Amendment 0005 USCG OPC.pdf
PDF 914 KB Posted
- Attached to
- Design-Bid-Build, USCG Offshore Patrol Cutters (OPC) Homeport Pier, Naval Station Newport, Newport RI
- Solicitation number
- N4008526R0001
About this file
This is Amendment 005 to a Design-Bid-Build solicitation (N4008526R0001) issued by the U.S. Navy for construction of the USCG Offshore Patrol Cutters (OPC) Homeport Pier at Naval Station Newport, Newport, Rhode Island. The amendment extends the proposal due date from June 15, 2026 to June 22, 2026 at 2:00 PM EDT and updates key contract documents including evaluation factors, drawings, specifications, and pricing forms. The contract completion schedule has been extended to 1,283 calendar days inclusive of all options and 15 days for bond approval, with an estimated award date of September 23, 2026. Critical updates include revised pile wall thickness specifications (changed to 7/8 inches), updated mechanical and electrical drawings, modified fender pile tip elevations, and clarifications on compressed air system scope allocation between base bid and bid options.
The amendment provides pre-proposal inquiry responses addressing schedule feasibility, marine mammal monitoring requirements, material specifications, and construction logistics. Key technical changes include revisions to bulkhead design details, precast concrete plank reinforcement specifications, utility trench requirements, and electrical/mechanical systems integration. The updated Attachment H price proposal form (REV 3) reflects revised quantities for dredging, mercury light ballast removal, lead removal units of measure, and asbestos-containing material disposal. Contractors are directed to contact NAVFACSYSCOM Mid-Atlantic (Kristy Gerrek) for all solicitation correspondence, and the Government has incorporated known permit requirements while noting that earlier work start dates are permissible with 90+ days advance notice and marine mammal monitoring plan approval.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Block 14 (Description of Amendment/Modification): Solicitation NO: N4008526R0001, Design-Bid-Build, USCG Offshore Patrol Cutters (OPC) Homeport Pier, Naval Station Newport, Newport RI
SEE SF 30 BLOCK 14 CONTINUATION PAGE.
ALL CORRESPONDENCE REGARDING THIS SOLICITATION SHALL BE DIRECTED VIA EMAIL TO KRISTY GERREK AT KRISTY.L.
GERREK.CIV@US.NAVY.MIL.
This amendment is issued to incorporate the following:
1. Extend the proposal due date from 15 JUNE 2026 TO 22 JUNE 2026 NLT 2:00 P.M. EDT.
2. Provide updated Evaluation Factors for Award: Factor 2 - Management Approach and Schedule (Enclosed)
3. Update Commencement, Prosecution, and Completion of Work (Enclosed)
4. Provide continuation sheet for drawings and specifications (Enclosed)
5. Provide Attachment W - Pier 1 - Amendment 005 Drawings (Attached separately)
6. Provide Updated Attachment H - UCCG OPC Pier Price Proposal Form REV 3 (Attached separately)
7. Provide Attachment X - Appendix A Record Drawing 12819 135 Submarine Cable (Attached separately)
8. Provide Attachment Y - Appendix A Record drawing 11836 125 Submarine Cable Relocation (attached separately)
9. Provide Driving Logs and Geotechnical Data from NOAA Pier Project (Attached separately)
10. Provide PPI Responses (Enclosed)
Section 00 00 00 - Procurement and Contracting Requirements
The following changes have been made:
INFORMATION FROM TO
Response Due Date 15 Jun 2026 22 Jun 2026
Section 00 73 00 - Supplementary Conditions
The following attachments were added:
Amendment 0005 Continuation Page
N4008526R00010005
SECTION SF30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The following have been added by full text:
AMENDMENT 0005
This amendment is issued to incorporate the following:
1. Extend the proposal due date from 15 JUNE 2026 TO 22 JUNE 2026 NLT 2:00 P.M. EDT.
2. Provide updated Evaluation Factors for Award: Factor 2 – Management Approach and Schedule
(Enclosed)
3. Update Commencement, Prosecution, and Completion of Work (Enclosed)
4. Provide continuation sheet for drawings and specifications (Enclosed)
5. Provide Attachment W - Pier 1 - Amendment 005 Drawings (Attached separately)
6. Provide Updated Attachment H - UCCG OPC Pier Price Proposal Form REV 3 (Attached separately)
7. Provide Attachment X - Appendix A Record Drawing 12819 135 Submarine Cable (Attached separately)
8. Provide Attachment Y - Appendix A Record drawing 11836 125 Submarine Cable Relocation (attached separately)
9. Provide Driving Logs and Geotechnical Data from NOAA Pier Project (Attached separately)
10. Provide PPI Responses (Enclosed)
1. The proposal due date is extended from 15 JUNE 2026 TO 22 JUNE 2026 NLT 2:00 P.M. EDT.
**PLEASE NOTE THAT NO ADDITIONAL PPI’S WILL BE ACCEPTED.**
2. Updated Evaluation Factors for Award: Factor 2 – Management Approach and Schedule (updates notated in red)
Factor 2 - Management Approach and Schedule
(i) Solicitation Submittal Requirements:
The offeror shall submit a narrative and schedule for this factor. The narrative shall not exceed ten (10) pages, 8-1/2" x 11" size. Provide the schedule, documenting any multiple critical paths, in 11" x 17" pages and in an Adobe PDF file. There is no page limit on the schedule.
The narrative shall address the following issues:
1. Provide a narrative describing the proposed approach to management, for both subcontractors and your workforce, to ensure schedule adherence, early detection and correction of problems and the execution of the base bid items and all options, as referenced in the RFP.
2. Identify activities that may affect the project timeline, including other/off site work activities.
3. Describe how your firm will handle technical complexities relating to: pier demolition, bulkhead construction, pier construction and landside work to include installation of site utilities and paving.
4. Describe how your firm will handle unforeseen problems with: material deliveries, subcontractor progress, weather, re-work, differing site conditions, and inspections relating to the subject project.
The schedule shall include:
1. Provide a Critical Path Method (CPM) construction schedule that illustrates your ability to achieve the schedule and meet all the requirements of the RFP (1,283 calendar days inclusive of all options, including 15 days for bond approval). For evaluation purposes, Offerors should use an estimated award date of on or about 23 September 2026. This date is for proposal purposes only and is not intended to indicate an anticipated/planned award date. Any proposed duration shorter than the RFP requirements will be incorporated into the contract award.
3. Update Commencement, Prosecution, and Completion of Work (Enclosed)
COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
The Contractor shall be required to (a) commence work under this contract within fifteen (15) calendar days after the date the Contractor receives notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 1,283 calendar days. The time stated for completion shall include final cleanup of the premises.
