This solicitation provides details for a construction project to replace the fuels storage complex at the Quonset Point Rhode Island Air National Guard Station. The project scope includes replacing the truck offload and fillstand positions and associated pumping and filtration equipment, constructing a new 600 gallon per minute pumphouse with control room, upgrading the refueler parking area, and reusing existing storage tanks with the new system. Construction will be phased to allow the existing system to operate until most of the new system is complete. The work is estimated to cost between $5-10 million and will be solicited as a small business set-aside using Best Value tradeoff procedures. The Department of the Army Corps of Engineers Engineering District New England will issue the solicitation.

View the file

Other files

File Type Posted
Amendment 0010.pdf PDF
A-202 BUILDING SECTIONS.pdf PDF
Amendment 0009 - G-009 PHASING PLAN 1.pdf PDF
M-603 FUEL SYSTEM FLOW DIAGRAM (2 OF 2).pdf PDF
M-302 FUELING SYSTEM PIPING ELEVATIONS (2 OF 2).pdf PDF
Amendment 0009 - ES403 ENLARGED SITE PLAN (3 OF 4).pdf PDF
EP101 PUMP HOUSE POWER PLAN.pdf PDF
Amendment 0009 - ES404 ENLARGED SITE PLAN (4 OF 4).pdf PDF
A-002 CODE ANALYSIS.pdf PDF
A-103 REFLECTED CEILING AND ROOF PLANS.pdf PDF
ES101 ELECTRICAL OVERALL SITE PLAN.pdf PDF
Amendment 0009 - EP601 POWER DIAGRAMS AND SCHEDULES.pdf PDF
Amendment 0009 - Spec Section 01 22 00 - 05OCT20.pdf PDF
Amendment 0009.pdf PDF
Amendment 0009 - ES508 STORAGE TANK ELECTRICAL ELEVATION.pdf PDF
EP602 ELECTRICAL SCHEDULES.pdf PDF
Amendment 0009 - 26 24 19.00 40.pdf PDF
EP603 ELECTRICAL SCHEDULES.pdf PDF
Amendment 0009 - Schedule of Special Inspections.pdf PDF
E-001 ELECTRICAL LEGEND AND ABBREVIATIONS.pdf PDF
M-403 TRUCK FILLSTAND PIPING LAYOUT PLAN AND ELEVATION.pdf PDF
Quonset Modified document and comments.pdf PDF
ES507 PRODUCT RECOVERY TANK PLAN AND DETAIL.pdf PDF
EP604 ELECTRICAL SCHEDULES.pdf PDF
A-302 WALL SECTIONS AND DETAILS.pdf PDF
A-101 FLOOR PLAN.pdf PDF
Amendment 0008 - 03 30 00.pdf PDF
Amendment 0008 - G-013 MISCELLANEOUS WORK ITEMS AND NOTES.pdf PDF
Amendment 0008.pdf PDF
Amendment 0008 - 32 13 13.06.pdf PDF
Amendment 0008 - ES401 ENLARGED SITE PLAN (1 OF 4).pdf PDF
Amendment 0008 - 33 52 43.11.pdf PDF
Amendment 0008 - C-407 PUMPHOUSE AND PRT GRADING AND DRAINAGE PLAN - PHASE 1.pdf PDF
Amendment 0007.pdf PDF
Amendment 0006 - Wage Determination.pdf PDF
Amendment 0006 - 1802100MH-101-R1.pdf PDF
Amendment 0006 - 09 90 00 (Q - RTA - Bolded-2).pdf PDF
Amendment 0006 - 10 71 19.16 - Q - RTA - Bolded-2.pdf PDF
Amendment 0006.pdf PDF
Amendment 0006 - 33 56 19 - Q - RTA - Bolded-2.pdf PDF
Amendment 0006 - A-501 (SCHEDULES).pdf PDF
Amendment 0005.pdf PDF
Amendment 0004.pdf PDF
Amendment 0003.pdf PDF
Amendment 0002.pdf PDF
Amendment 0001.pdf PDF
Solicitation Drawing.zip ZIP file
Supplemental Price Breakdown to the Bidding Schedule.xlsx XLSX spreadsheet
Specs - Volume 2.pdf PDF
W912WJ20R0011_Solicitation.pdf PDF
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RTA

SPECIFICATIONS

MAY 2020

VOLUME 1

Robert and Company 229 Peachtree Street, NE International Tower, Suite 2000 Atlanta, GA 30303-2120

DESC20S1 Replace Fuel Facilities, Quonset Air National Guard Base, North Kingstown, Rhode Island

THIS PAGE INTENTIONALLY LEFT BLANK

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 41 00 BIDDING SCHEDULE

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 14 00 PROJECT SITE COORDINATION

01 16 00 PROJECT MEETINGS, MANAGEMENT AND COORDINATION

01 22 00 MEASUREMENT AND PAYMENT

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01 PROJECT SCHEDULE

ATTACHED SUBMITTAL REGISTER

ATTACHED ENGINEERING FORM 4025

01 33 00 SUBMITTAL PROCEDURES

01 33 29 SUSTAINABILITY REPORTING

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 QUALITY CONTROL

01 45 01 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 45 35 SPECIAL INSPECTIONS

