S02 36C78626R0058 Amendment 0004.docx
DOCX document 994 KB Posted
- Solicitation number
- 36C78626R0058
About this file
This is Amendment 0004 to Solicitation 36C78626R0058 issued by the Department of Veterans Affairs National Cemetery Administration for correcting Facilities Condition Assessment (FCA) deficiencies at Camp Nelson National Cemetery in Nicholasville, Kentucky. The amendment extends the proposal deadline from November 13, 2026 to December 7, 2026 and provides responses to 150 pre-bid RFI questions, amended drawings, specifications, and a change log for the project.
The project involves comprehensive renovation and restoration work at the cemetery, including facility exterior closure commissioning, hazardous materials abatement (historic windows with lead-based paint in antique glazing putty), fence and gate restoration with specialized coating systems, masonry repair and repointing, structural modifications to multiple buildings, utility infrastructure improvements including new fuel storage tanks (500/500-gallon above-ground), fire alarm system upgrades, and site work including pond and crypt field sections. Key deliverables include separate price proposals for the base bid and three bid alternates evaluated in chronological order, with a total performance period of 360 calendar days for all awarded items. The work requires compliance with Kentucky Transportation Cabinet and local traffic control standards, maintains ongoing cemetery operations and approximately 20 interments per week, and mandates separate dedicated Site Safety and Health Officer and Quality Control personnel. The contractor must provide temporary office and restroom trailers for government staff, handle equipment relocation, obtain NPDES permit, coordinate with National Park Service regarding adjacent parkland, and ensure historic preservation compliance for buildings subject to State Historic Preservation Office (SHPO) approval. The RFI responses clarify scope ambiguities regarding fence quantities and finishes, crypt field identification layer replacement using new materials, building envelope testing requirements, plumbing fixture specifications with manufacturer details, and commissioning requirements limited to Building A restroom/wash bay (excluding the wash bay itself).
View the file
Other files
Show 40 more
Latest 50 of 67 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
11-10-2026
833CM3030
36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle VA 22172
36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle VA 22172 To all Offerors/Bidders
36C78626R0058
X
Please see page 2-42 for modification description.
Clarelle Sylvain Contracting Officer
The purpose of this amendment is to:
1. Answer questions posed during the RFI period of the solicitation.
2. Extending the RFP answer from 11/13/2026 to 12/7/2026
3. Provide amended Specs and drawings for this requirement. The files named (Amendment4-833CM3030) are associated with the Q&A associated with the RFI’s.
RFI RESPONSES
AMENDMENT 004 | AMENDED DRAWINGS, SPECIFICATIONS & CHANGE LOG
| PROJECT |
| 833CM3030 – Correct FCA Deficiencies at Camp Nelson National Cemetery |
| SOLICITATION NO. |
| 36C78626R0058 |
| AMENDMENT |
| 004 |
AMENDED DRAWINGS
| DRAWING |
| TITLE |
| GI-002 |
| General Notes |
| GI-104 |
| Phase Plan |
| HA-001 |
| Hazardous Materials Abatement Notes and Schedules |
| CD-102 |
| Site Demolition Plan |
| CG-201 |
| Pond and Crypt Field Sections |
| CP-105 |
| Paving Plan |
| CU-105 |
| Utility Plan |
| S-101 |
| Structural Plan |
| S-202 |
| Materials Storage Building Framing |
| AD-150 |
| Historic Maintenance Garage Demolition |
| AE-150 |
| Historic Maintenance Garage |
| AE-110 |
| Public Restroom & Wash Bay Building Floor Plan |
| AE-141 |
| Equipment Storage Garage Elevations |
| SN-104 |
| Historic Brick Stable Security Plan |
| SN-105 |
| Maintenance Storage Building Security Plan |
AMENDED SPECIFICATIONS
| SECTION |
| TITLE |
| 07 27 27 |
| Fluid-Applied Membrane Air Barriers, Vapor Retarding |
| 23 11 13 |
| Fuel Storage Tanks |
| 32 17 23 |
| Facility Natural Gas Piping |
| 32 84 00 |
| Plant Irrigation |
| 32 90 00 |
| Planting |
| 33 56 10 |
| Temporary Fuel Storage Tanks |
Prebid RFIs and Responses – AMENDMENT 004
SOLICITATION NUMBER: 36C78626R0058
AMENDMENT 004
PROJECT TITLE: 833CM3030 Correct FCA Deficiencies at Camp Nelson NC Question 1 Fence limits and quantity: CI-201 Keynote 01 shows 480 + 24 + 1,548 nominal LF (2,052 LF). GI-103 Keynote 15 describes about 350 LF of front metal fence. Does the 350 LF overlap the CI-201 front segment, and which front limit/length govern?
Answer 1 The 350 LF overlaps the CI-201 front segment. Refer to CI-201 for full limits.
Question 2 Fence preparation and finish: CI-201 specifies wet abrasive blasting and Tnemec 66 / 1072. Volume 1 A-001 specifies 94-H2O / N69 / 1071 and a 15-year color/gloss warranty. Volume 2 AP-100, the historic wall-option sheet, gives conservation cleaning and an alkyd system for historic ferrous metal. Please identify the governing preparation/coating system and limits for each fence/gate area, including the approximately 350-foot frontage.
