Amendment 0008 - 32 13 13.06.pdf
PDF 156 KB Posted
- Solicitation number
- W912WJ20R0011
About this file
This document provides details for a forthcoming solicitation for construction services. The U.S. Army Corps of Engineers, New England District will issue a solicitation to replace the truck offload, fillstand positions, and associated pumping/filtration equipment at the Quonset Point Fuels Storage Complex at the Rhode Island Air National Guard Station in North Kingstown, Rhode Island. The scope of work includes constructing a new 600 gallon per minute pumphouse with control room, offload skids, fuel pumps, filter/separator vessels, truck fillstand equipment, and associated valves, piping and electrical components. Existing storage tanks will be reused. The work will be conducted in phases to allow current system operations until most of the new system is completed. The estimated value is between $5 million and $10 million. The NAICS code is 236220. This will be a small business set-aside procurement using Best Value Tradeoff procedures.
View the file
Other files
Show 40 more
Latest 50 of 51 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Fuel Storage Replacement Amendment 00 07 Quonset, ANG Rhode Island September 24, 2020
SECTION 32 13 13.06
PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE FACILITIES
11/11
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONCRETE INSTITUTE (ACI)
ACI 211.1 (1991; R 2009) Standard Practice for Selecting Proportions for Normal, Heavyweight and Mass Concrete
ACI 301 (2016) Specifications for Structural Concrete
ACI 305.1 (2014) Specification for Hot Weather Concreting
ACI 306.1 (1990; R 2002) Standard Specification for Cold Weather Concreting
ACI 325.12R (2002; R 2013) Guide for Design of Jointed Concrete Pavements for Streets and Local Roads
ACI 330R (2008) Guide for the Design and Construction of Concrete Parking Lots
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C215 (2016) Extruded Polyolefin Coatings for Steel Water Pipe
ASTM INTERNATIONAL (ASTM)
ASTM A184/A184M (2017) Standard Specification for Welded Deformed Steel Bar Mats for Concrete Reinforcement
ASTM A615/A615M (2016) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
ASTM A775/A775M (2017) Standard Specification for Epoxy-Coated Steel Reinforcing Bars
ASTM A966/A966M (2015) Standard Test Method for Magnetic Particle Examination of Steel Forgings Using Alternating Current
ASTM C31/C31M (2019) Standard Practice for Making and
SECTION 32 13 13.06 Page 1
Fuel Storage Replacement Amendment 000 7
Curing Concrete Test Specimens in the Field
ASTM C33/C33M (2018) Standard Specification for Concrete Aggregates
ASTM C78/C78M (2018) Standard Test Method for Flexural Strength of Concrete (Using Simple Beam with Third-Point Loading)
ASTM C94/C94M (2018) Standard Specification for Ready-Mixed Concrete
ASTM C143/C143M (2015) Standard Test Method for Slump of Hydraulic-Cement Concrete
ASTM C150/C150M (2018) Standard Specification for Portland Cement
ASTM C172/C172M (2017) Standard Practice for Sampling Freshly Mixed Concrete
ASTM C231/C231M (2017a) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method
ASTM C260/C260M (2010a; R 2016) Standard Specification for Air-Entraining Admixtures for Concrete
ASTM C309 (2011) Standard Specification for Liquid Membrane-Forming Compounds for Curing Concrete
ASTM C494/C494M (2017) Standard Specification for Chemical Admixtures for Concrete
ASTM C595/C595M (2018) Standard Specification for Blended Hydraulic Cements
ASTM C618 (2019) Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete
ASTM C989/C989M (2018a) Standard Specification for Slag Cement for Use in Concrete and Mortars
ASTM C1077 (2017) Standard Practice for Agencies Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Testing Agency Evaluation
ASTM C1157/C1157M (2017) Standard Performance Specification for Hydraulic Cement
ASTM C1602/C1602M (2018) Standard Specification for Mixing Water Used in Production of Hydraulic Cement Concrete
SECTION 32 13 13.06 Page 2
Fuel Storage Replacement Amendment 0 007
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 3-250-01 (2016) Pavement Design for Roads and Parking Areas
1.2 DESIGN
This materials and construction specification is intended to be used on projects where the design was completed using UFC 3-250-01 Pavement Design for Roads, Streets, Walks, and Open Storage Areas, ACI 330R , Guide for the Design and Construction of Concrete Parking Lots or ACI 325.12R , Guide for Design of Jointed Concrete Pavements for Streets and Local Roads, or equivalent.
1.3 RELATED SECTIONS
Portland cement concrete pavement must use Section 32 11 23 AGGREGATE BASE COURSES FOR FLEXIBLE PAVING PAVING, in addition to this section.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Curing Materials ; G
Admixtures ; G
Dowel ; G
Reinforcement ; G
Submit a complete list of materials including type, brand and applicable reference specifications.
Cementitious Materials ; G
Aggregate ; G
Provide information identifying the reflectance of the pavement.