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL

01 58 00 PROJECT IDENTIFICATION AND SIGNS

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

01 78 23.33 OPERATION AND MAINTENANCE MANUALS FOR AVIATION FUEL

SYSTEMS

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION

02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL (Option

Item)

02 82 00 ASBESTOS REMEDIATION

02 83 00 LEAD REMEDIATION

DIVISION 03 - CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

DIVISION 04 - MASONRY

04 20 00 UNIT MASONRY

DIVISION 05 - METALS

05 12 00 STRUCTURAL STEEL

05 21 00 STEEL JOIST FRAMING

05 30 00 STEEL DECKS

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 51 33 METAL LADDERS

05 52 00 METAL RAILINGS

Fuel Storage Replacement Quonset, ANG Rhode Island

RTA Submittal May 15, 2020

E6EDTRSL

Typewritten Text

DELETED

E6EDTRSL

Cross-Out

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 BOARD AND BLOCK INSULATION

07 21 16 MINERAL FIBER BLANKET INSULATION

07 42 63 FABRICATED WALL PANEL ASSEMBLIES

07 60 00 FLASHING AND SHEET METAL

07 61 14.00 20 STEEL STANDING SEAM ROOFING

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 STEEL DOORS AND FRAMES

08 51 23 STEEL WINDOWS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 91 00 METAL WALL LOUVERS

DIVISION 09 - FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 GYPSUM BOARD

09 51 00 ACOUSTICAL CEILINGS

09 65 00 RESILIENT FLOORING

09 90 00 PAINTS AND COATINGS

09 97 13.17 THREE COAT EPOXY INTERIOR COATING OF WELDED STEEL

PETROLEUM FUEL TANKS

09 97 13.27 EXTERIOR COATING OF STEEL STRUCTURES

DIVISION 10 - SPECIALTIES

10 14 00.10 EXTERIOR SIGNAGE

10 44 16 FIRE EXTINGUISHERS

10 71 19.16 REMOVABLE FLOOD BARRIERS

DIVISION 13 - SPECIAL CONSTRUCTION

13 34 19 METAL BUILDING SYSTEMS

13 34 19.20 METAL CANOPY SYSTEMS

DIVISION 21 - FIRE SUPPRESSION

21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

22 08 00 HEAT TRACING FOR FREEZE PROTECTION

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS

Fuel Storage Replacement Quonset, ANG Rhode Island

RTA Submittal May 15, 2020

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING

CONTROL SYSTEMS

23 34 23.00 40 HVAC POWER VENTILATORS

23 37 13.00 40 DIFFUSERS, REGISTERS, AND GRILLS

23 82 00.00 20 TERMINAL HEATING UNITS

23 82 02.00 10 UNITARY HEATING AND COOLING EQUIPMENT

DIVISION 26 - ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 13.00 40 MEDIUM-VOLTAGE CABLES

26 08 00 APPARATUS INSPECTION AND TESTING

26 12 19.10 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED TRANSFORMERS

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 24 19.00 40 MOTOR CONTROL CENTERS

26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION

26 32 15.00 10 DIESEL-GENERATOR SET STATIONARY 100-2500 KW, WITH

AUXILIARIES

26 41 00 LIGHTNING PROTECTION SYSTEM

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 64.00 10 FIRE DETECTION AND ALARM SYSTEM, ADDRESSABLE

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 62 13.20 PRECAST/PRESTRESSED CONCRETE PILES

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID

PAVEMENTS

32 11 23 AGGREGATE BASE COURSES

32 12 13 BITUMINOUS TACK COATS

32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS

32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE

FACILITIES

32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 PAVEMENT MARKINGS

32 31 13.53 HIGH-SECURITY CHAIN LINK FENCES AND GATES

32 92 19 SEEDING

DIVISION 33 - UTILITIES

33 01 50.60 CLEANING OF PETROLEUM STORAGE TANKS

33 08 53 AVIATION FUEL DISTRIBUTION SYSTEM START-UP

33 09 52 FUEL PUMP CONTROL AND ANNUNCIATION SYSTEM (NON-HYDRANT)

Fuel Storage Replacement Quonset, ANG Rhode Island

33 11 00 WATER UTILITY DISTRIBUTION PIPING

33 40 00 STORM DRAINAGE UTILITIES

33 52 23.15 POL SERVICE PIPING WELDING

33 52 43.11 AVIATION FUEL MECHANICAL EQUIPMENT

33 52 43.12 AVIATION FUEL PANTOGRAPHS

33 52 43.13 AVIATION FUEL PIPING

33 52 43.14 AVIATION FUEL CONTROL VALVES

33 52 43.23 AVIATION FUEL PUMPS

33 52 43.28 FILTER SEPARATOR, AVIATION FUELING SYSTEM

33 56 10 FACTORY-FABRICATED FUEL STORAGE TANKS

33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT

41 22 13.15 BRIDGE CRANES, OVERHEAD MANUAL, UNDER RUNNING

-- End of Project Table of Contents --

Fuel Storage Replacement Quonset, ANG Rhode Island

Fuel Storage Replacement RTA Submittal Quonset, ANG Rhode Island May 15, 2020

SECTION 01 11 00

SUMMARY OF WORK

12/94

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

The general description below is given to indicate the approximate scope of this project only. It does not limit the work required under the project drawings and specifications.

