Tabulation of Bids - MS NP NATR 3N18 3H27 ETC - Signed.pdf
PDF 735 KB Posted
- Attached to
- MS NP NATR 3N18 3H27 ETC - Geotechnical, Pavement Rehabilitation, and Structural Repairs
- Solicitation number
- 693C73-25-B-000003
About this file
This Tabulation of Bids document details the bid results for a federal highway infrastructure project on the Natchez Trace Parkway. Three contractors submitted bids for geotechnical, pavement rehabilitation, and structural repairs between mile posts 121 and 204: Estes Bros. Const., Inc. ($32,428,068.10), Central Southern Construction Corp. ($35,961,600.00), and ERon Road Construction LLC ($42,249,777.00). The project, solicited under number 693C73-25-B-000003 by the Department of Transportation Federal Highway Administration, covers multiple counties in Mississippi (Choctaw, Webster, Madison, Leake, Attala) and involves extensive roadway and structural work including excavation, pavement milling, concrete repairs, erosion control, and infrastructure improvements.
The bid tabulation includes detailed line-item pricing across 59 different categories, ranging from mobilization and construction surveys to specific infrastructure repairs like bridge railing replacement, concrete overlay, and geosynthetic reinforcement. Estes Bros. Const., Inc. submitted the lowest bid, which is 30.21% below the engineer's original estimate of $46,468,273.00. The contract appears to be a base schedule type with work scheduled to be performed across various infrastructure elements, suggesting a comprehensive roadway rehabilitation project for the Natchez Trace Parkway.
View the file
Other files
Show 40 more
Latest 50 of 53 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 12/20/24
1 out of 9
Project No: MS NP NATR 3N18 3H27 ETC
Project Name: Geotechnical, Pavement Rehabilitation, and Structural Repairs between MP 121 and MP
204 (Phase 2)
Schedule: A
Schedule Type: Base
Solcitation No: 693C73-25-B-000003
Division: Eastern Federal Lands
State: MS County: Choctaw, Webster, Madison, Leake, Attala
Federal Land: Natchez Trace Parkway Opened at: Ashburn, Va
Opened by: Rubrena Johnson
Date: 12/20/24
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Estes Bros. Const., Inc. $32,428,068.10 126 Sugar Run Road Jonesville, VA 24263
Central Southern Construction Corp. $35,961,600.00 119 Sewald Street Jacksonville, FL 32204
ERon Road Construction LLC $42,249,777.00 11938 Mayfield Road Building 1 Chardon, OH 44024
Engineer's Estimate $46,468,273.00
Senior Technical Specialist 12/20/2025
Shirley A. Anderson
Estes, Bros., Const., Inc. 3/26/2025
2 out of 9
Project No: MS NP NATR 3N18 3H27 ETC
Project Name: Geotechnical, Pavement Rehabilitation, and Structural Repairs between MP 121 and MP
204 (Phase 2)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0100 15101-0000 MOBILIZATION
Estes Bros. Const., Inc. Lump Sum $4,851,490.36 Central Southern Construction Corp. Lump Sum $3,750,000.00 ERon Road Construction LLC Lump Sum $5,379,877.00 Engineer's Estimate ALL LPSM Lump Sum $4,157,948.00
A0110 15201-0000 CONSTRUCTION SURVEY AND STAKING
Estes Bros. Const., Inc. Lump Sum $567,872.36 Central Southern Construction Corp. Lump Sum $1,275,000.00 ERon Road Construction LLC Lump Sum $607,542.00 Engineer's Estimate ALL LPSM Lump Sum $1,090,000.00
A0120 15401-0000 CONTRACTOR TESTING
Estes Bros. Const., Inc. Lump Sum $1,066,872.36 Central Southern Construction Corp. Lump Sum $1,495,000.00 ERon Road Construction LLC Lump Sum $922,543.00 Engineer's Estimate ALL LPSM Lump Sum $1,010,000.00
