S02_Attachment - SF 1413 updated.pdf

Standard Form PDF 687 KB Posted

Attached to
Fort Bliss National Cemetery, Gravesite Expansion and FCA Deficiencies
Solicitation number
36C78626B0028
Issued by

About this file

STANDARD FORM 1413 – Statement and Acknowledgment

This is a Standard Form 1413 (Rev. 10/2023), a federal contracting form prescribed by GSA/FAR (48 CFR 53.222(e)) used to document subcontract awards under prime federal contracts. The form facilitates communication between prime contractors and subcontractors regarding labor standards compliance and contractual obligations.

The form contains two primary sections. Part I requires the prime contractor to provide a statement identifying the prime contract number, subcontract award date, subcontract number, and details of both the prime contractor and subcontractor (name and address). The prime contractor must indicate whether the prime contract contains the "Contract Work Hours and Safety Standards Act – Overtime Compensation" clause, identify the firm awarding the subcontract, describe the work to be performed, specify the project and location, and provide authorization through signature, title, and date. Part II requires the subcontractor to acknowledge receipt and inclusion of specific labor standards clauses from the prime contract, including provisions for contract work hours and safety standards, payrolls and basic records, withholding of funds, labor standards disputes, construction wage rate requirements, apprentices and trainees, Copeland Act compliance, subcontract labor standards, contract termination-debarment provisions, and certification of eligibility. The form also includes space for listing any intermediate subcontractors and requires signature, title, and date from an authorized subcontractor representative. The OMB control number is 9000-0066 with an expiration date of 5/31/2027.

View the file

Other versions and copies of SF 1413

File Revision Posted Attached to
B2_DRAFT_08.3_Sec_J_SF1413_exp_05-2027.pdf Same revision and size as this file May 2027 SLAC Job Order Contract
SF-1413_Statement_and_Acknowledgement_Form_(Subcontracting).pdf Revision not stated IE181 - WHS Greenhouse Construction
SF 1413-23A - Statement and Acknowledgment.pdf Same revision and size as this file Revision not stated 70Z03026QCLEV0106 - USCG STA/ANT BUFFALO GENERATOR MAINTENANCE
B08_Attachment_9_Subcontractor_Ack_SF1413-23a_upon_award.pdf Same revision and size as this file Revision not stated EROS Removal and replacement of chilled and conden
Exhibit I - Statement of Acknowledgment (SF-1413).pdf Revision not stated Central Utility Building Addition and Renovation Construction, UIP Subproject 1-CUB
S02_Attachment - Standard Form 1413.pdf Revision not stated Fort Bliss National Cemetery, Gravesite Expansion and FCA Deficiencies
S02_Attachment - Standard Form 1413.pdf Revision not stated CAMP NELSON NATIONAL CEMETERY, KY 833CM3030 – CORRECT FCA DEFICIENCIES
Exhibit K - SF1413.pdf Revision not stated Fire Sprinkler Repair_XGal_IB2A_Lab1_MI50
SF 1413-23A - Statement and Acknowledgment (2).pdf Same revision and size as this file Revision not stated 70Z03026QCLEV0100 - GROUND MAINTENANCE AND SNOW REMOVAL FOR USCG STATION ST. IGNACE
SF 1413-23A - Statement and Acknowledgment (2).pdf Same revision and size as this file Revision not stated 70Z03026QCLEV0101 - GROUND MAINTENANCE AND SNOW REMOVAL FOR SECTOR NORTHERN GRREAT LAKES
SF 1413 - Statement and Acknowledgment.pdf Same revision and size as this file Revision not stated 70Z03026QCLEV0071 - USCG STA LORAIN SECURITY SYSTEM WITH CCTV PROJECT
Exhibit I SF1413_fill-ins.pdf Revision not stated MINOS High Bay Roof Replacement & Masonry Wall Repair
SF 1413 - Statement and Acknowledgment.pdf Same revision and size as this file Revision not stated 70Z03026QCLEV0099 Replacement HVAC Station Building at STA Sodus Point
S02_Attachment - Standard Form 1413.pdf Revision not stated Leavenworth National Cemetery, Gravesite Expansion
SF 1413 - Statement and Acknowledgment.pdf Same revision and size as this file Revision not stated 70Z03026QCLEV0097 - U. S. Coast Guard Station Lorain Gate Replacement
B08_Attachment_7_Subcontractor_Statement_and_Acknowledgment_SF1413-23a.pdf Same revision and size as this file Revision not stated DREDGING OF SEDIMENT POND & CONTACT POOL
SF 1413-23A - Statement and Acknowledgment (1) (1).pdf Same revision and size as this file Revision not stated 70Z03026QCLEV0053- USCG STATION ST. IGNACE REPLACEMENT SHOWER STALL
Exhibit K SF1413_printed.pdf Revision not stated Roof Maintenance and Repair Services IDIQ
SF1413 Statement of Acknowledgement.pdf Revision not stated CSS 99147 Mini Splits Scranton, PA (PA162)
SF1413REVOCT2023.pdf Revision not stated REMOVE AND REPLACE EXISTING FAILED BOILER SYSTEM, USCG STATION SHINNECOCK, HAMPTON BAYS, NY 11946-3223
Show all 20