The work of this project includes the construction of a new fuels complex that includes a pump house with a control room, product recovery tank, refueling vehicle parking, truck loading and unload ing points, and supporting facilities. The new fuel facility shall supply the refueling trucks that service the airfield. The project shall also involve demolition and site improvements to include electrical and communication work. Lastly, a temporary truck fueling area shall be built to ensure fuel issue and receipt capabilities are maintained during construction .

In addition to this work there are eight Option items:

1.2 SPECIAL CONSTRUCTION FEATURES

1.2.1 Sole Source Product

JELLYFISH FILTER SYSTEM (MODEL JF-6) AND CARTRIDGES (MANHOLE CONFIGURATION)

See Specification Section 33 40 00 for additional information.

1.2.2 Government Furnished Contractor Installed (GFCI)

Water Meter - The Government will provide a Badger E series 1-inch water meter with a Galaxy transmitter to register in gallons fro the Contractor to install at the pumphouse. (GFCI) see Specification Section 33 40 00 for additional information.

The Contractor shall note that a site walk is required prior to the initiation of other on site work to determine the condition, alignment, and other related features of the work.

1.3 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

SECTION 01 11 00 Page 1

1. Canopy Foundation

2. Canopy Superstructure

3. Contaminated soil testing and stockpiling

4. Contaminated soil transporting and disposal

5. Asbestos containing gasket

6. Transite pipe

7. Lead contaminated materials

8. ATG related work

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Utility Outage Requests ; G, RO

Utility Connection Requests ; G, RO

Welding Permits ; G, RO

SD-07 Certificates

Request Application ; G, RO

Request Application to work outside the hours of operation.

1.5 SUPERINTENDENCE BY THE CONTRACTOR

a. At all times during the performance of the contract and until the work is completed and accepted, the Contractor shall directly superintend the work and have on the worksite a competent project superintendent who is satisfactory to the Contracting Officer and has the authority to act for the Contractor.

b. The qualified superintendent, and competent alternate, shall be capable of reading, writing, and conversing fluently in the English language.

c. The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on fuel facility related projects . The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

d. The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.

The superintendent is required to attend partnering meetings, and quality control meetings.

e. The project superintendent shall maintain a physical presence at the site at all times and be responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.

SECTION 01 11 00 Page 2

f. The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.6 PROJECT/SITE CONDITIONS

1.6.1 Site Security

The Contractor shall report any vandalism, suspicious activities or devices to the Contracing Officer or local police as soon as possible.

The Contracting Officer will notify the Contractor of any heightened security measures and will expect vigilant monitoring of equipment, grounds and security fencing while working. At a heightened security posture, there may be work areas that are restricted. The Contracting Officer will notify the Contractor of these restricted areas, and work may be delayed or restricted or will be performed in these areas under the direct supervision of U.S. Army Corps of Engineers personnel.

See Section 01 14 00 PROJECT SITE COORDINATION for additional requirements.

1.7 WORK SEQUENCE AND SCHEDULING

1.7.1 Hours of Operations

Normal work hours are from 7:00 a.m. through 3:30 p.m., Monday through Friday. The Contractor will not be permitted to work on Saturday, Sunday or legal holidays unless otherwise authorized by the Contracting Officer.

The exclusion of work on Saturday, Sunday and legal holidays has been considered in computing the performance time of this contract. The following legal holidays are observed:

January 1st Third Monday in January Third Monday in February Last Monday of May July 4th 1st Monday of September 2nd Monday of October 11th of November Fourth Thursday of November 25th of December

When one of the above designated legal holidays falls on a Sunday, the following Monday will be observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday.

Work outside the normal hours of operation requires Contracting Officer approval. The request to work outside the hours of operation shall be made in writing to the Contracting Officer 10 calendar days prior to such work to allow arrangements to be made by the Government. The request application shall include specific dates, hours, location, type of work to be performed, contract number and project title, and names of all individuals who will be working outside the hours of operations. During

SECTION 01 11 00 Page 3 periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer.

1.7.1.1 Installation Hours of Operation

The Installation is on a 4-Day work week with Mondays off. This will not affect the Contractor's ability to perform work on a Monday. However, the Contractor must notify the COR/143d CES if they plan work on a Base Holiday. For example, if MLK Jr. Holiday is on a Monday, the base will typically have the Friday prior as a Holiday. This ensures enough security personnel will be allotted for work to continue. The Base Holiday schedule can be obtained from the 143d CES.

1.7.2 Work Sequence

1.7.2.1 General

There are certain essential criteria relative to the preparation of a work sequence and time schedule which the Contractor will be required to implement and follow during the prosecution of the work. Minor variations in the sequence of the items of work as specified may be made by the Contractor, provided such variations do not conflict with critical elements of the schedule. Proposed minor variations shall be noted on the progress charts submittal required by CONTRACT CLAUSE, entitled SCHEDULES FOR CONSTRUCTION CONTRACTS. Variations shall be approved by the Contracting Officer prior to implementation.

1.7.3 Organization at the Site

1.7.3.1 General

The Contractor shall employ ample personnel and sufficient equipment to accomplish the work of this contract in the least amount of time, within the prosecution period specified in SPECIAL CONTRACT REQUIREMENTS, Clause

COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK (APR 1984) FAR 52.211-10.