Answer 2 Volume 1 A-001 specifies 94-H2O… for historic metal restoration, not non-historic. The general field fencing pictured on CI-201 is non-historic and should follow direction on that page. Wrought iron, cast iron, and other materials older than modern metals shall be treated accordingly (i.e. Volume 2 treatment for Volume 2 scope) Question 3 Replacement scope: FCA item 350905 says replace 23 fence sections and 15 base rails. Is this replacement part of the base bid in addition to recoating? Please identify the locations and replacement size/profile/detail, and whether the 15 base rails are additional to the 23 replacement sections.
Answer 3 Contractor is to include the replacement of (23) twenty-three +/- 20’ fence sections and 15 base rails in addition to the recoating, locations to be determined during recoating process and shall be approved by COR prior to installation.
Question 4 Gate scope: FCA item 350911 calls for scraping, preparation and repainting of the wrought iron hinged gates at the newer main front entry. Please distinguish these from the older historic entrance/pedestrian gates in FCA 350885/350887 and Volume 2 AP-100. Confirm base-bid versus alternate limits and the preparation/finish for each gate group and its metal components.
Answer 4 FCA Item 350911 refers to the gate directly off of Danville Road, as pictured below. This entry gate information can be found on AE-001 and 002 and as part of Volume 1, they should be included in the base bid. Images and information on the historic section gates can be found in Volume 2 on AP-100 and AS-205.
FCA Items 350885/350887 refer to the historic portion of the cemetery at the end of Camp Nelson Cemetery Road past the Lodge.
MAIN ENTRY, VOLUME 1
HISTORIC SECTION, VOLUME 2
Question 5 Containment: CI-201 requires Class 3 or higher containment in designated areas. Please identify those fence/gate areas and any applicable access limits.
Answer 5 Entire fence length requires containment.
Question 6 Existing coating tests: Please provide fence/gate lead and other hazardous-metal test results, if available. If testing is not available, please define the required bid allowance or removal/disposal basis and who is responsible for testing. The building hazardous-material notes do not establish the fence/gate coating condition.
Answer 6 See ‘20240726 - Camp Nelson - Asbestos & HazMat Inspection Report.pdf’ Question 7 Bollards: CP-105 repeats Keynote 05, "(4) Bollards 12/CP-202," at the maintenance building; AE-120 also shows four front bollards. Please confirm the total base-bid quantity and locations, including the front and east-side groups, so architectural and civil views are not counted twice. Are the four pipe-bollard symbols at S-202 material storage additional Alternate 2 work?
Answer 7 CP-105 and AE-120 confirm the same four bollards. On S-202, as part of the materials spoils shed, bollards are part of Alternate 2 work.
Question 8 Construction-entry gate: GI-103 Keynote 11 calls for a 16-foot chain-link double-swing gate. Does this gate remain after construction, and which height, fence type and gate detail govern?
Answer 8 The Construction gate to be removed after custody transfer/project completion by the Contractor.
Question 9 Storage steel: S-202 detail 10 identifies MC8x20 hot-dip-galvanized steel channel purlins. Does this apply to all roof purlins? Please identify the required spacing/layout and confirm any member-design responsibility beyond the connection design already listed on the sheet.
Answer 9 Yes, applies to all purlins. Layout pattern shown in elevation views 4 and 5, sheet S-202. 9 rows of purlins Question 10 Garage lintel: AD-150 note 3 enlarges an opening to 3 feet 4 inches and calls for a new steel lintel. Please identify the lintel size, bearing and supporting detail.
Answer 10 AD-150 REVISED SPECIFYING THE FOLLOWING LINTEL SIZE: (2) ASTM A36 L5 x 5 x 5/16 embed minimum 5” into wall beyond door. Selective removal of existing brick is required and shown on elevations and plans. Brace opening during construction.
Question 11 Field verification: May bidding subcontractors arrange a site visit to measure the fence, repair sections, gates and new railings before bids are due? Please provide the access contact and procedure.
Answer 11 Please contact the COR, Brian Ballweg @ brian.ballweg@va.gov for coordination of site access.
Question 12 Please confirm that the proposal deadline is October 15, 2026, at 10:00 a.m. Eastern and revise SF 1442 Item 13, which states September 15, 2026.
Answer 12 Amendment 003 will extend the proposal deadline.
Question 13 Please provide the RFI form referenced in Section L.10.1 or confirm that an offeror-generated RFI form is acceptable.
Answer 13 No RFI form will be provided by the Government. An offeror-generated RFI form is acceptable.
Question 14 Please provide the missing base-bid drawings. The supplied set appears to stop at drawing/page 154, while GI-001 lists 166 base drawings, including SH-104, SH-105, and X-101 through X-109.
Answer 14 Drawings included in Amendment 4.
Question 15 Please verify that all drawing books referenced as “bk1 through bk13” have been issued and identify the complete drawing-book list.
Answer 15 See revised drawings and technical coversheet for full list of amended drawings.
Question 16 Please provide the limitations-on-subcontracting certification attachment referenced in Sections J and L.10.2.2.
Answer 16 See updated attachments Question 17 Does the government require a separate Price Proposal Breakdown for the base bid and each alternate, or one consolidated CSI breakdown?
Answer 17 NCA requires a separate Price Proposal Breakdown for the base bid and each bid alternate price proposal separated from the base bid.
Question 18 Confirm the government’s intended order of priority for awarding the three alternates and whether all alternates are included in the total evaluated price.
Answer 18 NCA will award the three alternate bid items in chronological order (01, 02, 03). The bid alternates are included in the total evaluated price.
Question 19 Confirm that the 360-calendar-day period includes all awarded alternates and identify whether any alternate receives additional time.
Answer 19 The Period of Performance for all bid items is a total of 360 calendar days. No bid alterates received additional time.
