Addendum 01 Narrative.docx
DOCX document 65 KB Posted
- Solicitation number
- W50S8T25BA011
- Issued by
-
Department of the Army National Guard
About this file
This is an Addendum dated February 17, 2025 for the renovation of Building 1040 at the 137th Will Rogers Air National Guard Base in Oklahoma City. The addendum modifies the original bidding documents dated September 12, 2024, with extensive revisions to 14 specification sections and 16 drawing sheets, totaling 152 pages.
The key modifications include changes to finish carpentry, aluminum doors and frames, glazing, toilet compartments, lockers, cell phone lockers, and removal of rooftop fall protection anchors specifications. Notable drawing revisions affect partition types, floor plans, ceiling plans, building elevations, and room finish schedules. The related solicitation (W50S8T25BA011) is a 100% small business set-aside under NAICS 236220 with a project magnitude of $5-10 million. A pre-bid conference is scheduled for January 27, 2025 at 1000 CST, with bids due February 27, 2025 at 1000 CST. The Army National Guard anticipates funds will become available prior to September 30, 2025, though funds are not currently available.
View the file
Other files
Show all 50
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM 01
November 2, 2024
CLIENT NAME
PROJECT NAME
Project Number: 2024-000-00
FRANKFURT-SHORT-BRUZA ASSOCIATES, P.C.
5801 Broadway Extension, Suite 500 Oklahoma City, OK 73118
ADDENDUM 01
February 17, 2025
OKLAHOMA AIR NATIONAL GUARD 137TH
RENOVATE BUILDING 1040
Project Number: 2020-484-00; YZEU142025
FRANKFURT-SHORT-BRUZA ASSOCIATES, P.C.
5801 Broadway Extension, Suite 500 Oklahoma City, OK 73118
NOTICE TO BIDDERS
This Addendum forms a part of the Contract Documents and modifies the original Bidding Documents dated September 12, 2024, Addendum Number 01 dated February 17, 2025. Items not specifically revised remain in effect.
Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may subject the Bidder to disqualification.
This Addendum consists of (152) page(s) and the attached (14) Specification Sections and (16) Drawings Sheets.
REFERENCE THE SPECIFICATIONS
ITEM 1-1 SPECIFICATION TABLE OF CONTENTS
The attached revised Table of Contents indicated and dated February 17, 2025 shall supersede the Table of Contents dated September 12, 2024.
ITEM 1-2 SPECIFICATION SECTION 01 45 35 – SPECIAL INSPECTIONS
The attached revised Specification Section indicated and dated February 17, 2025 shall supersede the Specification Section dated September 12, 2024.
A. Refer to part 1.2. G sheet numbers revised to match.
ITEM 1-3 SPECIFICATION SECTION 06 20 00 – FINISH CARPENTRY
The attached revised Specification Section indicated and dated February 17, 2025 shall supersede the Specification Section dated September 12, 2024.
A. Refer to part 1.2, SD-03. Countertops removed.
B. Refer to part 2.1.3. Section removed.
C. Refer to parts 2.6.2 through 2.6.6.5. Sections removed.
D. Refer to part 3.2. Section removed.
ITEM 1-4 SPECIFICATION SECTION 06 41 16.00 10 – PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS The attached revised Specification Section indicated and dated February 17, 2025 shall supersede the Specification Section dated September 12, 2024.
A. Refer to part 1.5.1. Changed wording.
B. Refer to part 2.9. Changed wording.
C. Refer to part 2.9.5.2.1. Section removed.
ITEM 1-5 SPECIFICATION SECTION 08 11 16 – ALUMINUM DOORS AND FRAMES
The attached revised Specification Section indicated and dated February 17, 2025 shall supersede the Specification Section dated September 12, 2024.
A. Refer to part 2.3.2.3. Section added.
B. Refer to part 2.3.8.1. Added color.
C. Refer to part 2.3.8.2. Removed section.
ITEM 1-6 SPECIFICATION SECTION 08 41 13 – ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS The attached revised Specification Section indicated and dated February 17, 2025 shall supersede the Specification Section dated September 12, 2024.
