Updated Attachment H - UCCG OPC Pier Price Proposal Form REV 2.docx
DOCX document 53 KB Posted
- Attached to
- Design-Bid-Build, USCG Offshore Patrol Cutters (OPC) Homeport Pier, Naval Station Newport, Newport RI
- Solicitation number
- N4008526R0001
About this file
This is a Bid Price Schedule form for the USCG Offshore Patrol Cutter (OPC) Homeport Initiative pier construction project at Naval Station Newport, Newport, Rhode Island (eProject No. 1826479). Bidders must provide line item unit prices and subtotals for a comprehensive pier construction and demolition project executed on a design-bid-build basis.
The base price (Line Item 0001) encompasses the entire scope of work including demolition of existing Pier 1, construction of landside areas and new Bulkhead S45S, and construction of the new OPC Pier 1. Detailed line items require unit pricing for specialized construction activities: installation of various pile types (36-inch diameter reinforced concrete filled steel pipe piles at 30,510 linear feet; HP 14x102-inch piles at 416 linear feet; HP 10x42-inch piles at 512 linear feet; 30-inch diameter steel pipe piles at 598 linear feet; and polymeric fender piles at 40,996 linear feet); dynamic pile load testing (5 tests for steel pipe piles and 3 tests for polymeric fender piles); dredging and material disposal activities with separate unit prices for asbestos-containing material (1,200 cubic yards) and non-asbestos soil (21,630 tons); steel sheet pile installation for bulkhead S45S (213 tons); and extensive hazardous material removal including asbestos roofing (4,000 square feet), PCB-containing caulking (510 linear feet), PCB light ballasts (14 units), mercury light ballasts (14 units), PCB transformers (1 unit), mercury thermostats (2 units), lead from anchors (2 tons), and PCB-impacted concrete materials (606 cubic feet). Additional line items address soil removal, debris disposal, subsurface water treatment, an in-lieu fee for potential eel grass damage, and dredging and disposal activities. The form is a template requiring contractors to insert pricing for each line item.
View the file
Other files
Show 40 more
Latest 50 of 90 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCG OCR Homeport Initiative OPC Pier eProject No. 1826479 Newport Naval Station – Newport, RI
BID PRICE SCHEDULE
Provide line item prices, where indicated by blank underlines, for the following items:
| Line Item |
| Description |
| Quantity |
| Unit |
| Unit Price |
| Sub-Total |
| Total Price |
| 0001 |
| BASE PRICE: Total Price for (subtotals of Line Items 0001A through 0001Z) the entire work for USCG OCR Homeport OPC Pier, including demolition of existing Pier 1, construction of landside area and new Bulkhead S45S, and construction of new OPC Pier 1 at Naval Station Newport, RI, in accordance with the drawings and specifications, complete, but excluding work provided as Option Items. |
| 1 |
| LS |
| 0001A |
| Price for the construction of the new OPC Pier, and all associated site work and utilities as indicated on the drawings and in the specifications excluding work provided in another priced line item. |
| 1 |
| LS |
| 0001AA |
| Unit price for dredging and disposal of dredged material containing greater than 1% Asbestos Containing Material (ACM) in accordance with applicable environmental regulations, material not shown in contract drawings or specifications. |
| 1,200* |
| CY |
| 0001AB |
| Unit price to remove and dispose of all soil containing greater than 1% Asbestos Containing Material (ACM), not shown in contract drawings or specifications. |
| 2,000* |
| CY |
| $___________ |
0001B
Unit price to furnish and install 36” diameter reinforced concrete filled steel pipe piles for the pier, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item.
| 30,510* |
| LF |
0001C
Unit Price for providing all work in connection with installation of Steel Pipe Pile/Casing Pipe Obstruction (less than one cubic yard). Documents, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item.
52*
EA
0001CA
Unit price for demolition, removal, and disposal of debris larger than 1 cubic yard (i.e. abandoned foundations, utility structures, timber piles, etc.) encountered within planned excavations (i.e., utilities, foundations) or encountered at planned pile locations that is not indicated on the Demolition Plans.
| 50* |
| Tons (Truck Scale Measure) |
| $___________ |
0001D
Unit price to furnish and install HP 14x102” piles for the pier, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item.
| 416* |
| LF |
0001E
| Unit price to furnish and install HP 10x42” piles for the pier, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item. |
| 512* |
| LF |
0001F
| Unit price to furnish and install 30” diameter reinforced concrete filled steel pipe piles for the pier, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item. |
| 598* |
| LF |
0001G
Unit price to furnish and install polymeric fender piles for the pier, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item.
| 40,996* |
| LF |
0001H
Unit price to provide dynamic pile load PDA test for 36" diameter steel pipe piles (includes re-strike) for the pier, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item.
