This is Amendment 0007 to Solicitation N4008526R0001 for a Design-Bid-Build project to demolish an existing condemned US Navy pier (1,570 feet long x 100 feet wide) and construct a new pier (1,000 feet long x 80 feet wide) for four Offshore Patrol Cutters (OPCs) at Naval Station Newport, Newport, Rhode Island. The project also includes construction of a new bulkhead (360 feet long), laydown area, parking, stormwater management, fire/potable water, electrical, telecommunications, and compressed air utilities.

The amendment revises the proposal due date from 22 June 2026 to 21 August 2026 at 2:00 PM ET for those invited to participate in discussions and initiates discussion questions for offerors in the competitive range. Updated evaluation factors for corporate experience require submission of two to five relevant construction projects demonstrating experience with reinforced concrete wharf/pier construction ($50 million+ final cost) and collectively demonstrating controlled demolition of reinforced concrete structures, steel pile supported pier/wharf construction, and installation of industrial grade mechanical and electrical utility services. Projects must be 90-100% complete and completed within ten years prior to solicitation issuance. The amendment updates the Contract Line Item Number (CLIN) schedule, adds new option line items for compressed air systems and concrete pavement alternatives, provides continuation sheets for drawings and specifications, updates the wage determination (RI20260001 07/30/2026), includes revised drawings clarifying base bid and option work scope, updates environmental requirements and specifications, and adds applicable DFARS clauses including small business subcontracting plan requirements and Chinese military company prohibitions. The solicitation is unrestricted with full and open competition and requires submission of a signed Project Labor Agreement complying with FAR 52.222-33 and 52.222-34, with non-compliance resulting in proposal rejection.

View the file

Other files

File Type Posted
Amendment 0009 USCG OPC.pdf PDF
USCG OPC Pier Amendment 0009 Drawings.pdf PDF
Updated Attachment H - USCG OPC Pier Price Proposal Form REV 5.docx DOCX document
USCG OPC Pier Amendment 007 Drawings.pdf PDF
Amendment 0006 USCG OPC.pdf PDF
Attachment Z - Pier 1 - Amendment 006 Drawings.pdf PDF
Updated Attachment H - UCCG OPC Pier Price Proposal Form REV 4.docx DOCX document
Amendment 0005 USCG OPC.pdf PDF
Attachment W - Pier 1 - Amendment 005 Drawings.pdf PDF
Attachment Y - Appendix A Record drawing 11836 125 Submarine Cable Relocation.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.07.24 to 08.08.24.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.20.24 to 08.23.24 (1).pdf PDF
Bulkhead Pile Plan.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.20.24 to 08.23.24.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 09.03.24 to 09.06.24.pdf PDF
NOAA OMAO Survey Reports 100 Percent Pre-Final Submittal 04072022.pdf PDF
SUB-0105 Trestle Piles 4C 6B - PDA and Test Pile Logs.pdf PDF
Trestle Summary.pdf PDF
SUB-0TBD Interim PDA and Test Pile Logs For Trestle Pile 17B.pdf PDF
Attachment X - Appendix A Record Drawing 12819 135 Submarine Cable.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.15.24 to 07.19.24.pdf PDF
Amendment 0004 USCG OPC.pdf PDF
Attachment U - Appendix A - Pier 1 Extension 1968.pdf PDF
Updated Attachment H - UCCG OPC Pier Price Proposal Form REV 2.docx DOCX document
Attachment Q - Spc 100 Final Specs Appendix D - (With Placeholders).pdf PDF
Attachment P - Spc 100 Final Specs Appendix F - Soil GW Sed Sampling Reports.pdf PDF
Attachment R - 26 08 00 - Electrical Shore Ties CSTO (Rev B) - Section 2.4.6 Testing.pdf PDF
JA ML-26-41 USCG Comm Shore Tie Receptacle - Redacted.pdf PDF
JA ML-26-42 USCG Line Insulation Monitor - Redacted.pdf PDF
Amendment 0002 USCG OPC.pdf PDF
Updated Attachment H - UCCG OPC Pier Price Proposal Form REV 1.pdf PDF
Attachment M - 01 45 35_Schedule_of_Special_Inspections.pdf PDF
Attachment N - 01 45 35_Statement_of_Special_Inspections.xlsx XLSX spreadsheet
Attachment O - OPC Pier 1 - Amendment 002 Revised Drawings.pdf PDF
Updated Attachment F - SB Participation Commitment Document.pdf PDF
Amendment 0001 USCG OPC.pdf PDF
Solicitation - N4008526R0001.pdf PDF
Attachment D - Past Performance Questionnaire.pdf PDF
Attachment H - UCCG OPC Pier Price Proposal Form.pdf PDF
1826479dwg01of05_GEN-CIV.pdf PDF
Attachment E - Historical Small Business Utilization.pdf PDF
Attachment J Site Visit Meeting Location.pdf PDF
Specifications USCG OPC Newport.pdf PDF
1826479dwg02of05_STRUC1.pdf PDF
1826479dwg03of05_STRUC2.pdf PDF
Attachment A - Pre Proposal Inquiry Log.xlsx XLSX spreadsheet
Attachment C - Construction Experience Project Data Sheet.pdf PDF
Attachment F - SB Participation Commitment Document.pdf PDF
Attachment G - Individual SB Subcontrating Plan.pdf PDF
Attachment K - WD RI20260001 01-30-2026.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

Created On:

07 Aug 2026, 16:33 PM Greenwich Mean Time

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Block 14 (Description of Amendment/Modification): Solicitation NO: N4008526R0001, Design-Bid-Build, USCG Offshore Patrol Cutters (OPC) Homeport Pier, Naval Station Newport, Newport RI

SEE SF 30 BLOCK 14 CONTINUATION PAGE.

ALL CORRESPONDENCE REGARDING THIS SOLICITATION SHALL BE DIRECTED VIA EMAIL TO KRISTY GERREK AT KRISTY.L.

GERREK.CIV@US.NAVY.MIL.

This amendment is issued to incorporate the following:

1. Revise proposal due date for those invited to participate in Discussions

2. Initiate Discussion Questions to invited Offerors in the Competitive Range (emailed separately)

3. Provide updated Evaluation Factors for Award; Factor 1 - Corporate Experience; (i) Solicitation Submittal Requirements (Enclosed)

4. Update Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN Schedule) (Enclosed)

5. Provide continuation sheet for Drawings and Specifications (Enclosed)

6. Provide updated Wage Determination (RI20260001 07/30/2026) (Enclosed)

7. Provide USCG OPC Pier Amendment 007 Drawings (Attached separately)

8. Provide Amendment 0007 SPC USCG OPC Pier Appendix D (With Placeholders) (Attached separately)

9. Provide Updated Attachment H - USCG OPC Pier Price Proposal Form REV 5 (Attached separately)

10. Update applicable Clauses and Provisions (Enclosed)

Section 00 00 00 - Procurement and Contracting Requirements

The following changes have been made:

INFORMATION FROM TO

Contract Description

SOLICITATION NO: N4008526R0001This Design- Bid-Build project will demolish an existing condemned US Navy pier (1,570 feet long x 100 feet wide) and construct a new pier (1,000 feet long x 80 feet wide) for four Offshore Patrol Cutters (OPCs), along with a new bulkhead (360 feet long), laydown area, parking, stormwatermanagement, fire/potable water, electrical, telecommunications and compressed air utilities, etc.THIS ACQUISITION IS BEING

SOLICITED ON AN UNRESTRICTED BASIS

WITH FULL AND OPEN COMPETITION.THIS

SOLICITATION INCLUDES CMMC LEVEL 1

(SELF) REQUIREMENTS IN ACCORDANCE

WITH DFARS 252.204-7025 AND 252.204-7021.

This project is considered a “Large-scale Construction Project” as defined in FAR 22.502. Accordingly, the requirements of FAR Subpart 22.5 will apply. The Offeror shall submit a signed Project Labor Agreement with their Price Proposal submission, in accordance with FAR Provision52.222-33 and FAR Clause 52.222-

34. Offerors that do not include a signed Project Labor Agreement complying with the terms of FAR 52.222- 33 and 52.222-34 shall be considered nonresponsive and ineligible for award.ALL CORRESPONDENCE

REGARDING THIS SOLICITATION SHALL BE

DIRECTED VIA EMAIL TO KRISTY GERREK AT

KRISTY.L.GERREK.CIV@US.NAVY.MIL.

