Geotechnical Engineering Report Summary

This is a Geotechnical Engineering Report prepared by ECS Southeast, LLC for Camp Nelson National Cemetery renovations located at 6980 Danville Road, Nicholasville, Kentucky. The report, dated July 11, 2024 (ECS Project No. 61:3189), documents subsurface exploration and geotechnical analyses for proposed renovations including building, fuel tanks, leach field, pavements, and detention basin modifications. Seven soil test borings were performed using direct push drilling methodology with Standard Penetration Testing, and laboratory testing included natural moisture content and Atterberg limits analysis. The site geology indicates underlying Tyrone Limestone and Oregon Formation with high karst potential, requiring careful consideration of potential solution features such as sinkholes.

The subsurface exploration revealed approximately 1 to 6 inches of topsoil, existing uncontrolled fill in four of seven borings (brown lean clay with gravel and wood fragments, extending 1 to 4 feet below grade), and native soils of low to moderate plasticity lean clay underlain by moderate to high plasticity fat clay. Key geotechnical concerns include soft/near-surface soils, existing fill, high plasticity clays, karst conditions, degradable soils, existing utilities, existing pavements, and weather-dependent construction challenges. Design recommendations specify net allowable bearing pressures of 2,000 psf for continuous wall foundations and 2,500 psf for isolated column foundations on stiff undisturbed native soils, structural fill, flowable fill, or lean concrete. Floor slabs should be designed as grade-supported with a subgrade modulus of 100 pci. Flexible and rigid pavement sections are provided for 20-year design life, with rigid pavements recommended for high-traffic areas. Seismic Site Classification is "C" per the 2018 Kentucky Building Code. Extensive construction monitoring by ECS is recommended to confirm subsurface conditions and ensure compliance with recommendations.

View the file

Other files

File Type Posted
Amendment 4-833CM3030 - CD1 - Historic Hardware.pdf PDF
Amendment 4-833CM3030 - BID - HA-001 from 20260422 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - CU-105 from 20260107 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - 23 11 13 Fuel Storage Tanks.pdf PDF
Amendment 4-833CM3030 - BID - 037 - CU-105 UTILITY PLAN (R2).pdf PDF
Amendment 4-833CM3030 - BID - 26 29 23 Engine Control and Monitoring.pdf PDF
Amendment 4-833CM3030 - BID - 028 - CP-105 PAVING PLAN (R2).pdf PDF
Amendment 4-833CM3030 - BID - SN-104 105 and X-series from 20260107 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - Historic Pages from 20260422 - 833CM3030 - BID - SET A-004 005 132 133 154 155.pdf PDF
Amendment 4-ConVault Specification with UL 752 Level 8.pdf PDF
Amendment 4-Convault Storage tank 500 GL-telford.pdf PDF
Amendment 4-Convault Brochure 2019 (003).pdf PDF
Amendment 4-833CM3030 - BID - 020 - CG-201 POND AND CRYPT FIELD SECTIONS (R1).pdf PDF
Amendment 4-AE-113 from 20260422 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-AE-113 833CM3030 - BID - SET.pdf PDF
S02 36C78626R0058 Amendment 0004.docx DOCX document
Amendment 4-833CM3030 - CD1 - Historic Preservation.pdf PDF
Amendment 4-SED FCA - 04212022_Camp Nelson.pdf PDF
Amendment 4-833CM3030 - BID - AE-110 from 20260422 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - 328400 Plant Irrigation_10-31-24.pdf PDF
Amendment 4- 36C78626R0058 FuelForce 814 Advanced Fuel Controller Brochure.pdf PDF
Amendment 4-240524-Camp Nelson National Cemetery - KY- SUE Field Report Deliverable.pdf PDF
Amendment 4-833CM3030 - BID - AE-150 from 20260422 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - 07 42 43 Plastic Panel.pdf PDF
Amendment 4-833CM3030 - BID- EQUIPMENT STORAGE GARAGE-AE-141.pdf PDF
Amendment 4-GI-104 from 20260107 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - 231123 NatGas.pdf PDF
Amendment 4- 833CM3030 - BID - 072727 - BARRIER VAPOR.pdf PDF
Amendment 4-3189 ECS Geotechnical Engineering Report - Expansion Area.pdf PDF
Amendment 4-833CM3030 - BID - 329000 Planting.pdf PDF
Amendment 4-3189 ECS Geotechnical Engineering Report - Camp Nelson Cemetery.pdf PDF
Amendment 4-833CM3030 - BID - 050 - S-101 STRUCTURAL PLAN (R2).pdf PDF
Amendment 4-Lightning Protection Asmnt Report_Camps Nelson Cemetery.pdf PDF
Amendment 4-Dispensing System Controller-SafeSite DSC with specs.pdf PDF
Amendment 4-833CM3030 - BID - CD-102 from 20260107 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-AD-150 from 20260107 - 833CM3030 - BID - SET.pdf PDF
Amendment 4-833CM3030 - BID - 33 56 10 Temporary Fuel Storage Tanks.pdf PDF
Amendment 4-833CM3030 - BID - 052 - S-202 MATERIALS STORAGE BLDG. FRAMING (R2).pdf PDF
S06_36C78626R0058 Amend. 0003.pdf PDF
S02 Amendement 36C78626R0058 0002.pdf PDF
S02 amendment 2.pdf PDF
S02 Fire Alarm Panel.pdf PDF
S02 Liquidated Damages 833CM3030_CNNC FCA Corrections CONS.pdf PDF
S02 12 from 833CM3030_CNNC FCA Corrections_CONS_BD DRAWINGS_VOL 1_addendum01.pdf PDF
S02 Amendment 36C78626R0058 0001.pdf PDF
P07 Jessamine Camp Nelson Building.pdf PDF
S02_Price Proposal Breakdown.docx DOCX document
S02_Attachment - Past Performance Questionnaire.docx DOCX document
P07 Jessamine Camp Nelson Highway.pdf PDF
S02_Attachment - DOL Payroll Form.pdf PDF
Show 40 more

Latest 50 of 67 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ECS Southeast, LLC Geotechnical Engineering Report

Camp Nelson National Cemetery – Renovations

6980 Danville Road Nicholasville, Jessamine County, Kentucky 40356

ECS Project Number 61:3189

July 11, 2024

Camp Nelson National Cemetery – Renovations July 11, 2024 ECS Project No. 61:3189 Page i

July 11, 2024

Noah Goldman, RA AIA, NCARB Senior Project Manager Walker Federal Services 7820B Womans Mill Road, Unit 162 Frederick, MD 21701

ECS Project No. 61:3189

Reference: Geotechnical Engineering Report Camp Nelson National Cemetery – Renovations 6980 Danville Road Nicholasville, Jessamine County, Kentucky 40356

Dear Ms. Goldman, ECS Southeast, LLC (ECS) has completed the subsurface exploration and geotechnical engineering analyses for the above-referenced project. Our services were performed in general accordance with our agreed scope of work and the subcontract agreement 833CM3030 issued by Walker Federal Services, dated April 26, 2024.