SD-05 Design Data
Concrete Mix Design ; G
Thirty days minimum prior to concrete placement, submit a mix design, with applicable tests, for each strength and type of concrete for approval. Submit a complete list of materials including type; brand; source and amount of cement, fly ash, slag, and admixtures; and applicable reference specifications. Provide mix proportion data using at least three different water-cement ratios for each type of mixture, which will produce a range of strength encompassing those required for each class and type of concrete required. Submittal must clearly indicate where each mix
SECTION 32 13 13.06 Page 3 design will be used when more than one mix design is submitted.
Obtain acknowledgement of approvals prior to concrete placement.
Submit a new mix design for each material source change.
SD-06 Test Reports
Aggregate Tests; G
Concrete Slump Tests ; G
Air Content Tests ; G
Flexural Strength Tests ; G
Cementitious Materials ; G
SD-07 Certificates
Ready-mixed Concrete Plant ; G
Batch Tickets ; G
Cementitious Materials ; G
1.5 DELIVERY, STORAGE, AND HANDLING
ASTM C94/C94M.
1.6 QUALITY ASSURANCE
1.6.1 Ready-mixed Concrete Plant Certification
Unless otherwise approved by the Contracting Officer, ready mixed concrete must be produced and provided by a National Ready-Mix Concrete Association (NRMCA) certified plant. If a volumetric mobile mixer is used to produce the concrete, rather than ready-mixed concrete, the mixer(s) must conform to the standards of the Volumetric Mixer Manufacturers Bureau (VMMB).
Verification must be made by a current VMMB conformance plate affixed to the volumetric mixer equipment.
1.6.2 Contractor Qualifications
Unless waived by the Contracting Officer, the Contractor must meet one of the following criteria:
a. Contractor must have at least one National Ready Mixed Concrete Association (NRMCA) certified concrete craftsman and at least one American Concrete Institute (ACI) Flatwork Finisher Certified craftsman on site, overseeing each placement crew during all concrete placement.
b. Contractor must have no less than three NRMCA certified concrete installers and at least two American Concrete Institute (ACI) Flatwork Finisher Certified installers, who must be on site working as members of each placement crew during all concrete placement.
1.6.3 Required Information
Submit copies of laboratory test reports showing that the mix has been
SECTION 32 13 13.06 Page 4 successfully tested to produce concrete with the properties specified and that mix will be suitable for the job conditions. The laboratory test reports must include mill test and all other test for cementitious materials, aggregates, and admixtures. Provide maximum nominal aggregate size, combined aggregate gradation analysis, percentage retained and passing sieve, and a graph of percentage retained verses sieve size.
Submit test reports along with the concrete mix design. Sampling and testing of materials, concrete mix design, sampling and testing in the field must be performed by a commercial testing laboratory which conforms to ASTM C1077. The laboratory must be approved in writing by the Contracting Officer.
1.6.4 Batch Tickets
ASTM C94/C94M. Submit mandatory batch ticket information for each load of ready-mixed concrete.
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Cementitious Materials
Cementitious materials in concrete mix must be 20 to 50 percent non-portland cement pozzolanic materials or slag by weight. Provide test data demonstrating compatibility and performance of concrete satisfactory to Contracting Officer.
2.1.1.1 Cement
ASTM C150/C150M, Type I or II or V low alkalior ASTM C595/C595M, Type IS, IP, or P MS or ASTM C1157/C1157M MS.
2.1.1.2 Fly Ash and Pozzolan
ASTM C618, Type F, or N. Fly ash certificates must include test results in accordance with ASTM C618.
2.1.1.3 Ultra Fine Fly Ash and Ultra Fine Pozzolan
Ultra Fine Fly Ash (UFFA) and Ultra Fine Pozzolan (UFP) must conform to ASTM C618, Class F or N, and the following additional requirements:
a. The strength activity index at 28 days of age must be at least 95 percent of the control specimens.
b. The average particle size must not exceed 6 microns.
2.1.1.4 Slag
ASTM C989/C989M, Slag Cement (formerly Ground Granulated Blast Furnace Slag) Grade 100 or 120. Certificates must include test results in accordance with ASTM C989/C989M.
2.1.1.5 Supplementary Cementitious Materials (SCM) Content
The concrete mix must always contain one of the SCMs listed in Table 1 within the range specified therein, whether or not the aggregates are found to be reactive in accordance with the paragraph ALKALI REACTIVITY
SECTION 32 13 13.06 Page 5
TEST".
TABLE 1
SUPPLEMENTARY CEMENTITIOUS MATERIALS CONTENT
Supplementary Cementitious Material Minimum Content (percent)
Maximum Content (percent)
Class N Pozzolan and Class F Fly Ash
SiO2 + Al2O3 + Fe2O3 > 70 percent 25 35
SiO2 + A12O3 + Fe2O3 > 80 percent 20 35
SiO2 + A12O3 + Fe2O3 > 90 percent 15 35
UFFA and UFP 7 16
GGBF Slag 40 50
2.1.2 Water
Water must conform to ASTM C1602/C1602M . Hot water must not be used unless approved by the Contracting Officer.