SOLICITATION NO: N4008526R0001This Design- Bid-Build project will demolish an existing condemned US Navy pier (1,570 feet long x 100 feet wide) and construct a new pier (1,000 feet long x 80 feet wide) for four Offshore Patrol Cutters (OPCs), along with a new bulkhead (360 feet long), laydown area, parking, stormwatermanagement, fire/potable water, electrical, telecommunications and compressed air utilities, etc.THIS ACQUISITION IS BEING

SOLICITED ON AN UNRESTRICTED BASIS

WITH FULL AND OPEN COMPETITION.THIS

SOLICITATION INCLUDES CMMC LEVEL 1

(SELF) REQUIREMENTS IN ACCORDANCE

WITH DFARS 252.204-7025 AND 252.204-7021.

This project is considered a “Large-scale Construction Project” as defined in FAR 22.502. Accordingly, the requirements of FAR Subpart 22.5 will apply. The Offeror shall submit a signed Project Labor Agreement with their Price Proposal submission, in accordance with FAR Provision 52.222-33 and FAR Clause 52.222-34. Offerors that do not include a signed Project Labor Agreement complying with the terms of FAR 52.222-33 and 52.222-34 shall be considered nonresponsive and ineligible for award.ALL

CORRESPONDENCE REGARDING THIS

SOLICITATION SHALL BE DIRECTED VIA

EMAIL TO KRISTY GERREK AT KRISTY.L.

GERREK.CIV@US.NAVY.MIL.

Response Due Date 22 Jun 2026 21 Aug 2026

Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN) Schedule

The following CLIN(s) / SLIN(s) / ELIN(s) were added:

Item Supplies / Services Quantity Unit Unit Price Amount

Option Line Item

Option Item No. 3: Total Price (subtotals of Line Items 0005A through 0005B) for all work associated with the Compressed Air System complete in accordance with the drawings and specifications, but excluding work provided under another priced line item.

Product Service Code: Y1LB Centralized Unique Program Identification

(CUPID): 000

Program Code: C20 Pricing Arrangement: Firm Fixed Price

1 Project

Item Supplies / Services Quantity Unit Unit Price Amount

Option Line Item

Option Item No. 4: Additional costs to provide cast-in-place concrete pavement for the designated laydown area in lieu of asphalt pavement, complete in place.

Product Service Code: Y1LB Centralized Unique Program Identification

(CUPID): 000

Program Code: C20 Pricing Arrangement: Firm Fixed Price

1 Project

The following CLIN(s) / SLIN(s) / ELIN(s) were modified:

INFORMATION FROM TO

Description

BASE PRICE: Total Price for Line Items 0001A through 0001Z for the entire work for USCG OCR Homeport OPC Pier, including demolition of existing Pier 1, construction of landside area and new Bulkhead S45S, and construction of new OPC Pier 1 at Naval Station Newport, RI, in accordance with the drawings and specifications, complete, but excluding work provided as Option Items.

BASE PRICE: Total Price (subtotals of Line Items 0001A through 0001Z) for all work associated with demolition of existing Pier 1 and construction of the new OPC Pier 1 from the landside connection to the expansion joint between Bents 30 and 31, including removal and disposal of all existing pier structures, foundations, and appurtenances; dredging and dredged material disposal; construction of the fendering system, mooring system, Bulkhead S45S, pier utilities (to the expansion joint between Bents 30 and 31), civil site work, grading, drainage, site utility systems; and all other incidental work, complete in accordance with the drawings and specifications, but excluding work provided under another priced line item.

Option Line Item 0002

INFORMATION FROM TO

Description Option Item No. 1: Compressed Air System: Furnish and install in accordance with the drawings and specifications

Option Item No. 1: Total Price (subtotals of Line Items 0003A through 0003E) for all work associated with construction of the OPC Pier 1 extending from the expansion joint between bents 30 and 31 to the end of the pier, including utility systems, fendering, mooring systems and all other components complete in accordance with the drawings and specifications, but excluding work provided under another priced line item.

Option Line Item 0003

INFORMATION FROM TO

Description Option Item No. 2: Additional costs to provide cast-in-place concrete pavement for the designated laydown area in lieu of asphalt pavement, complete.

Option Item No. 2: Polymeric Fender Piles: Additional costs to provide polymeric fender piles with H-pile extension for the pier in lieu of steel pipe piles, complete.

Section 00 70 00 - Conditions of the Contract

Additional Information/Notes

The following clauses were added:

DFARS Clauses Incorporated by Reference

Number Title Effective Date Alternate/ Deviation

Variation Effective Date

252.219-7996 Small Business Subcontracting Plan (DoD Contracts). (DEVIATION 2026- O0037)

Jul 2026 Deviation 2026-O0037 Jul 2026

252.240-7007 Prohibitions Relating to Chinese Military Companies. (DEVIATION 2026- O0025)

Jun 2026 Deviation 2026-O0025 Jun 2026

252.240-7995 Prohibition on Contract Awards with Entities That Contract with Lobbyists for Chinese Military Companies--Representation. (DEVIATION 2026- O0025)

Jun 2026 Deviation 2026-O0025 Jun 2026

252.240-7996 Prohibition on Contract Awards to Chinese Military Companies-- Representation. (DEVIATION 2026-O0025)

Jun 2026 Deviation 2026-O0025 Jun 2026

The following clauses were modified:

52.222-90Addressing DEI Discrimination by Federal Contractors. (Deviation 2026-O0040, Revision 1)Apr 2026

The following clauses were deleted:

DFARS Clauses Incorporated by Reference

Number Title Effective Date Alternate/ Deviation

Variation Effective Date

252.225-7058 Postaward Disclosure of Employment of Individuals Who Work in the People's Republic of China.

Jan 2023

Section 00 73 00 - Supplementary Conditions

The following attachments were added:

Amendment 0007 Continuation Page-1 Amendment 0007 SPC USCG OPC Pier Appendix D (With Placeholders) Attachment H - USCG OPC Pier Price Proposal Form REV 5 USCG OPC Pier Amendment 007 Drawings

Section 01 00 00 - General Requirements

The Requirements text has been modified to:

This Design-Bid-Build project will demolish an existing condemned US Navy pier (1,570 feet long x 100 feet wide) and construct a new pier (1,000 feet long x 80 feet wide) for four Offshore Patrol Cutters (OPCs), along with a new bulkhead (360 feet long), laydown area, parking, stormwater management, fire/potable water, electrical, telecommunications and compressed air utilities, etc.

SECTION SF30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The following have been added by full text:

AMENDMENT 0007

This amendment is issued to incorporate the following:

1. Revise proposal due date for those invited to participate in Discussions

2. Initiate Discussion Questions to invited Offerors in the Competitive Range (emailed separately)

3. Provide updated Evaluation Factors for Award; Factor 1 – Corporate Experience; (i) Solicitation

Submittal Requirements (Enclosed)

4. Update Section 00 10 00 – Solicitation, Contract Line Item Number (CLIN Schedule) (Enclosed)

5. Provide continuation sheet for Drawings and Specifications (Enclosed)

6. Provide updated Wage Determination (RI20260001 07/30/2026) (Enclosed)

7. Provide USCG OPC Pier Amendment 007 Drawings (Attached separately)

8. Provide Amendment 0007 SPC USCG OPC Pier Appendix D (With Placeholders) (Attached separately)

9. Provide Updated Attachment H - USCG OPC Pier Price Proposal Form REV 5 (Attached separately)

10. Update applicable Clauses and Provisions (Enclosed)

1. Revised proposals for those invited to participate in discussions are due on 21 AUGUST 2026 by

2:00PM ET.

2. Initiate Discussion Questions to invited Offerors in the Competitive Range (Emailed Separately).

For those Offeror’s notified that they are included in the Competitive Range, please refer to your

Evaluation Notice for submission requirements for revised proposals.

3. Provide updated Evaluation Factors for Award; Factor 1 – Corporate Experience; (i) Solicitation

Submittal Requirements (Enclosed) (updates notated in red)

Factor 1 – Corporate Experience

(i) Solicitation Submittal Requirements:

Offerors shall submit a minimum of two (2) up to a maximum of five (5) relevant construction projects that best demonstrate their experience on relevant projects similar in size, scope, and complexity to this RFP.

