.1 Justification of Delay |
| 3.8.2 Time Impact Analysis Prospective Analysis |
| 3.8.3 Forensic Schedule Analysis Retrospective Analysis |
| 3.8.4 Fragmentary Network Fragnet |
| 3.8.5 Time Extension |
| 3.8.6 Impact to Early Completion Schedule |
| 3.9 FAILURE TO ACHIEVE PROGRESS |
| 3.9.1 Artificially Improving Progress |
| 3.9.2 Failure to Perform |
| 3.9.3 Recovery Schedule |
| 3.10 OWNERSHIP OF FLOAT |
| 3.11 TRANSFER OF SCHEDULE DATA INTO RMS/QCS |
| 3.12 PRIMAVERA P6 MANDATORY REQUIREMENTS |
| 01 33 00 _Sub Registry |
| 01 33 00 |
| 01 33 00 - SUBMITTAL PROCEDURES |
| PART 1 GENERAL |
| 1.1 DEFINITIONS |
| 1.1.1 Submittal Descriptions SD |
| 1.1.2 Approving Authority |
| 1.1.3 Work |
| 1.2 SUBMITTALS |
| 1.3 SUBMITTAL CLASSIFICATION |
| 1.3.1 Government Approved G |
| 1.3.2 For Information Only |
| 1.4 PREPARATION |
| 1.4.1 Submittal Format |
| 1.4.1.1 Format of SD-01 Preconstruction Submittals |
| 1.4.1.2 Format for SD-02 Shop Drawings |
| 1.4.1.2.1 Drawing Identification |
| 1.4.1.3 Format of SD-03 Product Data |
| 1.4.1.3.1 Product Information |
| 1.4.1.3.2 Standards |
| 1.4.1.3.3 Data Submission |
| 1.4.1.4 Format of SD-04 Samples |
| 1.4.1.4.1 Sample Characteristics |
| 1.4.1.4.2 Sample Incorporation |
| 1.4.1.4.3 Comparison Sample |
| 1.4.1.5 Format of SD-05 Design Data |
| 1.4.1.6 Format of SD-06 Test Reports |
| 1.4.1.7 Format of SD-07 Certificates |
| 1.4.1.8 Format of SD-08 Manufacturer's Instructions |
| 1.4.1.8.1 Standards |
| 1.4.1.9 Format of SD-09 Manufacturer's Field Reports |
| 1.4.1.10 Format of SD-10 Operation and Maintenance Data O&M |
| 1.4.1.11 Format of SD-11 Closeout Submittals |
| 1.4.2 Source Drawings for Shop Drawings |
| 1.4.2.1 Source Drawings |
| 1.4.2.2 Terms and Conditions |
1.4.3 Electronic File Format
| 1.5 QUANTITY OF SUBMITTALS |
| 1.5.1 Number of SD-01 Preconstruction Submittal Copies |
| 1.5.2 Number of SD-04 Samples |
| 1.5.3 Number of SD-05 Design Data Copies |
| 1.5.4 Number of SD-06 Test Report Copies |
| 1.5.5 Number of SD-07 Certificate Copies |
| 1.5.6 Number of SD-08 Manufacturer's Instructions Copies |
| 1.5.7 Number of SD-09 Manufacturer's Field Report Copies |
| 1.5.8 Number of SD-10 Operation and Maintenance Data Copies |
| 1.6 PROJECT SUBMITTAL REGISTER |
| 1.6.1 Submittal Management |
| 1.6.2 Preconstruction Use of Submittal Register |
| 1.6.3 Contractor Use of Submittal Register |
| 1.6.4 Approving Authority Use of Submittal Register |
| 1.6.5 Delivery of Copies |
| 1.7 VARIATIONS |
| 1.7.1 Considering Variations |
| 1.7.2 Proposing Variations |
| 1.7.3 Warranting that Variations are Compatible |
| 1.7.4 Review Schedule Extension |
| 1.8 SCHEDULING |
| 1.9 GOVERNMENT APPROVING AUTHORITY |
| 1.9.1 Review Notations |
| 1.10 DISAPPROVED SUBMITTALS |