*The calendar days to complete this contract includes the 15 calendar days for submission and approval of performance and payment bonds after the contract award.
4. Continuation Sheet for Drawings and Specifications (Enclosed)
CONTRACT DRAWINGS
DWG
NO
NAVFAC
NO
CHANGE NO TITLE
G-002 12936571 005 INDEX OF DRAWINGS - SHEET 1 OF 2
C-001 12936603 005 CIVIL LEGEND, ABBREVIATIONS & GENERAL NOTES
C-102 12936608 005 UTILITY PLAN - PIER 1 LANDSIDE
C-103 12936609 005 COMPOSITE UTILITY LAYOUT PLAN - PIER 1 LANDSIDE
C-504 12936615 005 SITE DETAILS - SHEET 3 OF 6
S-002 12936620 005 STRUCTURAL GENERAL NOTES – SHEET 1 OF 2
S-005 12936623 005 STRUCTURAL DESIGN LOADS AND STANDARD DETAILS
- SHEET 2 OF 2
S-103 12936639 005 PILE PLAN – SHEET 1 OF 7
S-104 12936640 005 PILE PLAN – SHEET 2 OF 7
S-105 12936641 005 PILE PLAN – SHEET 3 OF 7
S-106 12936642 005 PILE PLAN – SHEET 4 OF 7
S-107 12936643 005 PILE PLAN – SHEET 5 OF 7
S-108 12936644 005 PILE PLAN – SHEET 6 OF 7
S-109 12936645 005 PILE PLAN – SHEET 7 OF 7
S-110 12936646 005 FRAMING PLAN – SHEET 1 OF 7
S-115 12936651 005 FRAMING PLAN – SHEET 6 OF 7
S-207 12936681 005 REPAIRED S45N BULKHEAD ELEVATION & PIER 1
SECTION
S-208 12936682 005 S45S BULKHEAD ELEVATION
S-307 12936689 005 PIER TRANSVERSE SECTIONS SHEET 1 OF 5
S-402 12936695 005 OUTBOARD SUBSTATION PART PLAN
S-403 12936696 005 INBOARD SUBSTATION PART PLAN
S-502 12936699 005 PILE DETAILS – CONCRETE FILLED STEEL PIPE PILES
S-503 12936700 005 PILE DETAILS - STEEL PILES
S-505 12936706 005 CONCRETE PILE CAP DETAILS – SHEET 2 OF 3
S-506 12936703 005 CONCRETE PILE CAP DETAILS – SHEET 3 OF 3
S-507 12936704 005 REINFORCED BOLLARD FOUNDATION DETAILS
S-513 12936710 005 TYPICAL PIER DUCTBANK DETAILS
S-515 12936712 005 PRECAST CONCRETE PLANK DETAILS
S-517 12936714 005 PRECAST MANHOLE DETAILS
S-518 12936715 005 UTILITY TRENCH COVER DETAILS
S-527 12936724 005 S45S BULKHEAD DETAILS – SHEET 2 OF 3
S-528 12936725 005 S45S BULKHEAD DETAILS – SHEET 3 OF 3
S-529 12936726 005 AIR COMPRESSOR FOUNDATION & STEEL FRAME PART
PLAN
S-530 12936727 005 AIR COMPRESSOR DETAILS
M-102 12936737 005 MECHANICAL PLAN - SHEET 2 OF 7
M-105 12936740 005 MECHANICAL PLAN - SHEET 5 OF 7
M-107 12936742 005 MECHANICAL PLAN - SHEET 7 OF 7
M-401 12936746 005 MECHANICAL COMPRESSED AIR ENCLOSURE - PART
PLAN
M-402 12936747 005 REDUCED PRESSURE BACKFLOW PREVENTER DETAILS -
SHEET 1 OF 2
M-501 12936748 005 NORTHERN MECHANICAL ENCLOSURE DETAILS
M-502 12936749 005 SOUTHERN MECHANICAL ENCLOSURE DETAILS
M-503 12936750 005 PIER HEATED ENCLOSURE - SANITARY AND FRESH
WATER
E-512 12936792 005 MISCELLANEOUS DETAILS – SHEET 1 OF 2
E-604 12936798 005 COMMUNICATIONS ONE LINE DIAGRAM
E-608 12936802 005 HEAT TRACE ONE LINE DIAGRAM & SCHEDULES
ES604 12936816 005 BREAKER 152-11 COMMUNICATIONS DIAGRAM
All NAVFAC Drawings and Specifications
REMOVE THE TERM “Base Bid” from all drawings and specifications. The base bid and options are as defined in the Bid Price Schedule.
ADD the following drawings to the INDEX OF DRAWINGS under the corresponding discipline and drawing number. These drawings accompany this Amendment:
On NAVFAC Dwg. No. 12936571 (G-002)
CHANGE G-002 INDEX OF DRAWINGS - SHEET 1 OF 2 as follows:
REVISE NAVFAC DWG. NO. FROM 12936613 TO 12936609 for drawing C-103 COMPOSITE
UTILITY LAYOUT PLAN – PIER 1 LANDSIDE.
REVISE NAVFAC DWG. NO. FROM 12936699 TO 12936695 for drawing S-402 OUTBOARD
SUBSTATION PART PLAN.
REVISE NAVFAC DWG. NO. FROM 12936700 TO 12936696 for drawing S-403
INBOARD SUBSTATION PART PLAN.
REVISE NAVFAC DWG. NO. FROM 12936704 TO 12936700 for drawing S-503
PILE DETAILS – STEEL PILES.
REVISE NAVFAC DWG. NO. FROM 12936706 TO 12936702 for drawing S-505 CONCRETE PILE
CAP DETAILS – SHEET 2 OF 3.
REVISE NAVFAC DWG. NO. FROM 12936708 TO 12936704 for drawing S-507 REINFORCED
BOLLARD FOUNDATION DETAILS.
REVISE NAVFAC DWG. NO. FROM 12936730 TO 12936726 for drawing S-529
AIR COMPRESSOR FOUNDATION & STEEL FRAME PART PLAN
On NAVFAC Dwg. No. 12936603 (C-001)
CHANGE C-001 CIVIL LEGEND, ABBREVIATIONS & GENERAL NOTES (BASE BID) as follows:
ADD Weekend Paving Trench Note – “Contractor must provide temporary trench repair by the close of operations every Friday for all trench work within paved areas. See detail a1 on plan
C-502. No unpaved trenching within areas of travel, parking, or pedestrian movements will be allowed over the weekend.”
REMOVE “Base Bid” from the drawing title.
