24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.13.24 to 08.15.24.pdf

PDF 40 MB Posted

Attached to
Design-Bid-Build, USCG Offshore Patrol Cutters (OPC) Homeport Pier, Naval Station Newport, Newport RI
Solicitation number
N4008526R0001
Issued by

About this file

This is a Pile Driving Summary Table documenting the installation of bulkhead piles at Naval Station Newport, Rhode Island. The document records data for 45 steel pipe piles (18-inch outer diameter with 0.5-inch wall thickness, open-ended) driven between July 26 and August 15, 2024. Each pile entry includes specifications such as driven depth (ranging from 26 to 48 feet), tip elevation (-30.25 feet), top elevation (42.50 feet), pile length (10.25 feet), end-of-drive stroke (16.75 feet), working grade (40.50 feet), cut-off length (12.25 feet), and final blow count (8-10 blows). The project is associated with the USCG Offshore Patrol Cutters (OPC) Homeport Pier development at the Newport location.

The work was performed by Skanska (contractor) for NOAA OMAO (client) with Geosciences Testing and Research, Inc. providing on-site representation through GTR representative J. Roth. Most piles were vibration-driven on dates between July 26 and August 14, 2024, with final drive completion occurring on August 13-15, 2024. Several piles (S25-S38, S81-S87) were noted as "Not Vibed" and processed on August 14-15, 2024. The documentation indicates pile driving operations commenced on August 8 with initial mushrooming of the top requiring cutting and completion by August 14. This table serves as technical documentation of construction completion and pile specifications for the Naval Station Newport coastal marine infrastructure project.

View the file

Other files

File Type Posted
USCG OPC Pier Amendment 0009 Drawings.pdf PDF
2026-0816-HAI-USCG Homeport OPC Pier-Geotech Engineering Report Rev 2.pdf PDF
Amendment 0009 USCG OPC.pdf PDF
Updated Attachment H - USCG OPC Pier Price Proposal Form REV 5.docx DOCX document
Amendment 0008 USCG OPC.pdf PDF
Amendment 0007 SPC USCG OPC Pier Appendix D (With Placeholders).pdf PDF
Updated Attachment H - USCG OPC Pier Price Proposal Form REV 6.docx DOCX document
USCG OPC Pier Amendment 0008 Drawings.pdf PDF
USCG OPC Pier Amendment 007 Drawings.pdf PDF
Amendment 0007 USCG OPC.pdf PDF
Attachment Z - Pier 1 - Amendment 006 Drawings.pdf PDF
Appendix A - Telecom Room Photos.pdf PDF
Updated Attachment H - UCCG OPC Pier Price Proposal Form REV 4.docx DOCX document
Amendment 0006 USCG OPC.pdf PDF
24.168 NOAA OMAO Prime Pier Pile Driving Summary Report.pdf PDF
Pier Pile Plan.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.26.24 to 08.30.24 (1).pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.22.24 to 07.26.24.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.15.24 to 07.19.24.pdf PDF
Attachment Y - Appendix A Record drawing 11836 125 Submarine Cable Relocation.pdf PDF
SUB-0123 Interim PDA and Test Pile Logs - Trestle Piles 10B 14B.pdf PDF
SUB-0TBD Interim PDA and Test Pile Logs For Trestle Pile 17B.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.26.24 to 08.30.24.pdf PDF
Updated Attachment H - UCCG OPC Pier Price Proposal Form REV 3.docx DOCX document
SUB-0105 Trestle Piles 4C 6B - PDA and Test Pile Logs.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.20.24 to 08.23.24.pdf PDF
24.107 NOAA OMAO Ship & Support Facility Relocation Newport RI - PDA Report - Pier Bent 19.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 06.25.24 to 06.27.24.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.31.24 to 08.01.24.pdf PDF
SUB-0284 PDA49B_A.pdf PDF
SUB-0262 Interim PDA Test Pile Logs for Pier Piles - Bent 35 B - A.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.07.24 to 08.08.24.pdf PDF
Trestle Summary.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 08.20.24 to 08.23.24 (1).pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.01.24 - 07.02.24.pdf PDF
Bulkhead Pile Plan.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 09.03.24 to 09.06.24.pdf PDF
Attachment W - Pier 1 - Amendment 005 Drawings.pdf PDF
24.168 NOAA OMAO Bulkhead Pile Driving Summary Table 07.11.24.pdf PDF
24.107 NOAA OMAO Ship Support Facility Relocation Newport RI - PDA Report - Pier Bent 25 and 27.pdf PDF
NOAA OMAO Survey Reports 100 Percent Pre-Final Submittal 04072022.pdf PDF
Amendment 0005 USCG OPC.pdf PDF
Attachment X - Appendix A Record Drawing 12819 135 Submarine Cable.pdf PDF
Attachment U - Appendix A - Pier 1 Extension 1968.pdf PDF
Attachment V - Pier 1 - Amendment 004 Drawings.pdf PDF
Updated Attachment K - WD RI20260001 05-18-2026.pdf PDF
Amendment 0004 USCG OPC.pdf PDF
Attachment T - REF(m) Existing Pier 1 Drawings 1 of 2.pdf PDF
Attachment C - Construction Experience Project Data Sheet.docx DOCX document
Attachment E - Historical Small Business Utilization.docx DOCX document
Show 40 more

