This is an amendment to a federal construction solicitation that addresses questions submitted during the Request for Information (RFI) period.
The amendment clarifies several key aspects of the project. Fire alarm modifications are included in the scope, with the required equipment specified as a FireWarden-100-2/E/C/ Addressable Fire Control Panel. Missing drawings from the original submission have been provided in an addendum package titled "12 from 833CM3030_CNNC FCA Corrections_CONS_BD Drawings_VOL 1_addendum01," which includes drawings EN-101, EN-102, EN-103, and X-101 through X-109. Administrative clarifications confirm that an RFI form is not required for submitting questions and that advance registration is not necessary for the September 25 site visit. Regarding contract terms, liquidated damages are applicable to this construction project under FAR clause 52.211-12, with the specific daily liquidated damages amount provided in an attached worksheet referenced in the amendment.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The purpose of this amendment is to answer questions posed during the RFI period of the solicitation.
Question: confirm whether the work includes fire alarm modifications? If so, what is the existing/required manufacturer and panel model?
Response; Scope is in the project documents. Manufacturer and panel model is “FireWarden-100-2/E/C/ Addressable Fire Control Panel.” Picture of Fire Alarm Panel provided.
Question: The RFP states that contractors are required to use the attached RFI form for submitting questions; however, no RFI form appears to have been provided with the solicitation documents for this project.
Response: RFI form not required.
Question: The following drawings appear to be missing from the drawing sets provided:
o EN-101 o EN-102 o EN-103 o X-101 o X-102 o X-103 o X-104 o X-105 o X-106 o X-107 o X-108 o X-109 Please provide the above-referenced drawings to ensure complete and accurate contractor pricing.
Response: See attached drawing set “12 from 833CM3030_CNNC FCA Corrections_CONS_BD Drawings_VOL 1_addendum01.”
Question: Please also confirm whether advance registration is required for the September 25 site visit.
Response: Registration is not required.
Question: Liquidated Damages – Section F, Deliveries or Performance Section F.1 of the solicitation incorporates FAR clause 52.211-12 LIQUIDATED DAMAGES—CONSTRUCTION (SEPT 2000). However, we noticed that there is no daily liquidated damages amount provided.
Could you please confirm what amount this will be, or advise whether liquidated damages are not applicable to this solicitation?
Response: Yes, LDs are included. Please see attached worksheet.