On NAVFAC Dwg. No. 12936608 (C-102)
CHANGE C-102 UTILITY PLAN - PIER 1 LANDSIDE as follows:
REVISE existing contours between the bulkhead and the existing Pier Access Road.
On NAVFAC Dwg. No. 12936609 (C-103)
CHANGE C-103 COMPOSITE UTILITY LAYOUT PLAN – PIER 1 LANDSIDE as follows:
On NAVFAC Dwg. No. 12936615 (C-504)
CHANGE C-504 SITE DETAILS - SHEET 3 OF 6 as follows:
REVISE detail A1 “Sanitary Pump Station Detail” has been revised to require a precast concrete storage tank.
On NAVFAC Dwg. No. 12936620 (S-002)
CHANGE S-002 STRUCTURAL GENERAL NOTES – SHEET 1 OF 2 as follows:
REVISE Foundation Notes – Steel Pipe Piles note 3 to change pile wall thickness to 7/8”.
On NAVFAC Dwg. No. 12936623 (S-005)
CHANGE S-005 STRUCTURAL DESIGN LOADS AND STANDARD DETAILS - SHEET 2 OF 2
as follows:
ADD NAVFAC DWG. NO. 12936623 within the title block.
On NAVFAC Dwg. No. 12936639 (S-103)
CHANGE S-103 PILE PLAN SHEET 1 OF 7 as follows:
REVISE General sheet note 1 to change pile thickness to 7/8”.
On NAVFAC Dwg. No. 12936640 (S-104)
CHANGE S-104 PILE PLAN SHEET 2 OF 7 as follows:
On NAVFAC Dwg. No. 12936641 (S-105)
CHANGE S-105 PILE PLAN SHEET 3 OF 7 as follows:
On NAVFAC Dwg. No. 12936642 (S-106)
CHANGE S-106 PILE PLAN SHEET 4 OF 7 as follows:
On NAVFAC Dwg. No. 12936643 (S-107)
CHANGE S-107 PILE PLAN SHEET 5 OF 7 as follows:
On NAVFAC Dwg. No. 12936644 (S-108)
CHANGE S-108 PILE PLAN SHEET 6 OF 7 as follows:
On NAVFAC Dwg. No. 12936645 (S-109)
CHANGE S-109 PILE PLAN SHEET 7 OF 7 as follows:
On NAVFAC Dwg. No. 12936646 (S-110)
CHANGE S-110 FRAMING PLAN SHEET 1 OF 7 as follows:
REMOVE Cast-in-place slab shading from the manholes between Bents 41-42 and pile lines B-C.
On NAVFAC Dwg. No. 12936651 (S-115)
CHANGE S-115 FRAMING PLAN SHEET 6 OF 7 as follows:
REMOVE Cast-in-place slab shading from the manholes between Bents 7-8 and pile lines D-E.
On NAVFAC Dwg. No. 12936681 (S-207)
CHANGE S-207 REPAIRED S45N BULKHEAD ELEVATION AND PIER 1 SECTION as follows:
ADD Anodes to the repaired section of Bulkhead S45N.
On NAVFAC Dwg. No. 12936682 (S-208)
CHANGE S-208 S45S BULKHEAD ELEVATION as follows:
ADD General note to provide anode size, weight, and type.
REMOVE ”(Base Bid)” from sheet title.
On NAVFAC Dwg. No. 12936689 (S-307)
CHANGE S-307 PIER TRANSVERSE SECTIONS – SHEET 1 OF 5 as follows:
REVISE Water stops between precast and cast-in-place concrete to be swellable.
On NAVFAC Dwg. No. 12936695 (S-402)
CHANGE S-402 OUTBOARD SUBSTATION PART PLAN as follows:
REVISE NAVFAC DWG. NO. FROM 12936699 TO 12936695 within the title block.
On NAVFAC Dwg. No. 12936696 (S-403)
CHANGE S-403 INBOARD SUBSTATION PART PLAN as follows:
REVISE NAVFAC DWG. NO. FROM 12936700 TO 12936696 within the title block.
On NAVFAC Dwg. No. 12936699 (S-502)
CHANGE S-502 PILE DETAILS – CONCRETE FILLED STEEL PIPE PILES as follows:
REVISE Details A1, A3 and D5 to change pile wall thickness to 7/8”.
On NAVFAC Dwg. No. 12936700 (S-503)
CHANGE S-503 INBOARD SUBSTATION PART PLAN as follows:
REVISE NAVFAC DWG. NO. FROM 12936704 TO 12936700 within the title block.
On NAVFAC Dwg. No. 12936706 (S-505)
CHANGE S-505 CONCRETE PILE CAP DETAILS – SHEET 2 OF 3 as follows:
REVISE Detail A2 to show a 4-ft tall pile cap.
On NAVFAC Dwg. No. 12936703 (S-506)
CHANGE S-506 CONCRETE PILE CAP DETAILS – SHEET 3 OF 3 as follows:
REVISE Detail C2 to update pipe pile callout.
On NAVFAC Dwg. No. 12936704 (S-507)
CHANGE S-507 REINFORCED BOLLARD FOUNDATION DETAILS as follows:
REVISE NAVFAC DWG. NO. FROM 12936708 TO 12936704 within the title block.
On NAVFAC Dwg. No. 12936710 (S-513)
CHANGE S-513 TYPICAL PIER DUCTBANK DETAILS as follows:
ADD NAVFAC DWG. NO. 12936710 within the title block.
On NAVFAC Dwg. No. 12936712 (S-515)
CHANGE S-515 PRECAST CONCRETE PLANK DETAILS as follows:
REPLACE Drawing S-515 in its entirety.
On NAVFAC Dwg. No. 12936714 (S-517)
CHANGE S-517 PRECAST MANHOLE Details as follows:
ADD Section A4 to drawing.
On NAVFAC Dwg. No. 12936715 (S-518)
CHANGE S-518 UTILITY TRENCH COVER DETAILS as follows:
REVISE Manhole opening size in detail C1 from 36” to 30”.
On NAVFAC Dwg. No. 12936724 (S-527)
CHANGE S-527 S45S BULKHEAD DETAILS – SHEET 2 OF 3 (BASE BID) as follows:
ADD General note to clarify wale to sheeting connection applies to the deadman.
On NAVFAC Dwg. No. 12936725 (S-528)
CHANGE S-528 S45S BULKHEAD DETAILS – SHEET 3 OF 3 (BASE BID) as follows:
REVISE Detail A4 title to clarify the detail is applicable to both the main bulkhead and the deadman system.
On NAVFAC Dwg. No. 12936726 (S-529)
CHANGE S-529 AIR COMPRESSOR FOUNDATION & STEEL FRAME PART PLAN as follows:
REVISE NAVFAC DWG. NO. FROM 12936730 TO 12936726 within the title block.