This report presents our understanding of the geotechnical aspects of the project along with the results of the field exploration, laboratory testing conducted, and our geotechnical related design and construction recommendations.

It has been our pleasure to be of service to Walker Federal Services during the design phase of this project. We would appreciate the opportunity to remain involved during the continuation of the design phase and would like to provide our services during construction operations as well to confirm the interpreted subsurface conditions utilized in this report. Should you have any questions concerning the information contained in this report, or if we can be of further assistance to you, please contact the writers.

Respectfully submitted, ECS Southeast, LLC

Sam Abdollahian, Ph.D., P.E. Seth J. Barnett John D Godfrey Jr., P.E.

Geotechnical Department Manager Project Geologist Senior Principal Engineer Sabdollahian@ecslimited.com Sjbarnett@ecslimited.com JGodfrey@ecslimited.com mailto:Sabdollahian@ecslimited.com mailto:Sjbarnett@ecslimited.com

ECS Project No. 61:3189 Page ii

TABLE OF CONTENTS

EXECUTIVE SUMMARY

1.0 INTRODUCTION

1.1 General

1.2 Scope of Services

2.0 PROJECT INFORMATION

2.1 Site Information

2.2 Proposed Construction

3.0 SITE GEOLOGY

4.0 FIELD EXPLORATION AND LABORATORY TESTING

4.1 Subsurface Characterization

4.2 Laboratory Test Summary

5.0 GEOTECHNICAL CONCERNS

5.1 Soft/Near Surface Soils

5.2 Existing Fill

5.3 High Plasticity Clays

5.4 Existing Pavements

5.5 Existing Utilities

5.6 Karst

5.7 Degradable Soils

5.8 Reuse of On-site Soils

5.9 Subgrade Improvement

5.10 Weather Considerations

6.0 SITE CONSTRUCTION RECOMMENDATIONS

6.1 Planning

6.2 Subgrade Preparation

6.3 Structural Fill

6.4 Highly Plastic Clays

6.5 Site Karst Conditions

7.0 DESIGN RECOMMENDATIONS

7.1 Shallow Foundations

7.2 Floor Slabs

7.3 Seismic Design Considerations

7.4 Flexible Pavement Design

7.5 Rigid Pavement Design

8.0 CLOSING

APPENDICES

Appendix A – Drawings & Reports

• Site Location Diagram

• Boring Location Diagram Appendix B – Field Operations

• Refence Notes for Boring Logs

• Geotechnical Boring Logs

• Generalized Subsurface Profiles

• Field Procedures Appendix C – Laboratory Testing

• Laboratory Results

• Laboratory Procedures Appendix D – Supplemental Report Documents and Calculations

• GBA “Important Information About Your Geotechnical Engineering Report”

ECS Project No. 61:3189 Page 1

EXECUTIVE SUMMARY

The following conditions were characteristic of the encountered site and subsurface conditions:

• The project includes renovations to the existing Camp Nelson National Cemetery including building, fuel tanks, leach field, pavements, and the detention basin.

• The site is generally undulating with about 30 to 40 feet of elevation difference across the area of exploration. Surface drainage appeared to be fair.

• Surface materials consisted of approximately 1 to 6 inches of topsoil in most of the borings, except for Borings B-03 and B-04 where approximately 3 to 3.5 inches of concrete underlain by approximately 8 inches of crushed stone was encountered at the surface.

• Existing uncontrolled fill was encountered in four (4) of the seven (7) borings beneath surface materials and generally consisted of brown LEAN CLAY with some gravel, and wood fragments. The existing fill extended to approximately 1 to 4 feet below existing grades.

• Surface materials and fill were generally underlain by native soils which consisted of brown and orangish brown, low to moderate plasticity, soft to hard, moist, silty, LEAN CLAY (CL) with few black oxide nodules, and brown and orangish brown, moderate to high plasticity, very stiff to hard, moist to very moist, silty, FAT CLAY (CH) with few black oxide nodules and few rock fragments.

• Drilling equipment refusal ranged between approximately 6 foot to 22 feet below the existing grades in five (five) of the seven (7) borings. The remaining two (2) borings were extended to 20 feet below existing grades without encountering refusal.

• Groundwater was not observed in the borings at the time of drilling.

GEOTECHNICAL CONCERNS:

− Soft/Near Surface Soils

− Existing Fill

− High Plasticity Clays

− Existing Pavements

− Existing Utilities

− Karst

− Degradable Soils

− Reuse of On-Site Soils

− Subgrade Improvement

− Weather Consideration

DESIGN & CONSTRUCTION RECOMMENDATIONS:

• Soft to firm soils were encountered in the upper approximate 1.5 to 4 feet of four (4) of the seven (7) borings. See Section 5.1 in the report for details. Undercutting and/or stabilization of marginal strength soils should be anticipated in planned construction areas (foundations, floor slabs).

• If existing fill is encountered in foundation excavations, the excavation should be extended to penetrate the existing fill and bear on stiff native soils.

• The proposed building may be supported on conventional shallow foundations bearing on stiff or stronger undisturbed inorganic clay (native materials), structural fill as defined by ECS, flowable fill or lean concrete. The following net allowable design bearing pressures may be used in foundation design:

– 2,000 psf for continuous wall foundations bearing on soil.

– 2,500 psf for isolated column foundations bearing on soil.

• The foundation excavations and floor subgrades should be evaluated by an ECS representative during construction to confirm that encountered conditions are consistent with this exploration.

• Floors may be designed as slabs-on-grade with a subgrade modulus of 100 pci.

• A site class of “C” may be used in seismic design per the 2018 Kentucky Building Code.

• Flexible and/or rigid pavements may be used in proposed pavement areas. Rigid pavements should be considered for entranceways, dumpster pads, or other areas where heavy vehicles will turn on a tight radius or be parked for extended periods of time.

This Executive Summary is intended as a very brief overview of the primary geotechnical conditions that are expected to affect design and construction. Information gleaned from this Executive Summary should not be utilized in lieu of reading the entire geotechnical report.

