This document is a specification section for a Factory-Assembled Aboveground Storage Tank (FAST) System for Camp Nelson National Cemetery, Kentucky, as part of project 833CM3030 to correct FCA deficiencies. The specification requires a single manufacturer-supplied integrated FAST system for diesel fuel storage with factory-assembled components, pre-plumbed dispensing systems, factory-installed vents, valves, and appurtenances. The system must be UL 2085 certified for protected secondary contained aboveground tanks for flammable liquids and must meet UL 752 Level 8 bullet-resistance standards. Non-factory-assembled substitutions are explicitly not acceptable. The manufacturer must have a minimum of 10 years of experience manufacturing UL 2085 tanks, and the installation contractor must have a minimum of three years documented experience. The tank must provide a 30-year manufacturer's warranty against defects in material or workmanship, with an additional one-year warranty on parts, work quality, and installation.

The FAST System must include a double-wall, thermally insulated, fire-resistant horizontal steel tank with primary and secondary containment (minimum 110 percent of primary capacity), an integral monitoring area between tanks, 2-hour fire-resistant rating, and comply with NFPA 30, NFPA 30A, NFPA 70, IFC 2012, and other specified standards. The system includes a submersible pump compatible with ethanol and MTBE blends, a fleet-rated fuel dispenser with mechanical register rated to 22 GPM, and an electronic tank monitoring system with leak detection. Electrical systems must conform to NEC Class-1, Division 1 hazardous location requirements, and all components must be UL-listed. Field installation requires verification of site conditions, hydrostatic or pneumatic testing if required by the authority having jurisdiction, system flushing with fuel grade prior to activation, and manufacturer approval of the final installation. Operational training for government personnel and compliance with local inspection, reporting, and registration requirements are required before system acceptance.

View the file

Other files

File Type Posted
Amendment 4-833CM3030 - CD1 - Historic Hardware.pdf PDF
Amendment 4-833CM3030 - BID - HA-001 from 20260422 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - CU-105 from 20260107 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - 037 - CU-105 UTILITY PLAN (R2).pdf PDF
Amendment 4-833CM3030 - BID - 26 29 23 Engine Control and Monitoring.pdf PDF
Amendment 4-833CM3030 - BID - 028 - CP-105 PAVING PLAN (R2).pdf PDF
Amendment 4-833CM3030 - BID - SN-104 105 and X-series from 20260107 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - Historic Pages from 20260422 - 833CM3030 - BID - SET A-004 005 132 133 154 155.pdf PDF
Amendment 4-ConVault Specification with UL 752 Level 8.pdf PDF
Amendment 4-Convault Storage tank 500 GL-telford.pdf PDF
Amendment 4-Convault Brochure 2019 (003).pdf PDF
Amendment 4-833CM3030 - BID - 020 - CG-201 POND AND CRYPT FIELD SECTIONS (R1).pdf PDF
Amendment 4-AE-113 from 20260422 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-AE-113 833CM3030 - BID - SET.pdf PDF
S02 36C78626R0058 Amendment 0004.docx DOCX document
Amendment 4-833CM3030 - CD1 - Historic Preservation.pdf PDF
Amendment 4-SED FCA - 04212022_Camp Nelson.pdf PDF
Amendment 4-833CM3030 - BID - AE-110 from 20260422 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - 328400 Plant Irrigation_10-31-24.pdf PDF
Amendment 4- 36C78626R0058 FuelForce 814 Advanced Fuel Controller Brochure.pdf PDF
Amendment 4-240524-Camp Nelson National Cemetery - KY- SUE Field Report Deliverable.pdf PDF
Amendment 4-833CM3030 - BID - AE-150 from 20260422 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - 07 42 43 Plastic Panel.pdf PDF
Amendment 4-833CM3030 - BID- EQUIPMENT STORAGE GARAGE-AE-141.pdf PDF
Amendment 4-GI-104 from 20260107 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - 231123 NatGas.pdf PDF
Amendment 4- 833CM3030 - BID - 072727 - BARRIER VAPOR.pdf PDF
Amendment 4-3189 ECS Geotechnical Engineering Report - Expansion Area.pdf PDF
Amendment 4-833CM3030 - BID - 329000 Planting.pdf PDF
Amendment 4-3189 ECS Geotechnical Engineering Report - Camp Nelson Cemetery.pdf PDF
Amendment 4-833CM3030 - BID - 050 - S-101 STRUCTURAL PLAN (R2).pdf PDF
Amendment 4-Lightning Protection Asmnt Report_Camps Nelson Cemetery.pdf PDF
Amendment 4-Dispensing System Controller-SafeSite DSC with specs.pdf PDF
Amendment 4-833CM3030 - BID - CD-102 from 20260107 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-AD-150 from 20260107 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - 33 56 10 Temporary Fuel Storage Tanks.pdf PDF
Amendment 4-833CM3030 - BID - 052 - S-202 MATERIALS STORAGE BLDG. FRAMING (R2).pdf PDF
Amendment 4-3189 ECS Geotechnical Engineering Report - Maintenance Area.pdf PDF
S06_36C78626R0058 Amend. 0003.pdf PDF
S02 Amendement 36C78626R0058 0002.pdf PDF
S02 amendment 2.pdf PDF
S02 Fire Alarm Panel.pdf PDF
S02 Liquidated Damages 833CM3030_CNNC FCA Corrections CONS.pdf PDF
S02 12 from 833CM3030_CNNC FCA Corrections_CONS_BD DRAWINGS_VOL 1_addendum01.pdf PDF
S02 Amendment 36C78626R0058 0001.pdf PDF
P07 Jessamine Camp Nelson Building.pdf PDF
S02_Price Proposal Breakdown.docx DOCX document
S02_Attachment - Past Performance Questionnaire.docx DOCX document
P07 Jessamine Camp Nelson Highway.pdf PDF
S02_Attachment - DOL Payroll Form.pdf PDF
Show 40 more