On NAVFAC Dwg. No. 12936727 (S-530)
CHANGE S-530 AIR COMPRESSOR DETAILS as follows:
ADD NAVFAC DWG. NO. 12936727 within the title block.
On NAVFAC Dwg. No. 12936733 (S-602)
CHANGE S602 FENDER PILE SCHEDULE – SHEET 1 OF 2 as follows:
REDUCE the length of each fender pile by 10 ‘-0”
On NAVFAC Dwg. No. 12936734 (S-603)
CHANGE S602 FENDER PILE SCHEDULE – SHEET 2 OF 2 as follows:
REDUCE the length of each fender pile by 10 ‘-0”
On NAVFAC Dwg. No. 12936737 (M-102)
CHANGE M-102 MECHANICAL PLAN - SHEET 2 OF 7 as follows:
ADD note 22 – “provide a sign/plate at each mechanical heated enclosure with the following message -
“warning: dead-end water main: potable water must be monitored and tested frequently, and flushed prior to berthing. do not connect to the vessel until the required fac residual has been confirmed”.”
On NAVFAC Dwg. No. 12936740 (M-105)
CHANGE M-105 MECHANICAL PLAN - SHEET 5 OF 7 as follows:
ADD note 22 – “provide a sign/plate at each mechanical heated enclosure with the following message -
“warning: dead-end water main: potable water must be monitored and tested frequently, and flushed prior
On NAVFAC Dwg. No. 12936742 (M-107)
CHANGE M-107 MECHANICAL PLAN - SHEET 7 OF 7 as follows:
REVISE notes 6, 9, 15, 16 & 17 to include “(BID OPTION)”.
REVISE note 21 to include “(BASE OPTION)”.
REVISE note 10 “Provide 3-inch compressed air piping routed to the packaged compressed air enclosure. Compressed air piping shall be direct buried from the point of demarcation. The buried compressed air piping and associated enclosure are included under the bid option. Refer to drawings for the point of demarcation at the pier trench manhole located between bents 0 and 1. Install a pipe drop as required to provide vertical offset and avoid conflicts with adjacent buried utilities.”
On NAVFAC Dwg. No. 12936746 (M-401)
CHANGE M-401 MECHANICAL COMPRESSED AIR ENCLOSURE - PART PLAN as follows:
REVISE detail C3, “COMPRESSED AIR ENCLOSURE – PART PLAN,” and detail A1
“COMPRESSED AIR ENCLOSURE – SECTION” to include “(BID OPTION)” at the end of the titles.
REVISE detail A2, “UTILTIY SECTION - COMPRESSED AIR ENCLOSURE – EAST ELEVATION
(BID OPTION)” to call out 3” dia CA pipes as bid option.
REVISE note 6 to correct drawing numbers, from S-401, S-541 & S-542, TO S-529 & S-533.
On NAVFAC Dwg. No. 12936747 (M-402)
CHANGE M-402 REDUCED PRESSURE BACKFLOW PREVENTER DETAILS - SHEET 1 OF 2
as follows:
ADD note 8 – “provide conduit to mechanical enclosure. For PVC coated RGS conduits penetration and distribution refer to electrical drawings for further information. See detail C4 / E-512”.”
On NAVFAC Dwg. No. 12936748 (M-501)
CHANGE M-501 NORTHERN MECHANCIAL ENCLOSURE DETAILS as follows:
ADD note 11 – “provide a sign/plate at each mechanical heated enclosure with the following message -
“warning: dead-end water main: potable water must be monitored and tested frequently, and flushed prior
On NAVFAC Dwg. No. 12936749 (M-502)
CHANGE M-502 SOUTHERN MECHANCIAL ENCLOSURE DETAILS as follows:
ADD note 11 – “provide a sign/plate at each mechanical heated enclosure with the following message -
“warning: dead-end water main: potable water must be monitored and tested frequently, and flushed prior
On NAVFAC Dwg. No. 12936750 (M-503)
CHANGE M-503 PIER HEATED ENCLOSURE - SANITARY AND FRESH WATER as follows:
ADD note 3 – “provide a sign/plate at each mechanical heated enclosure with the following message -
“warning: dead-end water main: potable water must be monitored and tested frequently, and flushed prior
On NAVFAC Dwg. No. 12936792 (E-512)
CHANGE E-512 BREAKER 152-11 COMMUNICATIONS DIAGRAM as follows:
ADD Detail C3 BACKFLOW PREVENTER ENCLOSURE - ELEVATION
On NAVFAC Dwg. No. 12936798 (E-604)
CHANGE E-604 COMMUNICATIONS ONE LINE DIAGRAM as follows:
REVISE Clarifications of communications/alarm feeders run to the MAT Building 1406.
On NAVFAC Dwg. No. 12936802 (E-608)
CHANGE E-608 HEAT TRACE ONE LINE DIAGRAM & SCHEDULES as follows:
REVISE Note 4. “HEAT TRACE CONTROLLER MUST PROVIDE OUTPUT ALARM SIGNAL FOR
FAILURE OF HEAT TRACING SYSTEM TO MAT BUILDING 1406. SEE E-604 FOR
CONNECTIONS OF SIGNAL WIRING TO MAT BUILDING.”
On NAVFAC Dwg. No. 12936816 (ES604)
CHANGE ES604 BREAKER 152-11 COMMUNICATIONS DIAGRAM as follows:
REVISE NAVFAC DWG. NO. FROM 12936716 TO 12936816 within the title block.
SPECIFICATIONS
Specification Section 01 35 26 – GOVERNMENTAL SAFETY REQUIREMENTS
ADD Paragraph 2.2 Personal Flotation Devices
Provide (10) Type-V PFDs for Government use. Sizes to be determined.
Specification Section 01 35 40.00 20 – MARINE MAMMAL MONITORING PROTECTION
REVISE Paragraph 1.2.3 to replace references to NAVFAC with USCG.
REVISE the first sentence of Paragraph 1.4 – MARINE MAMMAL OBSERVATION AND
ACOUSTIC MONITORING PLAN to read “The Contractor is required to prepare and submit to the
Contracting Officer a Marine Mammal Observation and Acoustic Monitoring Plan for the construction of the new OPC Pier 1 and the construction of the new S45S bulkhead.”
ADD the following sentence after the first sentence of Paragraph 1.5 Incidental Harassment Authorization
Renewals : “The authorized start date for the Year 1 IHA is June 1, 2027. The Contractor may request, through the Government, authorization from NMFS to initiate covered activities prior to this date, subject to NMFS review and approval.”