Question 20 For Alternate 3, provide the anticipated removal depths and quantities for topsoil, fill, and hardened identification layer. Clarify whether unsuitable or contaminated material must be hauled offsite.
Answer 20 N/A Question 21 For Alternate 3, confirm the number of crypt lids anticipated to require repair or replacement and whether an allowance should be included for damaged crypt components.
Answer 21 N/A Question 22 Confirm that the hazardous-material survey represents the complete abatement scope. Are additional destructive surveys required before demolition, and is mold remediation included?
Answer 22 Confirmed. No destructive surveys required prior to demolition.
Question 23 Identify the manufacturers and service providers for existing fire alarm, security, CCTV, access-control, and monitoring systems. Will proprietary programming and monitoring fees be contractor-provided?
Answer 23 Manufacturer and panel model is “FireWarden-100-2/E/C/ Addressable Fire Control Panel.
Question 24 Division 28 requires the bidder to ask whether pre-delivery security-system testing is required. Please confirm whether a pre-delivery test will be required.
Answer 24 Pre-delivery test is required.
Question 25 Confirm the required capacity, duration, servicing, utility connections, and accessibility requirements for the temporary office and restroom trailers.
Answer 25 See GI-104 and CI-101 and below.
Temporary Office Capacity: 12 cemetery staff in field Duration: For the period of construction per the contractor’s phasing/schedule and Government acceptance of renovated facilities.
Servicing: Maintain existing cleaning schedule - current restrooms are cleaned twice everyday- first in the morning then before we leave at 4:30pm Utility Connections: Contractor to verify existing conditions, see plans and specifications; CI-101 calls for water and sewer tanks Accessibility Requirements: Accessible ramps required. See plans and specifications Temporary Restroom Capacity: We average around 20-30 visitors a day. For holidays and high traffic events, cemetery augments current restroom capacity with portable toilets contracts.
Duration: Same as above Servicing: Same as above Utility Connections: Contractor to verify existing conditions and determine best points of connections to maintain service throughout construction and/or provide tanks per contractor’s phasing/schedule. See plans and specifications.
Accessibility Requirements: Accessible ramp(s) required to accessible restroom(s). See plans and specifications.
Question 26 Identify which wage determination—Building, Heavy, or Highway—applies to each principal work activity.
Answer 26 BUILDING Question 27 General Note GI-002 references New York City transportation requirements. Please confirm this reference is not applicable and identify the governing Kentucky/local traffic-control standard.
Answer 27 GI-002 REVISED. DO NOT BLOCK ROADS OR SIDEWALKS. PROVIDE FLAGGERS AND TRAFFIC CONTROL SIGNAGE WHEN ENTERING AND EXITING THE SITE. CONTRACTOR SHALL COMPLY WITH ALL APPLICABLE KENTUCKY TRANSPORTATION CABINET (KYTC) REQUIREMENTS, CITY OF NICHOLASVILLE REGULATIONS, AND JESSAMINE COUNTY TRAFFIC CONTROL STANDARDS.
Question 28 Please confirm if this project is state, federal and or contractor tax exempt?
Answer 28 The project is not tax exempt. The bid amount must include all applicable Federal, State, and local taxes. Also reference FAR 52.229-3 Federal, State, and Local Taxes in the solicitation.
Question 29 Please confirm is contractor can triple hat the project? Meaning site super can perform the roles of QA and SSHO or will the government require multiple individuals to fill these roles?
Answer 29 No, the Contractor may not triple hat the project. SSHO has to be a separate qualified individual from the Prime Contractor’s Superintendent and/or Quality Control Manager with duties only as the SSHO.
Question 30 If multiple individuals, how many individuals?
Answer 30 See Answer 29 response.
Question 31 Please confirm the size and diameter of the vegetation to be removed along the masonry fence adjacent to the burial grounds.
Answer 31 TREES ARE THE ONLY VEGETATION NOT TO BE REMOVED. SIZE AND DIAMETERS OF NON-TREE PLANTS VARY.
Question 32 Please confirm if the roof on the main building is to remain?
Answer 32 If by main building you mean Building A, the Restroom and Wash Bay building, yes. We are not doing anything that affects the roof on that building.
Question 33 Please confirm if the new fuel storage is to be above or below ground? Is there an approximate size?
Answer 33 Proceed with above-ground fuel storage as shown in drawings. 500/500.
Question 34 The solicitation requires past performance involving pre-placed burial crypts, in-ground cremains, and columbarium work. However, our review of the plans and specifications found no scope for installation or construction of these items. The documents appear to require protection of existing crypt fields and columbarium walls only. Accordingly, please revise the past-performance requirement to remove experience specific to pre-placed crypt installation, in-ground cremains, and columbarium construction.
Answer 34 The past performance will not be revised; past performance with cemetery construction is essential to the scope of work being performed at the Camp Nelson National Cemetery.
Question 35 If the monthly inspections are required, can they be performed by our Corporate Safety Officer?
Answer 35 In reference to random monthly inspections, the specifications are clear that these inspections are to be conducted by a Certified Safety Professional with specialized knowledge of construction safety or a certified construction Safety and Health Technician that are not a part of the project.