Only the experience of the Offeror, performed as a prime contractor shall be considered. Experience of proposed subcontractors will not be considered.

For purposes of this evaluation, a relevant project is further defined as:

Size: A final construction cost of $50,000,000 or greater.

Scope: Construction of reinforced concrete wharfs or pier structures.

Complexity: Relevant wharf or pier projects submitted shall, collectively, demonstrate experience with all of the following elements listed below:

• Controlled demolition of reinforced concrete structures;

• Steel pile supported pier/wharf construction;

• Installation of industrial grade mechanical and electrical utility services and controls

Note 1: The Offeror’s proposal shall, cumulatively, demonstrate experience with all of the elements listed under “Complexity”. All elements do not have to be included under one project, experience may be demonstrated collectively through all projects submitted meeting size and scope.

For all submitted projects, ensure that the project description clearly provides the final construction cost and addresses how the project meets the scope/complexity requirements. The absence of any such information may result in the project being considered Not Relevant, which could result in a rating of UNACCEPTABLE for this Factor, if the minimum requirements are not met.

Projects submitted for the offeror shall have been completed within the ten (10) years prior to the date of issuance of this RFP. Projects that are not 90% complete as of the date of issuance of this RFP will be considered “Not Relevant.” Additionally, projects completed more than ten (10) years prior to the date of issuance of this RFP will be considered “Not Relevant.”

If a submitted project is not 100% complete, but is at least 90% complete, include the percentage complete as of the date of issuance of this RFP on the Construction Experience Project Data Sheet

(Attachment C).

If a submitted project is not 100% complete, but is at least 90% complete, include the award cost and the current construction cost of that project as of the date of issuance of this RFP on the Construction

Experience Project Data Sheet (Attachment C).

A project is defined as a construction project performed under a single task order or contract. For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project; rather, offerors shall submit the work performed under a task order as a project. The submission of a multiple award and/or indefinite delivery/indefinite quantity type contract as a whole will be considered Not Relevant.

The attached Construction Experience Project Data Sheet (Attachment C) is MANDATORY and

SHALL be used to submit project information. Except as specifically requested, the Government will not consider information submitted in addition to this form nor will the Government consider submissions via any other medium. Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed two (2) pages. Information beyond this page limit will not be considered.

If the Offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the Joint Venture entity. If the Joint Venture does not have shared experience, projects may be submitted for the Joint Venture members. Offerors are still limited to a total of five (5) projects combined. Offerors may submit experience where a member of the offering JV performed as a JV with another entity, but must clearly demonstrate how its work on that project met size, scope, and complexity as defined above.

Likewise, Offerors that are not submitting as a JV may submit a project where it performed as a JV with another entity, but must clearly demonstrate how its work on that project met size, scope, and complexity as defined above. Offerors are still limited to a total of five (5) projects combined.

For a JV, the offeror shall submit the signed JV agreement. For an 8(a) Mentor-Protégé Joint Venture, the offeror shall submit the signed U.S. Small Business Administration (SBA) Mentor-Protégé approval letter and signed JV agreement.

If an Offeror is utilizing experience information of affiliates/subsidiaries/parent/LLC/LTD member companies (name is not exactly as stated on the SF1442), the proposal shall clearly demonstrate that the affiliate/subsidiary/parent firm will have meaningful involvement and clearly describe the role that firm will have in the performance of the contract. If meaningful involvement is not demonstrated, experience of the affiliate/subsidiary/parent firm will not be considered.

4. Update Section 00 10 00 – Solicitation, Contract Line Item Number (CLIN Schedule) (Enclosed)

5. Continuation Sheet for Drawings and Specifications (Enclosed)

DWG

NO

NAVFAC

NO

CHANGE NO TITLE

G-102 12936575 007 GENERAL SITE PLAN

CN101 12936599 007 OVERALL DREDGING PLAN

CD101 12936605 007 SITE DEMOLITION PLAN

CD102 12936606 007 UTILITY DEMOLITION PLAN - PIER 1 LANDSIDE

C-101 12936607 007 SITE PLAN

C-102 12936608 007 UTILITY PLAN – PIER 1 LANDSIDE

SD104 12936628 007 S45S BULKHEAD DEMOLITION PLAN

SD601 12936635 007 PIER 1 AND S45N BULKHEAD DEMOLITION

PHOTOGRAPHS

SD602 12936636 007 S45N BULKHEAD DEMOLITION PHOTOGRAPHS

S-002 12936620 007 STRUCTURAL GENERAL NOTES – SHEET 1 OF 2

S-003 12936621 007 STRUCTURAL GENERAL NOTES – SHEET 2 OF 2

S-101 12936637 007 OVERALL BULKHEAD PLAN

S-102 12936638 007 GENERAL DECK PLAN

S-103 12936639 007 PILE PLAN – SHEET 1 OF 7

S-104 12936640 007 PILE PLAN – SHEET 2 OF 7

S-105 12936641 007 PILE PLAN – SHEET 3 OF 7

S-106 12936642 007 PILE PLAN – SHEET 4 OF 7

S-107 12936643 007 PILE PLAN – SHEET 5 OF 7

S-108 12936644 007 PILE PLAN – SHEET 6 OF 7

S-109 12936645 007 PILE PLAN – SHEET 7 OF 7

S-111 12936647 007 FRAMING PLAN – SHEET 2 OF 7

S-117 12936653 007 CONCRETE PLANKS PLAN – SHEET 1 OF 7

S-118 12936654 007 CONCRETE PLANKS PLAN – SHEET 2 OF 7

S-124 12936660 007 DECK PLAN – SHEET 1 OF 7

S-125 12936661 007 DECK PLAN – SHEET 2 OF 7

S-126 12936662 007 DECK PLAN – SHEET 3 OF 7

S-127 12936663 007 DECK PLAN – SHEET 4 OF 7

S-128 12936664 007 DECK PLAN – SHEET 5 OF 7

S-129 12936665 007 DECK PLAN – SHEET 6 OF 7

S-130 12936666 007 DECK PLAN – SHEET 7 OF 7

S-131 12936667 007 FENDER PILE PLAN – SHEET 1 OF 6

S-132 12936668 007 FENDER PILE PLAN – SHEET 2 OF 6

S-133 12936669 007 FENDER PILE PLAN – SHEET 3 OF 6

S-134 12936670 007 FENDER PILE PLAN – SHEET 4 OF 6

S-135 12936671 007 FENDER PILE PLAN – SHEET 5 OF 6

S-136 12936672 007 FENDER PILE PLAN – SHEET 6 OF 6

S-137 12936673 007 DECK DRAINAGE PLAN – SHEET 1 OF 2

S-201 12936675 007 PIER SOUTHERN ELEVATION – SHEET 1 OF 3

S-202 12936676 007 PIER SOUTHERN ELEVATION – SHEET 2 OF 3

S-203 12936678 007 PIER SOUTHERN ELEVATION – SHEET 3 OF 3

S-204 12936678 007 PIER NORTHERN ELEVATION – SHEET 1 OF 3

S-205 12936679 007 PIER NORTHERN ELEVATION – SHEET 2 OF 3

S-206 12936680 007 PIER NORTHERN ELEVATION – SHEET 3 OF 3

S-301 12936683 007 PIER LONGITUDINAL SECTION – SHEETS 1 OF 2

S-304 12936686 007 LONGITUDUNAL SECTIONS AT UTILITY TRENCH

S-307 12936689 007 PIER TRANSVERSE SECTIONS – SHEET 1 OF 5

S-308 12936690 007 PIER TRANSVERSE SECTIONS – SHEET 2 OF 5

S-309 12936691 007 PIER TRANSVERSE SECTIONS – SHEET 3 OF 5

S-311 12936693 007 PIER TRANSVERSE SECTIONS – SHEET 5 OF 5

S-402 12936695 007 OUTBOARD SUBSTATION PART PLAN (OPTION 1)