| 1.11 APPROVED SUBMITTALS |
| 1.12 APPROVED SAMPLES |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 01 35 26 |
| 01 35 26 - GOVERNMENTAL SAFETY REQUIREMENTS |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 DEFINITIONS |
| 1.2.1 Competent Person CP |
| 1.2.2 Competent Person, Confined Space |
| 1.2.3 Competent Person, Cranes and Rigging |
| 1.2.4 Competent Person, Excavation/Trenching |
| 1.2.5 Competent Person, Fall Protection |
| 1.2.6 Competent Person, Scaffolding |
| 1.2.7 Competent Person CP Trainer |
| 1.2.8 High Risk Activities |
| 1.2.9 High Visibility Accident |
| 1.2.10 Load Handling Equipment LHE |
| 1.2.11 Medical Treatment |
| 1.2.12 Near Miss |
| 1.2.13 Operating Envelope |
| 1.2.14 Qualified Person QP |
| 1.2.15 Qualified Person, Fall Protection QP for FP |
| 1.2.16 Recordable Injuries or Illnesses |
| 1.2.17 Government Property and Equipment |
| 1.2.18 Load Handling Equipment LHE Accident or Load Handling Equipment |
| 1.3 SUBMITTALS |
| 1.4 MONTHLY EXPOSURE REPORTS |
| 1.5 REGULATORY REQUIREMENTS |
| 1.6 SITE QUALIFICATIONS, DUTIES, AND MEETINGS |
| 1.6.1 Personnel Qualifications |
| 1.6.1.1 Site Safety and Health Officer SSHO |
| 1.6.1.1.1 Additional Site Safety and Health Officer SSHO Requirements |
| 1.6.1.2 Competent Person Qualifications |
| 1.6.1.2.1 Competent Person for Confined Space Entry |
| 1.6.1.2.2 |
| 1.6.1.2.3 Competent Person for Fall Protection |
| 1.6.1.3 Qualified Trainer Requirements |
| 1.6.1.4 Crane Operators/Riggers |
| 1.6.2 Personnel Duties |
| 1.6.2.1 Duties of the Site Safety and Health Officer SSHO |
| 1.6.3 Meetings |
| 1.6.3.1 Preconstruction |
| 1.6.3.2 Safety Meetings |
| 1.7 ACCIDENT PREVENTION PLAN APP |
| 1.7.1 APP - Construction |
| 1.7.2 Names and Qualifications |
| 1.7.3 Plans |
| 1.7.3.1 Confined Space Entry Plan |
| 1.7.3.2 Standard Lift Plan SLP |
| 1.7.3.3 Critical Lift Plan - Crane or Load Handling Equipment |
| 1.7.3.3.1 Critical Lift Plan Planning and Schedule |
| 1.7.3.3.2 Lifts of Personnel |
| 1.7.3.4 Multi-Purpose Machines, Material Handling Equipment, and |
| 1.7.3.5 Fall Protection and Prevention FP&P Plan |
| 1.7.3.6 Rescue and Evacuation Plan |
| 1.7.3.7 Hazardous Energy Control Program HECP |
| 1.7.3.8 Excavation Plan |
| 1.7.3.9 Asbestos Hazard Abatement Plan |
| 1.7.3.10 Site Demolition Plan |
| 1.8 ACTIVITY HAZARD ANALYSIS AHA |
| 1.8.1 AHA Management |
| 1.8.2 AHA Signature Log |
| 1.9 DISPLAY OF SAFETY INFORMATION |
| 1.9.1 Safety Bulletin Board |
| 1.9.2 Safety and Occupational Health SOH Deficiency Tracking System |
| 1.10 SITE SAFETY REFERENCE MATERIALS |
| 1.11 EMERGENCY MEDICAL TREATMENT |
| 1.12 NOTIFICATIONS and REPORTS |
| 1.12.1 Mishap Notification |
| 1.12.2 Accident Reports |
| 1.12.3 LHE Inspection Reports |