Latest 50 of 90 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DATE:

PROJECT LOCATION:

CLIENT: CONTRACTOR:

GTR REP PILE INFO:

S105 26-Jul-24 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 40 8 - 9 S104 26-Jul-24 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 32 8 - 9 S103 26-Jul-24 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 30 8 - 9 S102 26-Jul-24 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 32 8 - 9 S101 26-Jul-24 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 34 8 - 9 S100 26-Jul-24 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 40 8 - 9 S99 26-Jul-24 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 26 8 - 9 S98 26-Jul-24 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 38 8 - 9 S97 26-Jul-24 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 38 8 - 9 S96 26-Jul-24 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 40 8 - 9 S95 26-Jul-24 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 32 8 - 9 S94 26-Jul-24 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 38 8 - 9 S93 29-Jul-24 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 36 8 - 9 S92 29-Jul-24 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 36 8 - 9 S91 29-Jul-24 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 28 8 - 9 S90 29-Jul-24 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 28 8 - 9 S89 29-Jul-24 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 34 8 - 9 S88 29-Jul-24 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 44 8 - 9 S87 Not Vibed 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 36 8 - 9 S86 Not Vibed 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 38 8 - 9 S85 Not Vibed 13-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 48 8 - 9 S115 26-Jul-24 14-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 30 8 - 9 S114 26-Jul-24 14-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 30 8 - 9 S113 26-Jul-24 14-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 34 8 - 9 S112 26-Jul-24 14-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 26 8 - 9 S111 26-Jul-24 14-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 28 8 - 9 S110 26-Jul-24 14-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 38 8 - 9 S109 26-Jul-24 14-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 26 8 - 9 S108 26-Jul-24 14-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 28 8 - 9 S107 26-Jul-24 14-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 32 8 - 9 S106 26-Jul-24 14-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 34 8 - 9 S84 Not Vibed 14-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 38 8 - 9 S81 Not Vibed 14-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 40 8 - 9 S38 Not Vibed 15-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 36 9 - 10 S37 Not Vibed 15-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 30 8 - 9

PILE

NO.

DRIVEN

DEPTH

(feet)

TIP

ELEVATION

(feet)

TOP

ELEVATION

(feet)

PILE

LENGTH

(feet)

EOD

STROKE

(feet)

WORKING

GRADE

(feet)

FINAL DRIVE

DATE

VIBRATION

DRIVE DATE

CUT-OFF

LENGTH

GTR JOB # 24.168

GEOSCIENCES TESTING AND RESEARCH, INC.

55 Middlesex Street, Suite 225, North Chelmsford, MA, Phone: (978) 251-9395 Fax: (978) 251-9396

COMMENTS

PILE DRIVING SUMMARY

J. Roth Steel 18-inch O.D. X 0.5-inch wall open-ended Pipe

Newport RI Naval Station Coastal Marine

NOAA OMAO

Skanska

15-Aug-24

CUT-OFF

ELEVATION

(feet)

BLOW

COUNT

FINAL FOOT

BULKHEAD PILES

Started drive 8/8, top mushroomed and needed to be cut, finished 8/14

DATE:

PROJECT LOCATION:

CLIENT: CONTRACTOR:

GTR REP PILE INFO:

PILE

NO.

DRIVEN

DEPTH

(feet)

TIP

ELEVATION

(feet)

TOP

ELEVATION

(feet)

PILE

LENGTH

(feet)

EOD

STROKE

(feet)

WORKING

GRADE

(feet)

FINAL DRIVE

DATE

VIBRATION

DRIVE DATE

CUT-OFF

LENGTH

GTR JOB # 24.168

GEOSCIENCES TESTING AND RESEARCH, INC.

55 Middlesex Street, Suite 225, North Chelmsford, MA, Phone: (978) 251-9395 Fax: (978) 251-9396

COMMENTS

PILE DRIVING SUMMARY

J. Roth Steel 18-inch O.D. X 0.5-inch wall open-ended Pipe

Newport RI Naval Station Coastal Marine

NOAA OMAO

Skanska

15-Aug-24

CUT-OFF

ELEVATION

(feet)

BLOW

COUNT

FINAL FOOT

BULKHEAD PILES

S36 Not Vibed 15-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 30 8 - 9 S35 Not Vibed 15-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 34 8 - 9 S34 Not Vibed 15-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 44 8 - 9 S33 Not Vibed 15-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 38 8 - 9 S32 Not Vibed 15-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 38 8 - 9 S31 Not Vibed 15-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 40 8 - 9 S30 Not Vibed 15-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 38 8 - 9 S29 Not Vibed 15-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 38 8 - 9 S28 Not Vibed 15-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 34 8 - 9 S27 Not Vibed 15-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 44 8 - 9 S26 Not Vibed 15-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 40 8 - 9 S25 Not Vibed 15-Aug-24 12.25 47 42.50 10.25 -30.25 16.75 40.50 34 8 - 9