Amendment 4-833CM3030 - BID - 33 56 10 Temporary Fuel Storage Tanks.pdf

PDF 125 KB Posted

Attached to
CAMP NELSON NATIONAL CEMETERY, KY 833CM3030 – CORRECT FCA DEFICIENCIES
Solicitation number
36C78626R0058
Issued by

About this file

This is a Specification section (Section 33 56 10) for temporary fuel storage tanks required for construction activities at Camp Nelson National Cemetery in Kentucky, as part of VA Project No. 833CM3030 (Correct FCA Deficiencies). The specification covers the requirements for one 250-gallon gasoline storage tank and one 250-gallon diesel storage tank to be provided, installed, maintained, and removed by the Contractor.

The temporary storage tanks must be factory-fabricated, UL 142-certified, double-walled aboveground storage tanks with a minimum capacity of 250 gallons each. Required tank features include lockable fill ports, venting systems, fuel level gauges, emergency venting per NFPA standards, and secondary containment to prevent spills and leaks. Tanks must be clearly labeled with appropriate signage and hazard identification per OSHA and NFPA standards. Accessories required include spill containment berms or double-walled containment per EPA regulations, fire extinguishers rated for fuel fires positioned within 10 feet of tanks, leak detection systems with audible and visual alarms, and grounding and bonding equipment per NFPA 30 requirements. Installation must occur on a stable, non-combustible foundation at least 15 feet from buildings, property lines, and ignition sources, with spill containment systems in place before fueling commences. The Contractor is responsible for initial fueling of both tanks and weekly inspections for leaks and damage. At project completion, the Contractor must remove all tanks, containment systems, and associated equipment, remediate any spills or contamination per EPA and local environmental regulations, and restore the site to its original condition. Compliance with NFPA 30, NFPA 31, NFPA 37, UL 142, EPA 40 CFR Part 112 (SPCC Rule), and OSHA 29 CFR 1926 is required.

View the file

Other files

File Type Posted
Amendment 4-833CM3030 - CD1 - Historic Hardware.pdf PDF
Amendment 4-833CM3030 - BID - HA-001 from 20260422 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - CU-105 from 20260107 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - 23 11 13 Fuel Storage Tanks.pdf PDF
Amendment 4-833CM3030 - BID - 037 - CU-105 UTILITY PLAN (R2).pdf PDF
Amendment 4-833CM3030 - BID - 26 29 23 Engine Control and Monitoring.pdf PDF
Amendment 4-833CM3030 - BID - 028 - CP-105 PAVING PLAN (R2).pdf PDF
Amendment 4-833CM3030 - BID - SN-104 105 and X-series from 20260107 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - Historic Pages from 20260422 - 833CM3030 - BID - SET A-004 005 132 133 154 155.pdf PDF
Amendment 4-ConVault Specification with UL 752 Level 8.pdf PDF
Amendment 4-Convault Storage tank 500 GL-telford.pdf PDF
Amendment 4-Convault Brochure 2019 (003).pdf PDF
Amendment 4-833CM3030 - BID - 020 - CG-201 POND AND CRYPT FIELD SECTIONS (R1).pdf PDF
Amendment 4-AE-113 from 20260422 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-AE-113 833CM3030 - BID - SET.pdf PDF
S02 36C78626R0058 Amendment 0004.docx DOCX document
Amendment 4-833CM3030 - CD1 - Historic Preservation.pdf PDF
Amendment 4-SED FCA - 04212022_Camp Nelson.pdf PDF
Amendment 4-833CM3030 - BID - AE-110 from 20260422 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - 328400 Plant Irrigation_10-31-24.pdf PDF
Amendment 4- 36C78626R0058 FuelForce 814 Advanced Fuel Controller Brochure.pdf PDF
Amendment 4-240524-Camp Nelson National Cemetery - KY- SUE Field Report Deliverable.pdf PDF
Amendment 4-833CM3030 - BID - AE-150 from 20260422 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - 07 42 43 Plastic Panel.pdf PDF
Amendment 4-833CM3030 - BID- EQUIPMENT STORAGE GARAGE-AE-141.pdf PDF
Amendment 4-GI-104 from 20260107 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - 231123 NatGas.pdf PDF
Amendment 4- 833CM3030 - BID - 072727 - BARRIER VAPOR.pdf PDF
Amendment 4-3189 ECS Geotechnical Engineering Report - Expansion Area.pdf PDF
Amendment 4-833CM3030 - BID - 329000 Planting.pdf PDF
Amendment 4-3189 ECS Geotechnical Engineering Report - Camp Nelson Cemetery.pdf PDF
Amendment 4-833CM3030 - BID - 050 - S-101 STRUCTURAL PLAN (R2).pdf PDF
Amendment 4-Lightning Protection Asmnt Report_Camps Nelson Cemetery.pdf PDF
Amendment 4-Dispensing System Controller-SafeSite DSC with specs.pdf PDF
Amendment 4-833CM3030 - BID - CD-102 from 20260107 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-AD-150 from 20260107 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - 052 - S-202 MATERIALS STORAGE BLDG. FRAMING (R2).pdf PDF
Amendment 4-3189 ECS Geotechnical Engineering Report - Maintenance Area.pdf PDF
S06_36C78626R0058 Amend. 0003.pdf PDF
S02 Amendement 36C78626R0058 0002.pdf PDF
S02 amendment 2.pdf PDF
S02 Fire Alarm Panel.pdf PDF
S02 Liquidated Damages 833CM3030_CNNC FCA Corrections CONS.pdf PDF
S02 12 from 833CM3030_CNNC FCA Corrections_CONS_BD DRAWINGS_VOL 1_addendum01.pdf PDF
S02 Amendment 36C78626R0058 0001.pdf PDF
P07 Jessamine Camp Nelson Building.pdf PDF
S02_Price Proposal Breakdown.docx DOCX document
S02_Attachment - Past Performance Questionnaire.docx DOCX document
P07 Jessamine Camp Nelson Highway.pdf PDF
S02_Attachment - DOL Payroll Form.pdf PDF
Show 40 more