| 5 |
| EA |
0001I
| Unit price to provide dynamic pile load test for polymeric fender piles with steel H-pile extension, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item. |
| 3 |
| EA |
| 0001J |
| Sampling, testing, treatment, and discharge or off‑site disposal of subsurface water encountered during construction. On‑site discharge must comply with RIPDES Remediation General Permit requirements, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item. |
| 1 |
| LS |
| 0001K |
| Price for entire work for Bulkhead S45S construction, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item. |
| 1 |
| LS |
| 0001L |
| Unit price to furnish and install steel sheet pile sheeting for Bulkhead S45S, including delivery, handling, driving, splicing, trimming, and application of coatings, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item. Costs of deadman anchors, tie rods, wales, should not be included in this line item. |
| 213 |
| TON |
| 0001M |
| “In lieu” Fee for potential Eel Grass damage / disturbance adjacent to new S45S bulkhead. |
| 1 |
| LS |
| 0001N |
| Price for the demolition of existing Pier 1 in its entirety and all associated landside demolition excluding work provided in another priced line item. |
| 1 |
| LS |
0001O
Unit price to remove and dispose of all soil considered to be non-hazardous from the site to a licensed RCRA facility, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item
| 21,630* |
| Tons (Truck Scale Measure) |
| $___________ |
0001P
| Unit price to remove and dispose of all soil considered hazardous, non-asbestos containing (asbestos <1%) from the site to a licensed RCRA facility, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item. |
| 1,350* |
| Tons (Truck Scale Measure) |
| 0001Q |
| Unit price to remove and dispose of asbestos containing materials (>1% ACM) from existing Pier 1 – Glazing compound from 24 windows at existing Pier 1 buildings, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item. |
| 372 |
| LF |
| 0001R |
| Unit price to remove and dispose of asbestos containing materials (>1% ACM) from existing Pier 1 –Tar roofing on existing buildings, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item. |
| 4,000 |
| SF |
| 0001S |
| Unit price to remove and dispose of caulking containing PCBs on existing Pier 1 Buildings, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item. |
| 510 |
| LF |
| 0001T |
| Unit price to remove and dispose of PCB containing light ballasts from Pier 1 buildings, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item. |
| 14 |
| Each |
| 0001U |
| Unit price to remove and dispose of PCB-Impacted CMU and Concrete/Asphalt from existing Pier 1 and existing Pier 1 buildings, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item. |
| 606 |
| CF |
| 0001V |
| Unit price to remove and dispose of Mercury containing light ballasts from Pier 1 buildings, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item. |
| 14 |
| Each |
| 0001W |
| Unit price to remove and dispose of PCB containing transformers from existing Pier 1, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item. |
| 1 |
| Each |
| 0001X |
| Unit price to remove and dispose of mercury containing thermostats from Pier 1 buildings, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item. |
| 2 |
| Each |
| 0001Y |
| Unit price to remove and dispose of lead from anchors in cleats and bollards from existing Pier 1, complete in accordance with the drawings and specifications, but excluding work provided in another priced line item. |
| 2 |
| Tons |
| 0001Z |
| Unit price for dredging and dredge disposal (Including allowable over dredge), complete in accordance with the drawings and specifications, but excluding work provided in another priced line item. Assumes dredged material contains <1% Asbestos Containing Material (ACM) |
| 11,375* |
| CY |
| 0002 |
| Option Item No. 1: Compressed Air System: Furnish and install in accordance with the drawings and specifications |
| 1 |
| LS |
| 0003 |
| Option Item No. 2: Additional costs to provide cast-in-place concrete pavement for the designated laydown area in lieu of asphalt pavement, complete. |
| 1 |
| LS |
TOTAL
Line Items 0001 – 0003
GENERAL BID NOTES
a. Award will be evaluated on the total proposed price for Line Items 0001 – 0003, Base Price and the sum of all Option Item prices. The subtotal of Line Item 0001A-0001Z is included in Line Item 0001.
b. The Government reserves the unilateral right to award any and all of Line Items 0002 and 0003 to the Contractor at the proposed price within 365 calendar days after the contract award and in accordance with all bid notes. A firm fixed proposed price is required for Line Items 0001-0003. No provision is made for economic price adjustment. If Line Items 0002 or 0003 are exercised, the contract completion date (CCD) remains 918 days after contract award.
c. Quantities on the bid schedule that are followed by an asterisk (*) are estimated quantities. Contractor shall only be paid for quantities/units of work actually performed. If the estimated quantity used in the bid schedule is not reached, a deductive modification shall be taken at the end of contract for quantities/units not performed. If the estimated quantity is exceeded, an equitable adjustment shall be made to the contract price for work performed over the estimated quantity. If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 15 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgement of the Contracting Officer, is justified.
d. Pile quantities on the bid schedule that are followed by an asterisk (*) are estimated quantities. Requirements mentioned in Item C of the General Bid Notes shall not apply to payment for piling. Each pile and test pile acceptably provided will be paid for at the bid unit price for units actually installed. The unit price shall include items incidental to furnishing and driving the piles including mobilization and demobilization, predrilling, probing, redriving uplifted piles, and cutting off piles at the cutoff elevation. Payment shall be made for production and test piles at the bid unit price for the length of pile, from tip to final cutoff, actually provided, including buildups and splices directed by the Contracting Officer to be made. Should the actual cumulative pile length driven (tip to cutoff) vary more than 25 percent from the total estimated pile length specified as a basis for bidding, the price shall be adjusted based upon any increase or decrease in costs due solely to the variation.
e. Evaluations of Options (JUL 1990). Except when it is determined in accordance with RFO 17.202 (b) not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the price for Line Items 0002 through 0003 to the total price for the Base Bid, (Line Item 0001). Evaluation of options will not obligate the Government to exercise the Option(s). (RFO 52.217-5).
f. The Government may reject an offer as non-responsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.
g. Failure to enter a price for any Line Item will result in a proposal being rejected.
h. For bid items where unit prices are indicated as required, bidders shall enter unit prices and extended totals in spaces provided. If there is a difference between a unit price and the extended total, the unit price will be held to be the intended bid and the total recomputed accordingly. If an Offeror provides a total but fails to enter a unit price, the total divided by the specified quantity will be held to be the intended unit price.
i. If any or all of Line Item 0002 and 0003 are exercised, additional bonding and consent of surety is required. Consequently, the Performance Bond must reflect 100 percent of the aggregate amount of all items.
File details come from the government source that posted it. Updated .