About this file

This document contains a section specification and submittal requirements for removable flood barriers for a federal construction project. The specification covers definitions for tropical cyclones and weather warnings, submittal requirements, product details for watertight door and window panels, performance requirements to withstand 100-year storm loads, quality assurance and installation specifications. Key materials include composite FRP/IPN chemical structure panels for flood panels and compressible closed cell gaskets. The related federal contract opportunity is for construction of a new fuels storage complex replacement at the Quonset Point Rhode Island Air National Guard Station, with an estimated value between $5-10 million. The work includes replacing truck offload and fillstand positions and associated pumping and filtration equipment to comply with fuel facility standards, and constructing a new 600 GPM pumphouse and upgrades to the refueler parking area. The requirement will be solicited as a small business set-aside by the Army Corps of Engineers New England District.

View the file

Other files

File Type Posted
Amendment 0010.pdf PDF
A-202 BUILDING SECTIONS.pdf PDF
Amendment 0009 - G-009 PHASING PLAN 1.pdf PDF
M-603 FUEL SYSTEM FLOW DIAGRAM (2 OF 2).pdf PDF
M-302 FUELING SYSTEM PIPING ELEVATIONS (2 OF 2).pdf PDF
Amendment 0009 - ES403 ENLARGED SITE PLAN (3 OF 4).pdf PDF
EP101 PUMP HOUSE POWER PLAN.pdf PDF
Amendment 0009 - ES404 ENLARGED SITE PLAN (4 OF 4).pdf PDF
A-002 CODE ANALYSIS.pdf PDF
A-103 REFLECTED CEILING AND ROOF PLANS.pdf PDF
ES101 ELECTRICAL OVERALL SITE PLAN.pdf PDF
Amendment 0009 - EP601 POWER DIAGRAMS AND SCHEDULES.pdf PDF
Amendment 0009 - Spec Section 01 22 00 - 05OCT20.pdf PDF
Amendment 0009.pdf PDF
Amendment 0009 - ES508 STORAGE TANK ELECTRICAL ELEVATION.pdf PDF
EP602 ELECTRICAL SCHEDULES.pdf PDF
Amendment 0009 - 26 24 19.00 40.pdf PDF
EP603 ELECTRICAL SCHEDULES.pdf PDF
Amendment 0009 - Schedule of Special Inspections.pdf PDF
E-001 ELECTRICAL LEGEND AND ABBREVIATIONS.pdf PDF
M-403 TRUCK FILLSTAND PIPING LAYOUT PLAN AND ELEVATION.pdf PDF
Quonset Modified document and comments.pdf PDF
ES507 PRODUCT RECOVERY TANK PLAN AND DETAIL.pdf PDF
EP604 ELECTRICAL SCHEDULES.pdf PDF
A-302 WALL SECTIONS AND DETAILS.pdf PDF
A-101 FLOOR PLAN.pdf PDF
Amendment 0008 - 03 30 00.pdf PDF
Amendment 0008 - G-013 MISCELLANEOUS WORK ITEMS AND NOTES.pdf PDF
Amendment 0008.pdf PDF
Amendment 0008 - 32 13 13.06.pdf PDF
Amendment 0008 - ES401 ENLARGED SITE PLAN (1 OF 4).pdf PDF
Amendment 0008 - 33 52 43.11.pdf PDF
Amendment 0008 - C-407 PUMPHOUSE AND PRT GRADING AND DRAINAGE PLAN - PHASE 1.pdf PDF
Amendment 0007.pdf PDF
Amendment 0006 - Wage Determination.pdf PDF
Amendment 0006 - 1802100MH-101-R1.pdf PDF
Amendment 0006 - 09 90 00 (Q - RTA - Bolded-2).pdf PDF
Amendment 0006.pdf PDF
Amendment 0006 - 33 56 19 - Q - RTA - Bolded-2.pdf PDF
Amendment 0006 - A-501 (SCHEDULES).pdf PDF
Amendment 0005.pdf PDF
Amendment 0004.pdf PDF
Amendment 0003.pdf PDF
Amendment 0002.pdf PDF
Amendment 0001.pdf PDF
Solicitation Drawing.zip ZIP file
Supplemental Price Breakdown to the Bidding Schedule.xlsx XLSX spreadsheet
Specs - Volume 1.pdf PDF
Specs - Volume 2.pdf PDF
W912WJ20R0011_Solicitation.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 10 71 1 9.1 6

REMOVABLE FLOOD BARRIERS

PART 1 GENERAL

1.1 DEFINITIONS

1.1.1 Tropical Cyclones

Tropical Cyclone is a terminology for storms of cyclonic atmospheric conditions originating over tropical waters. The following are international classifications for tropical cyclones:

a. Tropical disturbance: Thunderstorms in the tropics for 24 hours or more.

b. Tropical depression: Wind speed 38 miles per hour (33 knots) or less.

c. Tropical storm: Wind speed range of 39 to 73 miles per hour (34 to 63 knots).

d. Hurricane: Wind speed 74 miles per hour or more (64 knots).