A0130 15705-0100 SOIL EROSION CONTROL, SILT FENCE
Estes Bros. Const., Inc. $7.05 $124,785.00 Central Southern Construction Corp. $5.00 $88,500.00 ERon Road Construction LLC $21.00 $371,700.00 Engineer's Estimate 17,700 LNFT $11.00 $194,700.00
A0140 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
Estes Bros. Const., Inc. $8.00 $70,800.00 Central Southern Construction Corp. $5.00 $44,250.00 ERon Road Construction LLC $24.00 $212,400.00 Engineer's Estimate 8,850 LNFT $13.50 $119,475.00
A0150 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
Estes Bros. Const., Inc. Lump Sum $309,872.36 Central Southern Construction Corp. Lump Sum $55,000.00 ERon Road Construction LLC Lump Sum $126,099.00 Engineer's Estimate ALL LPSM Lump Sum $20,000.00
3 out of 9
Project No: MS NP NATR 3N18 3H27 ETC
Project Name: Geotechnical, Pavement Rehabilitation, and Structural Repairs between MP 121 and MP
204 (Phase 2)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0160 20301-2300 REMOVAL OF SIGN/MARKER
Estes Bros. Const., Inc. $150.00 $27,750.00 Central Southern Construction Corp. $100.00 $18,500.00 ERon Road Construction LLC $56.00 $10,360.00 Engineer's Estimate 185 EACH $510.00 $94,350.00
A0170 20301-2400 REMOVAL OF SIGN
Estes Bros. Const., Inc. $300.00 $7,200.00 Central Southern Construction Corp. $250.00 $6,000.00 ERon Road Construction LLC $429.00 $10,296.00 Engineer's Estimate 24 EACH $345.00 $8,280.00
A0180 20302-0150 REMOVAL OF BRIDGE RAILING (5570-120P SOUTHEAST SECTION)
Estes Bros. Const., Inc. $100.00 $2,200.00 Central Southern Construction Corp. $450.00 $9,900.00 ERon Road Construction LLC $536.00 $11,792.00 Engineer's Estimate 22 LNFT $170.00 $3,740.00
A0190 20305-1000 REMOVAL OF CONCRETE (STR 5570-099P BRIDGE SHOULDER, 2-INCH DEPTH)
Estes Bros. Const., Inc. $4,500.00 $45,000.00 Central Southern Construction Corp. $1,000.00 $10,000.00 ERon Road Construction LLC $1,141.00 $11,410.00 Engineer's Estimate 10 CUYD $2,375.00 $23,750.00
A0200 20315-0000 SAWCUTTING PAVEMENT
Estes Bros. Const., Inc. $15.00 $2,925.00 Central Southern Construction Corp. $50.00 $9,750.00 ERon Road Construction LLC $13.00 $2,535.00 Engineer's Estimate 195 LNFT $14.00 $2,730.00
A0210 20401-0000 ROADWAY EXCAVATION
Estes Bros. Const., Inc. $21.00 $913,500.00 Central Southern Construction Corp. $25.00 $1,087,500.00 ERon Road Construction LLC $58.00 $2,523,000.00 Engineer's Estimate 43,500 CUYD $70.00 $3,045,000.00
4 out of 9
Project No: MS NP NATR 3N18 3H27 ETC
Project Name: Geotechnical, Pavement Rehabilitation, and Structural Repairs between MP 121 and MP
204 (Phase 2)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0220 20701-0500 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE E
Estes Bros. Const., Inc. $3.21 $61,953.00 Central Southern Construction Corp. $5.00 $96,500.00 ERon Road Construction LLC $5.00 $96,500.00 Engineer's Estimate 19,300 SQYD $11.00 $212,300.00
A0230 20703-0000 GEOGRID (TYPE V)
Estes Bros. Const., Inc. $4.05 $105,300.00 Central Southern Construction Corp. $6.00 $156,000.00 ERon Road Construction LLC $7.00 $182,000.00 Engineer's Estimate 26,000 SQYD $11.50 $299,000.00
A0240 25501-1000 MECHANICALLY STABILIZED EARTH WALL, WELDED WIRE FACE (DEEP PATCH EMBANKMENT REPAIR)
Estes Bros. Const., Inc. $24.83 $489,151.00 Central Southern Construction Corp. $25.00 $492,500.00 ERon Road Construction LLC $15.00 $295,500.00 Engineer's Estimate 19,700 SQFT $55.00 $1,083,500.00