ECS Project No. 61:3189 Page 2

1.0 INTRODUCTION

1.1 GENERAL

The purpose of this report is to provide the results of our subsurface exploration, engineering analyses, and geotechnical recommendations for the design of foundations, floor slabs, and pavements for the proposed renovations for the Camp Nelson National Cemetery located at 6980 Danville Road in Nicholasville, Kentucky. Also included are geotechnical subgrade preparation guidelines. The recommendations developed for this report are based on project information supplied by Mr. Noah Goldman of Walker Federal Services.

1.2 SCOPE OF SERVICES

Seven (7) soil test borings were performed at the selected locations in the proposed construction areas. A laboratory testing program was also implemented to characterize the physical and engineering properties of the subsurface soils. This report describes our exploratory and testing procedures, presents our findings and evaluations, and includes the following:

• Summary of the project information provided.

• Description of existing site conditions, reported geology, and encountered subsurface conditions.

• Assessment of general adequacy of the site for the intended use from a geotechnical standpoint.

• Site preparation and structural fill placement recommendations.

• Recommended foundation type, design parameters, and construction guidelines.

• Recommended floor slab design parameters and construction guidelines.

• Preliminary recommended pavement design parameters and construction evaluations.

• Site class for seismic design based on the boring data and on available data from the vicinity.

• Other identified geotechnical concerns and recommended additional sampling/testing/analysis.

Our services were provided in accordance with our agreed scope of work and the subcontract agreement 833CM3030 issued by Walker Federal Services, dated April 26, 2024.

ECS Project No. 61:3189 Page 3

2.0 PROJECT INFORMATION

2.1 SITE INFORMATION

SUBJECT SUMMARY OF EXISTING SITE CONDITIONS

Site Address The site is located at 6980 Danville Road in Nicholasville, Kentucky. For location, refer to Site Location Diagram and Boring Location Diagram in Appendix.

General Description & Topography

The site is an existing cemetery with maintenance buildings, paved areas, and a detention basin. The site is generally undulating with about 30 to 40 feet of elevation difference across the area of exploration.

Surface Water Drainage Surface drainage appeared to be fair.

Ground Cover Mostly topsoil with some areas covered with concrete pavement.

2.2 PROPOSED CONSTRUCTION

SUBJECT DESIGN INFORMATION / EXPECTATIONS

Project Description The project includes renovations to the existing Camp Nelson National Cemetery including building, fuel tanks, leach field, pavements, and the detention basin.

Usage Cemetery.

Maximum Column Loads Less than 100 kips (assumed).

Maximum Wall Loads Less than 3 kips per linear foot (assumed).

Finish Floor Elevation EL 905 to 940 feet (assumed).

Maximum Cut/Fill ± 2 feet overall site grading (assumed).

ECS Project No. 61:3189 Page 4

3.0 SITE GEOLOGY

According to the Geologic Map of the Geologic map of the Little Hickman quadrangle, central Kentucky, published by the United States Geological Survey (USGS), and information obtained from the Kentucky Geological Survey (KGS) Geologic Information Service website, the subject site was underlain by the Tyrone Limestone and Oregon Formation.

Site Geology - Underlying Formations1

FORMATION1 DESCRIPTION1 KARST

POTENTIAL2,3

Tyrone Limestone

Primary Lithology: Limestone.

Description:

Limestone is light-brownish-gray, weathers light gray, cryptograined, laminated to thick-bedded, with very pale orange calcareous dolomite as irregular bodies or laminae, some beds without dolomite contain blebs and stringers of clear calcite, some beds are fossiliferous.

High4

Notes:

(1) Source: Geologic Map of the Geologic map of the Little Hickman quadrangle, central Kentucky, published by the United

States Geological Survey, and information obtained from the KGS Geologic Map Information Service website.

(2) Karst is topography commonly formed over limestone or dolomite and characterized by sinkholes, irregular rock conditions, underground drainage, springs, and caves.

(3) The karst potential level is based on the tendency for the site to develop or have karst features and is not necessarily indicative of the actual presence or absence of existing karst activity at the site.

(4) According to the KGS Karst Potential Classification definitions, development of karst features in areas with karst potential listed as “High” is Likely.

ECS Project No. 61:3189 Page 5

4.0 FIELD EXPLORATION AND LABORATORY TESTING

4.1 SUBSURFACE CHARACTERIZATION

SUBJECT SUMMARY OF SUBSURFACE EXPLORATION (1)

Boring Method Direct Push

Sampling Method Standard Penetration Testing (ASTM D-1586)

Number of Borings Seven (7) soil test borings (B-01 through B-07)

Boring Locations Refer to Boring Location Diagram in the Appendix for specific locations.

Boring Depths Refer to Geotechnical Boring Logs in the Appendix.

Logging Method Full-time presence of an ECS engineer or geologist to observe, manage, and document the drilling, sampling, and testing results, and encountered conditions. Water level measurement obtained in boreholes during drilling.

Groundwater Groundwater was not encountered in the borings at the time of drilling.

Refusal (2)

Drilling equipment refusal ranged between approximately 6 foot to 22 feet below the existing grades in five (five) of the seven (7) borings. The remaining two (2) borings were extended to approximately 20 feet below existing grades without encountering refusal.

Notes:

(1) Detailed descriptions of the exploration methods are listed in the Field Procedures section of the Appendix.

(2) Refusal is the term applied to material that cannot be penetrated with drilling tools or has a standard penetration resistance exceeding 50 blows per 6-inch increment or 10 blows with little to no penetration of the split spoon. Refusal may be encountered on continuous bedrock, discontinuous floaters, cemented soil, weathered rock, buried construction debris, buried structures, or other hard subsurface materials.

The following sections provide generalized characterizations of the soil strata. Please refer to the Boring Records and Boring Composites in the Appendix for detail at specific boring locations.

APPROXIMATE

DEPTH (FT)

STRATUM DESCRIPTION 1,2

N-VALUES

BLOWS PER

FOOT

(BPF)2

0.0 – 0.7 N/A

CONCRETE – Approximately 3 to 3.5 inches underlain by Approximately 8 inches of crushed stone. Encountered in B- 03 and B-04.

TOPSOIL – Approximately 1 to 6 inches. Encountered in five

(5) borings.

N/A

0.1 – 4.0 I EXISTING FILL (FILL) – Generally consisted of brown LEAN CLAY with some gravel, and wood fragments, Encountered below the surface material in four (4) of the seven (7) borings.