S-403 12936696 007 INBOARD SUBSTATION PART PLAN

S-404 12936697 007 BULKHEAD PART PLAN & SECTION

S-501 12936698 007 TURBIDITY CURTAIN NOTES & DETAILS

S-502 12936699 007 PILE DETAILS – CONCRETE FILLED PIPE PILES

S-503 12936700 007 PILE DETAILS – STEEL PILES

S-505 12936702 007 CONCRETE PILE CAP DETAILS – SHEET 2 OF 3

S-508 12936705 007 REINFORCEMENT DETAILS FOR CONCRETE BLOCK OUT

AT BENT 43 - SHEET 1 OF 2

S-509 12936706 007 REINFORCEMENT DETAILS FOR CONCRETE BLOCK OUT

AT BENT 43 - SHEET 2 OF 2

S-511 12936708 007 REINFORCEMENT DETAILS

S-516 12936713 007 CONDUITS AND FITTINGS AT EXPANSION JOINT

S-519 12936718 007 FENDER SYSTEM DETAILS - SHEET 1 OF 2

S-520 12936717 007 FENDER SYSTEM DETAILS – SHEET 2 OF 2

S-529 12936726 007 AIR COMPRESSOR FOUNDATIONS & STEEL FRAME PART

PLAN (OPTION 3)

S-530 12936727 007 AIR COMPRESSOR DETAILS (OPTION 3)

S-531 12936728 007 AIR COMPRESSOR FOUNDATIONS DETAILS (OPTION 3)

S-532 12936729 007 AIR COMPRESSOR STAIRS ACCESS DETAILS – SHEET 1 OF

2 (OPTION 3)

S-533 12936730 007 AIR COMPRESSOR STAIRS ACCESS DETAILS – SHEET 2 OF

2 (OPTION 3)

S-601 12936732 007 STEEL PILE SCHEDULE

S-602 12936733 007 FENDER PILE SCHEDULE – SHEET 1 OF 2

S-603 12936734 007 FENDER PILE SCHEDULE – SHEET 2 OF 2

M-101 12936736 007 MECHANICAL PLAN - SHEET 1 OF 7 (OPTION 1)

M-102 12936737 007 MECHANICAL PLAN - SHEET 2 OF 7 (OPTION 1)

M-103 12936738 007 MECHANICAL PLAN - SHEET 3 OF 7

M-107 12936742 007 MECHANICAL PLAN - SHEET 7 OF 7

M-301 12936743 007 MECHANICAL LONGITUDINAL SECTIONS - SHEET 1 OF 2

M-302 12936744 007 MECHANICAL LONGITUDINAL SECTIONS - SHEET 2 OF 2

M-401 12936746 007 MECHANICAL COMPRESSED AIR ENCLOSURE - PART

PLAN (OPTION 3)

M-601 12936754 007 MECHANICAL PIPE SCHEDULES

M-701 12936755 007 COMPRESSED AIR SCHEMATIC (OPTION 3)

M-702 12936756 007 COMPRESSED AIR HEAT RECOVERY SCHEMATIC

(OPTION 3)

M-703 12936757 007 POTABLE FRESH WATER (FW) SCHEMATIC

M-901 12936758 007 MECHANICAL UTILITIES ISOMETRIC VIEWS

E-101 12936760 007 ELECTRICAL DECK PLAN – SHEET 1 OF 7

E-102 12936761 007 ELECTRICAL DECK PLAN – SHEET 2 OF 7

E-103 12936762 007 ELECTRICAL DECK PLAN – SHEET 3 OF 7

E-105 12936764 007 ELECTRICAL DECK PLAN – SHEET 5 OF 7

E-106 12936765 007 ELECTRICAL DECK PLAN – SHEET 6 OF 7

E-107 12936766 007 ELECTRICAL DECK PLAN – SHEET 7 OF 7

E-109 12936768 007 ELECTRICAL SITE PLAN – PIER 1

E-112 12936771 007 CATHODIC PROTECTION PILE PLAN

E-113 12936772 007 GROUNDING PLAN – PIER WEST

E-114 12936773 007 GROUNDING PLAN – PIER EAST

E-115 12936774 007 LIGHTNING PROTECTION PLAN – PIER WEST

E-116 12936775 007 LIGHTNING PROTECTION PLAN – PIER EAST

E-401 12936776 007 SUBSTATION P1W PART PLAN & ELEVATION

E-402 12936777 007 SUBSTATION P1E PART PLAN & ELEVATION

E-403 12936778 007 SUBSTATION GROUNDING PART PLANS

E-404 12936779 007 SUBSTATION P1W VAULT PART PLAN & ELEVATION

E-502 12936782 007 15KV SWITCHGEAR STRUCTURE DETAILS

E-507 12936787 007 METERING SYSTEM DETAILS – SHEET 3 OF 3

E-509 12936789 007 HIGH MAST LIGHTING POLE DETAILS

E-511 12936791 007 SUBSTATION P1W SWITCHGEAR ELEVATIONS

E-512 12936792 007 MISCELLANEOUS DETAILS – SHEET 1 OF 2

E-513 12936793 007 MISCELLANEOUS DETAILS – SHEET 2 OF 2

E-514 12936794 007 HEAT TRACE CABINET & DETAILS

E-601 12936795 007 PRIMARY & DEMOLITION ONE LINE DIAGRAM

E-602 12936796 007 PIER ONE LINE DIAGRAM - EAST

E-603 12936797 007 PIER ONE LINE DIAGRAM - WEST

E-604 12936798 007 COMMUNICATIONS ONE LINE DIAGRAM

E-605 12936799 007 MANHOLE SCHEDULE & FOLDOUT DIAGRAMS

E-606 12936800 007 MINI POWER CENTER PANEL SCHEDULES

E-608 12936802 007 HEAT TRACE ONE LINE DIAGRAM & SCHEDULES

E-609 12936803 007 LIGHTING CONTROL DIAGRAMS

E-611 12936805 007 SUBSTATION P1W SWITCHGEAR SCHEDULE

E-612 12936806 007 SUBSTATION P1E PANEL SCHEDULES

E-613 12936807 007 SUBSTATION P1W PANEL SCHEDULES

E-614 12936808 007 FEEDER SCHEDULE – SHEET 1 OF 2

E-615 12936809 007 FEEDER SCHEDULE – SHEET 2 OF 2

S-535 TBD 007 COMPOSITE FENDER SYSTEM DETAILS (OPTION 2)

On NAVFAC Dwg. No. 12936575 (G-102)

CHANGE G102 GENERAL SITE PLAN as follows:

DEFINED limits of base bid and option work.

On NAVFAC Dwg. No. 129365995 (CN101)

CHANGE CN101 OVERALL DREDGING PLAN – BASE BID as follows:

On NAVFAC Dwg. No. 129366605 (CD101)

CHANGE CD101 SITE DEMOLITION PLAN as follows:

REVISED general note 2 to define limits of base bid and option work.

REVISED keynotes 3, 7, 8,15 and 16 to clarify removal work.

On NAVFAC Dwg. No. 129366606 (CD102)

CHANGE CD102 UTILITY DEMOLITION PLAN - PIER 1 LANDSIDE as follows:

REVISED general note 2 to define limits of base bid and option work

On NAVFAC Dwg. No. 129366607 (C-101)

CHANGE C101 SITE PLAN as follows:

REVISED general note 5 to define limits of base bid and option work.

REVISED keynote 9 to define bid option work.

On NAVFAC Dwg. No. 129366608 (C-102)

CHANGE C102 UTILITY PLAN – PIER 1 LANDSIDE as follows:

REVISED general note 3 to define limits of base bid and option work.

REVISED keynote 11 to define bid option work.

On NAVFAC Dwg. No. 12936628 (SD104)

CHANGE SD104 S45S BULKHEAD DEMOLITION PLAN as follows:

DELETE “Base Bid” from the drawing title.

On NAVFAC Dwg. No. 12936635 (SD601)

CHANGE SD601 PIER 1 AND S45N BULKHEAD DEMOLITION PHOTOGRAPHS as follows:

On NAVFAC Dwg. No. 12936636 (SD602)

CHANGE SD602 S45N BULKHEAD DEMOLITION PHOTOGRAPHS as follows:

On NAVFAC Dwg. No. 12936620 (S-002)

CHANGE S-002 STRUCTURAL GENERAL NOTES – SHEET 1 OF 2 as follows:

REVISE Structural Concrete Notes

Revise note 1A. – delete “piles”.

REVISE Foundation Notes – Steel Pipe Piles.

