This document is an Amendment 3 Attachment containing Questions and Answers for a building renovation project at the 137th Will Rogers Air National Guard Base. Key technical details include clarifications about electronic security systems (ESS), door hardware, and locks. Specifically, the amendment addresses contractor responsibilities for ESS rough-in locations, X-10 locks installation, and coordination requirements for door hardware and key systems.

The related solicitation is a small business set-aside project for renovating Building 1040, with a project value between $5-10 million under NAICS code 236220. The solicitation is issued by the Oklahoma City Air National Guard, with bids due on 27 February 2025 at 1000 hrs CST. Important notes include that funds are not currently available but are anticipated by 30 September 2025, and the contract will be awarded to the most advantageous bidder considering price and price-related factors. A pre-bid conference/site visit is scheduled for 27 January 2025 at 1000 hrs CST, and electronic or facsimile bids will not be accepted.

View the file

Other files

File Type Posted
Abstract (Final).pdf PDF
Solicitation Amendment 3 W50S8T25BA0110003.pdf PDF
NEW 6 Mar 25 Oklahoma NGB-WRWA - 100 CD Set Part 1.pdf PDF
NEW 6 Mar 25 Oklahoma NGB-WRWA - 100 CD Set Part 2.pdf PDF
Amendment 2 Attachment 2 - 09 72 00.pdf PDF
Amendment 2 Attachment 5 - IN600 - INTERIORS MATERIALS LEGEND.pdf PDF
Amendment 2 Attachment 3 - A-002 - PARTITION TYPES.pdf PDF
Amendment 2 Attachment 6 - Bldg 1040 Reno Questions and Answers.xlsx XLSX spreadsheet
Amendment 2 Attachment 1 - Addendum 02 Narrative.docx DOCX document
Solicitation Amendment 2 W50S8T25BA0110002.pdf PDF
Amendment 2 Attachment 4 - 08 11 16.pdf PDF
06 20 00.pdf PDF
21 13 13.pdf PDF
IN101 - FLOOR FINISH PLAN - SECTOR A.pdf PDF
Bldg 1040 Reno Questions and Answers - FSB and GOV Reponses.xlsx XLSX spreadsheet
EL101 - ELECTRICAL INTERIOR LIGHTING PLAN - SECTOR A.pdf PDF
AE102 - FLOOR PLAN - SECTOR A.pdf PDF
AE502 - DETAILS.pdf PDF
AE403 - ENLARGED PLANS.pdf PDF
10 21 13.pdf PDF
10 51 13.pdf PDF
08 41 13.pdf PDF
AE103 - FLOOR PLAN - SECTOR B.pdf PDF
08 81 00.pdf PDF
AE411 - INTERIOR ELEVATIONS.pdf PDF
AE402 - ENLARGED PLANS.pdf PDF
AE601 - DOOR SCHEDULE AND DETAILS.pdf PDF
26 05 73.pdf PDF
08 11 16.pdf PDF
AE602 - OLI 1 - EXTERIOR WINDOW FRAMES.pdf PDF
Addendum 01 Narrative.docx DOCX document
08 71 00.pdf PDF
IN102 - FLOOR FINISH PLAN - SECTOR B.pdf PDF
Solicitation Amendment 1 W50S8T25BA0110001 SF 30.pdf PDF
06 41 16.00 10.pdf PDF
AE201 - BUILDING ELEVATIONS.pdf PDF
TABLE OF CONTENTS.pdf PDF
A-002 - PARTITION TYPES.pdf PDF
01 45 35.pdf PDF
FA601 - FIRE ALARM - MASS NOTIFICATION RISER DIAGRAM.pdf PDF
AE151 - REFLECTED CEILING PLAN - SECTOR A.pdf PDF
AE600 - ROOM FINISH SCHEDULE.pdf PDF
10 51 16.pdf PDF
30 Jan 25 Site Visit Sign In Sheet.pdf PDF
BLDG 1040 Renovation Site Visit Slides 30 January 25.pptx PPTX presentation
ATTACHMENT 3 - 2024.09.12_OK-ANG_SQUADOPS B1040_TYPE B3_SPECIFICATIONS VOL. 2.pdf PDF
Solicitation - W50S8T25BA011.pdf PDF
ATTACHMENT 2 - 2024.09.12_OK-ANG_SQUADOPS B1040_TYPE B3_SPECIFICATIONS VOL. 1.pdf PDF
Bidders Checklist.docx DOCX document
ATTACHMENT 1 - 2024.09.12_OK-ANG_SQUADOPS B1040_TYPE B3_DRAWINGS.pdf PDF
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT 3 ATTACHMENT 1 – Bldg 1040 Reno Questions and Answers

Bid Inquiry #13: Plan Sheets TY-101 & TY-102 General Note O. states “ALL ELECTRONIC SECURITY SYSTEM (ESS) SHALL BE BY OWNER. ESS ROUGH IN ONLY…”

a. Ref. Hardware schedule in specification 08 71 00, hardware normally provided by the security contractor isn’t called out to be provided by ESS contractor. 08 71 00, 2.3.10.3 states “…Coordinate access control hardware with corresponding devices and systems specified in Division 28 ELECTRONIC SECURITY SYSTEMS (ESS).” There is not an Electronic Security System spec provided. Please advise on who is to provide items such as card readers and keypads.

a. TY101 and TY102 indicate that the ESS will be provided by owner. Contractor to coordinate with contracting officer to ensure correct rough-in locations. Hardware & cabling is GFGI.

b. Please advise on who is to provide the Cypher X-10 Locks as those can only be purchased and installed by authorized distributors and installers or the Government.

a. Contractor to provide all X-10s in coordination with door hardware. Contractor to coordinate with base for permanent cores & keys as identified in the specification.

b. Doors 129B & 169A need to be updated to Type II X-10 locks. Will update drawings spec in IFC set.

Bid Inquiry #14:Please provide facility key & lock manufacturer. (i.e. Best, Sargent, Corbin Russwin, Schlage, etc.).
Lock set must accept 7-pin Best core system.

Bid Inquiry #15: Please confirm that existing doors that are to remain do NOT get new hardware.

Existing doors to remain are NOT to receive new hardware.

See the attached sheet G201 from the B1040 plan set specifically note 4 that I have snipped where it states the owner shall employ one or more approved agencies to provide special inspections and TESTS for this project. This is uncommon and it surprised me since Type C services don’t typically cover testing.

Contractor to coordinate all testing & inspections as required by, but not limited to, the drawings, specifications, manufacturer’s requirements or recommendations, or code requirements as indicated. These are to be identified in the QC plan per the 01 45 00 specification. This note applies only to the owner for their third party as required.