Question 36 The total scope of specification 07 08 00Facility Exterior Closure Commissioning is unclear. Please answer all subitems below:
0. What buildings require building envelop testing?
0. What type of testing; i.e. air/moisture, heat loss around the buildings, etc?
0. Does the entire building need testing?
0. Do the exterior doors and windows get air/water testing?
Answer 36
0. Bldg A
0. Air/moisture, heat loss
0. Not the wash bay.
0. Yes Question 37 Our envelop testing firm is telling us that buildings with overhead doors cannot pass envelop testing. Please confirm the buildings with overhead doors are not included in the testing?
Answer 37 Building A, the Restroom and Wash Bay building require testing. However, the Wash Bay itself does not.
Question 38 Spec 01 00 02 1.4.B.C.1 says, “The General Contractor shall provide unarmed guards at the project site when theft or vandalism warrants.” Will the GC need to provide unarmed guards at the project? If unarmed guards are required, does this apply during work hours or after?
Answer 38 The Contractor is not required to provide unarmed guards or security at the project. Site security protocols are the responsibility of the Contractor. The Government is not responsible for vandalism to the project site or Contractor lost/stolen materials and equipment.
Question 39 01 00 02 1.14 says to provide professional surveyor. Please identify areas to be surveyed. Does this apply to only the areas disturbed by work under this contract?
Answer 39 Correct. This would apply to the Materials Spoils area where a new building will be built under that Option. Concrete pavement, asphalt pavement, and site grading horizontal and vertical layout shall be performed by land surveyor, as required by those respective specifications.
Question 40 There is a phasing note on GI-104 calling for relocation of GOV staff furniture, tools, lockers, refrigerator and microwave to temp trailers/storage. Is relocation back to the renovated spaces after construction included in this contract as well?
Answer 40 Yes.
Question 41 Phasing Note 7 says to complete paving in contractor trailer area. Is this referring to the concrete paving replacement work inside the fenced area with the buildings?
Answer 41 YES Question 42 Phase Plan 1/GI-104 shows a 56’ long office trailer. Is this the contractor’s office trailer or the GOV office trailer?
Answer 42 56’ Long office trailer is called the Construction Trailer in 1/G-104 because it is for the contractor’s office use.
Question 43 Note #03 on 3/CP-105 shows new concrete paving per section 3/CP-201. This section shows 8” thick concrete paving with a barrier curb. This new concrete paving appears to be replacing asphalt paving. This asphalt paving does not include curbs. Please confirm this section of paving shall match section 3/CP-201.
Answer 43 3/CP-105 area is not asphalt. It is existing concrete to be replaced with new concrete and shall be detailed per 3/CP-105 with barrier curb at the outer radius, opposite the drain.
Question 44 Note #04 sheet CD-102 calls for selective replacement of septic leach field piping. This is too vague of a description to accurately bid this work. To avoid large variation in pricing between bidders please quantify an assumed linear footage of pipe replacement.
Answer 44 See Note 5, Sheet CU-105.
Question 45 Sheet CG-101 shows a 2” water line at the pond. There is not a note for this water line. Is this a new water line or is it existing?
Answer 45 New.
Question 46 Sheet CG-201 shows a section at the edge of the pond 4/CU-201. However, section 4/CU-201 shows a buried manhole. Please provide the correct section for the pond as shown on sheet CG-201.
Answer 46 See revised sheet CG-201, reference numbers corrected.
Question 47 The section of historic stone wall to be restored is right against the chain-link fence surrounds the maintenance bldgs. Behind the admin bldg. Will this fence need to be removed and reinstalled in places where repairs are needed to the stone wall?
Answer 47 Yes Question 48 Does this project contain any asbestos, lead, or mold remediation?
Answer 48 The only hazmat are on the historic windows and can be found in the antique glazing putty.
Question 49 Can orange snow fence be used in lieu of welded wire fabric fence for tree protection?
Answer 49 Bid should follow materials specified in the plans and specifications. Substitutions will be handled at the discretion of Question 50 Can existing topsoil and fill be reused at locations of crypt identification layer?
Answer 50 Topsoil may be reused if it meets specifications. Fill beneath topsoil is hardened and must be removed from the Cemetery.
Question 51 Please define selectively repaired lateral drains for septic leach field as shown on CU-105. If this work is not clearly defined, it will result in discrepancies in contractor proposal pricing.
Answer 51 See Note 5, Sheet CU-105 Question 52 Many drawings are missing letters in words (see A-004, AE132, AE154, AP-100, etc.). Please provide corrected sheets for accurate pricing.
Answer 52 Need more information. Drawing text appears complete.
Question 53 Sheet AD-111 notes ceilings are to remain in some rooms where walls are being demolished. Please advise if the contractor is to remove these ceilings.
Answer 53 All ceilings are to be demolished except for Multipurpose Room and IT Room (and restroom vestibule). As indicated, a portion of the ceiling of the Multipurpose Room is to be demolished, the rest shall remain and be protected in place during construction.
Question 54 Sheet AD-111 Room A-103 does not show a ceiling type. Please identify.
Answer 54 It does. It is scheduled to be demolished and will be replaced with new per AE-111.
Question 55 For the AST replacement, please confirm whether the existing conduit and wiring may be reused, assuming this is a one-for-one replacement.
Answer 55 The ATS is new and not a replacement. The intent is to reuse the existing raceway where possible and pull new conductors from the ATS to the MDP.
Question 56 AE-131 Note 5 (along with other drawings) states to repair masonry walls. For bidding purposes, please quantify the amount of brick repair square footage expected per building.
Answer 56 Assume 36 SF of antique brick repair. see AD-131 for locations, mainly rebuilding masonry arches that have fallen out of alignment with the façade brick.