Latest 50 of 67 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA Project No. 833CM3030 Camp Nelson National Cemetery, KY

Correct FCA Deficiencies 100% CD2

7-8-2025

SECTION 23 11 13

FACTORY-ASSEMBLED ABOVEGROUND STORAGE TANK (FAST) SYSTEM

PART 1 – GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including

General and Supplementary Conditions and Division 01

Specification Sections, apply to this Section.

B. Related Sections:

1. Division 26 – Electrical connections.

1.2 SUMMARY

A. This Section includes furnishing and installing an aboveground, pre-manufactured, protected secondary containment fuel storage tank system for diesel fuel.

B. Provide factory assembled and integrated Factory-Assembled

Aboveground Storage Tank (FAST) System with pre-plumbed dispensing systems, factory installed vents, valves, and appurtenances. This specification requires that the system design, manufacture, and integration to be the responsibility of one specialized manufacturer in order to maintain quality through the steps of procurement, manufacturer, integration, and field installation. Non-factory assembled, substitutions are not acceptable, and will not be considered for this project.

C. The FAST System shall include a specialty fuel system sub-panel, emergency stop (ESO), and point-to-point wiring diagram to facilitate ease of installation for all system components.

D. Certifications: Each FAST System storage tank shall bear the

Underwriters Laboratories UL 2085 label for Protected Secondarily

Contained Aboveground Tanks for Flammable Liquids.

E. Delivery, Storage, and Handling: Coordinate delivery to allow crane offloading and placement in prepared and final location, minimizing the need for double handling. Keep FAST System protected from physical damage caused by other construction activities.

F. Field Measurements: Field-verify horizontal and vertical dimensions, clearances, and setbacks of spaces where FAST Systems will be installed prior to fabrication of FAST under this section.

G. Warranty Periods:

1. FAST System: Warranted by the manufacturer against defects in material or workmanship for 30 years following the delivery of the tank. Warranties that limit such coverage for shorter periods and/or limit the primary tank warranty to failure solely due to non-corrosion related cracking, breakup, or collapse will not be permitted.