1.7.3.2 Rate of Progress

Should the Contractor fail to maintain a satisfactory rate of progress in accordance with the Contractor's approved progress schedule, the Contracting Officer may require that additional personnel and equipment be placed on the work and weekend and overtime work be performed, in order that the work be brought up to schedule and maintained.

1.8 CONTRACTOR'S USE OF FACILITIES AND HAULING ROUTES

The Contractor shall be responsible for the following:

(1) Determining the trucking and hauling routes and associated restrictions to and from the work, to include the coordination for the use of such routes with local, State, and Federal authorities.

(2) Complying with all local, State, and Federal regulations and restrictions when using any facilities or hauling routes.

1.9 CONTRACTOR USE OF PREMISES

A. Limited Use:

SECTION 01 11 00 Page 4

1. Limit use of the premises for storage and execution of the Work to allow for Government occupancy and use of adjoining areas.

2. Coordinate with the Government to avoid interference of operations.

3. Conduct operations so as to ensure the least inconvenience to the Government.

B. Full Owner Occupancy: Cooperate with the Government during construction operations to minimize conflicts and facilitate Government usage.

1.9.1 Access to the Site and Storage/Staging Areas

Access to the project sites are available for construction traffic. The Contractor is responsible for maintaining access necessary for its equipment, material, and plant to and from the work area.

Access to temporary facilities and storage/staging areas shall be as specified in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS and as shown on the contract drawings.

1.9.2 Temporary Facilities and Utilities, and Storage Areas

The Contractor shall conform to Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS regarding temporary facilities, temporary utilities, and storage areas. Confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

1.9.3 Work Limits

Work shall be restricted to the limits of the work as shown on the contract drawings and to storage areas as indicated in Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS, as shown on the contract drawings, and as indicated by the Contracting Officer.

1.9.4 Protection and Security

a. Protection to Contractor personnel or their equipment cannot be provided at the worksite by the Government.

b. The Contractor shall protect all its personnel, Government personnel, and the general public from injury.

c. The Contractor shall conduct all its work so as to prevent injury or unsafe conditions during construction.

1.9.5 Work By Other Contractors

During the performance period of this contract, no other work is anticipated to occur by other contractors.

1.9.6 Emergency Contacts

The Contractor shall provide a list of emergency contacts to be used in the event of an emergency. The list shall include the contact names, SECTION 01 11 00 Page 5 addresses, and telephone numbers. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.9.7 Damaged Property

Work shall proceed in a manner which will minimize disturbance or risk of damage to structures and surrounding lands. The Contractor shall repair such items damaged in the course of carrying out the work at no additional cost to the Government. All repairs shall match similar existing items in all aspects. All replacements shall be in kind.

1.9.8 Contractor's Receipt of Supplies

The Contractor shall be responsible for all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site.

1.9.9 Daily Clean Up

The Contractor shall at all times keep rubbish from entering surrounding lands and water. Rubbish accumulated at the temporary facilities shall be removed from the premises daily.

1.9.10 Government Sanitary Facilities

Toilet facilities are not available on site for the Contractor's use. The Contractor shall provide portable toilets for its personnel and subcontractors as specified in Section 01 50 00 TEMPORARY CONSTRUCTION

FACILITIES AND CONTROLS.

1.10 ON-SITE PERMITS

1.10.1 Utility Outage Requests and Utility Connection Requests

a. Work shall be scheduled to hold outages to a minimum.

b. Planned utility outages and connections required during the prosecution of work that affect existing systems, such as HVAC, mechanical, or electrical shall be arranged for at the convenience of the Government and may have to be scheduled outside the regular working hours or on weekends.

c. Interruptions shall be defined as any Contractor operation that interferes with access through, or use of facilities or areas including utilities, Energy Monitoring and Control Systems (EMCS), parking lots, generators, or roads.

d. The Contracting Officer may permit utility outages at his discretion.

e. The Contractor shall not be entitled to additional payment for utility outages and connections required to be performed outside the regular work hours.

f. Request for planned utility outages and interruptions shall be submitted in writing at least 15 working days in advance of the date desired and includes at least one alternate date. Services shall not be interrupted until receipt of approval of proposed hours and dates are received from the Contracting Officer. The request shall include the

SECTION 01 11 00 Page 6 following information: Location(s) of outages and interruption(s), hours and dates of interruption(s), and which facilities, utilities and services are affected. Contractor is cautioned that outages and/or interruptions may not be granted on the date(s) requested.

g. Contractor shall notify the Contracting Officer at least 7 calendar days in advance of any cancellation of any scheduled interruption.

h. Dig Permit AF Form 103 Dig Permit should be obtained and Dig Safe should be called 2-weeks prior to any excavation. Also, utility location shall be the responsibility of the Contractor and noted in the specifications as such. 143d CES does not have the inherent capability to provide utility location services at this time.

1.10.2 Utility Cutovers

a. Ensure that new utility lines are complete, except for the final connection, before interrupting existing utility service(s).

b. Make utility cutovers during hours that will cause least impact to daily operations of the Installation. Conform to procedures required in Subpart "Work Outside Normal Hours of Operations".

c. A strict time limit on utility cutovers may be required.

d. Interruption to telephone service, electric service, and fire alarm shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours". Such interruption shall have a time limit.

e. All utility tie-ins performed by the Contractor shall be performed in the presence of the Contracting Officer.