Specification Section 01 50 00 – TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
ADD Paragraph 3.3.5 Temporary Pavement Patching
Provide a temporary hot mix asphalt trench patch shall be installed by the close of business every Friday for all disturbed paved areas subject to traffic.
Specification Section 03 30 00 – CAST-IN-PLACE CONCRETE
ADD the following sentence to Paragraph 3.6.2 under line time b.:
“The use of a hydration stabilizer admixture to extend placement time is acceptable. The hydration stabilizer must be included in the concrete mix design for review and approval and must be applied to the mix at the batch plan.”
Specification Section 06 71 00 - FIBERGLASS REINFORCED PLASTIC (FRP) LUMBER
DELETE Paragraph 2.1.1 - Materials
Specification Section 26 27 29 - MARINA ELECTRICAL WORK
REPLACE PARAGRAPH 2.17.3a Control and Monitoring Systems
“The monitoring system must have output alarm contacts for the fire protection/suppression heat trace circuits that report to the Fire Alarm radio box.” with:
“The monitoring system must have output alarm contacts for signaling failure of the heat trace system to
USCG MAT Building 1406.”
Specification Section 31 62 16.13 – STEEL PIPE PILES
REVISE the pile shoe type in section 2.2.2 from “inside fit” to “outside-ft” external cutting shoes.
Specification Section 33 71 01 UNDERGROUND ELECTRICAL DISTRIBUTION
ADD Paragraph 2.14 Manhole Frame and Cover
Provide cast iron frames and covers for manholes conforming to
CID A-A-60005. Cast the words "ELECTRIC" or "TELECOMMUNICATIONS" in the top face of power and telecommunications manhole covers, respectively. Diameter must be 36".
Appendix A – Record Drawings
ADD Drawing 11868 -125 “Location of Submarine Cables, Pier Box and Lighting Details”
ADD Drawing 12819-135 “Geographic Location Naval Base 22 kV 3 Phase 60 Cycle System”
5. Attachment W - Pier 1 - Amendment 005 Drawings is provided with this amendment (attached separately).
6. Updated Attachment H - UCCG OPC Pier Price Proposal Form REV 3 is provided with this amendment (attached separately).
7. Attachment X - Appendix A Record Drawing 12819 135 Submarine Cable is provided with this amendment (attached separately).
8. Attachment Y - Appendix A Record drawing 11836 125 Submarine Cable Relocation is provided with this amendment (attached separately).
9. Driving Logs and Geotechnical Data from NOAA Pier Project is provided with this amendment
(attached separately).
Bulkhead Attachments:
• 24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 06.25.24 to 06.27.24
• 24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.01.24 - 07.02.24
• 24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.11.24
• 24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.15.24 to 07.19.24
• 24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.22.24 to 07.26.24
• 24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.31.24 to 08.01.24
• 24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.07.24 to 08.08.24
• 24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.13.24 to 08.15.24
• 24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.20.24 to 08.23.24 (1)
• 24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.20.24 to 08.23.24
• 24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.26.24 to 08.30.24 (1)
• 24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.26.24 to 08.30.24
• 24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 09.03.24 to 09.06.24
• Bulkhead Pile Plan
Geotechnical Report:
• NOAA OMAO Survey Reports 100% Pre-Final Submittal 04072022
Pier Attachments:
• 24.107 NOAA OMAO Ship Support Facility Relocation Newport RI - PDA Report - Pier Bent
25 and 27
• 24.107 NOAA OMAO Ship & Support Facility Relocation Newport RI - PDA Report - Pier Bent
• 24.168 NOAA OMAO Prime Pier Pile Driving Summary Report
• Pier Pile Plan
• SUB-0262 Interim PDA Test Pile Logs for Pier Piles - Bent 35'B – A
• SUB-0284 PDA49B'_A
Trestle Attachments:
• SUB-0TBD Interim PDA and Test Pile Logs For Trestle Pile 17B
• SUB-0105 Trestle Piles 4C & 6B - PDA and Test Pile Logs
• SUB-0123 Interim PDA and Test Pile Logs - Trestle Piles 10B & 14B
• Trestle Summary
Note: these attachments are for informational purposes only (FIO).
10. Pre-proposal Inquiry Responses (Enclosed)
PPI # Page Section Paragraph Question Response
General General General
The project's scope of work includes utility crossings under existing railroad tracks. What is the name of the railroad company operating this track?
How many trains per day can we expect?
Are there any
Railroad Protective
Insurance requirements?
Please see continuation sheet provided with
Amendment 0003.
The Contractor will obtain a Physical
Alteration Permit from
RIDOT prior to performing any work within the RIDOT right-of-way or affecting
RIDOT infrastructure.
Work impacting railroad facilities will be coordinated in advance with both the Old Colony
& Newport Railway and the Newport Dinner
Train, with Dan Carlin serving as the primary point of contact for railroad operations.
Daily train activity is limited. For bidding purposes assume railroad protective insurance is required.
1.0 -
Specifications, Section 31 62
16.13 -1.3.2, and Attachment
H
1.0 -
Specifications, Section 31 62
16.13 -1.3.2, and Attachment
H
1.0 -
Specifications, Section 31 62
16.13 -1.3.2, and Attachment
H
Section 31 62 16.13
-1.3.2 says, "If the actual cumulative pile length driven
(tip to cut-off) vary more than 25 percent from the total pile length specified as a basis for bidding, at the direction of the Contracting
Officer, the unit price per unit length will be adjusted in accordance with provisions of
FAR 52.236-2
Please see Note D on the
Updated Attachment H –
USCG OPC Pier Price
Proposal Form REV3 provided with
Amendment 0005.
Differing Site
Conditions."
Attachment H
General Bid Notes c.
says in part
"Quantities on the bid schedule that are followed by an asterisk (*) are estimated quantities and FAR 52.211-18, Variations in
Estimated Quantity shall apply to these
Line Items. In accordance with
FAR 52.211-18; If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above
15 percent or below
85 percent of the estimated quantity."
Please clarify the quantity variation percentage triggering a unit price adjustment.
35 03.30.00 3.6.2.b
Paragraph states that concrete is to be placed within 90 minutes of batch time. Can retarders
Please see Continuation
Sheet provided with
Yes. The specification be used to get more time? There are no batch plants on the island and travel time may be significant.
has been amended to allow retarders.
03.31.29
This spec section spells out what is required for Marine
Concrete. Is there a material supplied by a local vendor that has already met this specification and would be acceptable for use on this project?
Local vendors are available that can meet the specification.
Specifications
Appendix D
Please provide the
NOAA Fisheries
Incidental
Harassment
Authorization and corresponding project application.
Please see Continuation
Sheet provided with
Amendment 0003. Permit was included by amendment in Appendix
D.