| 1.12.4 Certificate of Compliance and Pre-lift Plan/Checklist for LHE and |
| 1.13 HOT WORK |
| 1.13.1 Permit and Personnel Requirements |
| 1.13.2 Work Around Flammable Materials |
| 1.14 CONFINED SPACE ENTRY REQUIREMENTS |
| 1.14.1 Entry Procedures |
| 1.14.2 Forced Air Ventilation |
| 1.14.3 Sewer Wet Wells |
| 1.14.4 Rescue Procedures and Coordination with Local Emergency Responders |
1.15 SEVERE STORM PLAN
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 3.1 CONSTRUCTION AND OTHER WORK |
| 3.1.1 Worksite Communication |
| 3.1.2 Hazardous Material Exclusions |
| 3.1.3 Unforeseen Hazardous Material |
| 3.2 UTILITY OUTAGE REQUIREMENTS |
| 3.3 OUTAGE COORDINATION MEETING |
| 3.4 CONTROL OF HAZARDOUS ENERGY LOCKOUTTAGOUT |
| 3.4.1 Safety Preparatory Inspection Coordination Meeting with the |
| 3.4.2 Lockout/Tagout Isolation |
| 3.4.3 Lockout/Tagout Removal |
| 3.5 FALL PROTECTION PROGRAM |
| 3.5.1 Training |
| 3.5.2 Fall Protection Equipment and Systems |
| 3.5.2.1 Additional Personal Fall Protection Measures |
| 3.5.2.2 Personal Fall Protection Equipment |
| 3.5.3 Fall Protection for Roofing Work |
| 3.5.4 Horizontal Lifelines HLL |
| 3.5.5 Guardrails and Safety Nets |
| 3.5.6 Rescue and Evacuation Plan and Procedures |
| 3.6 WORK PLATFORMS |
| 3.6.1 Scaffolding |
| 3.6.2 Elevated Aerial Work Platforms AWPs |
| 3.7 EQUIPMENT |
| 3.7.1 Material Handling Equipment MHE |
| 3.7.2 Load Handling Equipment LHE |
| 3.7.3 Machinery and Mechanized Equipment |
| 3.7.4 Base Mounted Drum Hoists |
| 3.7.5 Use of Explosives |
| 3.8 EXCAVATIONS |
| 3.8.1 Utility Locations |
| 3.8.2 Utility Location Verification |
| 3.8.3 Utilities Within and Under Concrete, Bituminous Asphalt, and Other |
| 3.9 ELECTRICAL |
| 3.9.1 Conduct of Electrical Work |
| 3.9.2 Qualifications |
| 3.9.3 Arc Flash |
| 3.9.4 Grounding |
| 3.9.5 Testing |
| 01 42 00 |
| 01 42 00 - SOURCES FOR REFERENCE PUBLICATIONS |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 ORDERING INFORMATION |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 01 45 00.00 10 |
| 01 45 00.00 10 - QUALITY CONTROL |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 PAYMENT |
| 1.3 SUBMITTALS |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 3.1 GENERAL REQUIREMENTS |
| 3.2 CONTRACTOR QUALITY CONTROL CQC PLAN |
| 3.2.1 Content of the CQC Plan |
| 3.2.2 Acceptance of Plan |
| 3.2.3 Notification of Changes |
| 3.3 COORDINATION MEETING |
| 3.4 QUALITY CONTROL ORGANIZATION |
| 3.4.1 Personnel Requirements |
| 3.4.2 CQC System Manager |
| 3.4.3 CQC Personnel |
| 3.4.4 Additional Requirement |
| 3.4.5 Organizational Changes |
| 3.5 SUBMITTALS AND DELIVERABLES |
| 3.6 CONTROL |
| 3.6.1 Preparatory Phase |
| 3.6.2 Initial Phase |
| 3.6.3 Follow-up Phase |
| 3.6.4 Additional Preparatory and Initial Phases |