1.10.3 Pre-Outage Coordination Meeting

Once the request for a planned utility outage and interruption is approved, and prior to beginning work on the utility system requiring shut down, attend a pre-outage coordination meeting with the Contracting Officer to review the scope of work and the lock-out/tag-out procedures for worker protection. No work will be performed on energized electrical circuits unless proof is provided that no other means exist.

1.10.4 Utilities Not Shown

If the Contractor encounters, within the construction limits of the project, utilities not shown on the drawings and not visible as to the date of this contract and such utilities will interfere with construction operations, the Contractor shall immediately notify the Contracting Officer in writing to enable a determination by the Contracting Officer as to the necessity for removal or relocation. If such utilities are removed or relocated as directed by the Contracting Officer, the Contractor shall be entitled to equitable adjustment for any additional pertinent work or delay.

1.10.5 Welding Permits

Permits to perform welding work shall be requested 14 days prior to the work and shall be posted at a conspicuous location in the construction area.

SECTION 01 11 00 Page 7

The contractor must notify the 143d Fire & Emergency Services Flight prior to all Hot Work. This can usually be on the same day of the work to be performed, unless the work will require the Fire Department to be present. See specification section 01 35 25 paragraph 1.13 for hot permit requirements.

1.11 QUALITY ASSURANCE

a. All items of work not addressed in the contract documents shall be completed in strict accordance with the manufacturers’ specifications.

b. The Government is not obligated to inspect the Contractor’s work, or to protect the Contractor from the consequences of its work. Government inspections are a general examination of the Contractor’s conduct and workmanship and are solely for the purpose of the Government.

Government-designated Quality Assurance Representatives (QARs) do not have the authority to accept work, nor is a Government inspection to be construed as conclusive.

c. Government agents including QARs and project engineers are not authorized to change the contract without the written approval of the Contracting Officer; this lack of authority extends to all situations in which the action of these agents could be construed as constituting a change.

d. The quality of workmanship is subject to audit by Government or Government-designated QARs at any time during the contract. The Contractor shall cooperate fully and provide all information necessary for this audit.

e. The Contractor shall submit all requests for changes in writing to the Contracting Officer. Do not proceed with changes without possession of written authorization of the Contracting Officer.

f. The Contractor shall not conceal any work unless the Contracting Officer has approved all items of work which are to be concealed. The Contractor shall notify the Contracting Officer of its intention to conceal work at least 24 hours in advance of concealment.

1.12 GENERAL SAFETY REQUIREMENTS

1.12.1 General

The Contractor shall take all necessary precautions in observing safety regulations in accordance with Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS, and shall assume the responsibility to guard against causing of fires and/or explosions and to protect Government property. The Contractor shall perform the work in a manner consistent with security and with fire safety regulations especially with regards to ingress and egress. Temporary closures shall not compromise life safety, security or fire safety.

1.12.2 Contractor's Project Superintendent

The Contractor's project superintendent shall take an active role in enforcing the safety requirements by participation in safety conferences, hazard analysis, tool box meetings, walk-through inspections, correction of violations, etc., and including that of any subcontractor's work.

SECTION 01 11 00 Page 8

1.13 ENVIRONMENTAL PROTECTION

To provide for control of all environmental pollution arising from construction activities, the Contractor and its subcontractors, in the performance of this contract, shall comply with Section 01 57 19 ENVIRONMENTAL PROTECTION, and all applicable federal, state, and local laws and regulations concerning environmental protection pollution control and abatement.

1.14 PRECONSTRUCTION CONFERENCE

The Contracting Officer will conduct a preconstruction conference with key Contractor personnel. The purpose of the conference is to review contract requirements and to establish a working relationship between the Contractor's Staff and the U.S. Army Corps of Engineers personnel who will be closely associated with the project. During the conference, the Contracting Officer will inform the Contractor concerning Job Safety, Quality Control, Labor Relations, and Environmental Protection. The Contractor's Superintendent, Quality Control Representative, and Site Safety and Health Officer (SSHO) shall attend this conference.

1.15 WARRANTIES

At the end of Phase 1 and commissioning is complete, the government will take conditional acceptance of the facility and the government will operate the pump house. The contractor will not be held responsible for any damages or misuse attributable to the government personnel operating the facility, as determined by the Contracting Officer, however warranties will not go into effect until after Phase 2 commissioning and the entire system is turned over to the Government.

1.16 BADGING

Badging (DBIDS) for the project will have to be processed through the 143d Civil Engineer Squadron. Security Forces will only give the contractor up to 4 badges with Escort Privileges (One typically reserved for Company Executive). All vehicles will be searched daily. Please allow 3 weeks for application review. Badges are only good for 6 months. No Restricted Area Badges or Flight Line access should be needed for this job.