2.1.3 Aggregate
Coarse aggregate must consist of crushed or uncrushed gravel, crushed stone, or a combination thereof. Aggregates, as delivered to the mixers, must consist of clean, hard, uncoated particles. Coarse aggregate must be washed. Washing must be sufficient to remove dust and other coatings.
Fine aggregate must consist of natural sand, manufactured sand, or a combination of the two, and must be composed of clean, hard, durable particles. Both coarse and fine aggregates must meet the requirements of
ASTM C33/C33M.
2.1.3.1 Alkali Reactivity Test
Evaluate and test fine and coarse aggregates to be used in all concrete for alkali-aggregate reactivity. Test all size groups and sources proposed for use.
a. Evaluate the fine and coarse aggregates separately, using ASTM C1260.
Reject individual aggregates with test results that indicate an expansion of greater than 0.08 percent after 28 days of immersion in 1N NaOH solution, or perform additional testing as follows: utilize the proposed low alkali portland cement, blended cement, or SCM in combination with each individual aggregate. Test in accordance with ASTM C1567. Determine the quantity that meets all the requirements of these specifications and that lowers the expansion equal to or less than 0.08 percent after 28 days of immersion in a 1N NaOH solution.
Base the mixture proportioning on the highest percentage of SCM required to mitigate ASR-reactivity.
b. If any of the above options does not lower the expansion to less than
0.08 percent after 28 days of immersion in a 1N NaOH solution, reject the aggregate(s) and submit new aggregate sources for retesting.
SECTION 32 13 13.06 Page 6
Submit the results of testing for evaluation and acceptance.
2.1.3.2 Fine Aggregates
ASTM C33/C33M.
2.1.3.3 Coarse Aggregates
ASTM C33/C33M.
2.1.4 Admixtures
ASTM C494/C494M: Type A, water reducing; Type B, retarding; Type C, accelerating; Type D, water-reducing and retarding; and Type E, water-reducing and accelerating admixture. Do not use calcium chloride admixtures. Where not shown or specified, the use of admixtures is subject to written approval of the Contracting Officer.
ASTM C260/C260M: Air-entraining.
2.1.5 Reinforcement
2.1.5.1 Coated Dowel Bars
Bars must conform to ASTM A615/A615M , Grade 60 for plain billet-steel bars of the size and length indicated. Remove all burrs or projections from the dowel bars. Coating system must conform to AWWA C215, Type 2. Coat the bars with a double coat system or an epoxy coating system for resistance to penetration of oil and salt solutions. The systems must be in accordance with manufacturer's recommendation for coatings which are not bondable to concrete. Bond the coating to the dowel bar to resist laps or folds during movement of the joint. Coating thickness must be 7 mils minimum and 20 mils maximum.
2.1.5.2 Tie Bars
Bars must be billet or axle steel deformed bars and conform to ASTM A615/A615M or ASTM A966/A966M Grade 60 . Epoxy coated in accordance with ASTM A775/A775M .
2.1.5.3 Reinforcement
Deformed steel bar mats must conform to ASTM A184/A184M . Bar reinforcement must conform to ASTM A615/A615M , Grade 60 .
2.1.6 Curing Materials
2.1.6.1 Liquid Membrane-Forming Compound
ASTM C309, white pigmented, Type 2, Class B, free of paraffin or petroleum.
2.1.7 Joint Fillers and Sealants
Provide as specified in Section 32 01 19 FIELD MOLDED SEALANTS FOR SEALING
JOINTS IN RIGID PAVEMENTS.
2.1.8 Biodegradable Form Release Agent
Provide form release agent that is colorless and biodegradable. A minimum
SECTION 32 13 13.06 Page 7 of 87 percent of the total product must be biobased material. Provide product that does not bond with, stain, or adversely affect concrete surfaces and does not impair subsequent treatments of concrete surfaces.
Provide form release agent that does not contain diesel fuel, petroleum-based lubricating oils, waxes, or kerosene.
2.2 CONCRETE PAVEMENT
2.2.1 Joint Layout Drawings
If jointing requirements on the project drawings are not compatible with the proposed placement sequence, submit a joint layout plan shop drawing to the Contracting Officer for approval. No work must be allowed to start until the joint layout plan is approved. The joint layout plan must indicate and describe in the detail the proposed jointing plan for contraction joints, expansion joints, and construction joints, in accordance with the following:
a. Indicate locations of contraction joints, construction joints, and expansion joints. Spacing between contraction joints must not exceed 15 feet unless noted otherwise or approved by the Contracting Officer.
b. The larger dimension of a panel must not be greater than 125% of the smaller dimension.
c. The minimum angle between two intersecting joints must be 80 degrees, unless noted otherwise or approved by the Contracting Officer.
d. Joints must intersect pavement-free edges at a 90 degree angle the pavement edge and must extend straight for a minimum of 1.5 feet from the pavement edge, where possible .
e. Align joints of adjacent panels.
f. Align joints in attached curbs with joints in pavement when possible.
g. Ensure joint depth, widths, and dimensions are specified.
h. Minimum contraction joint depth must be 1/4 of the pavement thickness.