2. Not less than one (1) year for parts, work quality, and installation.

Correct FCA Deficiencies

95% CD1

5-20-2025

FACTORY-ASSEMBLED ABOVEGROUND STORAGE TANK (FAST) SYSTEM

SECTION 23 11 13 - 2

1.3 REFERENCE STANDARDS

A. The latest published edition of a reference shall be applicable to this Project, unless identified by a specific edition date.

B. All reference amendments adopted prior to the effective date of this Contract shall be applicable to this Project.

C. All materials, installation and workmanship shall comply with the applicable requirements and standards addressed within the following references:

1. NFPA 30 – Flammable and Combustible Liquids Code.

2. NFPA 30A – Motor Fueling Dispensing Facilities & Repair Garages

3. NFPA 37 - Installation and Use of Stationary Combustion Engines and Gas Turbines.

4. NFPA 70 – National Electric Code.

5. NFPA 110 – Emergency and Standby Power Systems.

6. UL 142 – Standard for Steel Aboveground Tanks for Flammable and

Combustible Liquids.

7. UL 508A – The UL Safety Standard for Industrial Control

Equipment.

8. UL 752 – Bullet-Resisting Equipment, Level 8.

9. UL 2085 – Protected Aboveground Tanks for Flammable and

Combustible Liquids.

10. IFC 2012 – Chapter 57 Flammable and Combustible Liquids

11. IFC 2012 – Chapter 6 Building Services and Systems

12. IFC 2012 – Chapter 23 Motor Fueling Dispensing Facilities &

Repair Garages

13. PEI / RP 200 – 08 Recommended Practices for Installation of ASTs

14. ASTM A36 – Standard Specification for Carbon Structural Steel

15. ASTM A53 – Specification for Pipe, Steel, Black/Hot Dipped, Zinc

Coated, Welded, SS

16. ACI 318 – Building Code Requirements for Structural Concrete.

17. All applicable state and local requirements.

1.4 QUALITY ASSURANCE

A. Manufacturer: Equipment, controls, and tank shall be provided by a single supplier to ensure a complete functional and coordinated system with single source responsibility. Supplier shall give guidance to equipment and tank installation and shall complete all commissioning and owner training. The supplier shall be a firm with five (5) years of documented experience in the installation of integrated dispensing fuel systems.

B. Manufacturer Qualifications: Minimum 10 years experience in manufacturing UL 2085 tanks.

C. Tank shall be listed and labeled by Underwriters Laboratories (UL) as meeting UL 2085 and UL 752 Level 8 standards.

D. Installer: Company specializing in performing the work of this

95% CD1

5-20-2025

FACTORY-ASSEMBLED ABOVEGROUND STORAGE TANK (FAST) SYSTEM

SECTION 23 11 13 - 3

Section with minimum three (3) years documented experience. Bidding installation contractor shall hold license(s) as required by the authority(ies) having jurisdiction.

E. All auxiliary components necessary to be integrated into the complete FAST System shall be installed at the tank manufacturing facility.

F. Tolerances: Coordinate fabrication and installation of FAST System with adjacent work and verify critical dimensions, clearances, emergency stop (ESO) location, conduits, and setbacks to ensure accurate installation.

1.5 SUBMITTALS

A. Submittals, including number of required copies, shall be submitted in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

B. Mark information and material submitted under this section

“SUBMITTED UNDER SECTION 23 11 13, FACTORY-ASSEMBLED ABOVE GROUND

TANK (FAST) SYSTEM,” with applicable paragraph identification.

C. Shop Drawings:

1. Show details, sizes and dimensions, openings, supports, anchorage locations, and accessory items.

2. Furnish setting diagrams for installation.

3. Where required by local jurisdiction, provide manufacturer's part numbers of integrated components to facilitate permitting requirements of the FAST System.

4. Do not proceed with fabrication prior to COR’s approval of shop

Drawings.

D. Product Data:

1. Product Data: Manufacturer’s data sheet for tank and accessories.

2. Provide catalog data on all controls, pumps, associated valves, piping, tanks, and other equipment including material of construction, dimensional data, and ratings.