| 3.7 TESTS |
| 3.7.1 Testing Procedure |
| 3.7.2 Testing Laboratories |
| 3.7.2.1 Capability Check |
| 3.7.2.2 Capability Recheck |
3.7.3 Onsite Laboratory
| 3.8 COMPLETION INSPECTION |
| 3.8.1 Punch-Out Inspection |
| 3.8.2 Pre-Final Inspection |
| 3.8.3 Final Acceptance Inspection |
| 3.9 DOCUMENTATION |
| 3.9.1 Quality Control Activities |
| 3.9.2 Verification Statement |
| 3.10 SAMPLE FORMS |
| 3.11 NOTIFICATION OF NONCOMPLIANCE |
| 01 45 35 |
| 01 45 35 - SPECIAL INSPECTIONS |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 GENERAL REQUIREMENTS |
| 1.3 DEFINITIONS |
| 1.3.1 Continuous Special Inspections |
| 1.3.2 Perform |
| 1.3.3 Observe |
| 1.3.4 Special Inspector SI |
| 1.3.5 Associate Special Inspector ASI |
| 1.3.6 Third Party |
| 1.3.7 Special Inspector of Record SIOR |
| 1.3.8 Contracting Officer |
| 1.3.9 Contractor's Quality Control QC Manager |
| 1.3.10 Structural Engineer of Record SER |
| 1.3.11 Statement of Special Inspections SSI |
| 1.3.12 Schedule of Special Inspections SSI |
| 1.3.13 Designated Seismic Systems DSS |
| 1.3.14 Definable Feature of Work DFOW |
| 1.4 SUBMITTALS |
| 1.5 SPECIAL INSPECTOR QUALIFICATIONS |
| 1.5.1 Steel Construction and High Strength Bolting |
| 1.5.1.1 Special Inspector |
| 1.5.1.2 Associate Special Inspector |
| 1.5.2 Welding Structural Steel |
| 1.5.2.1 Special Inspector |
| 1.5.2.2 Associate Special Inspector |
| 1.5.3 Nondestructive Testing of Welds |
| 1.5.3.1 Special Inspector |
| 1.5.3.2 Associate Special Inspector |
| 1.5.4 Cold Formed Steel Framing |
| 1.5.4.1 Special Inspector |
| 1.5.4.2 Associate Special Inspector |
| 1.5.5 Concrete Construction |
| 1.5.5.1 Special Inspector |
| 1.5.5.2 Associate Special Inspector |
| 1.5.6 Masonry Construction |
| 1.5.6.1 Special Inspector |
| 1.5.6.2 Associate Special Inspector |
| 1.5.7 Wood |
| 1.5.7.1 Special Inspector |
| 1.5.7.2 Associate Special Inspector |
| 1.5.8 Verification of Site Soil Condition, Fill Placement and Load-Bearing |
| 1.5.8.1 Special Inspector |
| 1.5.8.2 Associate Special Inspector |
| 1.5.9 Mastic and Intumescent Fire Resistant Coatings |
| 1.5.9.1 Special Inspector |
| 1.5.9.2 Associate Special Inspector |
| 1.5.10 Fire-Resistant Penetrations and Joints |
| 1.5.10.1 Special Inspector |
| 1.5.10.2 Associate Special Inspector |
| 1.5.11 Smoke Control |
| 1.5.11.1 Special Inspector |
| 1.5.11.2 Associate Special Inspector |
| PART 2 PRODUCTS |
| 2.1 FABRICATOR SPECIAL INSPECTIONS |
| PART 3 EXECUTION |
| 3.1 RESPONSIBILITIES |
| 3.1.1 Quality Control Manager |
| 3.1.2 Special Inspectors |
3.2 DEFECTIVE WORK
| 01 50 00 |
| 01 50 00 - TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 SUBMITTALS |
| 1.3 CONSTRUCTION SITE PLAN |
| 1.4 BACKFLOW PREVENTERS CERTIFICATE |
| 1.4.1 Backflow Tester Certificate |