The minimum joint width must be 1/8 inch .
i. Use expansion joints only where pavement abuts buildings, foundations, manholes, and other fixed objects.
2.3 CONTRACTOR-FURNISHED MIX DESIGN
Contractor-furnished concrete mix must be designed in accordance with ACI 211.1 except as modified herein, and the mix design must be as specified herein under paragraph SUBMITTALS. The concrete must have a minimum flexural strength of 650 pounds per square inch at 28 days. The concrete may be air entrained. If air entrainment is used the air content must be 6.0. Maximum size aggregate for slip forming must be 1.5 inches .
The slump must be one to 3 inches (or less when slip form is used). For slipformed pavement, at the start of the project, select a maximum allowable slump which will produce in-place pavement meeting the specified tolerances for control of edge slump. The selected slump must be applicable to both pilot and fill-in lanes.
If the cementitious material is not sufficient to produce concrete of the
SECTION 32 13 13.06 Page 8 flexural strength required it must be increased as necessary, without additional compensation under the Contract. The cementitious factor must be calculated using cement, Class F fly ash, and or GGBF slag. The mix must use a SCM material by weight in accordance with Table 1 in "Supplementary Cementitious Materials (SCM) Content"
PART 3 EXECUTION
3.1 FORMS
3.1.1 Construction
Construct forms to be removable without damaging the concrete.
3.1.2 Coating
Before placing the concrete, coat the contact surfaces of forms with a non-staining mineral oil, non-staining form coating compound, biodegradable form release agent, or two coats of nitro-cellulose lacquer.
3.1.3 Grade and Alignment
Check and correct grade elevations and alignment of the forms immediately before placing the concrete.
3.2 REINFORCEMENT
3.2.1 Coated Dowel Bars
Install bars, accurately aligned vertically and horizontally, at indicated locations and to the dimensions and tolerances indicated. Reject coatings which are perforated, cracked or otherwise damaged. While handling avoid scuffing or gouging of the coatings.
3.2.2 Tie Bars
Install bars, accurately aligned horizontally and vertically, at indicated locations.
3.2.3 Setting Slab Reinforcement
Reinforcement must be positioned on suitable chairs prior to concrete placement. At expansion, contraction and construction joints, place the reinforcement as indicated. Reinforcement, when placed in concrete, must be free of mud, oil, scale or other foreign materials. Place reinforcement accurately and wire securely. The laps at splices must be 12 inches minimum and the distances from ends and sides of slabs and joints must be as indicated.
3.3 MEASURING, MIXING, CONVEYING, AND PLACING CONCRETE
3.3.1 Measuring
ASTM C94/C94M.
3.3.2 Mixing
ASTM C94/C94M, except as modified herein. Begin mixing within 30 minutes after cement has been added to aggregates. When the air temperature is
SECTION 32 13 13.06 Page 9 greater than 85 degrees F , place concrete within 60 minutes. With the approval of the Contracting Officer, a hydration stabilizer admixture meeting the requirements of ASTM C494/C494M Type D, may be used to extend the placement time to 90 minutes. Additional water may be added to bring slump within required limits as specified in Section 11.7 of ASTM C94/C94M, provided that the specified water-cement ratio is not exceeded.
3.3.3 Conveying
ASTM C94/C94M.
3.3.4 Placing
Follow guidance of ACI 301 , except as modified herein. Do not exceed a free vertical drop of 5 feet from the point of discharge. Deposit concrete either directly from the transporting equipment or by conveyor on to the pre-wetted subgrade or subbase, unless otherwise specified. Do not place concrete on frozen subgrade or subbase. Deposit the concrete between the forms to an approximately uniform height. Place concrete continuously at a uniform rate, with minimum amount of segregation, without damage to the grade and without unscheduled stops except for equipment failure or other emergencies. If this occurs within 10 feet of a previously placed expansion joint, remove concrete back to joint, repair any damage to grade, install a construction joint and continue placing concrete only after cause of the stop has been corrected.
3.3.5 Vibration
Immediately after spreading concrete, consolidate concrete with internal type vibrating equipment along the boundaries of all slabs regardless of slab thickness, and interior of all concrete slabs 6 inches or more in thickness. Limit duration of vibration to that necessary to produce consolidation of concrete. Excessive vibration will not be permitted.
Vibrators must not be operated in concrete at one location for more than 15 seconds. Vibrating equipment of a type approved by the Contracting Officer may be used to consolidate concrete in unreinforced pavement slabs less than 6 inches thick.
3.3.5.1 Vibrating Equipment
Operate equipment, except hand-manipulated equipment, ahead of the finishing machine. Select the number of vibrating units and power of each unit to properly consolidate the concrete. Mount units on a frame that is capable of vertical movement and, when necessary, radial movement, so vibrators may be operated at any desired depth within the slab or be completely withdrawn from the concrete. Clear distance between frame-mounted vibrating units that have spuds that extend into the slab at intervals across the paving lane must not exceed 30 inches . Distance between end of vibrating tube and side form must not exceed 2 inches . For pavements less than 10 inches thick, operate vibrators at mid-depth parallel with or at a slight angle to the subbase. For thicker pavements, angle vibrators toward the vertical, with vibrator tip preferably about 2 inches from subbase, and top of vibrator a few inches below pavement surface. Vibrators may be pneumatic, gas driven, or electric, and must be operated at frequencies within the concrete of not less than 8,000 vibrations per minute. Amplitude of vibration must be such that noticeable vibrations occur at 1.5 foot radius when the vibrator is inserted in the concrete to the depth specified.