Revise Notes 6.1, 7.1

Added Notes 8.1 and 8.2

On NAVFAC Dwg. No. 12936621 (S-003)

CHANGE S-003 STRUCTURAL GENERAL NOTES – SHEET 2 OF 2 as follows:

REVISE FOUNDATION NOTES – STEEL PIPE PILES CONT as follows

REVISE Numbering

REVISE Foundation Notes – Fender Piles.

Add Notes 4.1 and 4.2.

On NAVFAC Dwg. No. 12936637 (S-101)

CHANGE S-003 OVERALL BULKHEAD PLAN as follows:

DELETE “Base Bid” from drawing title.

On NAVFAC Dwg. No. 12936638 (S-102)

CHANGE S-102 GENERAL DECK PLAN as follows:

REDUCED number of fender piles shown.

On NAVFAC Dwg. No. 12936639 (S-103) through No. 1296645 (S-109)

CHANGE S-103 PILE PLAN – SHEET 1 OF 7 through S-109 PILE PLAN – SHEET 7 OF 7 as follows:

REVISE pile thickness in general sheet note 1.

On NAVFAC Dwg. No. 12936645 (S-111)

CHANGE S-111 FRAMING PLAN – SHEET 2 OF 7 as follows:

On NAVFAC Dwg. No. 12936653 (S-117)

CHANGE S-117 CONCRETE PLANKS PLAN – SHEET 1 OF 7 as follows:

On NAVFAC Dwg. No. 12936653 (S-118)

CHANGE S-118 CONCRETE PLANKS PLAN – SHEET 2 OF 7 as follows:

On NAVFAC Dwg. No. 12936660 (S-124)

CHANGE S-124 DECK PLAN – SHEET 1 OF 7 as follows:

REDUCED Number of fender piles shown.

On NAVFAC Dwg. No. 12936661 (S-125)

CHANGE S-125 DECK PLAN – SHEET 2 OF 7 as follows:

On NAVFAC Dwg. No. 12936662 (S-126)

CHANGE S-126 DECK PLAN – SHEET 3 OF 7 as follows:

On NAVFAC Dwg. No. 12936663 (S-127)

CHANGE S-127 DECK PLAN – SHEET 4 OF 7 as follows:

On NAVFAC Dwg. No. 12936664 (S-128)

CHANGE S-128 DECK PLAN – SHEET 5 OF 7 as follows:

On NAVFAC Dwg. No. 12936665 (S-125)

CHANGE S-129 DECK PLAN – SHEET 6 OF 7 as follows:

On NAVFAC Dwg. No. 12936666 (S-130)

CHANGE S-130 DECK PLAN – SHEET 7 OF 7 as follows:

On NAVFAC Dwg. No. 12936667 (S-131)

CHANGE S-131 FENDER PILE PLAN – SHEET 1 OF 6 as follows:

On NAVFAC Dwg. No. 12936668 (S-132)

CHANGE S-132 FENDER PILE PLAN – SHEET 2 OF 6 as follows:

On NAVFAC Dwg. No. 12936669 (S-133)

CHANGE S-133 FENDER PILE PLAN – SHEET 3 OF 6 as follows:

On NAVFAC Dwg. No. 12936670 (S-134)

CHANGE S-134 FENDER PILE PLAN – SHEET 4 OF 6 as follows:

On NAVFAC Dwg. No. 12936671 (S-135)

CHANGE S-135 FENDER PILE PLAN – SHEET 5 OF 6 as follows:

On NAVFAC Dwg. No. 12936672 (S-136)

CHANGE S-136 FENDER PILE PLAN – SHEET 6 OF 6 as follows:

On NAVFAC Dwg. No. 12936673 (S-137)

CHANGE S-137 DECK DRAINAGE PLAN – SHEET 1 OF 2 as follows:

On NAVFAC Dwg. No. 12936675 (S-201)

CHANGE S-201 PIER SOUTHERN ELEVATION – SHEET 1 OF 3 as follows:

On NAVFAC Dwg. No. 12936676 (S-202)

CHANGE S-202 PIER SOUTHERN ELEVATION – SHEET 2 OF 3 as follows:

On NAVFAC Dwg. No. 12936677 (S-203)

CHANGE S-203 PIER SOUTHERN ELEVATION – SHEET 3 OF 3 as follows:

On NAVFAC Dwg. No. 12936678 (S-204)

CHANGE S-204 PIER NORTHERN ELEVATION – SHEET 1 OF 3 as follows:

On NAVFAC Dwg. No. 12936679 (S-205)

CHANGE S-205 PIER NORTHERN ELEVATION – SHEET 2 OF 3 as follows:

On NAVFAC Dwg. No. 12936680 (S-206)

CHANGE S-206 PIER NORTHERN ELEVATION – SHEET 3 OF 3 as follows:

On NAVFAC Dwg. No. 12936683 (S-301)

REVISED fender system callout.

On NAVFAC Dwg. No. 12936686 (S-304)

CHANGE S-304 LONGITUDUNAL SECTIONS AT UTILITY TRENCH as follows:

On NAVFAC Dwg. No. 12936689 (S-307)

CHANGE S-307 PIER TRANSVERSE SECTIONS – SHEET 1 OF 5 as follows:

ADD “OPTION 1” to drawing title

On NAVFAC Dwg. No. 12936690 (S-308)

On NAVFAC Dwg. No. 12936691 (S-309)

On NAVFAC Dwg. No. 12936693 (S-311)

On NAVFAC Dwg. No. 12936695 (S-402)

CHANGE S-402 OUTBOARD SUBSTATION PART PLAN (OPTION 1)as follows:

On NAVFAC Dwg. No. 12936696 (S-403)

On NAVFAC Dwg. No. 12936697 (S-404)

CHANGE S-404 BULKHEAD PART PLAN & SECTION as follows:

DELETED “BASE BID” from drawing title.

On NAVFAC Dwg. No. 12936698 (S-501)

CHANGE S-501 TURBIDITY CURTAIN NOTES & DETAILS as follows:

DELETED “BASE BID” from drawing title.

On NAVFAC Dwg. No. 12936699 (S-502)

CHANGE S-503 PILE DETAILS – CONCRETE FILLED PIPE PILES as follows:

REVISED Details A1, A3, A5, and D5.

On NAVFAC Dwg. No. 12936700 (S-503)

CHANGE S-503 PILE DETAILS – PIPE DETAILS – STEEL PILES as follows:

REVISED Detail A1

On NAVFAC Dwg. No. 1293702 (S-505)

On NAVFAC Dwg. No. 12936705 (S-508)

CHANGE S-508 REINFORCEMENT DETAILS FOR CONCRETE BLOCK OUT AT BENT 43 -

SHEET 1 OF 2 as follows:

On NAVFAC Dwg. No. 12936706 (S-509)

CHANGE S-509 REINFORCEMENT DETAILS FOR CONCRETE BLOCK OUT AT BENT 43 -

SHEET 2 OF 2 as follows:

On NAVFAC Dwg. No. 12936706 (S-511)

CHANGE S-511 REINFORCEMENT DETAILS as follows:

ADD Notes to detail A4

On NAVFAC Dwg. No. 12936706 (S-516)

CHANGE S-516 CONDUITS AND FITTINGS AT EXPANSION JOINT as follows:

On NAVFAC Dwg. No. 12936716 (S-519)

CHANGE S-519 FENDER SYSTEM DETAILS – SHEET 1 OF 2 as follows:

REVISED Drawing its’ entirety from composite to steel pipe fender piles.

On NAVFAC Dwg. No. 12936717 (S-520)

CHANGE S-520 FENDER SYSTEM DETAILS – SHEET 2 OF 2 as follows:

REVISED Drawing its’ entirety to steel pipe fender piles.