N/A

0.3 – 6.5 II

LOW PLASTICITY CLAY (CL) – Generally brown and orangish brown, low to moderate plasticity, soft to hard, moist, silty, LEAN CLAY (CL) with few black oxide nodules.

2 to 20

4.0 – 22.1 III

HIGH PLASTICITY CLAY (CH) – Generally orangish brown, moderate to high plasticity, very stiff to hard, moist to very moist, silty, FAT CLAY (CH) with few black oxide nodules and few rock fragments.

10 to 39

Notes:

(1) This summary is generalized and does not describe the actual conditions in each boring. These zones also may not occur at each location. Depths are approximate. Detailed descriptions of the encountered materials are listed on the Geotechnical Boring Logs in the Appendix.

(2) BPF – Blows per Foot

ECS Project No. 61:3189 Page 6

4.2 LABORATORY TEST SUMMARY

Laboratory testing was performed on selected samples obtained during our field exploration operations. Classification and index property tests were performed. The laboratory testing program included:

• Natural Moisture Content

• Atterberg Limits

Each sample was visually classified based on texture and plasticity in accordance with ASTM D2488 Standard Practice for Description and Identification of Soils (Visual-Manual Procedures), including Unified Soil Classification System (USCS) classification symbols, and ASTM D2487 Standard Practice for Classification for Engineering Purposes. After classification, the samples were grouped in the major zones noted on the Geotechnical Boring Logs in the Appendix. The group symbols for each soil type are indicated in parentheses along with the soil descriptions. The stratification lines between strata on the logs are approximate; in situ, the transitions may be gradual.

SUMMARY OF LABORATORY TEST RESULTS (1), (2)

STRATUM

MOISTURE

CONTENT (%)

LIQUID

LIMIT

PLASTIC

LIMIT

PLASTICITY

INDEX

UNIFIED SOIL

CLASSIFICATION

I 21.6 – 25.4 -- -- -- --

II 20.7 – 42.3 46 21 25 CL

III 24.1 – 46.0 73 31 42 CH

Notes:

(1) A more detailed summary of the laboratory test results is included on the Boring Records in the Appendix. Detailed descriptions of the laboratory test methods are listed in the Laboratory Procedures section of the Appendix.

ECS Project No. 61:3189 Page 7

5.0 GEOTECHNICAL CONCERNS

Analysis of the provided project information, observed site conditions, encountered subsurface conditions, and our experience with similar projects, revealed the following important geotechnical considerations. These considerations must be properly addressed in planning, budgeting, design, and construction phases to reduce impacts on construction cost, completion schedule, performance of the building and site improvements, and long-term maintenance of the proposed construction. Our recommendations for addressing these concerns are provided in subsequent sections of this report.

5.1 SOFT/NEAR SURFACE SOILS

• At the time of the subsurface exploration very soft to firm, moist to very moist soils were encountered in the upper approximately 1.5 to 4 feet in four (4) of the seven (4) borings.

• Due to the presence of marginal strength soils at potential bearing elevations, the allowable bearing pressures were lowered to accommodate soils of marginal strength and reduce remediation measures during construction.

• If construction occurs during a period of dry weather (typically summer months), the dried out soils may create a stiffening effect on normally weak clay soils. During proofrolling and subgrade evaluations, it is important to consider the influence of the desiccated upper soils since they can mask the existence of soft soils. This can be accomplished by proofrolling with heavy, large wheeled vehicles such as a pan scraperand making sure that the person observing the subgrade during proofrolling is experienced with these conditions.

• Undercutting and/or stabilization of the upper low strength soils will likely be required in some areas of the site to achieve an adequate construction platform and fill base. The remediation methods used will be dependent on the actual conditions at the time of construction, but could include drying, use of additives such as lime, bridging, and/or undercutting and replacement.

• The depth and extent of undercutting/stabilization required will likely be heavily dependent on the time of year of construction, the weather preceding site work, and the site work techniques employed (site soils are easily disturbed and degraded).

• The marginal strength soils will restrict access by construction equipment to stabilized haul roads unless the entire site is stabilized (e.g., with lime stabilization).

5.2 EXISTING FILL

• Existing uncontrolled fill was encountered in four (4) of the seven (7) borings beneath surface materials and generally consisted of brown LEAN CLAY with some gravel, and wood fragments.

• The existing fill extended to approximately 1 to 4 feet below existing grades.

• The existing fill should be considered uncontrolled fill since no records are available documenting the material quality or content. The unknown quality, consistency, and behavior characteristics of uncontrolled fill creates concerns for the behavior of overlying construction.

• Potential problems for the proposed construction created by the presence of the existing uncontrolled fill include larger than normal total and differential settlements, collapse of buried objects, and poor bearing support. The manifestation of these problems can cause poor foundation, and slab performance.

ECS Project No. 61:3189 Page 8

5.3 HIGH PLASTICITY CLAYS

• High plasticity clays (i.e., plasticity index greater than 30 – generally designated as “CH” in report and on boring logs) were encountered in the borings. Due to their insitu depth, it is unlikely that these materials will influence the construction aspects of this site.

• Highly plastic clays are susceptible to volume changes (shrink/swell problems) with changes in moisture. Accordingly, it is advisable to reduce the potential for moisture changes to the soil because of the shrink/swell concerns and the possible impact on the proposed construction.

• Volume changes associated with the highly plastic clays in the geologic formation underlying the site have the potential to produce damage (e.g., heave or subsidence, and pavement cracking).

• Movement may be cyclic (shrink when dry, swell when wet), continuing to produce distortions that require increased and regular maintenance or repair.

• Typically, the volume changes are not of the magnitude to result in damage that would impair the structural integrity.

• Exposure to prolonged wet or dry weather conditions during construction can result in volume changes in bearing and subgrade materials or problems achieving the required compaction levels.

• The risks associated with highly plastic clays are common for the project vicinity and are not unique to the site. Most of the effects of highly plastic clays can be reduced by employing the design and construction recommendations described in subsequent sections of this report.

5.4 EXISTING PAVEMENTS

• The proposed construction footprint is covered with concrete pavements in some areas.

• Water is commonly trapped under paved surfaces. Accordingly, soft, saturated soils may be present in some areas below these existing surfaces.

• Moisture conditioning of soils underlying these surface materials commonly is necessary and should be anticipated for this project.

• Existing pavements should be left in-place as long as possible, to act as a construction platform.

