Trestle Summary.pdf
PDF 6 MB Posted
- Attached to
- Design-Bid-Build, USCG Offshore Patrol Cutters (OPC) Homeport Pier, Naval Station Newport, Newport RI
- Solicitation number
- N4008526R0001
About this file
This is a Pile Installation Inspection Final Report documenting steel pipe pile installation and monitoring work performed for the NAVFAC NOAA OMAO Ship & Support Facility Relocation project in Newport, Rhode Island.
Geosciences Testing and Research, Inc. (GTR) served as the Contractor's Geotechnical Consultant and observed pile installation activities between June 10, 2024 and October 10, 2024. The project involved the successful installation of eighteen 18-inch outer diameter by 0.5-inch wall thickness steel pipe piles for the trestle pier. Each pile was designed for a compression load of 300 kips with an ultimate compression capacity of 680 kips (based on a factor of safety of 2.25). All piles were driven using a BSP CG240 Hydraulic Hammer at a 2.0-foot stroke to meet a minimum drive criteria of 6 blows per inch for 6 inches, which was established through Pile Dynamic Analysis Testing performed between June 18 and July 5, 2024. Pile axial deviation was monitored during installation with a maximum allowable deviation of 1-inch over four feet per project specifications. All piles were driven to minimum tip elevations ranging between -30 and -60 feet. The report includes a summary table of driven depths, elevations, final blow counts, and individual pile logs documenting installation details for each of the 18 piles, along with numbered pile location plans showing completion status for the project areas.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
55 Middlesex Street, Suite 225 80 Business Park Drive, Suite 306 No. Chelmsford, MA 01863 Armonk, NY 10504
(978) 251‐9395 (914) 600‐8101 www.gtrinc.net
November 15, 2024 GTR Project No. 24.168
Mr. Matt Coleman, P.E.
Quality Manager Skanska USA Civil 1365 Main Street Waltham, MA 01952
Re: Pile Installation Inspection Final – Trestle Piles NAVFAC NOAA OMAO Ship & Support Facility Relocation
Newport, Rhode Island
Dear Matt, Geosciences Testing and Research, Inc., (GTR) is pleased to present this report that summarizes steel Pipe‐pile installation and monitoring work performed at the above‐ referenced Project. At your request, GTR observed and documented installation activities between June 10, 2024 and October 10, 2024. GTR was on‐site to act as the Contractor’s Geotechnical Consultant as specified in the Project Specifications SECTION 31 62 16.13‐ STEEL PIPE PILES. Our scope of work included observing and documenting the Pipe‐pile installation process to ensure compliance with our proposed driving criteria. Refer to our PDA reports dated June 18, July 3, and July 8, 2024 for details on the testing.
Steel 18” O.D. x 0.5” Wall Pipe Pile Installation
Eighteen 18”x0.5” Pipe piles were successfully installed for the NAVFAC NOAA OMAO Ship & Support Trestle Pier. The piles have a design compression load of 300 kips. The ultimate compression capacity is 680 kips based on a factor of safety of 2.25. All of the piles were driven to a minimum drive criteria of 6 blows per inch for 6 inches using a BSP CG240 Hydraulic Hammer at a stroke of 2.0 feet. This drive criteria was established during Pile Dynamic Analysis Testing performed by GTR between June 18, 2024 and July, 5 2024 (see reports referenced above). In addition to the drive criteria, pile axial deviation was monitored during installation and recorded on the individual pile logs that can be found in Appendix A. A maximum angle of 1‐inch over four feet was the allowable maximum deviation per project specifications. All piles were driven to a minimum tip elevations ranging between elevations ‐30 and ‐60 feet. A summary table of driven depths, elevations, and final blow counts is attached in Table 1. A numbered pile location plan is presented in Figures 1A and 1B.
rwhitsel M&N SD Stamp
NAVFAC NOAA OMAO Ship & Support Facility Relocation November 15, 2024 GTR Project No. 24.168 Page 2 www.gtrinc.net
This report has been prepared in accordance with generally accepted geotechnical engineering principles with specific application to this project. Our conclusions are based on applicable standards of practice, including any information reported to and/or prepared for
us. No other warranty, expressed or implied, is made.