On NAVFAC Dwg. No. 12936726 (S-529)

CHANGE S-529 AIR COMPRESSOR FOUNDATIONS & STEEL FRAME PART PLAN

(OPTION 3) as follows:

On NAVFAC Dwg. No. 12936727 (S-530)

CHANGE S-530 AIR COMPRESSOR DETAILS (OPTION 3) as follows:

On NAVFAC Dwg. No. 12936728 (S-531)

CHANGE S-531 AIR COMPRESSOR FOUNDATIONS DETAILS (OPTION 3) as follows:

On NAVFAC Dwg. No. 12936729 (S-532)

CHANGE S-532 AIR COMPRESSOR STAIRS ACCESS DETAILS – SHEET 1 OF 2 (OPTION 3)

as follows:

On NAVFAC Dwg. No. 12936730 (S-533)

CHANGE S-532 AIR COMPRESSOR STAIRS ACCESS DETAILS – SHEET 2 OF 2 (OPTION 3)

On NAVFAC Dwg. No. (S-535)

ADD Drawing S-535 COMPOSITE FENDER SYSTEM DETAILS (OPTION 2)

On NAVFAC Dwg. No. 12936733 (S-601)

CHANGE S-601 STEEL PILE SCHEDULE as follows:

REVISE Pile Schedule.

ADD the following note: “The contractor shall verify the top of weathered rock and glacial till in the field and adjust the pile tip elevations accordingly.”

On NAVFAC Dwg. No. 12936733 (S-602)

CHANGE S-602 FENDER PILE SCHEDULE – SHEET 1 OF 2 as follows:

REVISE Fender Pile Schedules.

ADD the following note: “The contractor shall verify the top of weathered rock and glacial till in the field and adjust the pile tip elevations accordingly.”

ADD the following note: “The fender pile tip elevations are the same for the pipe (base bid) and polymeric (option 2) pile types.”

On NAVFAC Dwg. No. 12936734 (S-603)

CHANGE S-603 FENDER PILE SCHEDULE – SHEET 2 OF 2 as follows:

Delete Fender Pile Schedules.

ADD the following note: “THIS SHEET WAS INTENTIONALLY LEFT BLANK”

On NAVFAC Dwg. No. 12936736 (M-101)

CHANGE M-101 MECHANICAL PLAN - SHEET 1 OF 7 (OPTION 1) as follows:

DEFINED limits of bid option 1 work scope.

On NAVFAC Dwg. No. 12936737 (M-102)

CHANGE M-102 MECHANICAL PLAN - SHEET 2 OF 7 (OPTION 1) as follows:

DEFINED limits of option 1 and base bid work scope.

On NAVFAC Dwg. No. 12936738 (M-103)

CHANGE M-103 MECHANICAL PLAN - SHEET 3 OF 7 (OPTION 1) as follows:

DEFINED limits of base bid work scope.

ADDED “OPTION 1” to drawing title

ADD Fire Protection (Fresh Water) Loop towards the edge of "Base Bid" Pier. Located between bend 29 and bend 30.

ADD Sheet Note Add: **PROVIDE FIRE PROTECTION LOOP PER KEYED NOTES IF OPTION 1

IS NOT EXERCISED.

ADD Freshwater Piping Keyed Notes - "If option 1 is not exercised"

Notes: 10, 11, 12, and 13.

On NAVFAC Dwg. No. 12936742 (M-107)

CHANGE M-107 MECHANICAL PLAN - SHEET 7 OF 7 as follows:

DEFINED limits of base bid and option 3 work scope.

REVISE Compressed air scope of work notes – Option 3.

Revise Notes 6, 9, 10,15, 16, 17 and Note 21.

On NAVFAC Dwg. No. 12936743 (M-301)

CHANGE M-301 MECHANICAL LONGITUDINAL SECTIONS - SHEET 1 OF 2 as follows:

DEFINED limits of base bid and option 1 work scope in elevation views (B2, C2, and D2).

ADD the following note (D2/M-301): "Option 1" to freshwater piping loop.

ADD the following note (D2/M-301): **PROVIDE THIS SECTION AT BENT 30 IF OPTION 1 IS NOT

EXCERCISED.

ADD the following note (D2/M-301): "Option 1" to freshwater piping loop.

ADD the following note (D2/M-301): **PROVIDE THIS SECTION AT BENT 30 IF OPTION 1 IS NOT

EXCERCISED.

ADD The following pipe (B2/M-301): Fire Protection (Fresh Water) Loop towards the edge of "Base

Bid" Pier. Provided with butterfly valve, and manhole for valve access Located between bend 29 and bend 30.

ADD Sheet Note Add (B2/M-301): **IF OPTION 1 IS NOT EXCERCISED. PROVIDE

MECHANICAL SLEEVE AND SEAT AT PIPE PENETRATION INTO TRENCH. REFER TO DETAIL

A3 ON M-503 AND A4 ON M-505.

On NAVFAC Dwg. No. 12936744 (M-302)

CHANGE M-302 MECHANICAL LONGITUDINAL SECTIONS - SHEET 2 OF 2 as follows:

DEFINED limits of base bid and option 3 work scope in elevation views (B2).

REVISE sheets notes (B2/M-301): Compressed air pipes pier side (bid option) and buried pipes landside

(option 3).

On NAVFAC Dwg. No. 12936746 (M-401)

CHANGE M-601 MECHANICAL COMPRESSED AIR ENCLOSURE - PART PLAN (OPTION 3)

DEFINED limits of option 3 work scope.

ADD “OPTION 3” to drawing title

REVISE sheet and notes pertaining to compressed air packaged enclosure and buried CA pipe to "Bid

Option 3".

On NAVFAC Dwg. No. 12936754 (M-601)

CHANGE M-601 MECHANICAL PIPE SCHEDULE as follows:

DEFINED limits of base bid and option 1 work scope. Indicated on the schedules impacted.

REVISE Schedules: Thermal Expansion Joint Schedule, Structural Movement Joint Schedule, and

Sanitary Pump Schedule

On NAVFAC Dwg. No. 12936755 (M-701)

CHANGE M-701 COMPRESSED AIR SCHEMATIC (OPTION 3)

On NAVFAC Dwg. No. 12936756 (M-702)

CHANGE M-702 COMPRESSED AIR HEAT RECOVERY SCHEMATIC (OPTION 3)

On NAVFAC Dwg. No. 12936757 (M-703)

CHANGE M-703 POTABLE FRESH WATER (FW) SCHEMATIC as follows:

REVISE limits of base bid and option 1 work scope.

ADD Sheet Note: PROVIDE 10" FRESH WATER MAIN OUTSIDE OF UTILITY TRENCH AND

ABOVE THE PIER. - **PROVIDE IF OPTION 1 IS NOT EXERCISED.

On NAVFAC Dwg. No. 12936758 (M-901)

CHANGE M-901 MECHANICAL UTILITIES ISOMETRIC VIEWS as follows:

REVISED Detail A3: Add "Option 3" to compressed air enclosure isometric detail.

On NAVFAC Dwg. No. 12936760 (E-101)

CHANGE E-101 ELECTRICAL DECK PLAN – SHEET 1 OF 7 as follows:

DEFINED limits of Option 1 work.

REVISED ductbank feeder tags for lighting feeder changes.

On NAVFAC Dwg. No. 12936761 (E-102)

CHANGE E-102 ELECTRICAL DECK PLAN – SHEET 2 OF 7 as follows:

DEFINED limits of Option 1 work.

REVISED ductbank feeder tags for lighting feeder changes

On NAVFAC Dwg. No. 12936762 (E-103)

CHANGE E-103 ELECTRICAL DECK PLAN – SHEET 3 OF 7 as follows:

DEFINED modifications to work required for manholes, ductbanks, and heat tracing if Option 1 is not executed.

On NAVFAC Dwg. No. 12936764 (E-105)

CHANGE E-105 ELECTRICAL DECK PLAN – SHEET 5 OF 7 as follows:

REVISED ductbank feeder and Keynote 8 for high mast lighting pole LC2 being fed from Substation

P1E.

On NAVFAC Dwg. No. 12936765 (E-106)

CHANGE E-106 ELECTRICAL DECK PLAN – SHEET 6 OF 7 as follows:

REVISED ductbank feeder and added (2) ducts from Substation P1E to Manhole EMH-DE-0607 for high mast lighting pole LC2 being fed from Substation P1E.

On NAVFAC Dwg. No. 12936765 (E-107)

CHANGE E-107 ELECTRICAL DECK PLAN – SHEET 7 OF 7 as follows:

ADDED Keynote 7 and associated callouts to indicate the work associated with the Compressed Air

Enclosure being in Option 3.

On NAVFAC Dwg. No. 12936768 (E-109)

CHANGE E-109 ELECTRICAL SITE PLAN – PIER 1 as follows:

ADDED callouts to indicate the work associated with the Compressed Air Enclosure being in Option 3.