Question 57 AE-131 Note 6 (along with other drawings) states to repoint exterior brick walls. For bidding purposes, please quantify the amount of repointing square footage expected per building.
Answer 57 Assume 1,200 SF of historic exterior masonry raking, cleaning, and repointing.
Question 58 Plumbing fixture schedule on PN-601 lists “Per Owner/Architect” on several fixtures. Pricing for many of these items varies widely between manufacturers. Please provide manufacturer model number and specifications for all fixtures listed in this schedule.
Answer 58 See information below.
ICE-1 Manitowoc / Pentair Model SFA292, 30" wide Touchless Ice Dispenser with Water Valve https://www.manitowocice.com/product/fam_vnbytt/SFA292--30-wide--Touchless-Ice-Dispenser-with-Water-Valve# DF-1 and 2: Elkay ezH2O Model EZSTLDDWSSK, non-filtered https://www.elkay.com/products/drinking-water/bottle-filling-stations/standard-wall-mount/ezstlddwssk SHW-1: Uline Model H-9408 Boot-Boy® Industrial Boot Cleaner https://www.uline.com/Product/Detail/H-9408/Shoe-Boot-Scrapers/Boot-Boy-Industrial-Boot-Cleaner?pricode=WC1256&gadtype=pla&id=H-9408&ad_group_id=155254739695&gad_source=1&gad_campaignid=10688098445&gbraid=0AAAAAD_uetNhzmM3A4F8EYfjVqJ1K9suF&gclid=Cj0KCQjw8ofWBhCHARIsANBj4LsKsOvBsR3IWhlNMGLVbmWLM9OJU6JAH1CHKY6SYopIqr1ofkRZXSMaAoBeEALw_wcB SNK-1: Uline Model H-11726 Stainless Steel Wall-Mount Hand Sink https://www.uline.com/Product/Detail/H-11726/Stainless-Steel-Workbenches/Stainless-Steel-Wall-Mount-Hand-Sink?pricode=WC7788&gadtype=pla&id=H-11726&ad_group_id=181867549648&gad_source=1&gad_campaignid=11612151768&gbraid=0AAAAAD_uetPRWaY6H39o3ws8hUJtl7GG6&gclid=Cj0KCQjw8ofWBhCHARIsANBj4LuhKYgrswfRxfh01CuTx6zi0riAjX_9Etgk9PPro5I6hCUOQ0VjytQaAt1TEALw_wcB Question 59 AD-110 shows walls being demolished in public restrooms/wash bay buildings. There does not appear to be any indication of the wall types in the building. Please provide a drawing indicating wall types at each wall to be demolished.
Answer 59 Walls to be demolished are metal stud walls.
Question 60 2/AE115 shows an interior vapor barrier. There does not appear to be a specification for this material. Please provide a specification or basis of design for accurate pricing.
Answer 60 We will include the VA specs for vapor barriers. The direction is for the Contractor to match the existing adjacent, SEE 07 27 27.
Question 61 2/AE115 shows an exterior permeable barrier. There does not appear to be a specification for this material. Please provide a specification or basis of design for accurate pricing.
Answer 61 These details are from the original construction of the building. We will provide an air barrier spec. However, the contractor is directed to match existing.
Question 62 Note 4 on AD-120 states to “remove and dispose of all rot, repair damaged rafters and soffit as needed”. For bidding purposes, can the government provide an assumed quantity of rot removal, rafter repair, and roof soffit repair?
Answer 62 1,600 SF Question 63 Note 5 on AD-120 states to “remove flaking paint on rafters, fascia, and soffit”. Does this apply to all painted wood surfaces on a building or just certain areas on the painted surfaces? Please provide clear direction or, for bidding purposes, can the government provide an assumed quantity of paint removal on these surfaces?
Answer 63 200 SF
Question 64 Note 6 on AD-120 states to “remove staining, efflorescence, and bio growth from masonry surfaces”. Does this apply to entire buildings or just certain areas on a building? Please provide clear direction or, for bidding purposes, can the government provide an assumed quantity of masonry cleaning?
Answer 64 Entire building Question 65 Price breakdown attachment Reference: RFP Section L.10.2.2; supplied Price Proposal Breakdown The price breakdown attachment is labeled for Alabama National Cemetery rather than Camp Nelson. Can we use this form with the Camp Nelson project information, or will a corrected form be issued?
Answer 65 See updated attachments.
Question 66 Contract duration Reference: SF 1442, Item 11; Drawings GI-002 and GI-104; Spec. 01 32 17 The 360-calendar-day period covers several occupied buildings, historic restoration, sitework and phased turnovers. Does this period include any awarded alternates and all required agency reviews and inspections? Given the restrictions on sequencing and cemetery operations, would the VA consider extending the performance period to 540 calendar days?
Answer 66 See Response #19.
Question 67 Required sequence of work Reference: Drawings GI-002 and GI-104; Spec. 01 00 02, Section 1.7 GI-104 shows a sequence for the building renovations and allows certain sitework to run concurrently. Is this sequence mandatory, or may the contractor propose a different sequence and work in multiple areas at once, provided cemetery operations are maintained?
Answer 67 Contractor may deviate from suggested sequence, provided their ‘Performance Work Plan’ is approved by COR Question 68 Committal shelter and flagstone schedule notes Reference: Drawing GI-002, Construction Sequence Notes 2(b) and 2(c) GI-002 calls for a 45-day committal shelter schedule and a 15-day flagstone sidewalk/flagpole footing schedule. We do not find corresponding construction scope for these items in this FCA project. Can you confirm whether these notes apply?
