24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.07.24 to 08.08.24.pdf
PDF 27 MB Posted
- Attached to
- Design-Bid-Build, USCG Offshore Patrol Cutters (OPC) Homeport Pier, Naval Station Newport, Newport RI
- Solicitation number
- N4008526R0001
About this file
This is a summary table documenting bulkhead pile driving work conducted by NOAA's Office of Marine and Aviation Operations (OMAO) between August 7-8, 2024. The table tracks operational metrics for pile driving activities, likely related to marine infrastructure maintenance or construction. The document appears to be a daily or shift-level work log capturing specific details about pile driving operations, including work duration, quantities of piles driven, equipment used, and personnel involved in the underwater/waterfront construction activities.
The data in this summary table would typically support project documentation, progress reporting, and cost tracking for the USCG Offshore Patrol Cutters (OPC) Homeport Pier project at Naval Station Newport in Newport, Rhode Island. This Design-Bid-Build solicitation (N4008526R0001) involves substantial marine construction work, and the pile driving summary represents actual field work execution data that contractors would need to document for progress billing, schedule compliance, and quality assurance purposes. The file serves as an operational record demonstrating the scope and intensity of the marine construction activities required for the pier homeport facility.
View the file
Other files
Show 40 more
Latest 50 of 90 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DATE:
PROJECT LOCATION:
CLIENT: CONTRACTOR:
GTR REP PILE INFO:
S67 Not Vibed 7-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 40 9 - 10 S66 Not Vibed 7-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 38 8 - 9 S65 Not Vibed 7-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 42 8 - 9 S64 Not Vibed 7-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 36 8 - 9 S63 Not Vibed 7-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 38 8 - 9 S62 Not Vibed 7-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 34 9 - 10 S61 Not Vibed 7-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 38 9 - 10 S60 Not Vibed 7-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 36 8 - 9 S59 Not Vibed 7-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 32 8 - 9 S58 Not Vibed 7-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 30 8 - 9 S57 Not Vibed 7-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 38 9 - 10 S56 Not Vibed 7-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 34 9 - 10 S55 Not Vibed 7-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 34 8 - 9 S54 Not Vibed 7-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 30 8 - 9 S53 Not Vibed 7-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 28 8 - 9 S83 Not Vibed 8-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 42 9 - 10 S82 Not Vibed 8-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 36 8 - 9 S80 Not Vibed 8-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 32 8 - 9 S79 Not Vibed 8-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 32 8 - 9 S78 Not Vibed 8-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 34 8 - 9 S77 Not Vibed 8-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 34 8 - 9 S76 Not Vibed 8-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 36 8 - 9 S75 Not Vibed 8-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 34 8 - 9 S74 Not Vibed 8-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 38 8 - 9 S73 Not Vibed 8-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 32 8 - 9 S72 Not Vibed 8-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 38 8 - 9 S71 Not Vibed 8-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 36 8 - 9 S70 Not Vibed 8-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 38 8 - 9 S69 Not Vibed 8-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 40 8 - 9 S68 Not Vibed 8-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 38 9 - 10
PILE
NO.
DRIVEN
DEPTH
(feet)
TIP
ELEVATION
(feet)
TOP
ELEVATION
(feet)
PILE
LENGTH
(feet)
EOD
STROKE
(feet)
WORKING
GRADE
(feet)
FINAL DRIVE
DATE
VIBRATION
DRIVE DATE
CUT-OFF
LENGTH
GTR JOB # 24.168
GEOSCIENCES TESTING AND RESEARCH, INC.
55 Middlesex Street, Suite 225, North Chelmsford, MA, Phone: (978) 251-9395 Fax: (978) 251-9396
COMMENTS
PILE DRIVING SUMMARY
J. Roth Steel 18-inch O.D. X 0.5-inch wall open-ended Pipe
Newport RI Naval Station Coastal Marine
NOAA OMAO
Skanska
9-Aug-24
CUT-OFF
ELEVATION
(feet)
BLOW
COUNT
FINAL FOOT
BULKHEAD PILES