S02 amendment 2.pdf

PDF 37 KB Posted

Attached to
CAMP NELSON NATIONAL CEMETERY, KY 833CM3030 – CORRECT FCA DEFICIENCIES
Solicitation number
36C78626R0058
Issued by

About this file

This is an amendment to a federal construction solicitation that addresses questions submitted during the Request for Information (RFI) period.

The amendment clarifies several key aspects of the project. Fire alarm modifications are included in the scope, with the required equipment specified as a FireWarden-100-2/E/C/ Addressable Fire Control Panel. Missing drawings from the original submission have been provided in an addendum package titled "12 from 833CM3030_CNNC FCA Corrections_CONS_BD Drawings_VOL 1_addendum01," which includes drawings EN-101, EN-102, EN-103, and X-101 through X-109. Administrative clarifications confirm that an RFI form is not required for submitting questions and that advance registration is not necessary for the September 25 site visit. Regarding contract terms, liquidated damages are applicable to this construction project under FAR clause 52.211-12, with the specific daily liquidated damages amount provided in an attached worksheet referenced in the amendment.

View the file

Other files

File Type Posted
S06_36C78626R0058 Amend. 0003.pdf PDF
S02 Amendement 36C78626R0058 0002.pdf PDF
S02 12 from 833CM3030_CNNC FCA Corrections_CONS_BD DRAWINGS_VOL 1_addendum01.pdf PDF
S02 Liquidated Damages 833CM3030_CNNC FCA Corrections CONS.pdf PDF
S02 Fire Alarm Panel.pdf PDF
S02 Amendment 36C78626R0058 0001.pdf PDF
S02 07 from 833CM3030_CNNC FCA Corrections_CONS_BD DRAWINGS_VOL 1_05212026 1.pdf PDF
S02 03 from 833CM3030_CNNC FCA Corrections_CONS_BD DRAWINGS_VOL 1_05212026 1.pdf PDF
S02 04 from 833CM3030_CNNC FCA Corrections_CONS_BD DRAWINGS_VOL 1_05212026 1 (1).pdf PDF
S02 833CM3030_CNNC FCA Corrections_CONS_BD SPECIFICATIONS.pdf PDF
S02_Attachment - Standard Form 1413.pdf PDF
S02_Attachment - DOL Payroll Form.pdf PDF
P07 Jessamine Camp Nelson Highway.pdf PDF
P07 Jessamine Camp Nelson Heavy.pdf PDF
S02 10 from 833CM3030_CNNC FCA Corrections_CONS_BD DRAWINGS_VOL 1_05212026 1.pdf PDF
P07 Jessamine Camp Nelson Building.pdf PDF
S02 11 from 833CM3030_CNNC FCA Corrections_CONS_BD DRAWINGS_VOL 2_05212026 1.pdf PDF
S09 09 from 833CM3030_CNNC FCA Corrections_CONS_BD DRAWINGS_VOL 1_05212026 1.pdf PDF
S02 05 from 833CM3030_CNNC FCA Corrections_CONS_BD DRAWINGS_VOL 1_05212026 1.pdf PDF
S02 01 from 833CM3030_CNNC FCA Corrections_CONS_BD DRAWINGS_VOL 1_05212026 1.pdf PDF
S02 Camp Nelson Sol 36C78626R0058 draft 9-14-2026.pdf PDF
S02_Attachment - Davis-Bacon Act Poster.pdf PDF
S02_Attachment - Past Performance Questionnaire.docx DOCX document
S02_Price Proposal Breakdown.docx DOCX document
S02_Attachment - Project Sample Template.docx DOCX document
S02 08 from 833CM3030_CNNC FCA Corrections_CONS_BD DRAWINGS_VOL 1_05212026 1.pdf PDF
S02 06 from 833CM3030_CNNC FCA Corrections_CONS_BD DRAWINGS_VOL 1_05212026 1.pdf PDF
S02 02 from 833CM3030_CNNC FCA Corrections_CONS_BD DRAWINGS_VOL 1_05212026 1.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The purpose of this amendment is to answer questions posed during the RFI period of the solicitation.

Question: confirm whether the work includes fire alarm modifications? If so, what is the existing/required manufacturer and panel model?

Response; Scope is in the project documents. Manufacturer and panel model is “FireWarden-100-2/E/C/ Addressable Fire Control Panel.” Picture of Fire Alarm Panel provided.

Question: The RFP states that contractors are required to use the attached RFI form for submitting questions; however, no RFI form appears to have been provided with the solicitation documents for this project.

Response: RFI form not required.

Question: The following drawings appear to be missing from the drawing sets provided:

o EN-101 o EN-102 o EN-103 o X-101 o X-102 o X-103 o X-104 o X-105 o X-106 o X-107 o X-108 o X-109 Please provide the above-referenced drawings to ensure complete and accurate contractor pricing.

Response: See attached drawing set “12 from 833CM3030_CNNC FCA Corrections_CONS_BD Drawings_VOL 1_addendum01.”

Question: Please also confirm whether advance registration is required for the September 25 site visit.

Response: Registration is not required.

Question: Liquidated Damages – Section F, Deliveries or Performance Section F.1 of the solicitation incorporates FAR clause 52.211-12 LIQUIDATED DAMAGES—CONSTRUCTION (SEPT 2000). However, we noticed that there is no daily liquidated damages amount provided.

Could you please confirm what amount this will be, or advise whether liquidated damages are not applicable to this solicitation?

Response: Yes, LDs are included. Please see attached worksheet.