Answer 68 Please disregard these two items Question 69 Contractor staging and laydown Reference: Drawings GI-002, GI-103, GI-104 and CI-101; Spec. 01 00 02, Section 1.7 The plans identify a contractor yard and limit temporary storage at individual work areas. Can we rely on the depicted yard for construction trailers, subcontractor parking, equipment and materials throughout the project? Please confirm whether separate work-area laydown is limited to ten days as noted on GI-002 and whether additional offsite space is anticipated.
Answer 69 Parking, laydown areas, subject to change. Contact cemetery management for coordination information Question 70 Temporary office size Reference: Drawing GI-104; Spec. 13 34 23.13; Drawing ES-800 GI-104 shows a 56-foot office trailer, while Section 13 34 23.13 specifies a new office of at least 64 by 24 feet, together with the listed furnishings. Which size and layout should all bidders carry?
Answer 70 56-foot trailer is a notional layout for contractor’s office. Bidders should include required temporary restroom and temporary office trailers for Government use to maintain cemetery operations during construction.
Question 71 Temporary facility connections Reference: Drawings GI-104, ES-700 and ES-800; Specs. 13 34 23.13 and 13 34 23.19 The temporary office and restroom trailer need power, water, waste service and communications. Can the VA identify the available connection points and confirm their capacities? Please also confirm whether active telephone and internet service will be provided by the Government, with the contractor furnishing the specified internal cabling and connections.
Answer 71 Electrical Requirements: - Please refer to Drawing E-700 and E-800 for electrical power connection points. Note #1 clearly shows these requirements. Communication Requirements: See Note#4 on drawing E-700 and E-800.
Question 72 Staff relocation and temporary occupancy Reference: Drawing GI-104, Phasing Notes; Spec. 13 34 23.13 How many cemetery staff members are expected to occupy the temporary office, and at what point in the sequence must the office be ready? Can we assume one move into the temporary office and one move back into the renovated facilities, with the trailer removed after that move and final acceptance?
Answer 72 See response #25. Move sequencing according to the contractor’s phasing / schedule and Government acceptance of renovated facilities.
Question 73 Existing furniture and equipment relocation Reference: Drawing GI-104, Phasing Notes; Spec. 13 34 23.13, Paragraph N; Spec. 01 00 02, Section 1.8 GI-104 requires the contractor to relocate existing furniture, tools, lockers, refrigerators and microwaves, while Section 13 34 23.13 separately requires new office furnishings. Are the new items in addition to the existing items to be moved? Can the VA provide an inventory or walk-through of the items to be moved and confirm whether cemetery staff will pack and move computers, records and personal belongings?
Answer 73 Contractor to coordinate move of existing equipment. Contractor is responsible for temporary storage of existing equipment that cannot be moved to temporary trailers, secure areas, or temporary storage containers. Contractors should consider this and identify storage/moves in construction phasing/ schedule. Site visit to review was previously held as referenced in solicitation documents. Cemetery staff are responsible for move of personal belongings, telephones, and computers.
Question 74 Interim storage for cemetery property Reference: Drawings GI-103 and GI-104; Spec. 01 00 02, Sections 1.7 and 1.8 GI-104 shows a 40-foot storage container and fenced GSA parking, but does not identify how much cemetery equipment and material must be stored while the buildings are under renovation. Is the contractor to furnish the container and any additional secure or weather-protected storage for cemetery property? Please confirm the available on-site area and the requirements for storing existing equipment and vehicles during each phase.
Answer 74 Contractor to provide quantity one (1) 40 ft storage container for tool storage, two (2) 250 gal / each temporary fuel tanks, temporary restroom trailer, and temporary office trailers for Government use. Contractor is responsible for interim storage of all office furniture See CI -101 for additional detail. area TBD Question 75 Temporary office cleaning and supplies Reference: Spec. 13 34 23.13, Paragraphs L-N The office specification calls for daily janitorial services, restroom consumables and water-cooler service. For pricing, does daily cleaning mean each occupied workday, or are weekends and holidays also required? Please confirm that the Government will furnish ordinary administrative supplies, such as printer paper and toner, rather than including them in the contractor's janitorial obligation.
Answer 75 Facilities must be cleaned upon delivery and serviced after each government workday.
Question 76 Temporary public restroom operating and cleaning period Reference: Drawing GI-104; Spec. 13 34 23.19, Paragraphs 1.1, 1.2 and 3.2 The restroom trailer is to remain in use while the permanent restrooms are closed, with daily cleaning and ongoing water, waste and consumable service. Should bidders include restroom servicing and cleaning seven days a week while it is open to the public, including weekends and holidays? Are additional scheduled cleanings expected around Memorial Day, Veterans Day or other events, beyond the specified tank servicing?
Answer 76 Facilities must be cleaned upon delivery, serviced after each day the cemetery is open to the public, and should be sparkling clean and fully stocked in preparation for holidays like Memorial Day and Veterans Day.
Question 77 Independent testing and special inspections Reference: Specs. 01 00 02, Section 1.1; 01 45 00; references to Sections 01 45 29 and 01 45 35; Structural S-001 through S-203 The contractor is required to carry independent testing and applicable special inspections, but Sections 01 45 29 and 01 45 35 and the referenced special inspection schedule do not appear in the combined specifications. Can these documents be provided, or can the required special inspections be identified? May one qualified independent firm provide both testing and special inspections?
Answer 77 Special inspections shall be a historic masonry in-situ inspection for historic workmanship compliance and is subject to VA NCA Historic approval.