1.1.2 Weather Warnings

Weather warnings are issued for expected wind velocities. The following are international terminologies issued for weather warnings:

a. Gale warnings: Issued for expected wind velocity of 39-54 miles per hour (34-47 knots).

b. Storm warnings: Issued for expected wind velocity of 55-73 miles per hour (48-63 knots).

c. Hurricane watch: Issued for hurricane conditions within 36 hours.

d. Hurricane warning: Issued for sustained winds of 74 miles per hour (64 knots) expected in 24 hours or less.

1.1.3 Wind Velocities

Wind velocities for tropical cyclones and weather warnings are measurements taken 32 feet 10 inches above ground level.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

Provide shop drawings showing layout, profiles, and product components, including anchorage, hardware, and finishes. Include

SECTION 10 71 19.16 Page 1

Fuel Storage Replacement Quonset, ANG Rhode Island

Addendum 0003 Submittal September 09, 2020 dimensional plans, applicable material specifications, elevations and sections detailing mounting and connections, and load diagrams

Identification numbers, sizes, and types of shutters.

SD-03 Product Data

Calculations: Submit calculations approved by a qualified engineer to verify the flood panel's ability to withstand the design loading

Preparation instructions and recommendations

Installation instructions

SD-04 Samples

Flood Panel ; G

Where colors are not indicated, submit no less than 3 different samples of the manufacturer's standard colors for selection.

SD-10 Operation and Maintenance Data

Flood Panel ; G

Provide Operation and Maintenance data to include methods for maintaining installed products, precautions against cleaning materials, and methods detrimental to finishes and performance.

Submit data package in accordance with Section 01 78 23 OPERATION

AND MAINTENANCE DATA.

SD-11 Closeout Submittals

1.3 DELIVERY, STORAGE, AND HANDLING

A. Store products in manufacturer's unopened packaging container with identification labels intact until ready for installation.

B. Protect materials from exposure to moisture.

C. Store materials in a dry, warm, ventilated, weather-tight location. If outdoor storage is required, block materials to store at an incline, to prevent pooling of any moisture and pro-mote runoff.

Tarp materials in a tent-like arrangement, elevated above the product with open sides to allow airflow. Store all other hardware in a dry controlled environment.

D. Store materials so that no damage occurs to gaskets and attached hardware.

E. Use caution when unloading and handling product to avoid bending, denting, crushing, or other damage to the product.

F. When using forklifts, use forks of proper length to fully support product being moved. Consult shop drawings or consult with factory for proper lift points.

SECTION 10 71 19.16 Page 2

Fuel Storage Replacement Quonset, ANG Rhode Island

1.4 PERFORMANCE REQUIREMENTS

A. Design watertight panels to perform under load criteria as set forth is standards based on UFC 3-201-01 Table 2-1 . All water pressure loads and operating loads are transferred to the building structure.

B. Standard loading: Standard Flood Panels are designed for loads that could be anticipated during a 100-year storm event .

1.5 QUALITY ASSURANCE

A. Manufacturer Qualifications: Manufacturer must demonstrate previous successful experience in design and manufacture of similar flood-related closures. Upon request, provide supporting evidence including list of installations, descriptions, name, and method of contact.

B. Welder Qualifications: Welders certified in accordance with American Welding Society Procedures: AWS-1-GMAW-S, WPS No.

B2.004.90 for applicable material used in production of specified product.

1.6 PROJECT CONDITIONS

Maintain environmental conditions (temperature, humidity, and ventilation) within limits recommended by manufacturer for optimum results. Do not install products under environmental conditions outside manufacturer's absolute limits.

1.7 COORDINATION

Coordinate work with other trades, operations, and installation of adjacent materials to avoid damage.

1.8 WARRANTY

Watertight closure shall operate satisfactorily and be free of defects in material and workmanship for a period of not less than one year from the date of delivery.

PART 2 PRODUCTS

2.1 EQUIPMENT

2.1.1 Watertight Door and Window panels: Provide the following panels:

Basis of Design: Door Barrier Panel: Flood Risk America or approved equivalent

2.1.2 Product Details

1. Sealing Requirements: Flood Panel and gasket design shall provide an effective seal for short-term high water situations, to the protection level indicated on drawings.

2. Operation: Panels are non-operable .

3. Mounting/Load Transfer: Anchor to existing structure. Flood Panel

SECTION 10 71 19.16 Page 3

Fuel Storage Replacement Quonset, ANG Rhode Island designed for specified hydrostatic pressure (and other loads as specified) and will transfer loads to adjacent structure .