A0250 25510-0000 SELECT GRANULAR BACKFILL (#57 STONE)
Estes Bros. Const., Inc. $96.06 $1,835,706.60 Central Southern Construction Corp. $100.00 $1,911,000.00 ERon Road Construction LLC $158.00 $3,019,380.00 Engineer's Estimate 19,110 CUYD $120.00 $2,293,200.00
A0270 30101-4000 AGGREGATE BASE GRADING C OR D
Estes Bros. Const., Inc. $69.78 $322,383.60 Central Southern Construction Corp. $100.00 $462,000.00 ERon Road Construction LLC $90.00 $415,800.00 Engineer's Estimate 4,620 TON $85.00 $392,700.00
A0280 31302-0400 AGGREGATE-TOPSOIL COURSE, 4-INCH DEPTH
Estes Bros. Const., Inc. $22.45 $240,215.00 Central Southern Construction Corp. $50.00 $535,000.00 ERon Road Construction LLC $20.00 $214,000.00 Engineer's Estimate 10,700 SQYD $35.00 $374,500.00
5 out of 9
Project No: MS NP NATR 3N18 3H27 ETC
Project Name: Geotechnical, Pavement Rehabilitation, and Structural Repairs between MP 121 and MP
204 (Phase 2)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0300 40101-0500 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH NOMINAL MAXIMUM SIZE AGGREGATE, <0.3
MILLION ESAL (TYPE IV PAVEMENT ROUGHNESS, PG 67-22)
Estes Bros. Const., Inc. $292.00 $1,927,200.00 Central Southern Construction Corp. $300.00 $1,980,000.00 ERon Road Construction LLC $253.00 $1,669,800.00 Engineer's Estimate 6,600 TON $200.00 $1,320,000.00
A0320 40101-0900 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/4-INCH NOMINAL MAXIMUM SIZE AGGREGATE, <0.3
MILLION ESAL (PG 67-22)
Estes Bros. Const., Inc. $254.50 $1,145,250.00 Central Southern Construction Corp. $300.00 $1,350,000.00 ERon Road Construction LLC $254.00 $1,143,000.00 Engineer's Estimate 4,500 TON $270.00 $1,215,000.00
A0330 41201-0000 TACK COAT
Estes Bros. Const., Inc. $1,200.00 $42,000.00 Central Southern Construction Corp. $2,000.00 $70,000.00 ERon Road Construction LLC $1,268.00 $44,380.00 Engineer's Estimate 35 TON $1,900.00 $66,500.00
A0340 41301-0000 ASPHALT PAVEMENT MILLING (MICRO MILLING)
Estes Bros. Const., Inc. $28.85 $519,588.50 Central Southern Construction Corp. $10.00 $180,100.00 ERon Road Construction LLC $16.00 $288,160.00 Engineer's Estimate 18,010 SQYD $15.00 $270,150.00
A0350 41301-1200 ASPHALT PAVEMENT MILLING, 5-INCH DEPTH
Estes Bros. Const., Inc. $15.00 $412,500.00 Central Southern Construction Corp. $10.00 $275,000.00 ERon Road Construction LLC $13.00 $357,500.00 Engineer's Estimate 27,500 SQYD $40.00 $1,100,000.00
A0360 41801-1000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 1 (WITH STABILIZATION)
Estes Bros. Const., Inc. $163.13 $5,220,160.00 Central Southern Construction Corp. $180.00 $5,760,000.00 ERon Road Construction LLC $258.00 $8,256,000.00 Engineer's Estimate 32,000 SQYD $250.00 $8,000,000.00
6 out of 9
Project No: MS NP NATR 3N18 3H27 ETC
Project Name: Geotechnical, Pavement Rehabilitation, and Structural Repairs between MP 121 and MP
204 (Phase 2)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0370 41801-1000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 1
Estes Bros. Const., Inc. $121.90 $7,012,907.00 Central Southern Construction Corp. $130.00 $7,478,900.00 ERon Road Construction LLC $150.00 $8,629,500.00 Engineer's Estimate 57,530 SQYD $225.00 $12,944,250.00
A0380 55220-0000 REPAIR CONCRETE (DEEP, BRIDGE RAILING AND CURBS)
Estes Bros. Const., Inc. $3,500.00 $350,000.00 Central Southern Construction Corp. $7,100.00 $710,000.00 ERon Road Construction LLC $2,576.00 $257,600.00 Engineer's Estimate 100 SQYD $875.00 $87,500.00