SECTION 32 13 13.06 Page 10
3.3.6 Cold Weather
Except with authorization, do not place concrete when ambient temperature is below 40 degrees F or when concrete is likely to be subjected to freezing temperatures within 24 hours. When authorized, when concrete is likely to be subjected to freezing within 24 hours after placing, heat concrete materials so that temperature of concrete when deposited is between 65 and 80 degrees F . Methods of heating materials are subject to approval of the Contracting Officer. Do not heat mixing water above 165 degrees F . Remove lumps of frozen material and ice from aggregates before placing aggregates in mixer. Follow practices found in ACI 306.1 .
3.3.7 Hot Weather
Maintain required concrete temperature in accordance with Figure NRMCA
NOMOGRAPH FOR ESTIMATING EVAPORATION RATE ON THE BASIS OF MENZEL FORMULA
in ACI 305.1 to prevent evaporation rate from exceeding 0.2 pound of water per square foot of exposed concrete per hour. Cool ingredients before mixing or use other suitable means to control concrete temperature and prevent rapid drying of newly placed concrete. After placement, use fog spray, apply monomolecular film, or use other suitable means to reduce the evaporation rate. Start curing when surface of fresh concrete is sufficiently hard to permit curing without damage. Cool underlying material by sprinkling lightly with water before placing concrete. Follow practices found in ACI 305.1 .
3.4 PAVING
Pavement must be constructed with paving and finishing equipment utilizing fixed forms.
3.4.1 Consolidation
The paver vibrators must be inserted into the concrete not closer to the underlying material than 2 inches . The vibrators or tamping units in front of the paver must be automatically controlled so that they stop immediately as forward motion ceases. Excessive vibration must not be permitted. Concrete in small, odd-shaped slabs or in locations inaccessible to the paver mounted vibration equipment must be vibrated with a hand-operated immersion vibrator. Vibrators must not be used to transport or spread the concrete.
3.4.2 Operation
When the paver is operated between or adjacent to previously constructed pavement (fill-in lanes), provisions must be made to prevent damage to the previously constructed pavement, including keeping the existing pavement surface free of debris, and placing rubber mats beneath the paver tracks.
Transversely oscillating screeds and extrusion plates must overlap the existing pavement the minimum possible, but in no case more than 8 inches .
3.4.3 Required Results
The paver-finisher must be operated to produce a thoroughly consolidated slab throughout, true to line and grade within specified tolerances. The paver-finishing operation must produce a surface finish free of irregularities, tears, voids of any kind, and other discontinuities. It must produce only a minimum of paste at the surface. Multiple passes of the paver-finisher must not be permitted. The equipment and its operation
SECTION 32 13 13.06 Page 11 must produce a finished surface requiring no hand finishing, other than the use of cutting straightedges, except in very infrequent instances. No water, other than true fog sprays (mist), must be applied to the concrete surface during paving and finishing.
3.4.4 Fixed Form Paving
Forms must be steel, except that wood forms may be used for curves having a radius of 150 feet or less, and for fillets. Forms may be built up with metal or wood, added only to the base, to provide an increase in depth of not more than 25 percent. The base width of the form must be not less than eight-tenths of the vertical height of the form, except that forms 8 inches or less in vertical height must have a base width not less than the vertical height of the form. Wood forms for curves and fillets must be adequate in strength and rigidly braced. Forms must be set on firm material cut true to grade so that each form section when placed will be firmly in contact with the underlying layer for its entire base. Forms must not be set on blocks or on built-up spots of underlying material.
Forms must remain in place at least 12 hours after the concrete has been placed. Forms must be removed without injuring the concrete.
3.4.5 Placing Reinforcing Steel
Reinforcement must be positioned on suitable chairs securely fastened to the subgrade prior to concrete placement.
3.4.6 Placing Dowels and Tie Bars
Dowels must be installed with alignment not greater than 1/8 inch per ft .
Except as otherwise specified below, location of dowels must be within a horizontal tolerance of plus or minus 5/8 inch and a vertical tolerance of plus or minus 3/16 inch . The portion of each dowel intended to move within the concrete or expansion cap must be painted with one coat of rust inhibiting primer paint, and then oiled just prior to placement. Dowels and tie bars in joints must be omitted when the center of the dowel tie bar is located within a horizontal distance from an intersecting joint equal to or less than one-fourth of the slab thickness.
3.4.6.1 Contraction Joints
Dowels and tie bars in longitudinal and transverse contraction joints within the paving lane must be held securely in place by means of rigid metal basket assemblies. The dowels and tie bars must be welded to the assembly or held firmly by mechanical locking arrangements that will prevent them from becoming distorted during paving operations. The basket assemblies must be held securely in the proper location by means of suitable anchors.