On NAVFAC Dwg. No. 12936771 (E-112)

CHANGE E-112 CATHODIC PROTECTION PILE PLAN as follows:

ADDED callout to indicate the work that is included in Option 1.

On NAVFAC Dwg. No. 12936772 (E-113)

CHANGE E-113 GROUNDING PLAN – PIER WEST as follows:

ADDED callout to indicate the work that is included in Option 1 and modifications to the work if Option

1 is not executed.

On NAVFAC Dwg. No. 12936773 (E-114)

CHANGE E-114 GROUNDING PLAN – PIER EAST as follows:

ADDED Keynote 10 to indicate the work that is included in Option 3.

On NAVFAC Dwg. No. 12936774 (E-115)

CHANGE E-115 LIGHTNING PROTECTION PLAN – PIER WEST as follows:

ADDED ”-Option 1” to the view title to indicate the work in the view is included in Option 1.

On NAVFAC Dwg. No. 12936775 (E-116)

CHANGE E-116 LIGHTNING PROTECTION PLAN – PIER EAST as follows:

ADDED Keynote 7 to indicate the work related to the Compressed Air Enclosure is included in Option 3.

On NAVFAC Dwg. No. 12936776 (E-401)

CHANGE E-401 SUBSTATION P1W PART PLAN & ELEVATION as follows:

ADDED ”-Option 1” to the view titles to indicate the work in the views are included in Option 1.

On NAVFAC Dwg. No. 12936777 (E-402)

CHANGE E-402 SUBSTATION P1E PART PLAN & ELEVATION as follows:

ADDED Lighting Control Cabinet P1E-LCC to provide lighting control for Pole LC2.

On NAVFAC Dwg. No. 12936778 (E-403)

CHANGE E-403 SUBSTATION GROUNDING PART PLANS as follows:

ADDED ”-Option 1” to the Substation P1W part plan view title to indicate the work in the view is included in Option 1.

On NAVFAC Dwg. No. 12936779 (E-404)

CHANGE E-404 SUBSTATION P1W VAULT PART PLAN & ELEVATION as follows:

On NAVFAC Dwg. No. 12936782 (E-502)

CHANGE E-502 15KV SWITCHGEAR STRUCTURE DETAILS as follows:

ADDED Keynote 1 to indicate the work that is included in Option 1.

On NAVFAC Dwg. No. 12936789 (E-509)

CHANGE E-509 HIGH MAST LIGHTING DETAILS as follows:

REVISED Detail C2 to modify Lighting Pole LC2 for covering the pier up to Bent 30 if Option 1 is not executed, which would eliminate Lighting Pole LC1.

REVISED Detail A1 to clarify the quantity of fixtures per high mast lighting pole.

On NAVFAC Dwg. No. 12936791 (E-511)

CHANGE E-511 SUBSTATION P1W SWITCHGEAR ELEVATIONS as follows:

On NAVFAC Dwg. No. 12936792 (E-512)

CHANGE E-512 MISCELLANEOUS DETAILS – SHEET 1 OF 2 as follows:

REVISED Details A3 & B3 and added Keynote 3 to show required work for Lighting Control Cabinet

P1E-LCC and modify work required for Lighting Control Cabinet P1W-LCC.

On NAVFAC Dwg. No. 12936793 (E-513)

CHANGE E-513 MISCELLANEOUS DETAILS – SHEET 2 OF 2 as follows:

ADDED ”-Option 3” to the Detail C1 & C2 view titles to indicate the work in the views are included in

Option 3.

On NAVFAC Dwg. No. 12936794 (E-514)

CHANGE E-514 HEAT TRACE CABINET & DETAILS as follows:

ADDED Keynotes 2-5 to modify the work if Option 1 is not executed.

On NAVFAC Dwg. No. 12936795 (E-601)

CHANGE E-601 PRIMARY & DEMOLITION ONE LINE DIAGRAM as follows:

ADDED General Sheet Note 4 to modify the work if Option 1 is not executed.

On NAVFAC Dwg. No. 12936796 (E-602)

CHANGE E-602 PIER ONE LINE DIAGRAM - EAST PRIMARY & DEMOLITION ONE LINE

DIAGRAM as follows:

REVISED Panel P1E-IP-MDP to include breaker and feeder for Panel P1E-LCC.

REVISED Substations P1E-SPA & P1E-SPB to modify the phase loss relay connection in accordance with USCG Electrical Shore Ties CSTO Rev B.

On NAVFAC Dwg. No. 12936797 (E-603)

CHANGE E-603 PIER ONE LINE DIAGRAM - WEST PRIMARY & DEMOLITION ONE LINE

DIAGRAM as follows:

ADDED ”-Option 1” to the view title to indicate the work in the view is included in Option 1.

REVISED Substations P1W-SPA & P1W-SPB to modify the phase loss relay connection in accordance with USCG Electrical Shore Ties CSTO Rev B.

On NAVFAC Dwg. No. 12936798 (E-604)

CHANGE E-604 COMMUNICATIONS ONE LINE DIAGRAM as follows:

ADDED callout to indicate the extent of work to be included in Option 1.

On NAVFAC Dwg. No. 12936799 (E-605)

CHANGE E-605 MANHOLE SCHEDULE & FOLDOUT DIAGRAMS as follows:

ADDED callouts to indicate the extent of work to be included in Option 1.

On NAVFAC Dwg. No. 12936800 (E-606)

CHANGE E-606 MINI POWER CENTER PANEL SCHEDULES as follows:

ADDED Keynote 1 to indicate the extent of work to be included in Option 1.

On NAVFAC Dwg. No. 12936802 (E-608)

CHANGE E-608 HEAT TRACE ONE LINE DIAGRAM & SCHEDULES as follows:

REVISED Heat Trace Cable Schedule to indicate the work modifications if Option 1 is not executed.

On NAVFAC Dwg. No. 12936803 (E-609)

CHANGE E-609 LIGHTING CONTROL DIAGRAMS as follows:

REVISED Details A1, A3, B3, and C1 to utilize the modified Lighting Pole LC2, as shown on E-509, as the basis for the details.

On NAVFAC Dwg. No. 12936805 (E-611)

CHANGE E-611 SUBSTATION P1W SWITCHGEAR SCHEDULE as follows:

ADDED General Sheet Note 3 to indicate the work on the sheet is in Option 1.

On NAVFAC Dwg. No. 12936806 (E-612)

CHANGE E-612 SUBSTATION P1E PANEL SCHEDULES as follows:

REVISED Panel P1E-IP-MDP schedule for circuits serving Compressed Air Enclosure and Lighting

Control Cabinet P1E-LCC.

ADDED Panel schedules for P1E-LTG1 & P1E-LTG2, which are located in Lighting Control Cabinet

P1E-LCC.

On NAVFAC Dwg. No. 12936807 (E-613)

CHANGE E-613 SUBSTATION P1W PANEL SCHEDULES as follows:

ADDED Keynote 1 to indicate the work to be included in Option 1.

REVISED Panel schedules for panels P1W-LTG1 & P1W-LTG2 for modified names and removal of

Lighting Pole LC2 loads.

On NAVFAC Dwg. No. 12936808 (E-614)

CHANGE E-614 FEEDER SCHEDULE – SHEET 1 OF 2 as follows:

REVISED schedule to clarify the feeder modifications for the Bid Options.

On NAVFAC Dwg. No. 12936809 (E-615)

CHANGE E-615 FEEDER SCHEDULE – SHEET 2 OF 2 as follows:

REVISED schedule to clarify the feeder modifications for the Bid Options.

SPECIFICATIONS

Specification Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

Paragraph 1.5 SPECIAL ENVIRONMENTAL REQUIREMENTS

DELETE the following:

“Prior to commencement of dredging, Contractor will survey the dredge area to estimate the amount of shellfish present. Contractor will relocate shellfish if required by RIDEM and as noted in Project permits.”

ADD the following:

"Refer to Section 35 20 23 DREDGING for requirements related to decanting and management of dredged material."