A0390 55220-0000 REPAIR CONCRETE (TOP OF DECK OVER SHOULDERS AND LANES)
Estes Bros. Const., Inc. $400.00 $808,000.00 Central Southern Construction Corp. $1,000.00 $2,020,000.00 ERon Road Construction LLC $650.00 $1,313,000.00 Engineer's Estimate 2,020 SQYD $1,965.00 $3,969,300.00
A0400 55220-0000 REPAIR CONCRETE (DEEP, WINGWALL)
Estes Bros. Const., Inc. $4,500.00 $22,500.00 Central Southern Construction Corp. $1,000.00 $5,000.00 ERon Road Construction LLC $2,865.00 $14,325.00 Engineer's Estimate 5 SQYD $1,200.00 $6,000.00
A0410 55221-0000 REPAIR CONCRETE (DEEP, WINGWALL)
Estes Bros. Const., Inc. $3,000.00 $60,000.00 Central Southern Construction Corp. $1,700.00 $34,000.00 ERon Road Construction LLC $2,719.00 $54,380.00 Engineer's Estimate 20 CUYD $5,455.00 $109,100.00
A0420 55225-0000 CLEAN AND RESEAL JOINTS (SILICONE AND BACKER ROD, EXPANSION JOINTS)
Estes Bros. Const., Inc. $10.00 $35,000.00 Central Southern Construction Corp. $12.00 $42,000.00 ERon Road Construction LLC $35.00 $122,500.00 Engineer's Estimate 3,500 LNFT $35.00 $122,500.00
7 out of 9
Project No: MS NP NATR 3N18 3H27 ETC
Project Name: Geotechnical, Pavement Rehabilitation, and Structural Repairs between MP 121 and MP
204 (Phase 2)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0430 55235-0000 EXPANSION JOINTS (ASPHALTIC PLUG)
Estes Bros. Const., Inc. $450.00 $27,000.00 Central Southern Construction Corp. $500.00 $30,000.00 ERon Road Construction LLC $823.00 $49,380.00 Engineer's Estimate 60 LNFT $580.00 $34,800.00
A0440 55601-0500 BRIDGE RAILING, CONCRETE (5570-120P SOUTHEAST SECTION, REPLACE IN-KIND)
Estes Bros. Const., Inc. $730.00 $16,060.00 Central Southern Construction Corp. $1,000.00 $22,000.00 ERon Road Construction LLC $1,937.00 $42,614.00 Engineer's Estimate 22 LNFT $340.00 $7,480.00
A0450 55901-0000 MEMBRANE WATERPROOFING (PREFORMED MEMBRANE SYSTEM)
Estes Bros. Const., Inc. $196.62 $1,867,890.00 Central Southern Construction Corp. $221.00 $2,099,500.00 ERon Road Construction LLC $344.00 $3,268,000.00 Engineer's Estimate 9,500 SQYD $165.00 $1,567,500.00
A0460 56101-0000 STRUCTURAL CONCRETE INJECTION AND CRACK REPAIR (WINGWALL)
Estes Bros. Const., Inc. $236.50 $23,650.00 Central Southern Construction Corp. $300.00 $30,000.00 ERon Road Construction LLC $118.00 $11,800.00 Engineer's Estimate 100 LNFT $275.00 $27,500.00
A0470 56901-0000 CONCRETE OVERLAY (POLYERSTER POLYMER CONCRETE, 2-INCH DEPTH)
Estes Bros. Const., Inc. $646.47 $226,264.50 Central Southern Construction Corp. $631.00 $220,850.00 ERon Road Construction LLC $626.00 $219,100.00 Engineer's Estimate 350 SQYD $600.00 $210,000.00
A0480 57401-0000 GRS-IBS, GEOSYNTHETIC REINFORCEMENT
Estes Bros. Const., Inc. $650.01 $520,008.00 Central Southern Construction Corp. $400.00 $320,000.00 ERon Road Construction LLC $410.00 $328,000.00 Engineer's Estimate 800 SQYD $12.00 $9,600.00
8 out of 9
Project No: MS NP NATR 3N18 3H27 ETC
Project Name: Geotechnical, Pavement Rehabilitation, and Structural Repairs between MP 121 and MP
204 (Phase 2)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0490 60103-0020 CONCRETE, HEADWALL FOR 6-INCH PIPE CULVERT
Estes Bros. Const., Inc. $2,050.00 $102,500.00 Central Southern Construction Corp. $550.00 $27,500.00 ERon Road Construction LLC $2,473.00 $123,650.00 Engineer's Estimate 50 EACH $2,200.00 $110,000.00
A0500 60501-0000 STANDARD UNDERDRAIN SYSTEM
Estes Bros. Const., Inc. $45.94 $91,880.00 Central Southern Construction Corp. $100.00 $200,000.00 ERon Road Construction LLC $56.00 $112,000.00 Engineer's Estimate 2,000 LNFT $85.00 $170,000.00