3.4.6.2 Construction Joints-Fixed Form Paving
Installation of dowels and tie bars must be by the bonded-in-place method, supported by means of devices fastened to the forms. Installation by removing and replacing in preformed holes will not be permitted.
3.4.6.3 Dowels Installed in Hardened Concrete
Installation must be by bonding the dowels into holes drilled into the hardened concrete. Holes approximately 1/8 inch greater in diameter than the dowels must be drilled into the hardened concrete. Dowels must be
SECTION 32 13 13.06 Page 12 bonded in the drilled holes using epoxy resin injected at the back of the hole before installing the dowel and extruded to the collar during insertion of the dowel so as to completely fill the void around the dowel. Application by buttering the dowel is not permitted. The dowels must be held in alignment at the collar of the hole, after insertion and before the grout hardens, by means of a suitable metal or plastic collar fitted around the dowel. The vertical alignment of the dowels must be checked by placing the straightedge on the surface of the pavement over the top of the dowel and measuring the vertical distance between the straightedge and the beginning and ending point of the exposed part of the dowel.
3.4.6.4 Expansion Joints
Dowels in expansion joints must be installed by the bonded-in-place method or by bonding into holes drilled in hardened concrete, using procedures specified above.
3.5 FINISHING CONCRETE
Start finishing operations immediately after placement of concrete. Use finishing machine, except hand finishing may be used in emergencies and for concrete slabs in inaccessible locations or of such shapes or sizes that machine finishing is impracticable. Finish pavement surface on both sides of a joint to the same grade. Finish formed joints from a securely supported transverse bridge. Provide hand finishing equipment for use at all times. Transverse and longitudinal surface tolerances must not exceed 1/4 inch in 10 feet .
3.5.1 Side Form Finishing
Strike off and screed concrete to the required crown and cross-section by a power-driven transverse finishing machine. Transverse rotating tube or pipe is not permitted unless approved by the Contracting Officer.
Elevation of concrete must be such that, when consolidated and finished, pavement surface will be adequately consolidated and at the required grade. Equip finishing machine with two screeds which are readily and accurately adjustable for changes in pavement slope and compensation for wear and other causes. Make as many passes over each area of pavement and at such intervals as necessary to give proper compaction, retention of coarse aggregate near the finished surface, and a surface of uniform texture, true to grade and slope. Do not permit excessive operation over an area, which will result in an excess of mortar and water being brought to the surface.
3.5.1.1 Equipment Operation
Maintain the travel of machine on the forms without lifting, wobbling, or other variation of the machine which tend to affect the precision of concrete finish. Keep the tops of the forms clean by a device attached to the machine. During the first pass of the finishing machine, maintain a uniform ridge of concrete ahead of the front screed for its entire length.
3.5.1.2 Joint Finish
Before concrete is hardened, correct edge slump of pavement, exclusive of edge rounding, in excess of 0.02 foot . Finish concrete surface on each side of construction joints to the same plane, and correct deviations before newly placed concrete has hardened.
SECTION 32 13 13.06 Page 13
3.5.1.3 Hand Finishing
Strike-off and screed surface of concrete to elevations slightly above finish grade so that when concrete is consolidated and finished pavement surface is at the indicated elevation. Vibrate entire surface until required compaction and reduction of surface voids is secured with a strike-off template.
3.5.1.4 Longitudinal Floating
After initial finishing, further smooth and consolidate concrete by means of hand-operated longitudinal floats. Use floats that are not less than 12 feet long and 6 inches wide and stiffened to prevent flexing and warping.
3.5.2 Brooming
3.5.2.1 Brooming
Finish the surface of the slab by brooming the surface with a new wire broom at least 18 inches wide. Gently pull the broom over the surface of the pavement from edge to edge just before the concrete becomes non-plastic. Slightly overlap adjacent strokes of the broom. Broom perpendicular to centerline of pavement so that corrugations produced will be uniform in character and width, and not more than 1/16 inch in depth.
Broomed surface must be free from porous spots, irregularities, depressions, and small pockets or rough spots such as may be caused by accidentally disturbing particles of coarse aggregate embedded near the surface.
3.5.3 Edging
At the time the concrete has attained a degree of hardness suitable for edging, carefully finish slab edges, including edges at formed joints, with an edge having a maximum radius of 1/8 inch . When brooming is specified for the final surface finish, edge transverse joints before starting brooming, then operate broom to obliterate as much as possible the mark left by the edging tool without disturbing the rounded corner left by the edger. Clean by removing loose fragments and soupy mortar from corners or edges of slabs which have crumbled and areas which lack sufficient mortar for proper finishing. Refill voids solidly with a mixture of suitable proportions and consistency and refinish. Remove unnecessary tool marks and edges. Remaining edges must be smooth and true to line.
3.5.4 Repair of Surface Defects
Follow guidance of ACI 301 .