3. Submit complete installation instruction manual as published by the FAST System manufacturer.

E. Certifications:

1. UL 2085 label.

2. UL 752 Level 8 certification.

3. Manufacturer's ISO 9001 certification.

F. Record Documents:

1. Record documents shall include as-built Drawings indicating the location of FAST System and system components.

2. Provide FAST System start-up and commissioning check-

95% CD1

5-20-2025

FACTORY-ASSEMBLED ABOVEGROUND STORAGE TANK (FAST) SYSTEM

SECTION 23 11 13 - 4

lists and other applicable documentation.

G. Operation and Maintenance Data:

1. Include Manufacturer’s installation, operation and maintenance instructions, spare parts lists, and training information for distribution and review.

2. Provide a minimum of one complete O&M binder for use on-site.

H. Installation Instructions.

I. Warranty documentation.

1.6 REGULATORY REQUIREMENTS

A. Submit and comply with all the requirements of the EPA, state, and local authorities having jurisdiction. Include installation permit/fees for fuel storage tank and all accessories and appurtenances.

B. Comply with “National Electric Code” for equipment, wiring, and conduit installed under this section.

1.7 DELIVERY, STORAGE, AND HANDLING

A. Deliver tank to site with factory-applied lifting lugs.

B. Protect all openings and nozzles from contamination.

C. Store in a clean, dry, secure area until installation.

1.8 Warranty

A. Provide manufacturer’s standard warranty: 30-year limited warranty on tank and concrete encasement.

PART 2 - PRODUCTS

2.1 ConVault by Convault Systems, LLC – or approved equal meeting all specifications herein.

2.2 DISPENSING SYSTEM POWER DISTRIBUTION AND CONTROLS

A. Provide Dispensing System Power Distribution and Controls integrate the following functions into one system:

1. Control Panel Specifications

a. Single input power connection with main power disconnects.

b. NEMA 4X enclosure suitable for outdoor and high corrosion areas.

c. Panel mounted emergency stop control button.

d. Dedicated dispenser control and anti-siphon circuit.

e. Dedicated tank level gauge circuit.

f. Dedicated emergency stop controls circuit.

g. Dedicated motor starter control and overload protection

95% CD1

5-20-2025

FACTORY-ASSEMBLED ABOVEGROUND STORAGE TANK (FAST) SYSTEM

SECTION 23 11 13 - 5

circuit (1-1/2 HP max).

h. Dedicated dry output for remote emergency stop controls circuit.

B. Circuit Disconnects

1. General: Provide each circuit leading to or through dispensing equipment, including all associated power, communication, data, and video circuits, and equipment for remote pumping systems, with a clearly identified and readily accessible switch or other approved means, located remote from the dispensing devices, to disconnect simultaneously from the source of supply, all conductors of the circuits, including the grounded conductor, if any. Single pole breakers utilizing handle ties are not permitted.

2. Unattended Self-Service Motor Fuel Dispensing Facilities:

Install emergency controls as specified in 2011 NEC 514.11(A) at a location acceptable to the authority having jurisdiction, but the control shall be more than 6 m (20 ft.) and less than

30 m (100 ft.) from the dispensers. Install additional emergency controls on each group of dispensers or the outdoor equipment used to control the dispensers. Emergency controls shall shut off all power to all dispensing equipment at the station. Controls shall be manually reset only in a manner approved by the authority having jurisdiction.

2.3 STORAGE TANK

A. Description: Factory assembled, UL 142 and UL 2085, thermally insulated and fire-resistant, double-wall, horizontal, steel tank; with primary- and secondary-containment walls and insulation and with interstitial space. Secondary containment shall be not less than 110 percent of primary containment.

B. Construction: Fabricated with welded carbon steel and insulation; suitable for operation at atmospheric pressure and for storing fuel with specific gravity up to 1.1 and with test temperature according to UL 2085.

1. Designed for possible future relocation.

2. Welds shall be continuous on all sides and exterior seams, conforming to the American Welding Society Standard for continuous weld.

3. Pressure tested at 5 psig for a minimum of 24 hours.

4. All openings shall be from the top only. The tank shall be supplied with emergency vents for the primary and secondary tanks.