4. General: Panels to be anchored utilizing mechanical, anchor types as designed. Manufacturer to include all anchors, water-stop, and sealants, as designed .

5. Loading Direction Selection:

a) Standard: Positive Pressure Loading: (Direction of loading against flood panel so as to further compress gaskets against flood panel frame-"seating").

b) Optional: Reverse Pressure Loading: (Direction of loading against flood panel so as to force the flood panel away from the structure-"unseating").

6. Gaskets: Provide compression gasket, which requires no inflation.

7. Anchoring: Provide anchoring to all structural elements.

2.2 MATERIALS

2.2.1 Flood Panel : Composite FRP/IPN chemical structue panels

2.2.2 Gaskets

Gaskets to be factory mounted to flood panel assembly. Gaskets to be compressible closed cell type, and to be field replaceable.

2.2.3 Jamb Members

Jamb members to be designed and fabricated with appropriate material as required for the loading.

1. Aluminum: Aluminum 6061 of appropriate size and strength with welded or mechanical fastened construction.

2. Polyfiber: Polyfiber of appropriate size and strength with epoxied or mechanical fastened construction.

2.2.4 Sill Members

Sill members to be designed and fabricated with appropriate material as required for the loading:

1. Aluminum: Aluminum 6160 of appropriate size and strength with welded or mechanical fastened construction.

2. Polyfiber: Polyfiber of appropriate size and strength with epoxied or mechanical fastened construction.

2.2.5 Panel Mounting Hardware

Provide hardware sized for the size and weight of the flood panel and loads. Hardware to be factory located on panels, as practical. All loads are transferred to building structure.

SECTION 10 71 19.16 Page 4

Fuel Storage Replacement Quonset, ANG Rhode Island

2.2.6 Anchors

Manufacturer provided stainless steel 304 anchors as noted on shop drawings.

2.2.7 Aluminum Products

Aluminum products to be mill finish, welds are ground smooth, not polished, and are factory acid washed, neutralized and rinsed

2.2.8 Labeling

Each watertight panel and frame will be individually identified for matched installation.

PART 3 EXECUTION

3.1 EXAMINATION

Do not begin installation until substrates have been properly prepared.

If substrate preparation is the responsibility of another installer, notify Architect of unsatisfactory preparation before proceeding.

3.2 PREPARATION

Clean surfaces thoroughly prior to installation. Prepare surfaces using the methods recommended by the manufacturer for achieving the best result for the substrate under the project conditions

3.3 INSTALLATION

Install in accordance with manufacturer's installations instructions, approved shop drawings, shipping, handling, and storage instructions, and product carton instructions for installation. Panels shall be installed level, square, plumb, and rigid. Sealants, water-stop, and grouting to be applied per product application directions and in accordance with manufacturer's instructions. Tolerances: All dimensional requirements must be in accordance with manufacturer's installation instructions and shop drawings.

3.4 FIELD QUALITY CONTROL

Products to be operated and field verified including the sealing surfaces to assure that they maintain contact at the correct sealing points.

Verify all anchorage is in accordance with manufacture's installation instructions and applicable data sheets.

3.5 CLEANING

Repair or replace damaged installed products or components. Clean all sealing surfaces and touch up damaged finish.

3.6 PROTECTION

Protect installed products until completion of project. Touch-up, repair, or replace damaged products before substantial completion.

-- End of Section --

SECTION 10 71 19.16 Page 5

Fuel Storage Replacement Quonset, ANG Rhode Island

THIS PAGE INTENTIONALLY LEFT BLANK

SECTION 10 71 19.16 Page 6

Fuel Storage Replacement Quonset, ANG Rhode Island

10 71 19.16 - REMOVABLE FLOOD BARRIERS
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 Tropical Cyclones
1.1.2 Weather Warnings
1.1.3 Wind Velocities
1.2 SUBMITTALS
1.3 DELIVERY, STORAGE, AND HANDLING
1.4 PERFORMANCE REQUIREMENTS
1.5 QUALITY ASSURANCE
1.6 PROJECT CONDITIONS
1.7 COORDINATION
1.8 WARRANTY
PART 2 PRODUCTS
2.1 EQUIPMENT
2.1.1 Watertight Door and Window panels: Provide the following panels:
2.1.2 Product Details
2.2 MATERIALS
2.2.1 Flood Panel: Composite FRP/IPN chemical structue panels
2.2.2 Gaskets
2.2.3 Jamb Members
2.2.4 Sill Members
2.2.5 Panel Mounting Hardware
2.2.6 Anchors
2.2.7 Aluminum Products
2.2.8 Labeling
PART 3 EXECUTION
3.1 EXAMINATION
3.2 PREPARATION
3.3 INSTALLATION
3.4 FIELD QUALITY CONTROL
3.5 CLEANING
3.6 PROTECTION