5.5 EXISTING UTILITIES

• Future access to existing utilities will be difficult if covered by new construction.

• Existing utilities could be damaged by construction activity or by loads from the new structure.

• If existing or former underground utilities are abandoned and not removed or grouted full, soil may migrate into open voids (e.g., open pipes from utilities), causing subsidence of the overlying construction.

• In addition, existing utility lines, if located within proposed construction areas, may cause the new construction to behave unexpectedly due to the variable support conditions caused by old backfill.

• Furthermore, old backfill along utility lines also may provide inadequate support due to poor compaction. The poor support conditions may result in settlement or distress of the

ECS Project No. 61:3189 Page 9 overlying new construction. Based on our experience, existing utility backfill rarely is adequate for support of new foundations.

5.6 KARST

• The site was underlain by a formations that have high potential for solution features, such as an irregular rock surface with pinnacles and slots, isolated rock slabs or “floaters”, sinkholes, soil-filled or open joints and bedding planes, springs, etc.

• According to the Kentucky Geological Survey, there were several closed depressions mapped in the close vicinity of the site. However, signs of closed depressions were not observed during the geotechnical exploration at the location of the exploration.

• Construction in karst areas presents risks that the owner must be willing to accept. The primary geotechnical risks include:

- Settlement, subsidence and/or collapse of the subsurface materials.

- Deposits of soft and/or organic soils in existing sinkholes.

- Irregular upper rock surface, discontinuous rock layers, highly weathered rock, and generally variable conditions.

- Poor correlation between refusal depths and the actual depth to rock.

• Changes to natural sinkhole/spring drainage systems, as well as poor surface drainage, and leaking water or sewer lines can lead to the development of new sinkholes.

• Site development costs typically are higher in karst areas due to the costs associated with reducing the karst risks during design and construction.

• The risks associated with karst topography are common for the project vicinity, are not unique to the site, and can be reduced, but not eliminated, by following the recommendations provided in this report.

• Treatment of individual sinkholes, if encountered, is heavily dependent on the specific conditions unique to each sinkhole, but typically would consist of stabilization of the feature and construction of an inverted filter over the feature (larger rocks progressing to smaller rocks, enclosed in non-woven filter fabric)

5.7 DEGRADABLE SOILS

• Most of the soils on-site are susceptible to degradation. Degradable soils readily lose strength, become soft, and “pump” when subjected to construction equipment, especially under wet conditions.

• Undercutting and/or stabilization of soft clay soils could have a cost impact on the project, especially if not properly addressed in the project documents (e.g., definition of what is poor quality soils and the responsibility for maintenance of these soils once stabilized) or if not properly addressed during construction (e.g., subjected to repeated construction traffic with no protection).

5.8 REUSE OF ON-SITE SOILS

• In general, most of the on-site soils appeared adequate for reuse as structural fill provided the soils are moisture conditioned to appropriate moisture contents for compaction.

• Some wetting, drying, mixing or chemical treatment of the soils may be necessary to obtain workable moisture contents for the on-site soils, especially during wetter times of the year.

• Reuse of the on-site soils will be subject to the weather considerations described subsequently.

ECS Project No. 61:3189 Page 10

5.9 SUBGRADE IMPROVEMENT

• Subgrade improvement of upper soils should be expected due to existing sting pavements, high plasticity clays, and isolated marginal strength soils. The depth and extent of improvement required will be heavily dependent on the time of year of construction, the weather preceding site work, and the site work techniques employed.

• The required extent of improvement will depend to a large degree on when earthwork operations take place as well as on how the earthwork contractor prepares the site. The level of improvement likely will increase if:

- Construction traffic is concentrated along localized unstabilized routes.

- Earthwork occurs during cool, wet periods (typically November through May).

• Subgrade improvement alternatives, if required, include but are not limited to:

- Scarification, drying, and recompaction of surface materials.

- Removal of inadequate materials, and replacement with structural fill.

- Bridging with a thick lift of limestone aggregate.

• Subgrade improvement for stabilization of areas subject to construction traffic or other problematic areas, may require:

- Placement of a geosynthetic or geo-grid in combination with granular fill.

- Chemical stabilization (e.g., kiln dust, lime, or Portland cement).

• Provided construction occurs during the drier time of the year, it would be our expectation that much of the improvement could be achieved by scarifying, drying and recompacting the soils.

• If construction occurs during the wetter periods of the year, alternate remediation may be required (i.e., removal and replacement or chemical treatment).

• Some of the subgrade improvement alternatives provided above are affected by the weather considerations described previously. For example, scarification, drying, and recompaction of surface materials would be difficult during the cool, wet months of the year.

5.10 WEATHER CONSIDERATIONS

• Conducting site work during periods of cool and/or wet weather (typically November to May) can be problematic for sites in the project region.

• Proper compaction of clay fill generally is very difficult to achieve during periods of cool and/or wet weather. Some drying, mixing, or chemical treatment of the soils would be necessary to obtain workable moisture contents for the on-site soils or proposed borrow materials if placed during the cool, wet seasons.

• If compaction of clay fill takes place under wet weather conditions, increased earthwork costs, an extended construction schedule, and soil improvement (likely chemical stabilization) likely would be required. In addition, reuse of the site soils may be severely limited.

• Surface soils tend to be softer during wet weather conditions due to the excess moisture in the near surface soils.

• Weather-softened surface soils tend to result in more undercutting and/or stabilization than would be required during dry weather conditions, which increases site development costs.

• Project specifications should include definitions and require contractors to provide unit rates for subgrade stabilization, removal of inadequate soils, and replacement of

ECS Project No. 61:3189 Page 11 inadequate soils with structural fill appropriate for use during the anticipated construction season.

ECS Project No. 61:3189 Page 12

6.0 SITE CONSTRUCTION RECOMMENDATIONS

6.1 PLANNING

• Adjust project plans, specifications, schedules, and budgets to incorporate the issues discussed in Section 5.0 and the recommendations provided herein.

• It will be critical that the planning of earthwork operations is carefully considered and executed given the presence of degradable soils, New Albany Shale, shallow rock, existing fill, and highly plastic clays.

• Findings and recommendations in this report were based on provided finish floor elevations. As such, ECS should be contacted to provide appropriate values and recommendations for changes to the provided elevations.

6.2 SUBGRADE PREPARATION

• Subgrade improvement of the upper site soils should be expected in isolated areas. The depth and extent of improvement required will be heavily dependent on the time of year of construction, the weather preceding site work, and the site work techniques employed.