5. The interstitial monitoring area between the primary and secondary tanks shall be a true void, ensuring the immediate migration of any liquid contents to the monitoring point and reliability for verifiable pressure testing in accordance with the requirements of the Department of Defense Uniform

Facilities Criteria 3-460-01 (Design: Petroleum Fuel

Facilities) and 3-406-03 (Operations & Maintenance:

95% CD1

5-20-2025

FACTORY-ASSEMBLED ABOVEGROUND STORAGE TANK (FAST) SYSTEM

SECTION 23 11 13 - 6

Maintenance of Petroleum Systems). Designs incorporating insulation or other material in the secondary containment area will not be permitted.

6. The secondary containment shall be tested for tightness at the manufacturing plant and in the field before commissioning and use as may be required by local jurisdiction and code.

7. Permanently mounted on support saddles that elevate the tank a maximum of 12 inches above the underlying concrete slab.

8. All exposed steel, with the exception of stainless steel, shall be anti-oxidant powder coated to inhibit corrosion and meet ASTM B117.

9. Type: UL 2085-compliant, protected aboveground storage tank

(AST) with integral secondary containment.

10. Configuration: Rectangular or square, skid-mounted.

11. Construction:

a. Inner Tank: UL 142 carbon steel.

b. Interstitial Space: Monitored.

c. Outer Layer: Reinforced concrete, minimum 6-inch thick.

d. Protective Coating: Sealant or coating approved for long-term exposure.

12. Bullet Resistance: UL 752 Level 8 compliant (resistant to

7.62mm rifle rounds).

13. Fire Rating: 2-hour fire-resistant rating per UL 2085.

C. Capacities and Characteristics:

1. Indicated on plans.

2. Fuel Type: Diesel and gasoline.

D. Code Compliance: At minimum, comply with all provisions of the following:

1. UL 2085 Listed “Protected” tank

2. Ballistics and Impact protection per UL 2085

3. Both the inner and outer steel tanks built to UL standards

4. National Fire Protection Association (NFPA) 30 & 30A

5. International Fire Code (IFC)

6. California Air Resources Board (CARB) Standing Loss Control testing requirements for air emissions

7. Steel Tank Institute (STI) Standard F941 for Protected

Aboveground Storage Tanks

E. Thermal Protection: The tank system construction shall include monolithic thermal insulation as necessary to protect against extreme temperatures.

F. Fire Resistance: The tank system shall be designed and tested to provide 2 hour fire protection for the primary tank as per UL 2085

2-hour furnace fire test and 2 hour simulated pool fire test. The average maximum rise in temperature of the primary tank during the test shall not exceed 260° F and the maximum temperature of any single point on the primary tank shall not exceed 400° F. No steel members shall penetrate the walls or floor of the concrete encasement to assure isolation from pool fire heat.

95% CD1

5-20-2025

FACTORY-ASSEMBLED ABOVEGROUND STORAGE TANK (FAST) SYSTEM

SECTION 23 11 13 - 7

G. Fittings:

1. Normal Vent and Emergency Vent.

2. Fill Port with Drop Tube and Spill Containment.

3. Suction and Return Ports.

4. Leak detection port (for interstitial monitoring).

a. Factory-installed interstitial monitoring port compatible with electronic sensors. A through-tank leak detection monitoring tube terminating between the primary tank and the secondary containment tank shall be provided to monitor any leaks from the primary tank.

5. Overfill prevention valve (mechanical).

a. Tank system shall include a UL listed spill/overfill container manufactured as an integral part of the primary tank, surrounding the fill pipe, and protected by 2 hour fire rating of the enclosure. The spill/overfill container shall include a stick port and normally closed drain valve to release spilled product into the main tank. Exterior steel shall be stainless steel or anti-oxidant powder coated to inhibit rust. Overfill containment systems that are designed to release spilled product into the interstitial area will not be accepted.

b. Overfill protection shall be provided by each of the following methods:

• Direct reading level gauge visible from fill pipe access

• Valve rated for pressurized delivery located within fill pipe to close automatically at 95% full level

• High level alarm.