(UPDATED
RESPONSE)
S-208,S-404
26 42 13.00 20
Cathodic
Protection
Cathodic Anodes called out on
Drawings S-208 and
S-404 at the bulkhead are not shown or detailed on the Electrical
Drawings, nor mentioned and quantified in specification section
26 42 13.00 20.
Please provide this information.
Please see Continuation
Provide cathodic anodes of the same size and type as those indicated in the specification and dwg
E112 for pipe piles. The dwgs have been amended to show the number and locations.
SD001
Drawing SD001
PCB/Mercury notes states "During the inspection, 18 potential mercury-vapor lights were observed on Pier 1."
Attachment H Bid
Price Schedule line item 0001V - Unit
Price to remove and dispose of Mercury
Please see continuation
Sheet provided with
Amendment 0004 and
Please also see Updated
Attachment H – USCG
OPC Pier Price Proposal
Form REV3 provided with Amendment 0005.
The quantity has been containing light ballasts from Pier 1 buildings only list 14 each. Please advise where the other 4 each mercury-vapor lights will be paid.
revised to 15 and the note on SD001 has been revised to:
The location and type of mercury fixtures are as follows:
Building 394: 7 potential mercury-containing fluorescent light bulbs
Building 395: 2 potential fluorescent light bulbs and 1 assumed mercury-containing thermostat
Building 396: 2 potential fluorescent light bulbs, 4 potential mercury-containing exterior lights, and 1 assumed mercury-containing thermostat.
Additionally, under PCB/
Mercury
Notes, Add: ""All transformers and substations shall be assumed to have oil containing PCBs.5 See
Appendix A Pier 1
Existing Drawing
627078.
Appendix E Section 3.1
The Haley &
Aldrich
Geotechnical Report dated December
2025, provides recommendations on drivability, axial capacity and lateral fixity of 7/8" thick
36" OD piles. The drawings and specifications require 3/4" thick
36" OD piles.
Please see Continuation
The wall thickness has been updated to 7/8".
Has the thinner wall thickness of the piles shown in the contract drawings been accounted for when specifying the required minimum tip elevations?
Specifications
Technical
Specifications -
Appendix E
"Geotechnical
Engineering
Report"
3.1
Please provide all piledriving records for the referenced
NOAA OMAO Ship
& Support
Relocation Pier
(NOAA Pier) located approximately 800ft to the South of the project site
Please see Continuation
Piles logs and geotechnical info from the NOAA pier are provided for informational purposes only.
Specifications 02 41 00 1.2.2
Please provide any past inspection reports for Existing
Pier 1
Existing drawings readily available have been provided. Additional information may become available post award.
Specifications
Appendix A
"Existing Pier 1
Drawings"
11868-125 or
Y&D Dwg.
627080
The plan view detail at top right of the
Existing Pier 1
Drawing 11864-125 provided in
Appendix A shows submarine cables.
Are these cables still in service or have they been disconnected? Please provide locations of these cables.
Please see Continuation
Submarine cables have been relocated.
(UPDATED
RESPONSE)
S-503 Drawing Set 3
(Struc2)
Drawing S-503
Detail A1 shows a full length reinforcing cage full of concrete down to pile tip elevation.
This would require excavation and potentially drilling from within the pile.
Is discharging of the various strata shown
No. All dredged material needs to be disposed of offsite per the contract documents.
within the turbidity curtain acceptable?
(UPDATED
RESPONSE)
S-002; S-502
Drawing Set 2
(Struc1);
Drawing Set 3
(Struc2);
Geotechnical
Engineering
Report
Section 3.1 of the
Geotechnical
Engineering Report prepared by Haley &
Aldrich indicates that the recommended foundation system is to consist of 36" diameter, 7/8" wall thickness pipe piles.
Foundation Note 3 on Drawing S-002 states that bents 1 through 43 at Pier 1 must be supported by 36" diameter x
3/4" wall thickness driven steel pipe piles. Drawing S-
502 also indicates the pipe piles have a
3/4" wall thickness.
Please confirm the pipe pile wall thickness required
(3/4" or 7/8".
Please see Continuation
The wall thickness shall be 7/8".
Specifications
01 57 19
35 20 23
Appendix D
1.5
1.8
Prior to commencement of dredging, the dredge area is to be surveyed for shellfish with the amount estimated.
Then if required by
RIDEM, shellfish are to be relocated from dredge area.
Please provide a copy of the process described in the RI
DEM DMF
"Guidance for
Conducting Shellfish
Surveys for
Dredging Projects"
Please see Continuation
Sheet and updated
Appendix D provided with Amendment 0003.
referenced in
Appendix D.
V-103, C-005, C-102
Drawing Set 1
(Civil)
The existing conditions shown on
Drawing V-103 and
C-005 appear to be missing the grade lines between the construction fencing and the S45N bulkhead / future
S45S bulkhead. A note on Drawing V-
103 indicates that the area within the construction fence was under construction.
Drawing C-102 appears to rely on the same existing grade lines, leaving insufficient information to determine the cut-and-fill quantities for this area. Please provide an updated survey so that this portion can be accurately estimated.
Please see Continuation
Drawing C-102 has been updated to provide additional contour information within the area inaccessible during the initial site survey.
This contour information was provided based off available record information.
Spec section 01
35 40.00 20
Spec section 01
35 40.00 20
Spec section 01
35 40.00 20
Spec section 01 35
40.00 20 states that
“the Project has been issued two IHAs;
one each to cover
Year One and Year
Two covered activities.” Can you please provide a copy or draft of the
IHAs and confirm its application start date? Driving piles in the first quarter of
2027 is critical to meeting the overall schedule milestone.
Please see Continuation
Amendment 0002.
IHAs were provided with
Amendment 0002.
S-110, S-112, S-114, S-115 Section A2
Precast manholes
EMH-BC-4142
between bents B&C and 41&42, EMH-
CD-2930 and TMH-
CD-2930 between bents C&D and
29&30, EMH-CD-
1920 and TMH-CD-
1920 between bents
C&D and 19&20, EMH-CD-0910 and
TMH-CD-0910
between bents C&D and 9&10, and
EMH-DE-0607
between bents D&E and 6&7 are shaded on Drawings S-110, S-112, S-114 and S-
115, indicating a cast-in-place concrete slab. Please confirm these manholes are precast and do not require a cast-in-place slab.
Please see Continuation
Manhole EMH-BC-4142 and EMH-DE-0607 are precast and do not require a CIP slab at the base.
Manholes EMH-CD-
2930,TMH-CD-2930,
EMH-CD-1920, TMH-
CD-1920, EMH-CD-
0910, TMH-CD-0910 do not require CIP slabs.