3.6 CURING AND PROTECTION
Protect concrete adequately from injurious action by sun, rain, flowing water, frost, mechanical injury, tire marks and oil stains, and do not allow it to dry out from the time it is placed until the expiration of the minimum curing periods specified herein. Use White-Burlap-Polyethylene Sheet or liquid membrane-forming compound, except as specified otherwise herein. Do not use membrane-forming compound on surfaces where its appearance would be objectionable, on surfaces to be painted, where
SECTION 32 13 13.06 Page 14 coverings are to be bonded to concrete, or on concrete to which other concrete is to be bonded. Maintain temperature of air next to concrete above 40 degrees F for the full curing periods.
3.6.1 Liquid Membrane-Forming Compound Curing
Apply compound immediately after surface loses its water sheen and has a dull appearance and before joints are sawed. Agitate curing compound thoroughly by mechanical means during use and apply uniformly in a two-coat continuous operation by suitable power-spraying equipment. Total coverage for the two coats must be at least one gallon of undiluted compound per 200 square feet . Compound must form a uniform, continuous, coherent film that will not check, crack, or peel and must be free from pinholes or other imperfections. Apply an additional coat of compound immediately to areas where film is defective. Respray concrete surfaces that are subject to heavy rainfall within 3 hours after curing compound has been applied in the same manner.
3.6.1.1 Protection of Treated Surfaces
Keep concrete surfaces to which liquid membrane-forming compounds have been applied free from vehicular traffic and other sources of abrasion for not less than 72 hours. Foot traffic is allowed after 24 hours for inspection purposes. Maintain continuity of coating for entire curing period and repair damage to coating immediately.
3.7 FIELD QUALITY CONTROL
3.7.1 Sampling
The Contractor's approved laboratory must collect samples of fresh concrete in accordance with ASTM C172/C172M during each working day as required to perform tests specified herein. Make test specimens in accordance with ASTM C31/C31M.
3.7.2 Consistency Tests
The Contractor's approved laboratory must perform concrete slump tests in accordance with ASTM C143/C143M. Take samples for slump determination from concrete during placement. Perform tests at the beginning of a concrete placement operation and for each batch (minimum) or every 20 cubic yards (maximum) of concrete to ensure that specification requirements are met. In addition, perform tests each time test beams and cylinders are made.
3.7.3 Flexural Strength Tests
The Contractor's approved laboratory must test for flexural strength in accordance with ASTM C78/C78M. Make four test specimens for each set of tests. Test two specimens at 7 days, and the other two at 28 days.
Concrete strength will be considered satisfactory when the minimum of the 28-day test results equals or exceeds the specified 28-day flexural strength, and no individual strength test is less than 550 pounds per square inch . If the ratio of the 7-day strength test to the specified 28 -day strength is less than 65 percent, make necessary adjustments for conformance. Frequency of flexural tests on concrete beams must be not less than four test beams for each 50 cubic yards of concrete, or fraction thereof, placed. Concrete which is determined to be defective, based on the strength acceptance criteria therein, must be removed and replaced
SECTION 32 13 13.06 Page 15 with acceptable concrete.
3.7.4 Air Content Tests
Test air-entrained concrete for air content at the same frequency as specified for slump tests. Determine percentage of air in accordance with ASTM C231/C231M on samples taken during placement of concrete in forms.
3.7.5 Surface Testing
Surface testing for surface smoothness and plan grade must be performed as indicated below by the Testing Laboratory. The measurements must be properly referenced in accordance with paving lane identification and stationing, and a report given to the Contracting Officer within 24 hours after measurement is made. A final report of surface testing, signed by a Registered Engineer, containing all surface measurements and a description of all actions taken to correct deficiencies, must be provided to the Contracting Officer upon conclusion of surface testing.
3.7.5.1 Surface Smoothness Requirements
Surface smoothness must be measured every __500___ square feet . The finished surfaces of the pavements must have no abrupt change of 1/8 inch or more, and all pavements must be within the tolerances specified when checked with a 12 foot straightedge: 1/5 inch longitudinal and 1/4 inch transverse directions for roads and streets and 1/4 inch for both directions for other concrete surfaces, such as parking areas.
3.7.5.2 Surface Smoothness Testing Method
The surface of the pavement must be tested with the straightedge to identify all surface irregularities exceeding the tolerances specified above. The straightedge must be 12 feet and be constructed of aluminum or other lightweight metal and must have blades of box or box-girder cross section with flat bottom reinforced to ensure rigidity and accuracy. Straightedges must have handles to facilitate movement on pavement. The entire area of the pavement must be tested in both a longitudinal and a transverse direction on parallel lines approximately 15 feet apart. The straightedge must be held in contact with the surface and moved ahead one-half the length of the straightedge for each successive measurement. The amount of surface irregularity must be determined by placing the straightedge on the pavement surface and allowing it to rest upon the two highest spots covered by its length and measuring the maximum gap between the straightedge and the pavement surface, in the area between these two high points.
3.7.6 Plan Grade Testing and Conformance
The surfaces must vary not more than 0.06 foot above or below the plan grade line or elevation indicated. Each pavement category must be checked for conformance with plan grade requirements by running lines of levels at intervals to determine the elevation at each joint intersection.