Question 78 Historic preservation and archaeological consultants Reference: Drawings A-004, A-005, AE-001/002 and historic wall alternate; Spec. 01 00 02, Section 1.31 For the historic buildings and wall alternate, are qualified restoration subcontractors working under VA/A/E review sufficient, or must the contractor also retain a separate preservation architect, conservator or archaeologist? If a third-party professional or archaeological monitoring is required, please identify the applicable work and responsibility.
Answer 78 Not Applicable, N/A.
Question 79 National Park Service and preservation approvals Reference: Drawings GI-002 and GI-103; A-004 and A-005 GI-103 identifies adjoining National Park Service property, and the work is subject to historic preservation requirements. Does any planned work, access or staging require NPS property access or NPS/SHPO approval? If so, have those approvals been obtained, or are they the contractor’s responsibility?
Answer 79 Work in the materials spoils area is directly adjacent to National Parkland and coordinating with them is recommended when undergoing that portion of the work. Two of the buildings in the maintenance area are historic and will be subject to SHPO approval.
Question 80 Permits and stormwater documents Reference: RFP Section C, General Conditions; Spec. 01 00 02, Section 1.11(D); Drawings CE-101 through CE-201 The specifications identify an NPDES permit and state that the VA will make the application available. Can the current permit/application and any existing stormwater plan be provided? Please confirm which additional permits, if any, the contractor must obtain for the pond work, temporary entrance or temporary facilities.
Answer 80 The General Contractor is responsible for the NPDES permit. For plans see CE-101 through CE-201. The permit application is available to the public and can be submitted directly to the Authority Having Jurisdiction. Website link: https://eec.ky.gov/Environmental-Protection/Water/PermitCert/KPDES/Documents/SWPPPPermitPage.pdf
Question 81 Existing pond material and discharge conditions Reference: Drawings CG-101 and CG-201; Spec. 01 57 19 Have the existing pond sediments been tested, and are there known restrictions on excavation, disposal or discharge of dewatering water? If additional testing, treatment or environmental monitoring is required, please identify the requirement bidders should include.
Answer 81 No, the pond sediments have not been tested and reports are not available. Contractor should reference State of Kentucky Department of Environment for regulatory restrictions, required permits, monitoring, discharge, and disposal.
Question 82 Referenced existing-condition reports Reference: Spec. 01 00 02, Section 1.13; Drawing HA-001; Drawings A-004 and A-005 The contract documents reference geotechnical and existing-condition investigations. Can the underlying geotechnical report and the referenced hazardous-material and historic-preservation reports be made available to all bidders, with confirmation of which versions govern the work?
Answer 82 Yes, the Hazardous Materials Testing Report, Geotechnical Report and Subsurface Utility Engineering (SUE) report is provided with Amendment 04. There are no other existing conditions investigations available.
Question 83 Fuel system specifications and existing fuel Reference: Drawings GI-104 and ES-600; specifications TOC, Sections 23 11 23 and 33 56 10 The plans show temporary 250/250-gallon tanks and new 500/500-gallon tanks, but the fuel-storage specification sections listed in the table of contents do not appear in the combined specifications. Can these sections be provided? Also, is the contractor responsible for transferring and testing existing fuel when the tanks are changed over?.
Answer 83 Spec sections added. Contractor is responsible for transferring and testing existing fuel.
Question 84 Optional roadway and catch basin work Reference: Drawing GI-104, Phasing Note 6; RFP Section B, CLINs 0001–0004 GI-104 identifies catch-basin replacement and reconstruction of Roadways A and B as an option, but those items are not identified as separate bid alternates in Section B. Should this work be included in the base bid, or is the note not applicable?
Answer 84 See revised drawing.
Question 85 Historic wall alternate - limits of repair Reference: RFP Section B, CLIN 0002; Alternate 1 Drawings AP-100/101 and AS-201 through AS-208 For Alternate 1, should bidders price only the repairs specifically identified on the wall drawings? If additional concealed deterioration or unsuitable capstones are found during dismantling, will that work be addressed separately rather than assumed in the lump-sum price?
Answer 85 Refer to Sheet AP-100. All historic wall surfaces shall be cleaned and restored. Lump Sum pricing shall be in CLIN 002.
Question 86 Section C-C - existing crypt condition Reference: RFP Section B, CLIN 0004; Drawings CG-102 and CG-201 Alternate 3 requires excavation down to the existing crypt lids. Has their condition been documented? Can the VA confirm that the lids will be inspected and their existing condition recorded as they are exposed, before any repair or replacement is assigned to the contractor? We recognize the drawing requirement to replace components damaged by the contractor.
Answer 86 Existing conditions are not documented; any damage to crypt lids during excavation will be documented and inspected by the NCA and replaced by the Contractor. If damage is preexisting, the Contractor will not be held responsible for unforeseen conditions.
Question 87 Section C-C - replacement crypt lids and allowance Reference: RFP Section B, CLIN 0004; Drawing CG-102, Crypt Field Notes Who manufactured the existing crypts, and are matching spare crypts or lids available on site? If there are no spares, can the manufacturer and model be identified? Given that the existing condition is unknown and lids could be damaged during excavation, should bidders carry a common allowance or unit price for replacement of pre-existing damaged lids or other replacements directed by the VA? Please distinguish those from contractor-caused damage.
Answer 87 Crypts are VA standard size Preplaced Crypt (PPC). No spare crypt lids will be made available to the Contractor. PPC were made by the Ohio Plant of LINDSAY PRECAST - QUADCAST, www.lindsayprecast.com.