H. Fuel Level Gauge: Mechanical or remote-reading as required.

I. Lifting Lugs: Integral for handling and placement.

J. Exterior Finish: The tank system exterior shall be a low maintenance architectural coating or exposed aggregate concrete finish. Models with fiber clad or painted steel exterior tanks will not be accepted.

K. Signage: Tanks shall be marked on all sides with tank Manufacturer’s decals as indicated and complying with applicable state and local codes.

L. Execution: The tank system shall be installed in strict accordance with the Manufacturer’s recommendations, industry standards, and applicable fire and environmental codes. Obtain all state and local permits prior to installation. Handle, lift, store, and install the tank system in accordance with the Manufacturer’s instructions.

95% CD1

5-20-2025

FACTORY-ASSEMBLED ABOVEGROUND STORAGE TANK (FAST) SYSTEM

SECTION 23 11 13 - 8

Connect grounding conductors to bolts on the tank system for lightning protection in accordance with NFPA 780 and all electrical work shall be in accordance with applicable codes.

2.4 SUBMERSIBLE PUMPS

A. Compatibility: UL listed for fuel mixtures containing up to 10% ethanol, and 20% MTBE, 20% ETBE or 17% TAME with gasoline.

B. Pump shall include integral check valve, air eliminator, and pressure relief.

C. Anti-siphon solenoid valve and ball/isolation valve at pump discharge.

2.5 FUEL DISPENSER – FLEET, SINGLE REMOTE

A. Fuel Dispenser shall be a shelf-mounted, enhanced capacity compact single remote dispenser, rated up to 22 GPM/83 LPM at the discharge.

Designed for dispensing gasoline, including standard oxygenated blends; diesel, including biodiesel blends up to 20% (B20); and kerosene. The Fuel Dispenser shall include:

1. Compact design, 31 inches high or less, that can be mounted on a shelf attached to the tank or a remote shelf.

2. Volume only, non-computer mechanical register with power reset with interlock.

3. Mechanical resets or electronic registers are not acceptable.

4. A non-resettable accumulative totalizer displayed on the dial face.

5. All register openings shall be covered with tempered or double-strength glass (no plastic).

6. Cabinet:

a. All exterior panels made from galvannealed steel for corrosion resistance.

b. Finish: Powder-coated metallic silver sides, top, and back with blue door with black register decal.

c. Removable door, side, top, and back panels.

d. Lockable door.

7. A hose hanger.

8. One (1) positive displacement, stainless steel sleeved, two-piston meter with Teflon piston cups.

9. An explosion-proof junction box in the hydraulic cabinet to make all AC wire terminations. The junction box shall include a wire from the reset to provide a reset complete signal to an external control system.

10. Minimum 1 inch I.D. internal piping for maximum flow performance.

11. Each dispenser shall be equipped with a 1 inch two-stage solenoid valve.

12. Each supply inlet shall be 1-1/2 inch minimum. Inlet strainer shall be able to be removed vertically to prevent spillage when cleaning.

13. Discharge shall be 1 inch with a ¾ inch reducing bushing so that either a ¾ inch or 1 inch hose may be used.

95% CD1

5-20-2025

FACTORY-ASSEMBLED ABOVEGROUND STORAGE TANK (FAST) SYSTEM

SECTION 23 11 13 - 9

14. Nozzle boot shall be lane-oriented with lift-to-start nozzle hook to turn on/off dispenser.

15. Nozzle boot shall fit standard automatic or short spout balance vapor recovery nozzles.

16. Manufacturer’s Warranty: One year parts and labor except for the cabinet which shall be warranted against corrosion for 4 years.

B. Standards/Approvals: ADA compliant user controls per ANSI A117.1;

C-UL-US listed; and W&M approval.

2.6 TANK MONITORING SYSTEM

A. Configuration: Electronic system including high level, low level, leak indications, alarm panel, magnetostrictive tank gauging probe, discriminating leak sensor, remote alarm and printer.