A0510 60515-0000 UNDERDRAIN CLEANOUT (INSTALL WEEP HOLE FILTER)
Estes Bros. Const., Inc. $620.00 $26,040.00 Central Southern Construction Corp. $975.00 $40,950.00 ERon Road Construction LLC $410.00 $17,220.00 Engineer's Estimate 42 EACH $820.00 $34,440.00
A0520 61401-0000 LEAN CONCRETE BACKFILL
Estes Bros. Const., Inc. $450.00 $6,750.00 Central Southern Construction Corp. $750.00 $11,250.00 ERon Road Construction LLC $2,437.00 $36,555.00 Engineer's Estimate 15 CUYD $1,340.00 $20,100.00
A0530 62401-0300 FURNISHING AND PLACING TOPSOIL, 4-INCH DEPTH
Estes Bros. Const., Inc. $22.45 $228,990.00 Central Southern Construction Corp. $20.00 $204,000.00 ERon Road Construction LLC $10.00 $102,000.00 Engineer's Estimate 10,200 SQYD $12.50 $127,500.00
A0540 62501-0000 TURF ESTABLISHMENT
Estes Bros. Const., Inc. $8,500.00 $42,500.00 Central Southern Construction Corp. $15,000.00 $75,000.00 ERon Road Construction LLC $24,020.00 $120,100.00 Engineer's Estimate 5 ACRE $6,100.00 $30,500.00
9 out of 9
Project No: MS NP NATR 3N18 3H27 ETC
Project Name: Geotechnical, Pavement Rehabilitation, and Structural Repairs between MP 121 and MP
204 (Phase 2)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0550 62901-1000 ROLLED EROSION CONTROL PRODUCT, TYPE 3.B
Estes Bros. Const., Inc. $4.05 $38,272.50 Central Southern Construction Corp. $10.00 $94,500.00 ERon Road Construction LLC $7.00 $66,150.00 Engineer's Estimate 9,450 SQYD $11.00 $103,950.00
A0560 63304-0900 SIGNS, ALUMINUM PANELS, TYPE 3 SHEETING
Estes Bros. Const., Inc. $156.05 $67,413.60 Central Southern Construction Corp. $75.00 $32,400.00 ERon Road Construction LLC $283.00 $122,256.00 Engineer's Estimate 432 SQFT $90.00 $38,880.00
A0570 63308-3000 OBJECT MARKER, TYPE 3
Estes Bros. Const., Inc. $167.00 $30,895.00 Central Southern Construction Corp. $250.00 $46,250.00 ERon Road Construction LLC $87.00 $16,095.00 Engineer's Estimate 185 EACH $330.00 $61,050.00
A0580 63501-0000 TEMPORARY TRAFFIC CONTROL
Estes Bros. Const., Inc. Lump Sum $427,872.36 Central Southern Construction Corp. Lump Sum $950,000.00 ERon Road Construction LLC Lump Sum $985,978.00 Engineer's Estimate ALL LPSM Lump Sum $210,000.00
A0590 63701-0000 FIELD OFFICE
Estes Bros. Const., Inc. $84,000.00 $84,000.00 Central Southern Construction Corp. $150,000.00 $150,000.00 ERon Road Construction LLC $66,000.00 $66,000.00 Engineer's Estimate 1 EACH $69,500.00 $69,500.00
Total Schedule - All Items
Estes Bros. Const., Inc. $32,428,068.10 Central Southern Construction Corp. $35,961,600.00 ERon Road Construction LLC $42,249,777.00 Engineer's Estimate $46,468,273.00
Bid Error Report
1 out of 2
Project No: MS NP NATR 3N18 3H27 ETC
Project Name: Geotechnical, Pavement Rehabilitation, and Structural Repairs between MP 121 and MP
204 (Phase 2)
Schedule: A
Schedule Type: Base
Bid Item Check Pass
Bidder Line Item Number Bidder's Extension Computed Extension
No Line Item Errors Found
Bid Error Report
2 out of 2
Project No: MS NP NATR 3N18 3H27 ETC
Project Name: Geotechnical, Pavement Rehabilitation, and Structural Repairs between MP 121 and MP
204 (Phase 2)
Schedule: A
Schedule Type: Base
Bid Total Check Pass
Bidder Bidder's Bid Amount Computed Bid Amount Error
ERon Road Construction LLC $42,249,777.00 $42,249,777.00
Central Southern Construction Corp. $35,961,600.00 $35,961,600.00
Estes Bros. Const., Inc. $32,428,068.10 $32,428,068.10
The apparent low bidder is 30.21% below the engineer's estimate.