Latest 50 of 67 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA Project No. 833CM3030 Camp Nelson National Cemetery, KY

Correct FCA Deficiencies 100% CD2

7-8-2025

TEMPORARY FUEL STORAGE TANKS

SECTION 33 56 10 - 1

SECTION 33 56 10

TEMPORARY FUEL STORAGE TANKS

PART 1 – GENERAL

1.1 SUMMARY

A. This section covers the requirements for temporary fuel storage tanks to be used during construction, including one (1) 250-gallon gasoline storage tank and one (1) 250-gallon diesel storage tank.

B. The Contractor shall provide, install, maintain, and remove the temporary fuel storage tanks.

C. The Contractor shall provide initial fueling of the tanks; all subsequent fueling will be the responsibility of the Customer.

D. The Contractor shall ensure proper maintenance and compliance with all safety and environmental regulations.

1.2 REFERENCES

A. NFPA 30 – Flammable and Combustible Liquids Code

B. NFPA 31 – Standard for the Installation of Oil-Burning Equipment

C. NFPA 37 – Standard for the Installation and Use of Stationary Combustion Engines

D. UL 142 – Standard for Steel Aboveground Tanks for Flammable and Combustible Liquids

E. EPA 40 CFR Part 112 – Spill Prevention, Control, and Countermeasure (SPCC) Rule

F. OSHA 29 CFR 1926 – Safety and Health Regulations for Construction

1.3 SUBMITTALS

A. Product Data: Manufacturer’s specifications for fuel storage tanks.

B. Installation Plan: Proposed location, foundation, anchoring method, and spill containment provisions.

C. Safety Plan: Procedures for handling, refueling, spill response, and fire protection.

D. Compliance Documentation: Evidence that tanks meet applicable regulatory requirements.

PART 2 – PRODUCTS

2.1 TEMPORARY FUEL STORAGE TANKS

A. Tanks shall be factory-fabricated, UL 142-certified, double-walled aboveground storage tanks.

7-8-2025

TEMPORARY FUEL STORAGE TANKS

SECTION 33 56 10 - 2

B. Each tank shall have a minimum capacity of 250 gallons.

C. Tanks shall include:

1. Lockable fill ports and venting system.

2. Fuel level gauges.

3. Emergency venting per NFPA requirements.

4. Secondary containment to prevent spills and leaks.

D. Gasoline and diesel tanks shall be clearly labeled with appropriate signage and hazard identification per OSHA and NFPA standards.

2.2 ACCESSORIES

A. Spill containment berms or double-walled containment as required by EPA regulations.

B. Fire extinguishers rated for fuel fires placed within 10 feet of tanks.

C. Leak detection system with audible and visual alarms.

D. Grounding and bonding equipment per NFPA 30 requirements.

PART 3 – EXECUTION

3.1 INSTALLATION

A. Tanks shall be installed on a stable, non-combustible foundation and anchored per manufacturer’s instructions.

B. Tanks shall be located at least 15 feet from buildings, property lines, and ignition sources unless otherwise specified by local codes.

C. Spill containment systems shall be in place before fueling operations commence.

D. Contractor shall perform initial fueling of both tanks upon installation.

3.2 MAINTENANCE

A. Contractor shall inspect tanks weekly for leaks, damage, and proper operation.

B. Contractor shall maintain fueling equipment and containment systems.

C. Any leaks or damage shall be reported immediately and remediated per regulatory requirements.

3.3 REMOVAL

7-8-2025

TEMPORARY FUEL STORAGE TANKS

SECTION 33 56 10 - 3

A. At project completion, the Contractor shall remove tanks, containment systems, and all associated equipment.

B. Any spills or contamination shall be cleaned per EPA and local environmental regulations.

C. Site shall be restored to original condition upon tank removal.

- - - E N D - - -