This document is a Bridge Inspection Report for the Merchant Creek Bridge on the Natchez Trace Parkway. The report provides a detailed inspection of the bridge's condition, including an assessment of the deck, superstructure, substructure, and channel. It also includes recommendations for maintenance, rehabilitation, and reconstruction work, along with preliminary cost estimates.
The report notes the bridge is generally in good condition, with a few deficiencies that require attention, such as erosion around the piers, missing expansion joint material, and cracking in the railings and wearing surface. The report recommends repairs to address these issues, with an estimated rehabilitation/reconstruction cost of approximately $58,000. The bridge has an operating rating that meets or exceeds the design load capacity. No critical deficiencies were found.
View the file
Other files
Show 40 more
Latest 50 of 53 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BRIDGE INSPECTION REPORT
MERCHANT CREEK BRIDGE
NATCHEZ TRACE PARKWAY OVER MERCHANT CREEK
NATCHEZ TRACE PARKWAY
LN
STRUCTURE NO. 5570-120P
INSPECTION TYPE: ROUTINE
INSPECTION DATE: 3/14/2022
WU
Report prepared by:
Federal Highway Administration Federal Lands Bridge Office Bridge Inspection and Management Program 21400 Ridgetop Circle Sterling, Virginia 20166 https://bridge.flhd.fhwa.dot.gov
MILE POINT: 148.60
KILOMETER POINT: 45.29
RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 5570-120P
MERCHANT CREEK BRIDGE INSPECTION DATE : 03/14/2022
PRIORITY OF IMPROVEMENT226
A (Critical) - Structure is closed, in immediate damage of collapse, or presents a critical safety danger.
B (Major) - Structure is seriously deficient or presents a safety hazard, but can remain open at reduced loads or with frequent inspections.
C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.
D (Minor) - Structure is generally in good condition. Preventive maintenance may be required.
E (Special) - Structure is under construction or reconstruction.
D
Item No.
Maintenance Recommendations
(GENERALLY NOT FLHP ELIGIBLE)
QTY. UNIT UNIT
COST
PRELIM.
COST
ESTIMATE
PRELIM. MAINTENANCE TOTAL :
Item No.
REHABILITATION/RECONSTRUCTION
(TYPICALLY NEEDED WITHIN 5 YEARS)
QTY. UNIT
UNIT
COST
PRELIM. COST ESTIMATES
REHAB RECONSTR
60.17 REPAIR EROSION AND SCOUR AROUND PIERS
WITH ENGINEERED RIPRAP.
58.2 REPLACE EXPANSION JOINT MATERIAL IN
CURBS AND RAILINGS.
CONTRACT COSTS FOR MOBILIZATION,
TRAFFIC CONTROL, AND CONTINGENCIES.
58.10, 222.9
RESTRIPE EAST SHOULDER LINE
PRELIM. REHABILITATION/RECONSTRUCTION TOTAL :
COST ESTIMATE SUMMARY
PRELIM. MAINTENANCE TOTAL :
PRELIM. REHABILITATION TOTAL :
PRELIM. RECONSTRUCTION TOTAL : .
TOTAL ITEMIZED COSTS:
PRELIMINARY ESTIMATE TOTAL * :
(*Includes typical contract costs for mobilization, traffic control and design/construction engineering: but does not include detour bridges, work beyond the bridge limits, or work not listed above. Estimates are approximate and are for planning purposes only; they should not be used as a complete or final engineers estimate.)
Remarks : Cost estimates assume that recommended actions will be combined with similar work being performed on other structures.
STRUCTURE LOAD RATING STRUCTURE NO. 5570-120P
MERCHANT CREEK BRIDGE INSPECTION DATE: 03/13/2022
TRUCK TYPE
INVENTORY RATING (NORMAL TRAFFIC) OPERATING RATING (MAXIMUM LOAD)
TONS METRIC TONS TONS METRIC TONS
H 17 15 29 26
HS 26 24 43 39
TYPE 3 23 21 38 34
TYPE 3S2 27 24 46 42
TYPE 3-3 37 34 62 56
DESIGN LOADING: 2 - H 15
X CAPACITY MEETS OR EXCEEDS DESIGN LOAD
CAPACITY IS LESS THAN DESIGN LOAD
ORIGINAL LOAD RATING CALCULATION APPLICABLE
ORIGINAL LOAD RATING CALCULATION REVISED
DATE OF LOAD RATING CALCULATION: 04/18/2016
LOAD RATING CONTROLLED BY: MOMENT
REMARKS: SEE BRIDGE FILE FOR LOAD RATING CALCULATIONS.
STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 5570-120P
MERCHANT CREEK BR DGE INSPECTION DATE: 03/13/2022
STRUCTURE IDENTIFICATION
(201) PARK: NATCHEZ TRACE PARKWAY
(202) STRUCTURE NAME:..............MERCHANT CREEK BRIDGE
(203) STRUCTURE KIND:............... 1 - BRIDGE
(204) STRUCTURE NUMBER:.........5570-120 P
4 - SOUTHEAST(205) NPS REGION:
(206) ROUTE CODE NUMBER:
(207) ROAD SECTION NO:............. 120P
(208) NPS ROAD CLASS:............... 1 - PRINCIPAL PARK ROAD
(209) WITHIN NPS BNDRY?:.......... Yes
(210) OPERATING UNIT:.................KOSCIUSKO
(211) PROJECT NO(S):................... 3M8
(212) DRAWING NUMBERS:...........2290B
(21) MAINTAINED BY:......................66 - NATIONAL PARK SERVICE
(22) OWNER:................................... 66 - NATIONAL PARK SERVICE
(1) STATE:
(2) STATE HWY. AGENCY DIST:
(3) COUNTY CODE:
(4) CITY / PLACE CODE:
(5) INVENTORY ROUTE:
(6) FEATURES INTERSECTED:
(7) FACILITY CARRIED:
(8) STATE STRUCTURE NO:
(9) LOCATION:
(10) INV. RTE. - MIN. VERT. CLR:
(11) MILE POINT:
(27) YEAR BUILT:
(106) YEAR RECONSTRUCTED:
(20) TOLL:
(37) HISTORIC DESIGNATION:
284 - MISSISSIPPI
28079 LEAKE
00000
1 6 1 00001 0
MERCHANT CREEK
NATCHEZ TRACE PARKWAY
5570120P0000000
11.3 MILES SOUTH OF MS ROUTE 35
99.99 FT ( 99.99 M)
148.6 (KM PT: 45.29)
3 - ON FREE ROAD
5 - NOT ELIGIBLE
STRUCTURE DESCRIPTION, FOUNDATION, AND DECK TYPE
(43A) MAIN STR. MATERIAL:..........2 - CONCRETE CONTINUOUS (44A) APPR. STR. MATERIAL:............ 0 - Other
(43B) MAIN STR. TYPE:.................. 01 - SLAB (44B) APPR. STR. TYPE:.................... 00 - OTHER
(45) NO. OF MAIN SPANS:..............003 (46) NO OF APPROACH SPANS:
(48) MAX. SPAN LENGTH:..............40 FT ( 12.2 M)
(49) STRUCTURE LENGTH:........... 105. FT ( 32.1 M) (108) WEAR SURFACE/PROTECT SYSTEM:
(216A) ABUTMENT #1 FDN:........... 3 - SPREAD FOOTING ON PILES A) TYPE WEARING SURFACE:.. 6 - BITUMINOUS
(216B) ABUTMENT #2 FDN:........... 3 - SPREAD FOOTING ON PILES B) TYPE MEMBRANE:................. 0 - NONE
(217A) PREDOM. PIER FDN:.......... 3 - SPREAD FOOTING ON PILES C) TYPE PROTECTION:.............. 0 - NONE
(217B) SECOND. PIER FDN:.......... 3 - SPREAD FOOTING ON PILES (218) IS SALT USED?.......................... NO
(107) DECK TYPE:.......................... 1 - CONCRETE CAST-IN-PLACE
LOAD RATING AND POSTING
(31) DESIGN LOAD:.........................2 - H 15 (41) LOAD RESTRICTION:.................. A - OPEN
(66) INVENTORY RATING:..............26 METRIC TONS) (70) BRIDGE POSTING:...................... 5 - EQUAL TO OR ABOVE LEGALTONS ( 23.6
LOADS
(64) OPERATING RATING:..............43 TONS ( 39 METRIC TONS)
INSPECTION DATES
(90) INSPECTION DATE: 03/14/2022 (91) FREQ. OF INSP: 48 MONTHS (92 / 93) CRITICAL FEATURE INSPECTION (CFI):
(219) ADD. STUDIES NEEDED: N - 0 - NONE (A) FRACTURE CRITICAL:.......... N