B. Approvals: UL-listed, CUL-listed, CE-listed.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Install tank per manufacturer’s instructions and applicable codes.

B. Provide anchorage system where required per seismic and wind requirements.

C. Coordinate piping connections to generator or fuel delivery system.

D. Install spill containment and overfill protection in accordance with

EPA and NFPA guidelines.

E. The FAST System shall not be installed until substrates and adjacent construction has been properly constructed. Verify concrete tank slab, electrical service stub-ups, emergency stop location, bollard/barrier installation, clearances, setbacks, and other related work that may impact installation of the system. Do not proceed until unsatisfactory conditions have been corrected.

F. Notify Manufacturer of any detail or design deviations as may be determined by site conditions.

3.2 FUEL TANK INSTALLATION

A. Install FAST System in strict accordance with the manufacturer's recommendations, and applicable fire and environmental codes. Obtain state and local permits prior to installation.

B. Anchor legs/saddles to the slab per tank manufacturer’s recommendations.

95% CD1

5-20-2025

FACTORY-ASSEMBLED ABOVEGROUND STORAGE TANK (FAST) SYSTEM

SECTION 23 11 13 - 10

C. Ground tank in accordance with electrical codes. Use grounding lugs installed by tank manufacturer.

D. Tanks shall be clearly marked on all sides with warning signs, tank volume, product identification, and other signs as required by local jurisdictions and applicable code.

3.3 ELECTRICAL SYSTEMS

A. Design and install all wiring to meet the requirements of the NEC and

NFPA 70. Install all necessary branch circuit conduit and wiring, providing for a stub-up at designated location(s) to which components of the FAST system can be connected. Install specialty fuel system sub- pane and emergency stop to facilitate ease of installation.

B. All electrical devices used with or located within 20 feet of the

FAST shall conform to NFPA 70 Hazardous Locations. All electric conduits and wiring connected to the tank shall be explosion proof and in strict accordance with NEC Class-1, Division 1 or other local standards, whichever is stricter.

C. Pumps and all other equipment and all other equipment used in the hazardous areas shall be UL listed. Design and install all wiring to meet the requirements of the NEC and NFPA 70. Install all necessary branch circuit conduit and wiring as indicated on the Drawings.

D. Pumps and all other equipment used in the hazardous areas shall be UL listed.

3.4 FIELD QUALITY CONTROL

A. Verify all factory-installed fittings and gauges are in place and undamaged.

B. Hydrostatic or pneumatic testing of primary tank and interstitial space if required by AHJ.

C. Perform system inspection as outlined in manufacturer's installation manual.

D. Test fueling distribution in accordance with NFPA 30 and other applicable codes. Properly dispose of any fuel generated in adherence to environmental regulations.

E. Submit field installation inspection report to manufacturer COR.

F. Coordinate with FAST System Manufacturer to inspect the final FAST

System installation. FAST System Manufacturer’s approval if final installation is required prior to Acceptance.

3.5 SYSTEM ACTIVATION

A. Prior to activating the FAST System, flush system piping with grade of fuel to be used by Government to remove any debris and foreign

95% CD1

5-20-2025

FACTORY-ASSEMBLED ABOVEGROUND STORAGE TANK (FAST) SYSTEM

SECTION 23 11 13 - 11

matter in piping prior to filling tank for the first time.

B. Service all system filters and screens and dispose of fuel in accordance with EPA and NFPA regulations after flushing.

C. Open valves to correct position for system operation.

3.6 ADJUSTING AND CLEANING

A. Remove protective coverings.

B. Touch-up any damaged or abraded areas with the application of same coating used by the manufacturer. Obtain sufficient quantity of

Manufacturer’s touch-up paint from Manufacturer for this purpose.

C. Repair or replace damaged components.

3.7 OPERATIONAL TRAINING

A. Perform training of Government’s personnel per the materials included with the FAST system manufacturer's installation manual.

B. Comply with local requirements for system inspection, reporting and registration, as well as administrative paperwork requirements.

Coordinate with authorities having jurisdiction to obtain reviews.

- - - E N D - - -