C-504
No rebar details have been shown for the cast in place storage tank - please provide
Please see Continuation
The detail has been revised to require a precast concrete storage tank. Design must be per the precaster.
M-402/3
For the heated enclosure, no conduit is shown coming through the slab, do penetrations come through the sides?
Please see Continuation
Branch conduits must be provided to rise vertically and penetrate through the bottom slab to connect to mechanical enclosures and equipment.
S-001 31 62 16
Please verify that pile cutting shoes shall be outside fit as described in the structural drawings
Please see Continuation and not inside fit as described in specification section
31 62 16.
Pile shoes are to be outside fit.
S-505
Section A2/S-505
Typical Pile Cap
Reinforcement Bents
39-10 shows the top of the pile cap at the same elevation as the top of the utility trench, making the pile cap 4.5 feet in height. Pile cap typical sections on
S-504 note the pile cap to be 4.0 feet in height. Please clarify the correct pile cap dimensions.
Please see Continuation
All pile caps are 4-ft in height.
22 15 14.00 40
Please clarify what items from 22 15
14.00 40 GENERAL
SERVICE
COMPRESSED-
AIR SYSTEMS,
LOW PRESSURE is a part of the Base
Bid and what items are a part of the
OPTION 1
COMPRESSED
AIR SYSTEM.
Additionally, please provide an updated
Specification section for 22 15 14.00 40
GENERAL
SERVICE
COMPRESSED-
AIR SYSTEMS,
LOW PRESSURE
and an updated
Specification section for that which includes items for the OPTION 1
COMPRESSED
AIR SYSTEM.
Please see Continuation
Landside compressed air system including but not limited to, the compressor building and its' components, steel support dunnage, foundation, and electrical service are included in the option.
Compressed air system components located on the pier are included in the base bid. Dwgs M701 and M107 have been updated to show limits of the mechanical base bid and option.
Specs are complete as is.
Additional specs will not be provided.
M-401, M-701
Please provide an updated plan sheet for M-401
MECHANICAL
COMPRESSED
AIR ENCLOSURE
– PART PLAN and
M-701
COMPRESSED
AIR SCHEMATIC
(BID OPTION) as
Sheet M-401 references M-701 which is related to
Bid Option 1 not 22
15 14.00 40. Please clarify specifically which sheets are related to the 22 15
14.00 40 GENERAL
SERVICE
COMPRESSED-
AIR SYSTEMS,
LOW PRESSURE
and which sheets are related specifically to the OPTION 1
COMPRESSED
AIR SYSTEM.
Please see Continuation
The mechanical limits of the bid option have been added to dwg M107.
The only mechanical drawings specific to the option are M401, M701, and M702.
All compressed air requirements for both the base bid and option are included in Specification
22 15 14.00 40.
316 of 4611 02 81 1.4.1
Contract
Specifications dictate Contractor to provide a Hazardous
Waste Management
Plan, Transportation and Disposal
Coordinator, Emergency
Management Plan, provide record keeping, and provide a 24HR Emergency
Contact. In Section
01 57 19 1.11 Naval
Station Newport is defined as a Large
Quantity Generator, per EPA RCRA and
RIDEM Hazardous
Waste Regulations the generator is to
The contractor is responsible for writing a project specific
Hazardous Waste
Management Plan which is not related to the
NAVSTA Hazardous
Waste management Plan.
Refer to the Specification for the plan requirements.
fulfill these duties.
Please confirm that the Naval Station
Hazardous Waste
Management Plan /
Emergency
Management Plan will be provided and that record keeping, and 24 HR emergency contact will be provided by the Naval Station.
The contractor will provide waste determinations and arrange for transportation and disposal in accordance with the
Naval Stations appointed
Transportational and
Disposal
Coordinator. The
Contractor will provide training records waste determination, disposal manifests and weekly inspections of the hazardous waste storage area .
217 of 4611 01 57 19 1.7.9.2
Specification instructs Contractor to determine reporting requirements based on current installation permits.
Please provide copies of applicable
Installation Air
Permits
In accordance with the specification, fuel burning equipment start dates and specs shall be submitted to the contracting office during construction.
211 of 4611 01 57 19 1.5
Contractor is directed to comply with NAVSTA Soil
Management Plan provided as
Appendix G. This
The project soil disturbance provided is cumulative (> 50 tons).
All excavated soils must be removed and disposed from the Naval Station in
Plan details "DE
MINIMUS
ACTIVITIES -
Disturbed or excavated soil in amounts less than 50 tons or 38 cubic yards shall be exempt from the requirements in the above paragraph entitled, “COMMERCIAL
AND INDUSTRIAL
REUSE” pertaining only to reuse at
NAVSTA Newport.
For these minimum activities, excavations can be backfilled with the soils that were removed." Please confirm that sequencing of excavations to maintain less than 38 cubic yards of excavation in one area at one time is acceptable to meet the definition of DE
MINIMUS
ACTIVITIES.
accordance with the contract documents.
819 of 4611 31 23 00.00 20 3.2.4
Please confirm that screening of surplus soils to 3 inches if not required by the designated disposal facility may be ignored.
Any soil disposed offsite at a licensed facility must comply with the disposal facility’s requirements.
222 of 4611 01 57 19 3.2.5
Can you please provide a copy of the Installation MS4
Permit?
Please see PPI response number 37.
222 of 4611 01 57 19 3.3.1
In place RIPDES
CGP allows for surface infiltration of groundwater related to construction
This project falls within an IR site, and dewatering must follow the RI
Remediation GP. The contractor also has the option to containerize the dewatering as long as groundwater is not "Contaminated" please provide current characterization of site groundwater and confirm applicability of RIDEM GB
Groundwater
Objectives. Confirm that if construction dewatering is containerized, tested and profile indicates compliance with GB groundwater objectives on site infiltration is acceptable.
groundwater and dispose at a licensed disposal facility.
(UPDATED
RESPONSE)
Dwg. No. S-208 and S-404
2.0 - Drawing
Set
Dwg. No. S-208 and S-404
Per drawings S-208 and S-404, new sacrificial anodes are indicated to be installed at Bulkhead
S45S. Please confirm whether these anodes are intended to be the same size and weight as the anodes specified for pile installation, specifically 5" x 5" x
48" and 120 lbs.
Please see Continuation
The anodes are the same type, size, and weight.
S-518 Detail C1 and
B1
Drawing S-518, Detail C1 shows a
36" diameter opening. Detail B1 calls out a 30" diameter manhole frame and cover.
Please confirm the size of the opening and provide the make and model of the embedded cover.
Please see continuation
The openings within the trench covers are all 30" diameter.