Who attaches SF 1413

State Files
Florida 3
Colorado 1

Other files

File Type Posted
4101-AE201_ADD1.pdf PDF
2101-AE201_ADD1.pdf PDF
3004-E-111_ADD1.pdf PDF
S02_Attachment - Geotechnical Engineering Report.pdf PDF
092400 PORTLAND CEMENT PLASTERING_ADD1.pdf PDF
073213 CLAY ROOF TILES_ADD1.pdf PDF
2101-AE101_ADD1.pdf PDF
S02_Attachment - DOL Payroll Form updated.pdf PDF
S05_Attachment - RFIs and Responses.pdf PDF
2101-AE111_ADD1.pdf PDF
CE121_ADD1.pdf PDF
S02_Attachment - Statement of Work revised 10.26.2026.pdf PDF
3004-ED111_ADD1.pdf PDF
050385 HISTORIC DECORATIVE FORMED METAL REPAIR_WR IR_ADD1.pdf PDF
LK111_ADD1.pdf PDF
000110 TABLE OF CONTENTS_ADD1.pdf PDF
LP111_ADD1.pdf PDF
3003-ED111_ADD1.pdf PDF
2101-AD201_ADD1.pdf PDF
3003-E-501_ADD1.pdf PDF
S06_36C78626B0028 0002.pdf PDF
CB501_ADD1.pdf PDF
S02_Attachment - Addendum 1 Summary of Changes.pdf PDF
3003-E-111_ADD1.pdf PDF
087100 DOOR HARDWARE_ADD1.pdf PDF
2101-EL111_ADD1.pdf PDF
281300 PHYSICAL ACCESS CONTROL SYSTEM_ADD1.pdf PDF
2101-EP111_ADD1.pdf PDF
CB502_ADD1.pdf PDF
S04_Attachment - Site Visit Attendance Roster.pdf PDF
S06_36C78626B0028 Amend. 0001.pdf PDF
Fort Bliss Gravesite Expansion BD Part 1.pdf PDF
S02_Attachment - Limitations on Subcontracting Cert.docx DOCX document
S02_Attachment - DOL Payroll Form.pdf PDF
Fort Bliss Gravesite Expansion BD Part 3.pdf PDF
Fort Bliss Gravesite Expansion BD Part 5.pdf PDF
Fort Bliss Gravesite Expansion BD Part 10.pdf PDF
Fort Bliss Gravesite Expansion - Specifications Full Book.pdf PDF
Fort Bliss Gravesite Expansion BD Part 9.pdf PDF
Fort Bliss Gravesite Expansion BD Part 8.pdf PDF
S02_Attachment - 886CM3026 Fort Bliss NC SOW.pdf PDF
Fort Bliss Gravesite Expansion BD Part 4.pdf PDF
Fort Bliss Gravesite Expansion BD Part 7.pdf PDF
S02_36C78626B0028 Solicitation.pdf PDF
S02_Attachment - Davis-Bacon Act Poster.pdf PDF
S02_Attachment - Standard Form 1413.pdf PDF
Fort Bliss Gravesite Expansion BD Part 2.pdf PDF
Fort Bliss Gravesite Expansion BD Part 11.pdf PDF
S02_Attachment - Price Schedule Sheet.pdf PDF
S02_Attachment - Wage Determination Heavy.pdf PDF
Show 40 more