Specification Section 03 30 00 CAST IN PLACE CONCRETE

ADD Item “f. Pipe Piles” to paragraph 1.1 SCOPE OF WORK

Specification Section 03 31 29 MARINE CONCRETE WITH SERVICE LIFE MODELING

Paragraph 1.2 DEFINITIONS

DELETE second sentence of Item q. in its entirety

Specification Section 35 20 23 DREDGING

Paragraph 3.3.7 DREDGING OPERATIONS

ADD “Item b. The Contractor will load all dredged material onto a deck barge equipped with perimeter bin walls or jersey barriers. All barge scuppers and drain openings must be lined with filter fabric to ensure pervious containment. Dredged material shall undergo dewatering on the barge or at an authorized upland location adjacent to the project area for a minimum of 8 to 12 hours prior to off-loading. During off-loading at the nearshore transfer area, the Contractor will utilize spill aprons to prevent dredged material from discharging or falling back into waters of the United States. If the receiving landfill requires sediment modification for transport or disposal, the Contractor will amend the fill material directly on the barge prior to off-loading.”

ADD “Item c. The Contractor will place all dredged material in a self-contained, upland disposal site. The

Contractor will maintain the upland disposal site to prevent the discharge of dredged material and associated effluent into waters of the United States.”

Appendix D - Environmental Concurrence and Project Permit Documents (With Placeholders)

ADD RIDEM Rhode Island Pollutant Discharge Elimination System Construction General Permit (issued

July 8, 2026).

ADD Updated Stormwater Management Plan for the Proposed USCG OCR Homeport Initiative OPC Pier

(dated December 19, 2026 and Revised May 18, 2026).

ADD Memorandum of Agreement between Commander, Navy Region Mid-Atlantic and Naval Station

Newport and United States Coast Guard and the Rhode Island State Historic Preservation Officer.

Attachment H – Bid Price Schedule

ADD Revised Bid Price Schedule - USCG OPC Pier Price Proposal Form REV 5

6. Updated Wage Determination (RI20260001 07/30/2026) (Enclosed)

"General Decision Number: RI20260001 07/30/2026

State: Rhode Island

Construction Types: Building, Heavy and Highway

Counties: Rhode Island Counties of

Bristol, Kent, Newport, Providence and

Washington

Includes Marine Construction Projects

Modification Number Publication Date

2 01/30/2026

3 05/18/2026

4 07/30/2026

ASBE0006-006 09/01/2024

Rates Fringes

HAZARDOUS MATERIAL HANDLER (INCLUDES PREPARATION,

WETTING, STRIPPING, REMOVAL SCRAPPING, VACUUMING,

BAGGING & DISPOSING OF ALL INSULATION MATERIALS,

WHETHER THEY CONTAIN ASBESTOS OR NOT, FROM

MECHANICAL SYSTEMS).................................$ 49.91 36.63

ASBE0006-008 09/01/2024

ASBESTOS WORKER/INSULATOR (INCLUDES APPLICATION OF

ALL INSULATING MATERIALS, PROTECTIVE COVERINGS,

COATINGS & FINISHES TO ALL TYPES OF MECHANICAL

SYSTEMS)............................................$ 49.91 36.63

BOIL0029-001 01/01/2025

BOILERMAKER.........................................$ 50.62 28.82

BRRI0003-001 06/01/2022

BRICKLAYER, STONEMASON, POINTER, CAULKER & CLEANER..$ 46.86 29.14

BRRI0003-002 09/01/2022

MARBLE SETTER, TERRAZZO WORKER & TILE SETTER........$ 46.54 30.34

BRRI0003-003 09/01/2022

MARBLE, TILE & TERRAZZO FINISHER....................$ 38.78 29.61

CARP0330-001 06/02/2025

DIVER (WHEN NOT DIVING OR TENDING THE DIVER, THE

DIVER AND DIVER TENDER SHALL RECEIVE THE PILEDRIVER

RATE. DIVER TENDERS SHALL RECEIVE $1.00 PER HOUR

ABOVE THE PILE DRIVER RATE WHEN TENDING THE DIVER.)

...................................................$ 60.83 30.50

DIVER TENDER (WHEN NOT DIVING OR TENDING THE DIVER,

THE DIVER AND DIVER TENDER SHALL RECEIVE THE

PILEDRIVER RATE. DIVER TENDERS SHALL RECEIVE $1.00

PER HOUR ABOVE THE PILE DRIVER RATE WHEN TENDING

THE DIVER.) ......................................$ 48.68 30.50

CARPENTER: INCLUDES SOFT FLOOR LAYER (WORK ON

FREE-STANDING STACKS, CONCRETE SILOS & PUBLIC

UTILITY ELECTRICAL POWER HOUSES, WHICH ARE OVER 35

FT. IN HEIGHT WHEN CONSTRUCTED: $.50 PER HOUR

ADDITIONAL. WORK ON EXTERIOR CONCRETE SHEAR WALL

GANG FORMS, 45 FT. OR MORE ABOVE GROUND ELEVATION

OR ON SETBACK: $.50 PER HOUR ADDITIONAL.)...........$ 47.88 30.50

PILEDRIVER (WORK ON FREE-STANDING STACKS, CONCRETE

SILOS & PUBLIC UTILITY ELECTRICAL POWER HOUSES,

WHICH ARE OVER 35 FT. IN HEIGHT WHEN CONSTRUCTED:

$.50 PER HOUR ADDITIONAL. WORK ON EXTERIOR CONCRETE

SHEAR WALL GANG FORMS, 45 FT. OR MORE ABOVE GROUND

ELEVATION OR ON SETBACK: $.50 PER HOUR ADDITIONAL.

THE DESIGNATED PILEDRIVER, KNOWN AS THE ""MONKEY"":

$1.00 PER HOUR ADDITIONAL...........................$ 41.53 29.35

WELDER (WORK ON FREE-STANDING STACKS, CONCRETE

SILOS & PUBLIC UTILITY ELECTRICAL POWER HOUSES,

WHICH ARE OVER 35 FT. IN HEIGHT WHEN CONSTRUCTED:

$.50 PER HOUR ADDITIONAL. WORK ON EXTERIOR

CONCRETE SHEAR WALL GANG FORMS, 45 FT. OR MORE

ABOVE GROUND ELEVATION OR ON SETBACK: $.50 PER HOUR

ADDITIONAL.) .......................................$ 48.68 30.50

CARP1121-002 04/21/2025

MILLWRIGHT..........................................$ 45.72 31.50

ELEC0099-002 06/01/2025

ELECTRICIAN (WORK OF A HAZARDOUS NATURE, OR WHERE

THE WORK HEIGHT IS 30 FT. OR MORE FROM THE FLOOR,

EXCEPT WHEN WORKING OSHA-APPROVED LIFTS: 20% PER

HOUR ADDITIONAL. WORK IN TUNNELS BELOW GROUND LEVEL

IN COMBINED SEWER OUTFALL: 20% PER HOUR

ADDITIONAL.)........................................$ 56.11 24.74

TELEDATA SYSTEM INSTALLER (WORK OF A HAZARDOUS

NATURE, OR WHERE THE WORK HEIGHT IS 30 FT. OR MORE

FROM THE FLOOR, EXCEPT WHEN WORKING OSHA-APPROVED

LIFTS: 20% PER HOUR ADDITIONAL. WORK IN TUNNELS

BELOW GROUND LEVEL IN COMBINED SEWER OUTFALL: 20%

PER HOUR ADDITIONAL.)...............................$ 42.09 19.71

ELEV0039-001 01/01/2025

ELEVATOR MECHANIC (ADDTIONAL FRINGE TO BE PAID A.

PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY;

INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY;

THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING

DAY; AND CHRISTMAS DAY. B. EMPLOYER CONTRIBUTES 8%

BASIC HOURLY RATE FOR 5 YEARS OR MORE OF SERVICE OF

6% BASIC HOURLY RATE FOR 6 MONTHS TO 5 YEARS OF

SERVICE AS VACATION PAY CREDIT.)....................$ 64.52 38.44

ENGI0057-001 12/01/2025

POWER EQUIPMENT OPERATOR: POWER PLANTS, SEWER

TREATMENT PLANTS, PUMPING STATIONS, TUNNELS,

CAISSONS, PIERS, DOCKS, BRIDGES, WIND TURBINES,

SUBTERRANEAN & OTHER MARINE AND HEAVY CONSTRUCTION

WORK: GROUP 1: CRANES,…