(220) SPECIAL STUDY TYPE: 0 - NONE INSP. EVERY MONTHS - LAST INSP:
(221) SPECIAL STUDY DATE: (B) UNDERWATER:..................... N
INSP. EVERY MONTHS - LAST INSP:
(C) SPECIAL INSPECTION:........ N
INSP. EVERY MONTHS - LAST INSP:
STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 5570-120P
MERCHANT CREEK BR DGE INSPECTION DATE: 03/13/2022
GEOMETRY, TRAFFIC, AND NAVIGATIONAL DATA
(16) LATITUDE:................................ 32° 53'09 50" (51) CURB TO CURB WIDTH:............ 28.0 FT ( 8.5 M)
(17) LONGITUDE:............................ 89°38 '20 50" (52) DECK WIDTH:.......................... 32.4 FT ( 9.9 M)
(19) DETOUR LENGTH:.................. 17 MI ( 27 KM) (32) APPR. ROADWAY WIDTH:...... 32.0 FT ( 9.8 M)
(28A) LANES ON STRUCT:.............02 (213) APPR. PAVEMENT WIDTH:... 22.0 FT ( 6.7 M)
(28B) LANES UNDER STRUCT:......00 LEFT SHOULDER:............... 5 0 FT ( 1.5 M)
(42A) SERVICE ON:.........................1 - HIGHWAY RIGHT SHOULDER:.......... 5 0 FT ( 1.5 M)
(42B) SERVICE UNDER:................. 5 - WATERWAY (33) BRIDGE MEDIAN:.................... 0 - NO MEDIAN
(29) AVG DAILY TRAFFIC:..............1641 (34) SKEW ANGLE:......................... 30 °
(30) YEAR OF ADT:......................... 2012 (35) STRUCTURE FLARED:............ 0 - NO FLARE
(114) FUTURE ADT:.........................1805 (47) TOTAL HORIZ. CLEARANCE:.. 28 FT ( 8.5 M)
(115) YEAR OF FUTURE ADT:........2032 (50) SIDEWALKS
(101) PARALLEL STRUCTURE:......N - NO PARALLEL STRUCTURE LEFT:.................................... 0 0 FT ( 0 M)
(38) NAVIGATION CONTROL:.........0 - NO NAVIGATION CONTROL ON RIGHT:.................................. 0 0 FT ( 0 M)
WATERWAY (BRIDGE PERMIT NOT
REQUIRED)
(39) VERTICAL CLEARANCE:.........0 FT ( 0 M) (214) BRIDGE RAIL TYPE
1 - FULL HEIGHT (NO PARAPET)(40) HORIZ. CLEARANCE:..............0 FT ( 0 M) RAIL CONFIGURATION:
(111) ABUT OR PIER PROT:........... MATERIAL:........................... 1 - CONCRETE
LATERAL UNDERCLEARANCE: DESIGN TYPE:..................... 1 - CONTINUOUS RAIL
(55) RIGHT:...............................00 FT ( 0 M) (215) BRIDGE RAIL HEIGHT:.......... 2 33 FT ( 0.71 M)
(56) LEFT:................................ 0 FT ( 0 M) (53) MIN. VRT. CLR. OVER DECK: 99.99 FT ( 99.99 M)
(54) MIN. VRT. UNDRCLRANCE:... .00 FT ( 0 M)
CONDITION AND APPRAISAL DATA, PROPOSED IMPROVEMENTS, AND COST
(58) DECK:....................................... 6 (67) STRUCTURAL EVALUATION:
(59) SUPERSTRUCTURE:...............6 (68) DECK GEOMETRY:
(60) SUBSTRUCTURE:.......... 6 (69) UNDERCLEARANCES:................ N
(61) CHANNEL:................................6 (71) WATERWAY ADEQUACY:
(62) CULVERT:.................................N (72) APPROACH ALIGNMENT:
(222) APPROACHES:...................... 7 (113) SCOUR CRITICAL:.................... 4 - ACTION IS REQUIRED TO
PROTECT EXPOSED FOUNDATIONS