If you have any questions regarding this report, please do not hesitate to contact us.
Sincerely, Geosciences Testing and Research, Inc.
John Roth Les Chernauskas P.E.
Geotechnical Engineer Principal
William D. Oder P.E.
Technical Manager
Encl. Table 1 ‐ Pile Summary
Figures ‐ Pile Location Plans Appendix A ‐ Pile Logs
24.168 NOAA OMAO Pile Driving Summary Report Trestle Piles.docx asolari Oval asolari Oval asolari Text Box Daily Field Sketch Sheet 1 of 3 as of October 10, 2024 (Note: Sketch as shown only depicts trestle pile installation) rwhitsel Engineer rwhitsel Cloud+ please include platform piles when driven
Text Box Daily Field Sketch Sheet 2 of 3 as of October 10, 2024 (Note: Sketch as shown only depicts trestle pile installation)
Text Box Daily Field Sketch Sheet 3 of 3 as of October 10, 2024 (Note: Sketch as shown only depicts trestle pile installation) rwhitsel Cloud rwhitsel Callout for pier show prime Bents and Rows, and indicate piles on original bents that have been cutoff at mudline
FIGURES
PILE LOCATION PLAN
DATE:
PROJECT: LOCATION:
CLIENT: CONTRACTOR:
GTR REP: PILE INFO:
4C 10-Jun-24 20-Jun-24 0 75 56.50 8.28 -56.50 18.50 64.78 1.75-2 6,6,6,6,6,6
5B 11-Jun-24 20-Jun-24 0 75 60.00 8.39 -60.00 15.00 68.39 2.00 6,6,7,7,8,8
5C 11-Jun-24 20-Jun-24 0 75 64.00 8.39 -64.00 11.00 72.39 2.00 6,6,7,7,8,7
3B 21-Jun-24 21-Jun-24 0 75 41.50 8.17 -41.50 33.50 49.67 2.00 6,6,6,7,6,7
4B 21-Jun-24 21-Jun-24 0 75 48.00 8.28 -48.00 27.00 56.28 2.00 6,6,6,6,6,6
6B 10-Jun-24 21-Jun-24 0 80 61.00 8.51 -61.00 19.00 69.51 2.00 7,7,8,7,8,8
6C 7-Jun-24 21-Jun-24 0 75 60.50 8.51 -60.50 14.50 69.01 2.00 6,6,6,6,6,6
7B 14-Jun-24 21-Jun-24 0 75 64.00 8.62 -64.00 11.00 72.62 2.00 6,6,6,6,6,6
7C 14-Jun-24 21-Jun-24 0 75 61.50 8.62 -61.50 13.50 70.12 2.00 6,6,6,6,6,6
8B 13-Jun-24 21-Jun-24 0 75 59.50 8.74 -59.50 15.50 68.24 2.00 6,6,6,6,6,6
8C 14-Jun-24 21-Jun-24 0 75 58.00 8.74 -58.00 17.00 66.74 2.00 6,6,6,6,6,6
3C 24-Jun-24 24-Jun-24 0 80 51.50 8.17 -51.50 28.50 59.67 2.00 6,6,6,6,6,7
10B 1-Jul-24 1-Jul-24 5.5 80 72.25 8.97 -66.75 13.25 75.72 2.00 6,6,6,6,6,6
11C 1-Jul-24 1-Jul-24 0 80 62.00 9.08 -62.00 18.00 71.08 2.00 5,6,6,6,10<1"
9B 2-Jul-24 2-Jul-24 0 80 66.00 8.85 -66.00 14.00 74.85 2.00 6,6,6,6,6,6
9C 2-Jul-24 2-Jul-24 0 80 47.00 8.85 -47.00 33.00 55.85 2.00 6,6,6,6,6,7
10C 2-Jul-24 2-Jul-24 0 80 66.00 8.97 -66.00 14.00 74.97 2.00 6,6,6,7,7,7
11B 2-Jul-24 2-Jul-24 0 80 61.00 9.08 -61.00 19.00 70.08 2.00 6,6,6,6,6,6
12B 2-Jul-24 2-Jul-24 0 80 62.50 9.20 -62.50 17.50 71.70 2.00 6,6,6,6,6,7
12C 2-Jul-24 2-Jul-24 0 80 62.00 9.20 -62.00 18.00 71.20 2.00 6,6,6,6,7,7
13B 2-Jul-24 2-Jul-24 0 80 63.40 9.31 -63.40 16.60 72.71 2.00 6,6,6,6,6,10
13C 2-Jul-24 2-Jul-24 0 80 64.80 9.31 -64.80 15.20 74.11 2.00 6,6,6,6,6,10
14B 2-Jul-24 2-Jul-24 5.5 80 79.17 9.42 -73.67 6.33 83.09 2.00 5,6,6,6,6,8
14C 2-Jul-24 2-Jul-24 0 80 65.70 9.42 -65.70 14.30 75.12 2.00 6,6,8,8,9,10
15B 5-Jul-24 5-Jul-24 5 80 71.58 9.54 -66.58 13.42 76.12 2-2.25 6,6,6,6,7,6
15C 5-Jul-24 5-Jul-24 5 80 73.25 9.54 -68.25 11.75 77.79 2-2.25 6,6,6,6,7,8
16B 5-Jul-24 5-Jul-24 5 80 73.92 9.65 -68.92 11.08 78.57 2-2.25 6,6,6,8,7,8
16C 5-Jul-24 5-Jul-24 5 80 73.75 9.65 -68.75 11.25 78.40 2-2.25 6,6,6,6,8,8
17B 5-Jul-24 5-Jul-24 5 85 79.00 9.77 -74.00 11.00 83.77 2-2.25 6,6,6,6,6,7
17C 5-Jul-24 5-Jul-24 5 80 72.08 9.77 -67.08 12.92 76.85 2-2.25 6,7,6,6,6,6
18B 8-Jul-24 8-Jul-24 0 90 73.22 9.88 -73.22 16.78 83.10 2.00 6,6,6,8,7,10
18C 8-Jul-24 8-Jul-24 0 90 70.33 9.88 -70.33 19.67 80.21 2.00 6,6,6,6,6,7
2C 24-Jul-24 24-Jul-24 12 80 53.50 8.05 -41.50 38.50 49.55 2.00 6,6,6,6,6,6
2B 24-Jul-24 24-Jul-24 12 80 53.00 8.05 -41.00 39.00 49.05 2.00 6,6,6,6,6,7
1B 10-Oct-24 10-Oct-24 12 75 45.50 7.99 -33.50 41.50 41.49 2.00 6,6,6,9,10,10
1C 10-Oct-24 10-Oct-24 12 75 45.17 7.99 -33.17 41.83 41.16 2.00 6,6,6,6,6,7
GTR JOB # 24.168
GEOSCIENCES TESTING AND RESEARCH, INC.
55 Middlesex Street, Suite 225, North Chelmsford, MA, Phone: (978) 251-9395 Fax: (978) 251-9396
COMMENTS
PILE DRIVING SUMMARY
TEST PILE
J. Roth Steel Pipe Pile 18" x 0.5"
Newport RI Naval Station Coastal Marine
NOAA OMAO
Skanska
13-Nov-24
CUT-OFF
ELEVATION
(feet)
TEST PILE
PILE NO. FINAL BLOW
COUNT
DRIVEN
DEPTH
(feet)
TIP
ELEVATION
(feet)
TOP
ELEVATION
(feet)
PILE
LENGTH
(feet)
EOD
STROKE
(feet)
WORKING
GRADE
(feet)
FINAL DRIVE
DATE
VIBRATION
DRIVE DATE
CUT-OFF
LENGTH
TEST PILE
Highlight rwhitsel Highlight rwhitsel Highlight rwhitsel Highlight rwhitsel Cloud+ rwhitsel Cloud+ Verify Length, as test piles are at least 5 ft longer that production piles, check math in driving logs rwhitsel Cloud+ rwhitsel Cloud+ Verify length (add 12 ft for working grade?)
APPENDIX A
PILE LOGS
Cloud+ rwhitsel Cloud+ Check Math