1.17 Chain of Custody for Hazardous Material Disposal

If the Contractor is required to dispose of hazardous materials (Option items) the Contractor shall follow all local, state and federal laws and regulations for disposal as indicated in the specifications and shall provide all required chain of custody documents and receipts to the Contracting Officer.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section --

SECTION 01 11 00 Page 9

THIS PAGE INTENTIONALLY LEFT BLANK

SECTION 01 11 00 Page 10

SECTION 01 14 00

PROJECT SITE COORDINATION

11/11

PART 1 GENERAL

1.1 SECURITY/TRAFFIC CONTROL

A. General: Rhode Island Air National Guard facilities are controlled access Federal Military Reservations. As such, there are strict controls over access to these facilities. Procedures instituting these controls have been developed and will be delineated and explained in these specifications and/or in the pre-construction conference.

1. All vehicles entering Rhode Island Air National Guard Bases do so with the understanding that they will be subject to periodic inspections for contraband or Government property. Any person found with unauthorized Government property in his/her possession will be prosecuted to the fullest extent of the law.

2. In the event an employee of the Contractor terminates employment with the Contractor, or is no longer assigned to a construction job on a Rhode Island National Guard Installation, the Contracting Officer should be notified immediately to be aware of potential unauthorized access.

3. Should the contract requirement necessitate being on the flight line at the Rhode Island Air National Guard Base, vehicle passes with authorized flight line access will be required. However, unless the passes state flight line access and the Contractor has business in the flight line area, Contractor employees are not allowed anywhere near aircraft operating areas.

4. In order to facilitate issuance of vehicle passes, the Contractor shall provide to the Contracting Officer, a list of individuals who will be working on this contract and the length of time they are expected to be working. This list shall include all subcontractors working on the contract.

5. Material suppliers are normally given one day passes, however, if the supplier will be making frequent deliveries, notify the Contracting Officer and a pass to accommodate the situation will be issued. The Contractor is cautioned to give suppliers the exact title of the job and location of where materials are to be delivered. Do not send supplies to a military warehouse. The Contractor is cautioned to also instruct suppliers that gate guards, if applicable, will not sign for deliveries. Contractor personnel shall be present to receive deliveries.

6. Blocking of Streets: In the event the Contractor or any subcontractor finds it necessary to barricade any street or road on base, the Contracting Officer must be notified at least 24 hours in advance. Adequate notification must be given in order to coordinate rerouting of emergency vehicles.

7. Material and Tool Safety: The Contractor is solely responsible

SECTION 01 14 00 Page 1 for the securing of its tools, equipment and materials. The U.S.

Government takes no responsibility or liability for any material, tool, or equipment, which is missing. Should the Contractor notice that it is missing any materials or equipment, the contractor shall notify the Contracting Officer immediately and complete required reports.

8. Seat Belts: The wearing of seat belts is mandatory when operating a vehicle on any RI Air National Guard Base. Periodic checks will be made and individuals not wearing seat belts will be restricted from driving on base.

9. Motorcycles: Any individual operating a motorcycle on a RI Air National Guard Base is subject to all State of Rhode Island laws governing the operation of motorcycles. These include, but are not limited to, the wearing of helmets, running with headlights on, etc.

Prior to operating a motorcycle on Base, all operators must comply with the Base Motorcycle Safety Policy.

10. Posted Speeds: All personnel operating motor vehicles on base must observe a 15mph Speed limit, all stop signs, and all pedestrian walkways. Any person stopped for exceeding the posted speeds or not stopping for pedestrians in crosswalks will be restricted from driving on base.

11. Vehicle Parking: All Contractor personnel shall park in the Contractors designated staging area as directed by the Contracting Officer and in no case shall they use any parking space designated for base personnel.

1.2 SAFETY AND PROTECTION OF WORK AND EXISTING PROPERTY

A. General:

1. Attention is directed to the fact that the Contractor may be working in an area that is an active airport. If so, many aircraft-related service vehicles travel about the site daily. The Contractor must carry out the work called for in this Contract in such manner as to interfere in the least possible degree with the full and continuous use of the airport. Also on the site are concentrations of active utility lines located below ground. The Contractor shall exercise extreme caution during the course of operations so as not to cause any damage to any part of the existing utilities.

2. The Contractor shall take all reasonable steps to prevent injury to persons (including employees) and property in performance of this contract, including all steps and actions required under safety provisions of applicable laws and applicable construction codes.

B. Work Performance:

1. Contractor shall provide for the safety and protection of the work as set forth in Subpar1 1.1. The Contractor shall provide protection at all times against rain, wind, storms, frost, freezing, condensation or heat so as to maintain all work, equipment and materials free from injury or damage. At the end of each day, all new work likely to be damaged shall be protected/covered.

2. The Contracting Officer shall be notified immediately at any time

SECTION 01 14 00 Page 2 operations are stopped due to conditions, which make it impossible to continue operations safely or to obtain proper results.

3. Contractor shall construct and maintain all necessary temporary drainage and do all pumping necessary to keep excavations, pits and trenches and ducts free of water. The pumped water shall be pumped into a container and disposed of in appropriate areas. No pumped water shall be allowed on the aircraft-parking apron.

4. Concrete/Asphalt surfaces shall be protected from damage by proper covering and care when handling heavy equipment or handling mortar or other such materials, and proper cribbing and shoring shall be used to prevent overloading of concrete/asphalt surfaces while moving heavy equipment. Provide metal pans under pipe-threading machines and clean such pans daily, keep oil off floors and restore floors to former condition where damaged or stained.

