24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.20.24 to 08.23.24 (1).pdf

PDF 512 KB Posted

Attached to
Design-Bid-Build, USCG Offshore Patrol Cutters (OPC) Homeport Pier, Naval Station Newport, Newport RI
Solicitation number
N4008526R0001
Issued by

About this file

This document is a Pile Driving Summary and associated Pile Driving Logs prepared by Geosciences Testing and Research, Inc. (GTR) for a project located at Newport RI Naval Station.

The project involves the driving of steel 18-inch O.D. x 0.5-inch wall open-ended pipe bulkhead piles for NOAA OMAO (Office of Marine and Aviation Operations), with Skanska as the contractor and Coastal Marine as the sub-contractor. The work was performed in August 2024 (August 20-23, 2024) and documented under GTR Job #24.168. A total of nine bulkhead piles (BH5 through BH13) were driven to specified depths, with all piles measuring 60 feet in length. The piles were not vibration-driven and achieved a working grade of 12.25 feet with tip elevations at -43.25 feet and top elevations at 16.75 feet. Cut-off elevations were standardized at 53.50 feet across all piles. Blow counts for the final foot ranged from 9 to 11 blows per foot, with driven depths varying from 28 to 54 feet depending on the individual pile. The Pile Driving Logs provide detailed stroke-by-stroke data for selected piles (BH10, BH11, BH12, BH5, BH6, BH7, and BH8), documenting blow counts at incremental depths using an ICE D-50 single-acting diesel hammer. All elevations referenced in the documentation are based on NAVD 88 (North American Vertical Datum of 1988).

View the file

Other files

File Type Posted
USCG OPC Pier Amendment 0009 Drawings.pdf PDF
2026-0816-HAI-USCG Homeport OPC Pier-Geotech Engineering Report Rev 2.pdf PDF
Amendment 0009 USCG OPC.pdf PDF
Updated Attachment H - USCG OPC Pier Price Proposal Form REV 5.docx DOCX document
Amendment 0008 USCG OPC.pdf PDF
Amendment 0007 SPC USCG OPC Pier Appendix D (With Placeholders).pdf PDF
Updated Attachment H - USCG OPC Pier Price Proposal Form REV 6.docx DOCX document
USCG OPC Pier Amendment 0008 Drawings.pdf PDF
USCG OPC Pier Amendment 007 Drawings.pdf PDF
Amendment 0007 USCG OPC.pdf PDF
Attachment Z - Pier 1 - Amendment 006 Drawings.pdf PDF
Appendix A - Telecom Room Photos.pdf PDF
Updated Attachment H - UCCG OPC Pier Price Proposal Form REV 4.docx DOCX document
Amendment 0006 USCG OPC.pdf PDF
24.168 NOAA OMAO Prime Pier Pile Driving Summary Report.pdf PDF
Pier Pile Plan.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.26.24 to 08.30.24 (1).pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.22.24 to 07.26.24.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.15.24 to 07.19.24.pdf PDF
Attachment Y - Appendix A Record drawing 11836 125 Submarine Cable Relocation.pdf PDF
SUB-0123 Interim PDA and Test Pile Logs - Trestle Piles 10B 14B.pdf PDF
SUB-0TBD Interim PDA and Test Pile Logs For Trestle Pile 17B.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.26.24 to 08.30.24.pdf PDF
Updated Attachment H - UCCG OPC Pier Price Proposal Form REV 3.docx DOCX document
SUB-0105 Trestle Piles 4C 6B - PDA and Test Pile Logs.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.20.24 to 08.23.24.pdf PDF
24.107 NOAA OMAO Ship & Support Facility Relocation Newport RI - PDA Report - Pier Bent 19.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 06.25.24 to 06.27.24.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.31.24 to 08.01.24.pdf PDF
SUB-0284 PDA49B_A.pdf PDF
SUB-0262 Interim PDA Test Pile Logs for Pier Piles - Bent 35 B - A.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.07.24 to 08.08.24.pdf PDF
Trestle Summary.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.01.24 - 07.02.24.pdf PDF
Bulkhead Pile Plan.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 09.03.24 to 09.06.24.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.13.24 to 08.15.24.pdf PDF
Attachment W - Pier 1 - Amendment 005 Drawings.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.11.24.pdf PDF
24.107 NOAA OMAO Ship Support Facility Relocation Newport RI - PDA Report - Pier Bent 25 and 27.pdf PDF
NOAA OMAO Survey Reports 100 Percent Pre-Final Submittal 04072022.pdf PDF
Amendment 0005 USCG OPC.pdf PDF
Attachment X - Appendix A Record Drawing 12819 135 Submarine Cable.pdf PDF
Attachment U - Appendix A - Pier 1 Extension 1968.pdf PDF
Attachment V - Pier 1 - Amendment 004 Drawings.pdf PDF
Updated Attachment K - WD RI20260001 05-18-2026.pdf PDF
Amendment 0004 USCG OPC.pdf PDF
Attachment T - REF(m) Existing Pier 1 Drawings 1 of 2.pdf PDF
Attachment C - Construction Experience Project Data Sheet.docx DOCX document
Attachment E - Historical Small Business Utilization.docx DOCX document
Show 40 more

Latest 50 of 90 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DATE:

PROJECT LOCATION:

CLIENT: CONTRACTOR:

GTR REP PILE INFO:

BH13 Not Vibed 20-Aug-24 12.25 60 55.50 10.25 -43.25 16.75 53.50 40 9 - 11 BH12 Not Vibed 20-Aug-24 12.25 60 55.50 10.25 -43.25 16.75 53.50 50 10 - 11 BH11 Not Vibed 20-Aug-24 12.25 60 55.50 10.25 -43.25 16.75 53.50 28 10 - 11 BH10 Not Vibed 20-Aug-24 12.25 60 55.50 10.25 -43.25 16.75 53.50 50 10 - 11 BH9 Not Vibed 22-Aug-24 12.25 60 55.50 10.25 -43.25 16.75 53.50 50 10 - 11 BH8 Not Vibed 22-Aug-24 12.25 60 55.50 10.25 -43.25 16.75 53.50 42 9.5 - 10.5 BH7 Not Vibed 23-Aug-24 12.25 60 55.50 10.25 -43.25 16.75 53.50 44 10 - 11 BH6 Not Vibed 23-Aug-24 12.25 60 55.50 10.25 -43.25 16.75 53.50 54 10 - 11 BH5 Not Vibed 23-Aug-24 12.25 60 55.50 10.25 -43.25 16.75 53.50 52 10 - 11 and NZ26 Sheet Piles

PILE

NO.

DRIVEN

DEPTH

(feet)

TIP

ELEVATION

(feet)

TOP

ELEVATION

(feet)

PILE

LENGTH

(feet)

EOD

STROKE

(feet)

WORKING

GRADE

(feet)

FINAL DRIVE

DATE

VIBRATION

DRIVE DATE

CUT-OFF

LENGTH

GTR JOB # 24.168

GEOSCIENCES TESTING AND RESEARCH, INC.

55 Middlesex Street, Suite 225, North Chelmsford, MA, Phone: (978) 251-9395 Fax: (978) 251-9396

COMMENTS

PILE DRIVING SUMMARY

J. Roth Steel 18-inch O.D. X 0.5-inch wall open-ended Pipe

Newport RI Naval Station Coastal Marine

NOAA OMAO

Skanska

23-Aug-24

CUT-OFF

ELEVATION

(feet)

BLOW

COUNT

FINAL FOOT

BULKHEAD PILES

File details come from the government source that posted it. Updated .