3.7.7 Test for Pavement Thickness
Full depth cores of 4 inch diameter must be taken of concrete pavement every 500 square feet to measure thickness.
SECTION 32 13 13.06 Page 16
3.7.8 Reinforcement
Inspect reinforcement prior to installation to assure it is free of loose flaky rust, loose scale, oil, mud, or other objectionable material.
3.7.9 Dowels
Inspect dowel placement prior to placing concrete to assure that dowels are of the size indicated, and are spaced, aligned and painted and oiled as specified. Dowels must not deviate from vertical or horizontal alignment after concrete has been placed by more than 1/8 inch per foot .
-- End of Section --
SECTION 32 13 13.06 Page 17
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 32 13 13.06 Page 18
| 32 13 13.06 - PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE FACILITIES |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 DESIGN |
| 1.3 RELATED SECTIONS |
| 1.4 SUBMITTALS |
| 1.5 DELIVERY, STORAGE, AND HANDLING |
| 1.6 QUALITY ASSURANCE |
| 1.6.1 Ready-mixed Concrete Plant Certification |
| 1.6.2 Contractor Qualifications |
| 1.6.3 Required Information |
| 1.6.4 Batch Tickets |
| PART 2 PRODUCTS |
| 2.1 MATERIALS |
| 2.1.1 Cementitious Materials |
| 2.1.1.1 Cement |
| 2.1.1.2 Fly Ash and Pozzolan |
| 2.1.1.3 Ultra Fine Fly Ash and Ultra Fine Pozzolan |
| 2.1.1.4 Slag |
| 2.1.1.5 Supplementary Cementitious Materials SCM Content |
| 2.1.2 Water |
| 2.1.3 Aggregate |
| 2.1.3.1 Alkali Reactivity Test |
| 2.1.3.2 Fine Aggregates |
| 2.1.3.3 Coarse Aggregates |
| 2.1.4 Admixtures |
| 2.1.5 Reinforcement |
| 2.1.5.1 Coated Dowel Bars |
| 2.1.5.2 Tie Bars |
| 2.1.5.3 Reinforcement |
| 2.1.6 Curing Materials |
| 2.1.6.1 Liquid Membrane-Forming Compound |
| 2.1.7 Joint Fillers and Sealants |
| 2.1.8 Biodegradable Form Release Agent |
| 2.2 CONCRETE PAVEMENT |
| 2.2.1 Joint Layout Drawings |
2.3 CONTRACTOR-FURNISHED MIX DESIGN
| PART 3 EXECUTION |
| 3.1 FORMS |
| 3.1.1 Construction |
| 3.1.2 Coating |
| 3.1.3 Grade and Alignment |
| 3.2 REINFORCEMENT |
| 3.2.1 Coated Dowel Bars |
| 3.2.2 Tie Bars |
| 3.2.3 Setting Slab Reinforcement |
| 3.3 MEASURING, MIXING, CONVEYING, AND PLACING CONCRETE |
| 3.3.1 Measuring |
| 3.3.2 Mixing |
| 3.3.3 Conveying |
| 3.3.4 Placing |
| 3.3.5 Vibration |
| 3.3.5.1 Vibrating Equipment |
| 3.3.6 Cold Weather |
| 3.3.7 Hot Weather |
| 3.4 PAVING |
| 3.4.1 Consolidation |
| 3.4.2 Operation |
| 3.4.3 Required Results |
| 3.4.4 Fixed Form Paving |
| 3.4.5 Placing Reinforcing Steel |
| 3.4.6 Placing Dowels and Tie Bars |
| 3.4.6.1 Contraction Joints |
| 3.4.6.2 Construction Joints-Fixed Form Paving |
| 3.4.6.3 Dowels Installed in Hardened Concrete |
| 3.4.6.4 Expansion Joints |
| 3.5 FINISHING CONCRETE |
| 3.5.1 Side Form Finishing |
| 3.5.1.1 Equipment Operation |
| 3.5.1.2 Joint Finish |
| 3.5.1.3 Hand Finishing |
| 3.5.1.4 Longitudinal Floating |
| 3.5.2 Brooming |
| 3.5.2.1 Brooming |
| 3.5.3 Edging |
| 3.5.4 Repair of Surface Defects |
| 3.6 CURING AND PROTECTION |
| 3.6.1 Liquid Membrane-Forming Compound Curing |
| 3.6.1.1 Protection of Treated Surfaces |
| 3.7 FIELD QUALITY CONTROL |
| 3.7.1 Sampling |
| 3.7.2 Consistency Tests |
| 3.7.3 Flexural Strength Tests |
| 3.7.4 Air Content Tests |
| 3.7.5 Surface Testing |
| 3.7.5.1 Surface Smoothness Requirements |
| 3.7.5.2 Surface Smoothness Testing Method |
| 3.7.6 Plan Grade Testing and Conformance |
| 3.7.7 Test for Pavement Thickness |
| 3.7.8 Reinforcement |
| 3.7.9 Dowels |
File details come from the government source that posted it. Updated .