• The existing pavements should be left in pace as long as possible to act as a construction platform.

• The following subsections describe our general recommendations for preparing the site subgrade prior to fill placement operations.

Stripping and Grubbing:

• Materials required to be stripped:

− Existing pavements, topsoil, vegetation, large root zones, organic material, and excessively wet, desiccated, frozen, contaminated, or otherwise inadequate materials.

• Minimum extent of stripping:

− 5 feet beyond the building limits.

− 10 feet beyond the pavement limits.

• ECS should observe and document that topsoil and poor surficial materials have been removed prior to the placement of structural fill or construction of structures.

• Stripped material not meeting structural fill requirements should be considered for reuse in landscaped areas only.

Subgrade Improvement:

• Accommodations for the degradable and near surface soils should be expected either via stabilization measures (e.g., undercutting and replacement or lime stabilization), modification to normal construction procedures (e.g., by limiting construction traffic or pumping concrete), or the acceptance of risk.

• The construction budget should be adjusted to reflect the marginal subgrade conditions expected in some areas

ECS Project No. 61:3189 Page 13

Subgrade Evaluation:

• Proofroll the site in the presence of an ECS representative with a pneumatic-tired vehicle (e.g., triaxial dump truck) loaded as recommended by the ECS representative.

• Proofroll subgrades prior to filling or after excavation to grade.

• Proofroll slab and pavement subgrades prior to granular base placement.

• Areas judged by the ECS representative to deflect excessively during proofrolling should be remediated in accordance with ECS recommendations provided at that time.

• Prepare subgrades with a slight slope to maintain surface drainage.

Other Measures:

• Roll subgrade surfaces smooth if rain is expected.

• Slope final subgrades away from the proposed structure.

• Rough grade subgrades high to allow for removal of degraded soil.

• Remove soil frozen or softened by rain.

6.3 STRUCTURAL FILL

Subgrade Requirements:

• Subgrade proofrolled and required improvements completed.

Fill Material Requirements:

• No deleterious debris.

• No rock pieces larger than 3 inches.

• Less than 3% organic material (loss on ignition).

• Maximum dry density of at least 100 pcf according to the Standard Proctor compaction method (ASTM D698), unless specifically reviewed otherwise by ECS.

• Acceptable Unified Soil Classifications (USCS): CL, CH (if approved by ECS) ML, GW, GM, GC, GP, SW, SP, SM, SC.

• Unacceptable USCS classifications: CH (if not approved by ECS), OL, OH, Pt, MH.

• Evaluated and approved by ECS prior to construction.

Fill Placement Guidelines:

• Minimum compaction:

− 98 % Standard Proctor maximum dry density (ASTM D-698).

• Moisture Content:

− Within 2 % of optimum (ASTM D-698) with a plasticity index less than 30.

− At or up to 3 % above optimum (ASTM D-698) if plasticity index greater than or equal to 30.

• Maximum loose lift thickness: 8 inches.

ECS Project No. 61:3189 Page 14

• Compaction test frequency:

− One test per lift for each 5,000 square feet of fill placed.

− Minimum of 3 tests per lift.

• Bench new fill into existing slopes or sidewalls of deep excavations in 1-foot steps or as recommended by ECS at the time of construction.

• Compact and test each lift prior to placing additional lifts.

• Scarify smoothed fill surfaces prior to placing the next lift.

• Maintain positive surface drainage on fill surfaces during placement to avoid ponding of water.

• Roll fill surfaces smooth if rain is expected.

• Rough grade high to allow for removal of degraded surface soils if fill will be exposed to adverse weather conditions.

• Do not place fill on a frozen subgrade. At a minimum, remove frozen material, or allow to thaw and then recompact.

6.4 HIGHLY PLASTIC CLAYS

• The measures provided below will significantly reduce, but not eliminate, the likelihood the proposed construction will be impacted by the presence of highly plastic clays:

– Test the moisture content of subgrade soils. Adjust soil moisture if the results fall outside the range of optimum to plus 3% above optimum.

– Unlined landscape areas and trees should not be placed adjacent to the proposed parking lot, since the vegetation tends to absorb excess water, resulting in shrinkage, especially during droughts.

– Fill comprised of highly plastic clays should be placed at or up to 3% above the optimum moisture content.

– Proper drainage should be provided around the proposed construction (e.g., slope the surface away from the pavements).

• If the risks associated with the highly plastic clays are not acceptable, then:

– Do not place plastic clay fills within 2 feet of the planned finish subgrades.

– Undisturbed plastic clays within 2 feet of planned finish subgrades are removed and replaced with low to moderate plasticity clay fill soils.

6.5 SITE KARST CONDITIONS

• The rock formation mapped at the site is considered to have a high potential for karst features.

• Construction in karst areas presents risks that the owner must be willing to accept. The following measures can reduce these risks:

– Evaluate and proofroll the subgrades prior to fill placement under the direction of an ECS representative.

– Remediate disclosed karst features per recommendations provided by ECS during construction.

– Provide proper drainage around the proposed construction, including sloping the surface away from the pavements.

ECS Project No. 61:3189 Page 15

– The subgrades should be sloped to drain similar to the surface conditions.

Provide outlets for water that may collect in the floor slab gravel base. This may include installing weepholes in catchbasins in pavement areas.

– Provide drainage into storm sewers with granular utility bedding to reduce infiltration and ponding of water that tends to collect in granular backfill.

• It will be necessary to mitigate the karst features discovered within the construction limits when the subgrade is evaluated at the time of construction. In general, mitigation should be accomplished as follows:

– ECS should be retained to observe the encountered conditions at the time of construction to provide remedial recommendations for karst features observed within the construction limits at the time of construction.

– Retain ECS to observe proofrolling of the subgrades to identify sinkholes and springs not detected during the initial site reconnaissance. Extensive proofrolling does not eliminate the risk of building over an undiscovered sinkhole(s). However, it does reduce the risk.

– The ECS representative would provide specific remedial recommendations for these features at the time that site grading and construction is carried out. The details of remediation would depend on the actual subsurface conditions disclosed at each feature as well as the location of the feature. For example, different recommendations would apply for remediation of sinkholes in each of the following locations: building foundation; building floor slab; paved parking lot or drive lane; landscape area; and in a sinkhole that is to be used for stormwater drainage.

• In general, remediation typically would consist of excavating loose and poor-quality materials from the sinkhole and filling with select materials (generally by placing larger stones at the bottom and progressing to smaller stones at the top, encased in a non-woven geotextile fabric) chosen for the actual encountered conditions and overlying structure.