C. Existing Property:

1. Contractor shall provide for the safety and protection of existing property as set forth in the Paragraph 1.03. Any damage to existing facilities resulting from construction operations shall be reported immediately to the Contracting Officer and promptly repaired by the Contractor at no additional cost to the Government.

1.3 GOVERNMENT OCCUPANCY:

A. The Government may occupy adjoining areas during entire period of construction for the conduct of its normal operations.

B. Cooperate with the Government to minimize conflict, and to facilitate Government operations.

C. Provide a maintain access for Govermental personnel between Building 14 and the existing fuel facility at all times. See Drawing C-101 Note 12.

1.4 SECURITY PLAN

A. The Contractor shall ensure that all rules and regulations that pertain to safety and security are strictly adhered to at all time that work is conducted.

B. Identification will be required for entry. All construction workers will be subject to complete search and inspection, at any time. The access gate delineated on the plans will be the only authorized entry and exit point to the work area for the construction company personnel. All construction personnel will remain clear of all aircraft at all times when work is to take place at the Rhode Island Air National Guard Base. There is absolutely no valid excuse for construction personnel to be on or near any aircraft.

C. Vehicle passes will be issued by the Government security on an as-needed basis only. Vehicles not having a pass will not be allowed entry into the work area. Vehicles found to be violating safety procedures (speed limits, etc.) will not be allowed re-entry from date of violation.

D. The Contractor shall provide the Government 48-hour notice for overtime work during regular workdays. The Contractor shall provide the Government 10 day notices for work on Mondays, Saturdays, Sundays or

SECTION 01 14 00 Page 3 holidays observed by the Rhode Island National Guard. Any overtime must be approved by the Contracting Officer prior to commencement of said work.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

SECTION 01 14 00 Page 4

SECTION 01 16 00

PROJECT MEETINGS, MANAGEMENT AND COORDINATION

11/11

PART 1 GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on the project including, but not limited to, the following:

1. Coordination drawings.

2. Coordination with Contracting Officer for special requirements.

3. Administrative and supervisory personnel.

4. Project meetings.

5. Requests for information (RFIs).

B. Special Coordination with Contracting Officer: If there are inadvertent discoveries of archaeological material, bones, or funerary objects during construction or other soil disturbance, the Contractor shall contact the Contracting Officer immediately by telephone or radio, and work should cease in that area until National Historic Preservation Act (SOP3) and Native American Graves protection and Repatriation Act (SOP12) regulations are implemented for compliance. Any disposition of archeological deposits are the responsibility of the National Guard, not the Contractor.

C. Each contractor shall participate in coordination requirements.

Certain areas of responsibility will be assigned to a specific contractor.

D. Related Work Specified Elsewhere:

1. For preparing and submitting Contractor's construction progress schedule: SECTION 01 32 01 PROJECT SCHEDULE.

2. For project coordination: SECTION 01 14 00 PROJECT SITE

COORDINATION.

3. For Submittal Requirements: SECTION 01 33 00 SUBMITTAL PROCEDURES.

4. For coordinating closeout of the Contract: SECTION 01 78 00

CLOSEOUT SUBMITTALS.

1.2 DEFINITIONS

RFI (Request for Information): Request prepared by the Contractor, on a specific form provided by the Contracting Officer.

1.3 PRECONSTRUCTION CONFERENCE

See Section 01 11 00 SUMMARY OF WORK.

SECTION 01 16 00 Page 1

1.4 PROGRESS MEETINGS

A. Conduct Project progress meetings at weekly intervals. Intervals may change at the direction of the Contracting Officer. Coordinate dates of meetings with preparation of payment requests.

1. The Contractor shall provide call-in conference number.

B. Attendees: Representatives of Government, Contractor, Contracting Officer, and Designer (as necessary), shall be represented at these meetings. All participants shall be familiar with Project and authorized to conclude matters relating to the work.

C. Agenda: The Contracting Officer will review and correct or approve minutes of the previous progress meeting. Review with the Contracting Officer other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

1. Contractor's Construction Schedule: Review progress since the last progress meeting. Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to the Contractor's Construction Schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so.

Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Performance Period.

a. Contractor shall provide a written narrative to the Contracting Officer in the event the project is behind schedule more than two weeks from the approved CPM schedule.

2. Review present and future needs of each subcontractor present, including the following:

a. Interface requirements.

b. Sequence of operations.

c. Status of submittals.

d. Deliveries.

e. Off-site fabrication.

f. Access.

g. Site utilization.

h. Temporary facilities and controls.

i. Work hours.

j. Hazards and risks.

k. Progress cleaning.

l. Quality and work standards.

m. Status of correction of deficient items.

n. Field observations.

o. Request for Information.

p. Status of proposal requests.

q. Pending changes.

r. Status of Change Orders.

s. Documentation of information for payment requests.

3. Minutes: The Contractor will record the meeting minutes.

a. Contractor shall record meetings in digital audio or audio/video format and provide a copy to the contracting officer for record.

SECTION 01 16 00 Page 2

4. Reporting: Contractor shall record meeting results and distribute written copies to everyone in attendance and to others affected by decisions or actions resulting from each meeting. Minutes shall be distributed within two business days of the meeting.