(223) RETAINING WALL:.................N (225) PURPOSE OF IMPROVEMENT: 2 - REHAB/RECONSTRUCTION
(36) TRAFFIC SAFETY FEAT: 1 N N N (226) PRIORITY OF IMPROVEMENT: D - MINOR
(75A) TYPE OF WORK:................... (227) MAINTENANCE COST:
(75B) WORK DONE BY:.................. (228) REHAB / RECNSTR COST:
(76) IMPROVEMENT LENGTH:....... FT ( 0 M) (229) CONSTRUCTION COST:
ADDITIONAL INFORMATION
(230) STRUCTURE HISTORY:
2010 - ROADWAY RESURFACED; 2021 - PARAPET CIP REPAIRS
(231) ADDITIONAL CONSIDERATIONS:
(330) ADDITIONAL CONFIGURATION INFORMATION:
Inspector: Killian Baptiste Structure Number: 5570120P0000000
Inspection Date: 03/14/2022 Facility Carried: NATCHEZ TRACE PAR
Bridge Inspection Report
Pictures
PHOTO 3
Description LOOKING SOUTH TOWARD JACKSON
PHOTO 4
Description EAST (DOWNSTREAM) SIDE
Bridge Inspection Report
Pictures
PHOTO 5
Description GENERAL TOPSIDE VIEW LOOKING NORTH
PHOTO 6
Description GENERAL UNDERSIDE VIEW OF SOUTH SPAN LOOKING NORTH
Bridge Inspection Report
Pictures
PHOTO 7
Description GENERAL UNDERSIDE VIEW OF CENTER SPAN LOOKING NORTH; NOTE TRANSVERSE
AND TYPICAL LONGITUDINAL CRACKS ALONG CONSTRUCTION JOINTS
PHOTO 8
Description GENERAL UNDERSIDE VIEW OF NORTH SPAN LOOKING SOUTH
Bridge Inspection Report
Pictures
PHOTO 9
Description TYPICAL CRACKING OF APPROACH PAVEMENT, NORTHBOUND LANE OF SOUTH
APPROACH SHOWN
PHOTO 10
Description TYPICAL LONGITUDINAL CRACKING OF WEARING SURFACE
Bridge Inspection Report
Pictures
PHOTO 11
Description TYPICAL DETERIORATION OF SHOULDER LANE STRIPING, EAST SHOULDER SHOWN
PHOTO 12
Description TYPICAL MISSING JOINT FILLER MATERIAL IN RAIL EXPANSION JOINTS, EAST RAILING
OVER SOUTH ABUTMENT SHOWN; NOTE TYPICAL REPAIRS TO RAILING
Bridge Inspection Report
Pictures
PHOTO 13
Description TYPICAL VERTICAL AND TRANSVERSE CRACKING OF RAILINGS, EAST RAILING NEAR
MIDSPAN SHOWN
PHOTO 14
Description TYPICAL VERTICAL CRACK WITH EFFLORESCENCE ON EXTERIOR BEAMS OVER PIERS, EAST BEAM OVER SOUTH PIER SHOWN
Bridge Inspection Report
Pictures
PHOTO 15
Description GENERAL VIEW OF SOUTH ABUTMENT
PHOTO 16
Description DELAMINATED SPALL REPAIR AT EAST END OF SOUTH ABUTMENT
Bridge Inspection Report
Pictures
PHOTO 17
Description EROSION AT WEST END OF SOUTH PIER
PHOTO 18
Description GENERAL VIEW OF SOUTH FACE OF NORTH PIER; NOTE SCOUR AT EAST END
Bridge Inspection Report
Pictures
PHOTO 19
Description EROSION AT EAST END OF NORTH PIER
PHOTO 20
Description GENERAL VIEW OF NORTH ABUTMENT
Bridge Inspection Report
Pictures
PHOTO 21
Description SPALLING AT WEST END OF NORTH ABUTMENT
PHOTO 22
Description TYPICAL MOWER SCRAPES ON WINGWALLS, SOUTHWEST WINGWALL SHOWN
Bridge Inspection Report
Pictures
PHOTO 23
Description TYPICAL SLOUGHING OF CHANNEL BANKS, UPSTREAM CHANNEL SHOWN
PHOTO 24
Description LOOKING UPSTREAM
Bridge Inspection Report
Pictures
PHOTO 25
Description LOOKING DOWNSTREAM