A. Refer to part 2.1. Revised information.
ITEM 1-7 SPECIFICATION SECTION 08 71 00 – DOOR HARDWARE
The attached revised Specification Section indicated and dated February 17, 2025 shall supersede the Specification Section dated September 12, 2024.
A. Refer to door hardware schedule for revised tags and clarifications.
ITEM 1-8 SPECIFICATION SECTION 08 81 00 – GLAZING
The attached revised Specification Section indicated and dated February 17, 2025 shall supersede the Specification Section dated September 12, 2024.
A. Refer to part 2.1.1. Information added.
B. Refer to part 2.2. Information added.
ITEM 1-9 SPECIFICATION SECTION 10 21 13 – TOILET COMPARTMENTS
The attached revised Specification Section indicated and dated February 17, 2025 shall supersede the Specification Section dated September 12, 2024.
A. Refer to part 2.4. Information added.
ITEM 1-10 SPECIFICATION SECTION 10 51 13 – LOCKERS
The attached revised Specification Section indicated and dated February 17, 2025 shall supersede the Specification Section dated September 12, 2024.
A. Refer to part 2.2.1. Section removed.
ITEM 1-11 SPECIFICATION SECTION 10 51 16 – CELL PHONE LOCKERS
The attached revised Specification Section indicated and dated February 17, 2025 shall supersede the Specification Section dated September 12, 2024.
A. Refer to part 2.3. Revised information.
ITEM 1-12 SPECIFICATION SECTION 11 94 10 – ROOFTOP FALL PROTECTION ANCHORS
The Specification Section indicated and dated September 12, 2024 is hereby removed from the Project Manual.
ITEM 1-13 SPECIFICATION SECTION 21 13 13
The attached revised Specification Section indicated and dated February 17, 2025 shall supersede the Specification Section dated September 12, 2024.
A. Refer to part 3.4.8. Revised information.
ITEM 1-14 SPECIFICATION SECTION 26 05 73
The Specification Section indicated and dated February 17, 2025 is hereby added to the Project Manual.
REFERENCE THE DRAWINGS
ITEM 1-15 DRAWING SHEET A-002 – PARTITION TYPES
The attached revised Drawing Sheet indicated and dated February 17, 2025 shall supersede Drawing Sheet dated September 12, 2024.
A. Refer to Wall Series Legend.
B. Refer to Detail B2, Wall Types.
ITEM 1-16 DRAWING SHEET AE102 – FLOOR PLAN – SECTOR A
The attached revised Drawing Sheet indicated and dated February 17, 2025 shall supersede Drawing Sheet dated September 12, 2024.
A. Refer to Detail A1, Floor Plan – Sector A. Added tags to windows.
B. Refer to Detail A1, Floor Plan – Sector A. Revised cell phone locker in Room 129.
ITEM 1-17 DRAWING SHEET AE103 – FLOOR PLAN – SECTOR B
The attached revised Drawing Sheet indicated and dated February 17, 2025 shall supersede Drawing Sheet dated September 12, 2024.
A. Refer to Detail A2, Floor Plan – Sector B. Revised cell phone locker in Room 129.
ITEM 1-18 DRAWING SHEET AE151 – REFLECTED CEILING PLAN – SECTOR A
The attached revised Drawing Sheet indicated and dated February 17, 2025 shall supersede Drawing Sheet dated September 12, 2024.
A. Refer to Detail A1, Reflected Ceiling Plan – Sector A. Revised lighting in Room 111.
ITEM 1-19 DRAWING SHEET AE201 – BUILDING ELEVATIONS
The attached revised Drawing Sheet indicated and dated February 17, 2025 shall supersede Drawing Sheet dated September 12, 2024.
A. Refer to Detail C1, West Elevation. Revised material information.
ITEM 1-20 DRAWING SHEET AE402 – ENLARGED PLANS
The attached revised Drawing Sheet indicated and dated February 17, 2025 shall supersede Drawing Sheet dated September 12, 2024.