ECS Project No. 61:3189 Page 16

7.0 DESIGN RECOMMENDATIONS

7.1 SHALLOW FOUNDATIONS

General Comments:

• The proposed buildings may be supported on conventional shallow foundations.

• Foundations must penetrate the existing uncontrolled fill and bear on stiff or better undisturbed clay, structural fill, flowable fill, or lean concrete.

• Soft clays were encountered in four (4) of the seven (7) borings and may be present at varying depths between borings. Therefore, some undercutting and backfilling with structural fill, flowable fill or lean concrete should be anticipated during foundation excavation.

• Foundation bearing conditions should be carefully evaluated by ECS during construction.

• The design of the foundation should utilize the following parameters:

FOUNDATION DESIGN RECOMMENDATIONS

DESIGN

PARAMETER

CONTINUOUS WALL

FOUNDATIONS

ISOLATED COLUMN

FOUNDATIONS

Net Allowable Bearing Pressure (1), (3)

2,000 psf 2,500 psf

Acceptable Bearing Material

Stiff Undisturbed Native Soils, Structural Fill, Flowable Fill, or Lean Concrete.

Stiff Undisturbed Native Soils, Structural Fill, Flowable Fill, or Lean Concrete.

Minimum Width 18 inches 24 inches

Depth of Foundations Subject to Freezing

(Below slab or finished grade) (2)

30 inches 30 inches

Depth Foundations Protected from

Freezing 12 inches 12 inches

Estimated Total Settlement (4)

≤ 1 inch ≤ 1 inch

Estimated Differential Settlement (4)

≤ ¾ inch along 50 feet ≤ ¾ inch between columns

Notes:

(1) Net allowable bearing pressure is the applied pressure in excess of the surrounding overburden soils above the base of the foundation.

(2) The recommended net allowable bearing pressures may be increased 33 percent for transient loading.

(3) The 2018 Kentucky Building Code requires a minimum foundation embedment depth of 24 inches for foundations subject to freezing in Jessamine County. However, a minimum embedment of 30 inches is common for commercial development in the project region.

(4) The estimated settlement potential is based on the following: empirical guidelines for the project soil types and consistencies; the assumption that ECS will observe and test each foundation excavation during construction; and the provided project information.

Actual settlements will depend, in part, on site preparation and conditions at each foundation location

ECS Project No. 61:3189 Page 17

• Desiccation or disturbance may result in soil voids or cracks adjacent to foundations, reducing passive and uplift resistance. As a result, for these calculations, the upper 2.5 feet of soils should be neglected for passive resistance.

• Ignore passive earth pressure if the soil against the sides of the foundations may not be present during the life of the structure (e.g., the soil could be excavated or be subject to erosion).

Construction Guidelines:

• The bearing conditions of each foundation should be evaluated by ECS at the time of construction to confirm the presence of adequate bearing soils or rock and to provide recommendations for the remediation of poor soils, if present. This evaluation should be performed before the reinforcing steel is placed in the excavations.

• At rock-bearing foundations, the exposed bedrock should be cleaned of loose rock or soils and scratch tested with a backhoe bucket. An ECS representative should observe the backhoe bucket being scrapped across the exposed rock surface to verify an unweathered rock surface is present.

• Concrete should be placed the same day the foundations are excavated to reduce degradation of the bearing surface due to exposure. Alternatively, a “mud mat” of lean concrete should be placed to protect the bearing surface.

• Disturbed, degraded or loose material should be removed from the excavation bottoms prior to concrete placement.

7.2 FLOOR SLABS

General Comments:

• The limitations and recommendations associated with the site soft soil conditions, karst, and high plasticity clays are described in more detail in Sections 5.0 and 6.0 and should be carefully understood and incorporated into construction planning.

Slab Subgrade Recommendations:

• Recommended Slab Type: Grade supported floor slabs.

• The following graphic depicts our soil-supported slab recommendations.

PARAMETERS FOR FOUNDATION LATERAL RESISTANCE ESTIMATED VALUE (1)

Coefficient of Active Earth Pressure (Ka) (2) 0.41

Coefficient of At-Rest Earth Pressure (Ko) (2) 0.58

Coefficient of Passive Earth Pressure (Kp) (2) 2.46

Moist Unit Weight of Soil (γ) 125 pcf

Base Shear Adhesion [Concrete on Undisturbed Clay] 400 psf

Coefficient of Friction [Concrete on Clay] (μ) 0.30

Coefficient of Friction [Concrete on Rock] (μ) 0.50 Notes:

(1) These design parameters do not include factors of safety. Appropriate factors of safety should be included in the designs.

(2) Provided earth pressure coefficients are based on an assumed internal angle of friction (φ) of 25 degrees for clay. the assumption that ECS will observe and test each foundation excavation during construction; and the provided project information. Actual settlements will depend, in part, on site preparation and conditions at each foundation location

ECS Project No. 61:3189 Page 18

Notes:

(1) Drainage layer should consist of a minimum of 4 inches of well graded crushed stone or angular sand or open-graded coarse gravel. However, if open graded sone is selected then a minimum 2-inch layer of coarse aggregate with fines (e.g., Kentucky DGA) should be used to cap the open graded stone.

(2) Subgrade compacted to 98% maximum dry density per ASTM D698.

• Prepare subgrade in accordance with recommendations contained within this report.

• Subgrade proofrolled by an ECS representative and required improvements completed.

• Subgrade modulus for slab design: 100 pci.

• Unless specifically approved otherwise, do not support floor slabs directly over open-graded coarse aggregate. If coarse aggregate is used as a drainage base, cap the coarse aggregate with a 2-inch (minimum) layer of well-graded aggregate.

• Compact base material in accordance with the structural fill recommendations provided previously.

Construction Guidelines:

• If a vapor barrier is used, an adequate concrete design mix, placement, finishing, and curing techniques should be employed to reduce the potential for differential slab shrinkage, cracking, and curling.

• Special care must be taken to avoid puncturing the vapor barrier during construction. We recommend utilizing the ACI 302 guidelines for placement of the vapor barrier, manufactured sand layer, and concrete as a function of the construction sequence.

• Drying shrinkage and concrete curing methods frequently causes floor slab cracks. Control joints and saw cuts should be installed in accordance with ACI guidelines to control cracking.

• Slab joints should be doweled or keyed to allow rotation of the slab sections without localized vertical displacement.

• Penetrations of the floor slab by fixed objects, such as drains or piping, restrict shrinkage movement and must be isolated to reduce cracking potential.