| 1.4.2 Backflow Prevention Training Certificate |
| 1.5 DOD CONDITION OF READINESS COR |
| 1.6 CYBERSECURITY DURING CONSTRUCTION |
| 1.6.1 Contractor Computer Equipment |
| 1.6.1.1 Operating System |
| 1.6.1.2 Anti-Malware Software |
| 1.6.1.3 Passwords and Passphrases |
| 1.6.1.4 Contractor Computer Cybersecurity Compliance Statements |
| 1.6.2 Temporary IP Networks |
| 1.6.2.1 Network Boundaries and Connections |
| 1.6.3 Government Access to Network |
| 1.6.4 Temporary Wireless IP Networks |
| 1.6.5 Passwords and Passphrases |
| 1.6.6 Contractor Temporary Network Cybersecurity Compliance Statements |
| PART 2 PRODUCTS |
| 2.1 TEMPORARY SIGNAGE |
| 2.1.1 Bulletin Board |
| 2.1.2 Project Identification Signs |
| 2.1.3 Warning Signs |
| 2.2 TEMPORARY TRAFFIC CONTROL |
| 2.2.1 Haul Roads |
| 2.2.2 Barricades |
| 2.3 FENCING |
| 2.3.1 Polyethylene Mesh Safety Fencing |
| 2.3.2 Chain Link Panel Fencing |
| 2.3.3 Post-Driven Chain Link Fencing |
| 2.4 TEMPORARY WIRING |
| 2.5 BACKFLOW PREVENTERS |
| PART 3 EXECUTION |
| 3.1 EMPLOYEE PARKING |
| 3.2 AVAILABILITY AND USE OF UTILITY SERVICES |
| 3.2.1 Temporary Utilities |
| 3.2.2 Sanitation |
| 3.2.3 Telephone |
| 3.2.4 Obstruction LIghting of Cranes |
| 3.2.5 Fire Protection |
| 3.3 LIMITATIONS ON CONTRACTOR ACCESS |
| 3.3.1 Restricted Access Areas |
| 3.4 TRAFFIC PROVISIONS |
| 3.4.1 Maintenance of Traffic |
| 3.4.2 Protection of Traffic |
| 3.4.3 Dust Control |
| 3.5 REDUCED PRESSURE BACKFLOW PREVENTERS |
| 3.6 CONTRACTOR'S TEMPORARY FACILITIES |
| 3.6.1 Administrative Field Offices |
| 3.6.2 Storage Area |
| 3.6.3 Supplemental Storage Area |
| 3.6.4 Appearance of Trailers |
| 3.6.5 Trailers or Storage Buildings |
| 3.6.6 Safety Systems |
| 3.6.7 Weather Protection of Temporary Facilities and Stored Materials |
| 3.6.7.1 Building and Site Storm Protection |
| 3.7 PLANT COMMUNICATIONS |
| 3.8 TEMPORARY PROJECT SAFETY FENCING |
| 3.9 CLEANUP |
| 3.10 RESTORATION OF STORAGE AREA |
| 01 57 19 |
| 01 57 19 - TEMPORARY ENVIRONMENTAL CONTROLS |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 DEFINITIONS |
| 1.2.1 Class I and II Ozone Depleting Substance ODS |
| 1.2.2 Contractor Generated Hazardous Waste |
| 1.2.3 Electronics Waste |
| 1.2.4 Environmental Pollution and Damage |
| 1.2.5 Environmental Protection |
| 1.2.6 Hazardous Debris |
| 1.2.7 Hazardous Materials |
| 1.2.8 Hazardous Waste |
| 1.2.9 Land Application |
| 1.2.10 Municipal Separate Storm Sewer System MS4 Permit |
| 1.2.11 National Pollutant Discharge Elimination System NPDES |
| 1.2.12 Oily Waste |
| 1.2.13 Regulated Waste |
| 1.2.14 Sediment |
| 1.2.15 Solid Waste |
| 1.2.15.1 Debris |
| 1.2.15.2 Green Waste |
| 1.2.15.3 Material Not Regulated As Solid Waste |
| 1.2.15.4 Non-Hazardous Waste |