01 14 00
The specifications state work hour restriction Monday through Friday, 8
For bidding purposes, assume standard working hours.
hours per day. Given the Time of Year restrictions for in water work, will 10 or 12 hour days, or working Saturday, be permissible?
See PPI response #234 and #235 for additional information.
S-527
Detail C2 of drawing
S-527 shows bulkhead wale bolted connection to
PZ35 bulkhead steel sheet pile. Detail A2 does not show how the steel wale connect to PZ35 deadman steel sheet.
Please advise the connection detail of wale to deadman sheet pile.
Please see Continuation
The same wale to sheeting connection shown an A4 S-528 applies to the deadmen as well.
S-519
We refer to detail
A1 on drawing S-
519. Does the H-pile extension require a pile shoe?
No pile shoe is required for the fender piles.
S-519, S-602,S-
Bid document calls for 16" polymeric fender piles.
Amendment 002 provided the estimated tip pile elevation and estimated highly weathered rock
(HWR) elevation.
Based on the estimated pile tip and HWR elevation, composite fender piles are required to be driven to design tip elevation which is approximately up to 30.83 feet into the highly weather rock
(HWR). Polymeric composite pile manufacturer brochure indicates a lightweight hammer
See Continuation Sheet
Driving of the 16-inch polymeric fender piles into the dense weathered rock and dense glacial till may be difficult without damage to the pile. The
Contractor should be ready to pre-drill and grout these piles if needed so as to not damage the piles. The fender pile tip elevations have been revised to reflect the updated design loads.
with a rated energy of between 8,000 and 15,000 ft-lbs. be used to drive the composite pile. Our consultant Engineer does not believe a
15,000 ft-lbs. can drive the composite fender piles 30ft into the highly weathered rock. Please advise.
37 of 42 Amendment 3 Q&A #73
Since the U.S. Army
Corps of Engineers permit will not be issued until the start of construction, please confirm that if the permit includes requirements or conditions beyond those identified in the current bid documents, the
Contractor will be entitled to compensation for any resulting additional costs and time impacts.
The drawings and specs have incorporated known permit requirements.
Specification
Section 352023
Section 352023
Dredging, Part 1, paragraph 1.1 indicates;" This
Section covers... and placement of the dredge material within the prescribed material placement areas." Where are the prescribed material placement areas? How far are the placement areas from the dredging area?
The dredge material placement areas can be the same as the soil stockpile areas identified in the bid documents.
5 35 59 13.14.20 2.3
A safety factor of
2.0 is specified for flexure under normal berthing loads. What safety factor is required for abnormal berthing loads?
For abnormal/accidental berthing a 0.5 berthing factor should be applied to operation berthing energy. This will affect the total energy imposed on the fender system. The factor of safety will remain the same, as this is the loading used for the
"operational" loads on the system.
5 35 59 13.14.20 2.4.1
The spec section is titled “Allowable
Moment Capacity” but the text calls for testing of the
“ultimate bending moment”. Is the intent to specify the ultimate or allowable (ultimate divided by factor of safety) moment?
The allowable moment capacity should be specified along with ultimate capacity with factor of safety used to determine the allowable moment capacity.
Please see Continuation
Amendment 0005.
5 35 59 13.14.20 2.4
Please clarify if minimum properties refer to the average strength or the characteristic strength according to
ASTM D7290? Characteristic strength.
6 35 59 13.14.20 2.4.4
Please confirm the number of piles that are counted in absorbing the berthing energy. This specification calls for 4 piles while other recent projects like the Pier 32 replacement at NSB
New London have allowed the exact same berthing energy to be distributed to 8 of the 16” OD polymeric fender piles.
The berthing energy can be distributed to 8 fender piles as noted. The fender pile spacing at berthing location was tightened to allow for more piles to be utilized. The specification has been revised from 4 to 8.
3 06 71 00 2.1.1
Section 06 71 00 is titled Fiberglass
Reinforced Plastic
(FRP) Lumber which is manufactured using thermoplastic resins and a continuous
EXTRUSION
process. Part 2.1.1 describes Fiber
Reinforced Polymer
(FRP) materials which are manufactured using thermoset resins and a PULTRUSION process. This
PULTRUSION
process and materials are applicable to safety ladder cages as referenced in Part 1
– General. However, the requirements in
Part 2.1.1 are not applicable to the
Fiberglass
Reinforced Plastic
Lumber Wales or
Chocks shown on
Sheet S-519 (see
Detail A4).
Thermoplastic and
Thermoset resins are completely different materials that cannot be combined in the same specification. With the exception of Part
2.1.1, the remainder of the specification is applicable to
Fiberglass
Reinforced Plastic
Lumber.
Please see Continuation
35 20 23
Referencing
Attachment H - Bid
Price Schedule, Line
Item 0001Z indicates "Unit price for dredging and dredge disposal
(Including allowable over dredge), complete in accordance with the drawings and specifications, but excluding work provided in another priced line item." Please confirm where is the dredge disposal material paid for, is it under this Bid
Item?
It is included in Line Item
0001Z
35 20 23
Specification
Section 35 20 23
Dredging, Part 1.8
Environmental
Compliance And
Protection indicates
"The Government will secure the permit for dredging and placement of material as indicated." Please clarify is the
"Government" securing the permit for placing the dredge disposal materials? Is it the intent to place the dredge disposal materials on-shore or off-shore?
The Government has secured the RIDEM permit for dredging.
Material shall be sampled and disposed of in an approved landfill per paragraph 1.4 Sampling.
27 03 31 29 1.7.7a
Please reference specification section
03 31 29 paragraph
1.7.7a regarding placement of mass concrete temperature sensors. Minimum Confirmed.
required sensor locations are listed
"for each placement". Please confirm this amount of sensors are required for all placements under
400 CY regardless of the number of mass concrete structural elements contained within the placement
Attachment H -
Bid Price
Schedule
Addendum 3 added
Line item 0001AB for 'Unit price to remove and dispose of all soil containing greater than 1%
Asbestos Containing
Material (ACM)…' with a unit of measure of CY. All other soil removal and disposal items have a unit of measure of TONS.
Please confirm unit of measure line item
0001AB is CY.
Please see Updated
Attachment H – USCG
OPC Pier Price Proposal
The unit is Tons.
28 26 13 14 2.11.8.4
The capacitor bank manufacture requires a compatibility analysis prior to quoting per specification. Has an analysis been completed and is it available?
Compatibility analysis has not been completed.
This will be provided by the contractor to the manufacturer prior to the manufacturer providing their quote.
02 61 13 1.1
Will sediment removed for the inside of the permanent foundation piles pile to facilitate reinforced concrete installation be considered as
"Exca…