• Slab-on-grade floor should be structurally isolated from foundation supported walls.

• Backfill along foundation excavations should be carefully controlled to reduce differential slab settlement.

7.3 SEISMIC DESIGN CONSIDERATIONS

• The 2018 Kentucky Building Code (KBC) requires site classification for seismic design based on the upper 100 feet of a soil profile. At least two methods are utilized in classifying sites, namely the shear wave velocity (vs) method and the Standard Penetration Resistance (N-value) method. The second method (N-value) was used in classifying this site.

Concrete Slab Vapor Barrier (if required)

Granular Capillary Break/Drainage Layer

Compacted Subgrade

ECS Project No. 61:3189 Page 19

• Based upon our interpretation of the subsurface conditions, the appropriate Seismic Site Classification is “C” as shown in the preceding table.

• In addition to the seismic site classification noted above, ECS has determined the design spectral response acceleration parameters following the International Building Code (IBC) 2018 methodology. The Mapped Reponses were estimated from the OSHPD Seismic Design Map website (http://seismicmaps.org/). The design responses for the short (0.2-sec, SDS) and 1-second period (SD1) are noted at the right end of the following Table:

• The Site Class definition should not be confused with the Seismic Design Category designation which the Structural Engineer typically assesses.

7.4 FLEXIBLE PAVEMENT DESIGN

Application:

• Primary driving lanes, parking areas or other locations where heavy vehicles or other equipment will not turn on a tight radius or be parked for extended periods of time.

General Comments:

• The limitations and recommendations associated with the site soft soil conditions, karst, and high plasticity clays are described in more detail in Sections 5.0 and 6.0 and should be carefully understood and incorporated into construction planning.

• The pavement sections below are guidelines that may or may not comply with local jurisdictional minimums.

SEISMIC SITE CLASSIFICATION

Site Class

Soil Profile Name Shear Wave Velocity, Vs, (ft./s) N value (bpf)

A Hard Rock Vs > 5,000 fps N/A

B Rock 2,500 < Vs ≤ 5,000 fps N/A

C Very dense soil and soft rock 1,200 < Vs ≤ 2,500 fps >50

D Stiff Soil Profile 600 ≤ Vs ≤ 1,200 fps 15 to 50

E Soft Soil Profile Vs < 600 fps <15

GROUND MOTION PARAMETERS [IBC 2018 Method]

Period (sec)

Mapped Spectral Response

Accelerations (g)

Values of Site Coefficient for Site Class

Maximum Spectral Response Acceleration

Adjusted for Site Class (g)

Design Spectral Response

Acceleration (g)

0.2 SS 0.183 Fa 1.2 SMS=FaSs 0.220 SDS=2/3 SMS 0.146

1.0 S1 0.093 Fv 1.7 SM1=FvS1 0.159 SD1=2/3 SM1 0.106

http://seismicmaps.org/

ECS Project No. 61:3189 Page 20

Subgrade Requirements:

• Prepare subgrade in accordance with recommendations contained within this report.

• Proofroll under the direction of an ECS representative and complete required improvements.

• Pavement subgrades sloped to facilitate drainage.

Drainage Requirements:

• Permit water movement beneath curbs at the subgrade level.

• Design catch basins to include finger drains at the granular base level.

Construction Guidelines

• Pavements should be constructed in accordance with the construction and material guidelines set by the Kentucky Transportation Cabinet.

• Granular base should be compacted in accordance with the controlled fill recommendations provided in a previous section.

• In-place density, thickness, and gradation tests should be conducted by a ECS representative on the pavement components during construction to confirm compliance with project specifications.

7.5 RIGID PAVEMENT DESIGN

Application:

• Rigid pavements are adequate wherever flexible pavements can be used. Rigid pavements often provide better service for dumpster aprons, entranceways, or other areas where heavy trucks will turn on a tight radius or be parked for extended periods of time.

FLEXIBLE DESIGN PARAMETERS

DESIGN METHOD AASHTO Guide for Design of Pavement Structures (1993)

DAILY EQUIVALENT 18-KIP AXLE

LOADS

10 (Light Duty)

30 (Heavy Duty)

DESIGN LIFE 20 Years

CALIFORNIA BEARING RATIO (CBR) 3 (estimated)

RELIABILITY 85%

TERMINAL SERVICEABILITY INDEX 2.0

RECOMMENDED FLEXIBLE PAVEMENT SECTIONS (1)

PAVEMENT SECTION HOT MIX ASPHALT

WEARING SURFACE

HOT MIX ASPHALT

BINDER OR BASE

GRANULAR BASE

KENTUCKY DGA

Light Duty 1 ½ inches 2 inches 8 inches

Heavy Duty 1 ½ inches 2 ½ inches 10 inches

Notes:

(1) It should be noted that although flexible pavement for the 20-year design period is structurally sound, an asphalt overlay is usually necessary after 7 to 12 years due to normal wear and exposure of the surfacing layer. In general, asphalt pavement should be sealed approximately 3 to 5 years to extend the life of the asphalt.

ECS Project No. 61:3189 Page 21

General Comments:

• The limitations and recommendations associated with the site soft soil conditions, karst, and high plasticity clays are described in more detail in Sections 5.0 and 6.0 and should be carefully understood and incorporated into construction planning.

• The pavement sections below are guidelines that may or may not comply with local jurisdictional minimums.

RECOMMENDED RIGID PAVEMENT SECTIONS

PAVEMENT SECTION PORTLAND CEMENT CONCRETE

GRANULAR BASE

KENTUCKY DGA

Light Duty 5 inches 4 inches

Heavy Duty 7 inches 5 inches

Subgrade Requirements:

• Prepare subgrade in accordance with recommendations contained within this report.

• Proofroll under the direction of a ECS representative and complete required improvements.

• Pavement subgrades sloped to facilitate drainage.

Drainage Requirements:

• Permit water movement beneath curbs at the subgrade level.

• Design catch basins to include finger drains at the granular base level.

Concrete Recommendations:

• 4,000 pounds per square inch (psi) minimum 28-day compressive strength.

• 4 to 6 percent entrained air.

• Proper joint spacing to control shrinkage cracking.

• Dowels at construction joints to properly transfer loads between pavement sections.

• Control joints where concrete pavement abuts fixed structures or protrusions.

RIGID PAVEMENT DESIGN PARAMETERS

DESIGN METHOD ACI Guide for the Design and Construction of Concrete Parking Lots (ACI…