Latest 50 of 52 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement And Acknowledgment OMB Control Number: 9000-0066 Expiration Date: 5/31/2027

Part I - Statement Of Prime Contractor

1. Prime Contract Number 2. Date Subcontract

Awarded

3. Subcontract Number

Authorized For Local Reproduction Previous Edition Is Not Usable

STANDARD FORM 1413 (REV. 10/2023)

Prescribed by GSA/FAR (48 CFR) 53.222(e)

4. Prime Contractor 5. Subcontractor

a. Name a. Name

b. Street Address b. Street Address

c. City d. State e. ZIP Code c. City d. State e. ZIP Code

6. The prime contract does, does not contain the clause entitled "Contract Work Hours and Safety Standards Act -- Overtime Compensation."

7. The prime contractor states that under the contract shown in Item 1, a subcontract was awarded on the date shown in Item 2 to the subcontractor identified in Item 5 by the following firm:

a. Name Of Awarding Firm

b. Description Of Work By Subcontractor

8. Project 9. Location

10a. Name Of Person Signing 11. By (Signature) 12. Date Signed

10b. Title Of Person Signing

Part II - Acknowledgment Of Subcontractor

13. The subcontractor acknowledges that the following clauses of the contract shown in Item 1 are included in this subcontract:

Contract Work Hours and Safety Standards Act - Overtime Compensation (If included in prime contract see Block 6) Payrolls and Basic Records Withholding of Funds Disputes Concerning Labor Standards Compliance with Construction Wage Rate Requirements and Related Regulations

Construction Wage Rate Requirements Apprentices and Trainees Compliance with Copeland Act Requirements Subcontracts (Labor Standards) Contract Termination - Debarment Certification of Eligibility

Paperwork Reduction Act Statement - This information collection meets the requirements of 44 U.S.C. §

3507, as amended by section 2 of the Paperwork Reduction Act of 1995. You do not need to answer these questions unless we display a valid Office of Management and Budget (OMB) control number.

The OMB control number for this collection is 9000-0066. We estimate that it will take .05 hours to read the instructions, gather the facts, and answer the questions. Send only comments relating to our time estimate, including suggestions for reducing this burden, or any other aspects of this collection of information to: U.S. General Services Administration, Regulatory Secretariat Division (M1V1CB), 1800

F Street, NW, Washington, DC 20405.

15b. Title Of Person Signing

15a. Name Of Person Signing 16. By (Signature) 17. Date Signed

14. Name(s) Of Any Intermediate Subcontractors, If Any

A C

DB

STANDARD FORM 1413 (REV. 10/2023) BACK

1.6 Presentation Agent PDFlib 3.02 (C++/Win32) D:20050617125503-04'00' D:20080212101247-05'00' Presentation Agent Standard Form 1413 - Statement and Acknowledgment Statement And Acknowledgment OMB Control Number: 9000-0066 Expiration Date: 5/31/2027 Part I - Statement Of Prime Contractor

1. Prime Contract Number

2. Date Subcontract Awarded

3. Subcontract Number Authorized For Local Reproduction Previous Edition Is Not Usable

STANDARD FORM 1413 (REV. 10/2023)

Prescribed by GSA/FAR (48 CFR) 53.222(e)

4. Prime Contractor

5. Subcontractor

a. Name

a. Name

b. Street Address

b. Street Address

c. City

d. State

e. ZIP Code

c. City

d. State

e. ZIP Code

6. The prime contract does, does not contain the clause entitled "Contract Work Hours and Safety Standards Act -- Overtime Compensation."