Question 88 Existing systems and proprietary integration Reference: Drawings FA-001/002, FN-101 through FN-105, SS-100, SN-101 through SN-105 and telecommunications drawings The fire alarm, security and telecommunications work ties into existing systems. Can the VA identify the existing system manufacturers and confirm whether programming and integration can be performed by qualified subcontractors or will require specific manufacturer-authorized vendors?
Answer 88 Manufacturer and panel model is “FireWarden-100-2/E/C/ Addressable Fire Control Panel.
Question 89 SECTION 01 00 02 GENERAL REQUIREMENTS D. All Testing Laboratory services will be retained and paid for by the Contractor (see Spec Section 01 45 29, Testing Laboratory Services). However, the Department of Veterans Affairs may elect to retain its own Testing Laboratory for any purpose. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the RE/COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the RE/COR.
Please confirm if the DVA plans on retaining their own Testing Laboratory as this may impact scheduling of work/production Answer 89 The specification identifies notification requirements, so the Government has time to schedule observation and testing, if desired. Notifications should not impact scheduling. Contractor is required to perform the same notifications to the Government COR and inspector as regular duties so testing can be observed as part of the Contractor Quality Control /Government’s Quality Assurance process.
Question 90 Prior to commencing work, general contractor shall provide proof that an OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present. OSHA does not certify anyone as a “competent person”. Please confirm an OSHA 30 is acceptable.
Answer 90 Under 29 CFR 1926.32(f), a competent person is:
“One who is capable of identifying existing and predictable hazards in the surroundings or working conditions which are unsanitary, hazardous, or dangerous to employees, and who has authorization to take prompt corrective measures to eliminate them.”
Contractor provides:
1. Designation letters naming their competent person
2. Resume or experience summary showing hazard‑specific competence
3. Training records (OSHA 30 is commonly accepted as part of this) OSHA 30 is acceptable as part of demonstrating competence, but it cannot be the sole qualifier. The employer must designate the CP based on training + experience + authority, and this submittal will follow the standard approvals process.
Question 91 Please provide anticipated date of NTP issuance as there is a potential for material escalation.
Answer 91 Notice To Proceed to be issued No Later Than 30 days after contract award. Material escalation will not be applicable.
Question 92 Please provide average number of daily interments as these may impact construction production.
Answer 92 20 per week.
Question 93 The General Contractor shall provide unarmed guards at the project site when theft or vandalism warrants. Has the Project site experienced theft or vandalism in the past?
Answer 93 No. The Government is not responsible for vandalism to the project site or Contractor lost/stolen materials and equipment.
Question 94 Motor Vehicle Restrictions Vehicle authorization requests shall be required for any vehicle entering the site and such requests shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies. Please confirm this is applicable. If so, who would the requests be directed to?
Answer 94 Vehicle authorization requests to be submitted to the Contracting Officer Representative (COR) at least 3 days in advance.
Question 95 Construction Fence: Before construction operations begin, the Contractor shall provide a chain link construction fence, 7’ feet minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 15 inches. Bottom of fences shall extend to one inch above grade. The temporary fencing shall encompass the construction work area(s) to serve as a pedestrian barrier to alert cemetery patrons of the construction site. Remove the fence when directed by RE/COR. Will 6’ fence be acceptable? Will privacy screens be required on the temporary fence? If do, what colors are acceptable.
Answer 95 7’ minimum height required; yes, privacy screening required. Black is acceptable.
Question 96 Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS. Will any other construction or maintenance contracts be implemented during the expansion project’s completion timeline?
Answer 96 Yes, grounds maintenance and cemetery operations will continue throughout the duration of this project.
Question 97 Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge Elimination System (NPDES) permit is required for this project. THE CONTRACTOR IS RESPONSIBLE FOR OBTAINING THIS PERMIT PRIOR TO EARTH DISTURBANCE. VA will make the permit application available at the (appropriate NCA Central/Cemetery) office.
Has the agency issuing the permit already been presented with the construction plans?
Answer 97 The NPDES permit is the responsibility of the General Contractor. See Question 80 response.
Question 98 SECTION 01 32 17 NETWORK ANALYSIS SCHEDULES-The Contractor shall develop a Microsoft Project 2021 Gantt Chart ( bar chart) schedule demonstrating fulfillment of the contract requirements.
Will Primavera P6 be permitted in lieu of Microsoft Project?
Answer 98 Yes, Primavera P6 is acceptable.
Question 99 “SITE SAFETY AND HEALTH OFFICER” (SSHO) AND “COMPETENT PERSON” (CP): A. The Prime Contractor shall provide a Safety oversight team that includes a minimum of one (1) person at each project site, for each shift, to function as the Site Safety and Health Officer (SSHO). The Prime Contractor shall provide a minimum of one “Full-Time” SSHO at each project site, for each shift (with no other duties) that holds as current, a professional safety certification with at least 3 years of dedicated construction safety related experience. The SSHO shall ensure that the requirements of the VA and of 29 CFR 1926.16 are met for the project. The SSHO must be at the work site at all times, during construction activities, to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan. Can the project superintendent dual hat as the SSHO?
Answer 99 See Question 29 response.
Question 100 QUALITY CONTROL ORGANIZATION: A. Personnel Requirements: The requirements for the CQC organization are a Safety and Health Manager, CQC System Manager, a Design Quality Manager (if applicable), and a sufficient number of additional qualified personnel to ensure safety and Contract compliance.