A. Refer to Detail A1, Enlarged Plan. Revised cell phone locker detail in Room 129.
ITEM 1-21 DRAWING SHEET AE403 – ENLARGED PLANS
The attached revised Drawing Sheet indicated and dated February 17, 2025 shall supersede Drawing Sheet dated September 12, 2024.
A. Refer to Detail A1, Enlarged Plan – Breakroom 145. Changed detail note from”B1” to “B3”.
ITEM 1-22 DRAWING SHEET AE411 – INTERIOR ELEVATIONS
The attached revised Drawing Sheet indicated and dated February 17, 2025 shall supersede Drawing Sheet dated September 12, 2024.
A. Refer to Sheet Keynote 12.
ITEM 1-23 DRAWING SHEET AE502 – DETAILS
The attached revised Drawing Sheet indicated and dated February 17, 2025 shall supersede Drawing Sheet dated September 12, 2024.
A. Refer to Detail B1, Passage Window Detail. Revised information.
ITEM 1-24 DRAWING SHEET AE600 – ROOM FINISH SCHEDULE
The attached revised Drawing Sheet indicated and dated February 17, 2025 shall supersede Drawing Sheet dated September 12, 2024.
A. Refer to Room Finish Schedule. Multiple revisions across table.
ITEM 1-25 DRAWING SHEET AE601 – DOOR SCHEDULE AND DETAILS
The attached revised Drawing Sheet indicated and dated February 17, 2025 shall supersede Drawing Sheet dated September 12, 2024.
B. Refer to Detail A1, Interior Window Types. Notes provided & updated. IN4 dimensions provided.
ITEM 1-26 DRAWING SHEET AE602 – OLI #1 – EXTERIOR WINDOW FRAMES
The attached revised Drawing Sheet indicated and dated February 17, 2025 shall supersede Drawing Sheet dated September 12, 2024.
A. Refer to Detail B1, OLI #1 – Exterior Window Types. Type “E” removed. Notes provided & updated.
ITEM 1-27 DRAWING SHEET IN101 – FLOOR FINISH PLAN – SECTOR A
The attached revised Drawing Sheet indicated and dated February 17, 2025 shall supersede Drawing Sheet dated September 12, 2024.
A. Refer to Detail A3, Floor Finish Plan – Sector “A”. Revised hatch in Rooms 173 & 174B.
B. Refer to Finish Legend. RAF hatch pattern updated & carpet revised.
ITEM 1-28 DRAWING SHEET IN102 – FLOOR FINISH PLAN – SECTOR B
The attached revised Drawing Sheet indicated and dated February 17, 2025 shall supersede Drawing Sheet dated September 12, 2024.
A. Refer to Detail A2, Floor Finish Plan – Sector “B”. Revised hatch in Rooms 172 & 174A.
B. Refer to Finish Legend. RAF hatch pattern updated & carpet revised.
ITEM 1-29 DRAWING SHEET FA601 – FIRE ALARM & MASS NOTIFICATION RISER DIAGRAM
The attached revised Drawing Sheet indicated and dated February 17, 2025 shall supersede Drawing Sheet dated September 12, 2024.
A. Refer to Detail A1, Fire Alarm / Mass Notification Riser Diagram. Removed ICD 705 reference.
ITEM 1-30 DRAWING SHEET EL101 – ELECTRICAL INTERIOR LIGHTING PLAN – SECTOR A
The attached revised Drawing Sheet indicated and dated February 17, 2025 shall supersede Drawing Sheet dated September 12, 2024.
A. Refer to Detail A1, Electrical Interior Lighting Plan – Sector A. Light types updated in Room 111.
BIDDER QUESTIONS
The attached Bidder Questions Log is provided for reference. Answers are intended to provide clarification and are non-binding. Answers to Bidder Questions requiring revision to the Contract Documents are indicated above.
END OF ADDENDUM
Addendum Narrative.docx Page 1 of 1 FSB | fsb-ae.com FSB | DefineDesignDeliver