7. The prime contractor states that under the contract shown in Item 1, a subcontract was awarded on the date shown in Item 2 to the subcontractor identified in Item 5 by the following firm:

a. Name Of Awarding Firm

b. Description Of Work By Subcontractor

8. Project

9. Location 10a. Name Of Person Signing

11. By (Signature)

12. Date Signed 10b. Title Of Person Signing Part II - Acknowledgment Of Subcontractor

13. The subcontractor acknowledges that the following clauses of the contract shown in Item 1 are included in this subcontract:

Contract Work Hours and Safety Standards Act - Overtime Compensation (If included in prime contract see Block 6) Payrolls and Basic Records Withholding of Funds Disputes Concerning Labor Standards Compliance with Construction Wage Rate Requirements and Related Regulations Construction Wage Rate Requirements Apprentices and Trainees Compliance with Copeland Act Requirements Subcontracts (Labor Standards) Contract Termination - Debarment Certification of Eligibility Paperwork Reduction Act Statement - This information collection meets the requirements of 44 U.S.C. § 3507, as amended by section 2 of the Paperwork Reduction Act of 1995. You do not need to answer these questions unless we display a valid Office of Management and Budget (OMB) control number. The OMB control number for this collection is 9000-0066. We estimate that it will take .05 hours to read the instructions, gather the facts, and answer the questions. Send only comments relating to our time estimate, including suggestions for reducing this burden, or any other aspects of this collection of information to: U.S. General Services Administration, Regulatory Secretariat Division (M1V1CB), 1800 F Street, NW, Washington, DC 20405.

15b. Title Of Person Signing 15a. Name Of Person Signing

16. By (Signature)

17. Date Signed

14. Name(s) Of Any Intermediate Subcontractors, If Any A C D B

STANDARD FORM 1413 (REV. 10/2023) BACK

1. Enter the Prime Contract Number. :
4a. Enter the Prime Contractor's Name. :
4b. Enter the Prime Contractor's Street Address. :
4c. Enter the Prime Contractor's City.:
7a. Enter the Name of the Awarding Firm.:
10a. Enter the Name of the Person signing this form as the Prime Contractor. :
10b. Enter the Title of the Person signing this form as the Prime Contractor. :
8. Enter the Project name.:
9. Enter the Location. :
7b. Enter a Description of Work completed by the Subcontractor. :
5c. Enter the Subcontractor's City.:
4e. Enter the Prime Contractor's Zone Improvement Plan (ZIP) Code. :
5e. Enter the Subcontractor's Zone Improvement Plan (ZIP) Code. :
4d. Enter the Prime Contractor's State.:
5d. Enter the Subcontractor's State.:
3. Enter the Subcontract Number. :
5a. Enter the Subcontractor's Name.:
5b. Enter the Subcontractor's Street Address.:
2. Enter the Date the Subcontract was Awarded (enter 2 digit month, 2 digit day and 4 digit year).:
12. If you are the Prime Contractor, enter the Date you signed this form (enter 2 digit month, 2 digit day and 4 digit year).:
6. Click here to select, "the prime contract does contain the clause entitled "Contract Work Hours and Safety Standards Act -- Overtime Compensation.": 0
6. Click here to select, "the prime contract does NOT contain the clause entitled "Contract Work Hours and Safety Standards Act -- Overtime Compensation.": 0
16. Sign here if you are the Subcontractor.:
15b. Enter the Title of the Person Signing this form as the Subcontractor. :
15a. Enter the Name of the Person Signing this form as the Subcontractor. :
17. If you are the Subcontractor, enter the Date you signed this form (enter 2 digit month, 2 digit day and 4 digit year).:
14a. Enter the First Name of an Intermediate Subcontractor, If Any. :
14c. Enter the Third Name of an Intermediate Subcontractor, If Any.:
14d. Enter the Fourth Name of an Intermediate Subcontractor, If Any.:
14b. Enter the Second Name of an Intermediate Subcontractor, If Any.: