This document is a Task Assignment Change Order (TACO) issued by the State of Florida Department of Environmental Protection (FDEP) to Arcadis U.S. Inc. for remediation work at the Rivergate Drycleaners facility (Facility ID 26-9501255; ERIC_5413) located in Port St. Lucie, St. Lucie County. The change order is identified as DC031B-1 under Contract Number HW680 and was executed on March 19, 2024, with authorization from Teresa Booeshaghi (FDEP Secretary or Designee) and Gus Suarez (Arcadis Contract Manager).
The change order extends the task assignment completion date by 63 days, from September 20, 2024, to November 22, 2024, to accommodate the delayed delivery of remedial equipment necessary for system installation. There is no cost increase associated with this extension; the total task assignment value remains $158,374.35, comprised of a fixed unit rate of $157,174.35 and cost reimbursement of $1,200.00 for utility invoices. The scope of work authorizes Arcadis to install a soil vapor extraction system according to the approved Interim Source Removal Work Plan. Deliverables include construction completion and documentation, property purchase documentation, system startup/as-built reports, and first quarter operations and maintenance activities, with corresponding invoice amounts totaling $158,374.35. The extension was necessitated by Arcadis awaiting delivery of new remedial equipment for installation.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department’s Project Manager: Department’s Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number) Project Name:
4. There are no changes to the TA compensation.
The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. There are no changes to the TA Expiration Date.
The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. There are no changes to the Attachments.
Attachment ___ is replaced with Attachment -____.
7. No Additional Changes.
Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
DC031B 1 HW680
This change order authorizes a time extension of sixty-three days for equipment delivery.
Theresa Pepe 850-245-8966 Arcadis U.S. Inc.
Gus Suarez 813-205-4703
ERIC_5413
Rivergate Drycleaners
$ 157,174.35 $ 157,174.35
$ 1,200.00 1200
$ 158,374.35 $ 158,374.35
09/20/2024 11/22/2024 63
1 1 1
Arcadis U.S. Inc.
Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2024.03.19 14:27:37 -04'00'
Teresa Booeshaghi
Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2024.03.19 13:58:16 -04'00'
3/19/2024
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: Negotiation File Rivergate Drycleaners Facility ID No. 26-9501255; ERIC_5413 Port St. Lucie, St. Lucie County FROM: Theresa C. Pepe, Project Manager SUBJECT: Task Assignment Change Order DC031B-1 (HW680) DATE: March 19, 2024
Arcadis is awaiting delivery of the new remedial equipment for installation. A time extension of sixty days-three will allow completion of the work. For additional information, see the March 15, 2023, biweekly update from Doug McGlone of Arcadis.
This change order adds sixty-three days to the completion date. There is no cost change to the task assignment. Arcadis may invoice according to the attached schedule.
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor�st �s Project Manager: ontractor�s t�s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
HW680
DC031B Completion September 20, 2024
This Task Assignment authorizes Arcadis to install a soil vapor extraction system according to the approved Interim Source Removal (ISR) Work Plan.
The payment of utility invoices is the only portion of this Task Assignment that is Cost Plus.
Theresa Pepe 850-245-8966 Contractor Arcadis U.S. Inc. Contractor
Contractor Gus Suarez Contractor 813-205-4703
ERIC_5413
1193 SE Port St. Lucie Blvd, Port St. Lucie, St. Lucie County
Rivergate Drycleaners
Contractor Contractor
$ 157,174.35
$ 1,200.00
$ 158,374.35
Scope of Work
Arcadis U.S. Inc.
Contractor
Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2023.10.23 14:44:01 -04'00'
Teresa Booeshaghi
Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2023.10.23 12:31:34 -04'00'
10/23/2023
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Construction Completion & Documentation 03/29/2024
Submittal of Property Purchase Documentation 04/05/2024
System Startup/As-Built Reports 04/30/2024
First Quarter O&M email summary/IDW manifest 07/31/2024
First Quarter Utility Invoices 08/16/2024
FDEP approval of Construction Completion & Documentation $ 79,224.77
FDEP approval of Equipment Purchase with paid invoice;Property reporting form and component list $ 54,900.00
FDEP approval of System Startup/As-Built Reports $ 9,097.79
FDEP approval of First Quarter O&M email summary/IDW manifest/Project Management $ 13,891.79
FDEP approval of First Quarter Utility Invoices Utilities (Cost Plus Fixed Fee) = not to exceed $1,200.00 Utilities Handling Fee = $60.00
$ 1,260.00
$ 158,374.35
HW680
DC031B