1.5 PRE-INSTALLATION CONFERENCES

A. Pre-Installation Conferences shall be held prior to the start of various portions of the work, typically prior to the start of work for each construction trade. These meetings shall be held on an as needed basis as determined by the Contracting Officer.

B. Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: In addition to representatives of the Government, subcontractors, suppliers, and other entities involved in or affected by the installation and its coordination, or performance of preceded or future activities, shall be represented at these meetings. Advise the Contracting Officer of scheduled meeting dates.

2. Agenda: Contracting Officer will review progress of other construction activities and preparations for the particular activity under consideration, including the following requirements:

a. Protection of construction and personnel.

b. The Contract Documents.

c. Options.

d. Related RFIs.

e. Related Change Orders.

f. Purchases.

g. Deliveries.

h. Submittals.

i. Review of mockups.

j. Possible conflicts.

k. Compatibility problems.

l. Time schedules.

m. Weather limitations.

n. Manufacturer's written recommendations.

o. Warranty requirements.

p. Compatibility of materials.

q. Acceptability of substrates.

r. Temporary facilities and controls.

s. Space and access limitations.

t. Regulations applicable to the issue at hand.

u. Testing and inspecting requirements.

v. Installation procedures.

w. Coordination with other work.

x. Required performance results.

y. Protection of adjacent work.

3. Minutes: Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to the Contracting Officer and each party present and to parties who should have been present.

SECTION 01 16 00 Page 3

5. Do not proceed with the installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

1.6 COORDINATION MEETINGS

A. Conduct Project coordination meetings at weekly intervals. Project coordination meetings are in addition to specific meetings held for other purposes, such as progress meetings and preinstallation conferences.

B. Attendees: In addition to representatives of Government, Contracting Officer, and Designer (as necessary), subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the work.

C. Agenda: Review and correct or approve minutes of the previous coordination meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

1. Combined Contractor's Construction Schedule: Review progress since the last coordination meeting. Determine whether each subcontract is on time, ahead of schedule, or behind schedule, in relation to Combined Contractor's Construction Schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Performance Period.

2. Schedule Updating: There will be NO revision to the schedule unless it is due to a change order. If the change order required to revise the schedule is approved, revise Combined Contractor's Construction Schedule after each coordination meeting where revisions to the schedule have been made. Issue revised schedule concurrently with report of each meeting.

3. Review present and future needs of each subcontractor present, including the following:

a. Interface requirements.

b. Sequence of operations.

c. Status of submittals.

d. Deliveries.

e. Off-site fabrication.

f. Access.

g. Site utilization.

h. Temporary facilities and controls.

i. Work hours.

j. Hazards and risks.

k. Progress cleaning.

l. Quality and work standards.

m. Change Orders.

n. Request for Information.

D. Reporting: Contractor shall record meeting results and distribute copies to everyone in attendance and to others affected by decisions

SECTION 01 16 00 Page 4 or actions resulting from each meeting.

1.7 OTHER MEETINGS

Other meetings may be scheduled from time to time by the Contracting Officer to determine progress, the causes for the lack of progress, remedies and for clarification of the provisions of the contract.

1.8 COORDINATION

A. Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other contractors to allow optimum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to allow optimum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Government and separate contractors if coordination of their Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of others to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of construction progress schedule.

2. Preparation of the schedule of values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of Submittals.

5. Progress meetings.

6. Preinstallation conferences.

7. Project closeout activities.

8. Startup and adjustment of systems.

D. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials.

1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work. Refer to other Sections for disposition of salvaged materials that are designated as Governmentâ €™s property.

SECTION 01 16 00 Page 5

E. Coordination with Contracting Officer: Coordination of Work with Contracting Officer includes, but is not limited to, the following:

1. Deliveries of GF/GI equipment.

2. Utility connections for gas, electric, water, communications, sanitary sewer and storm sewer.

3. Review of schedules, samples, plans, and specifications that indicate information and recommended approval by Contracting Officer.

4. Key schedule and key cylinders.

1.9 REQUESTS FOR INFORMATION (RFIS)

A. Procedure: Immediately on discovery of the need for interpretation of the Contract Documents, prepare and submit an RFI on the form specified.

1. RFIs shall originate with Contractor. RFIs submitted by entities other than Contractor will be returned with no response.

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's Work or work of Subcontractors.

B. Content of the RFI: (Contractor to use Electronic Form provided by the Contracting Officer) Include a detailed, legible description of item needing interpretation and the following:

1. Project name.

2. Date.

3. Name of Contractor.

4. Contract number and title.

5. Name of Designer /Engineer and Contracting Officer.

6. RFI number, numbered sequentially.

7. Specification Section number and title and related paragraphs, as appropriate.

8. Drawing number and detail references, as appropriate.

9. Field dimensions and conditions, as appropriate.

10. Contractor's suggested solution(s). If Contractor's solution(s) impact the Contract Times or the Contract Price, Contractor shall state impact in the RFI.

11. Contractor's signature (digital format).

12. Attachments: Include drawings, descriptions, measurements, photos, product data, Shop Drawings, and other information necessary to fully describe items needing interpretation.

a. Supplementary drawings prepared by the Contractor shall include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments.

C. Hard-Copy RFIs

1. The General contractor…