This document contains questions and answers from a pre-solicitation conference for solicitation number N6264920R0003 for H-53 aircraft maintenance and repair services. The Navy is seeking proposals for depot-level maintenance, repair, and overhaul of H-53 aircraft to support the Navy and Marine Corps fleets. Offerors asked about paint stripping procedures and requested additional loading/unloading manuals. The Navy responded that alternative stripping methods using chemical removers could be proposed if composite materials are properly protected. One manual on C-5/C-17 loading procedures was still being researched for release. Interested parties must submit a non-disclosure agreement to receive the draft solicitation documents and are invited to provide feedback on the draft performance work statement and contract data requirements list.

View the file

Other files

File Type Posted
Pre-Sol Conference Q&A_3.docx DOCX document
H-53 Pre Solic Conf QAs.docx DOCX document
May 2019 HQMC_CNAF RESET Policy Message.pdf PDF
H-53E Att 09 Fac and AF Req 2019-12-13.docx DOCX document
CDRL A004 PRODUCTION PLAN H-53 12.13.19.pdf PDF
H-53E_Att_14_Price_Summary_Spreadsheet_DRAFT (2019-12-13).xlsx XLSX spreadsheet
04 - H-53E Att 01 PWS (2019-12-13) v1.docx DOCX document
H-53E_QUESTIONS_AND_ANSWERS_13DEC2019.xlsx XLSX spreadsheet
DRAFT RFP N6264920R0003 12.13.19.docx DOCX document
CDRL A007 SITUATION SUMMARY REPORT H-53 12.13.19.pdf PDF
Attachment_4_H-53_PRE_SOL_CONF_ACCEPTABLE_ID_FOR_NAFA_ACCESS.PPTX PPTX presentation
Attachment_2_H-53_PRE_SOLICITATION_CONFERENCE_Designated_Third_Country_Nationals.docx DOCX document
Attachment_1_H-53_PRE_SOLICITATION_CONFERENCE__Access_to_NAF_Atsugi.docx DOCX document
Attachment_3_H-53_PRE_SOL_CONF_Third_Designated_Country_List.pdf PDF
H-53E_Att_07_TEI_Process_at_Contarctor_Facilities_DRAFT.docx DOCX document
CDRL_B007_FINAL_MATERIAL_CONSUMPTION_REPORT_H-53.pdf PDF
CDRL_C001_MEETING_MINUTES_H-53.pdf PDF
CDRL_B002_AVDLR_TRACKER_H-53.pdf PDF
CDRL_A007_SITUATION_SUMMARY_REPORT_H-53.pdf PDF
CDRL_B009_EXCESS_MATERIAL_REPORT_H-53.pdf PDF
CDRL_A002_TECHNICAL_DIRECTIVES_REPORT__H-53.pdf PDF
CDRL_B010_ANNUAL_PHYSICAL_INVENTORY__H-53.pdf PDF
CDRL_G001_MONTHLY_MATERIAL_EXPENSE_REPORT_H-53.pdf PDF
CDRL_B014_DISCREPANT_PART_ON_INDUCTION_REPORT__H-53.pdf PDF
CDRL_B001_DAILY_REQUISITION_REPORT_(DRR)_H-53.pdf PDF
CDRL_A008_EXAMINATION_&_EVALUATION_(E&E)_DISCREPANCY_REPORT_H-53.pdf PDF
CDRL_A005_NOTIFICATION_OF_AIRCRAFT_DELAY_H-53.pdf PDF
CDRL_B004_RECEIPT_REPORT_H-53.pdf PDF
CDRL_A006_SCHEDULED_REMOVAL_CARDS_H-53.pdf PDF
CDRL_L001_TECHNICAL_DATA_INVENTORY_LIST_H-53.pdf PDF
CDRL_D004_CONTRACTOR_TRAINING_PLAN_H-53.pdf PDF
CDRL_C002_PRESENTATION_DOCUMENTATION_H-53.pdf PDF
CDRL_A001_TECHNICAL_DIRECTIVES_REPORT_10_DAY_REPORT__H-53.pdf PDF
CDRL_B008_SUPPORT_EQUIPMENT_(SE)_MAINTENANCE_HISTORY_REPORT_H-53.pdf PDF
CDRL_B011_SUPPORT_EQUIPMENT_MAINTENANCE_AND_CALIBRATION_REPORT_H-53.pdf PDF
CDRL_D002_TRANSITION_STATUS_REPORT_H-53.pdf PDF
CDRL_B013_PARTS_REQUIRED_REPORT_(PRR)_H-53.pdf PDF
CDRL_A004_PRODUCTION_PLAN.pdf PDF
CDRL_B006_ACTIVE_ITEM_REPORT__H-53.pdf PDF
CDRL_B012_COST_PER_BUNO_REPORT_H-53.pdf PDF
CDRL_A003_TDC_KIT_RECEIPT_AND_REPORTING_OF_PARTS_DISCREPANCY_REPORT__H-53.pdf PDF
CDRL_A010_MAINTENANCE_HISTORY_SUMMARY_REPORT_H-53.pdf PDF
CDRL_F001_INTEGRATED_MASTER_SCHEDULE_H-53.pdf PDF
CDRL_A009_NOTED_BUT_NOT_CORRECTED_(NBNC)_REPORT_H-53.pdf PDF
CDRL_D003_TRANSITION_INVENTORY_PLAN_(STAND-DOWN)_H-53.pdf PDF
CDRL_B005_SUPPLY_EFFECTIVENESS_REPORT_H-53.pdf PDF
CDRL_D001_PHASE-IN_TRANSITION_PLAN_H-53.pdf PDF
CDRL_B003_AIRCRAFT_AWAITING_PARTS_(AWP)_REPORT_H-53.pdf PDF
H-53E_Att_12_H-53E_PMID_Induction_Schedule_DRAFT.xlsx XLSX spreadsheet
DRAFT_RFP_N6264920R0003.docx DOCX document
Show 40 more

Latest 50 of 62 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N6264920R0003 – H-53 Pre-Solicitation Conference Q&A #2 Question 1.

a. We would like to ask a question about the H-53's paint stripping procedure and request an additional manual for the loading/unloading procedure.

H-53 PMI SPEC (NAVAIR H-53E PMID), Para 2-4.7.3.b.(1) Stripping Procedures - Exterior Stripping- This paragraph states "LES CP 68-00-BB-8190 provides paint stripping procedure using Plastic Media Blasting (PMB). DRP must ensure all PMB has been removed from the aircraft." It looks like the exterior paint is stripped by using PMB. But we would like to apply chemical paint remover MIL-R-81294 per NAVAIR 01-1A-509. Is it acceptable for this method by submittal of REI/TEI?

b. We have received maintenance manuals for H-53 PMI but one more document is required for the work evaluation. I would be grateful if you could send us the following manual:

NAVAIR A1-H53BE-CLG-500: C-5/C-17 Loading Procedures

Answer 1.

a. Chemical stripping response:

Chemical strippers cannot be used on significant portions of the H-53E due to the composite and special materials. If an offeror wants to propose use of a chemical stripper, please include detailed explanation on how composite and special materials will be protected. The PWS will be modified to allow Government consideration of alternate stripping methods.

b. We are still working on the manual.

Question 2.

Please provide us the manuals in the attached document.

Answer 2.

With the exception of "A1-H53BE-CLG-500 C-5/C-17 Loading Procedure," the Government declines to provide the requested documents. We are still researching the option of providing the C-5/C-17 Loading Procedure manual. Once a decision is made, it will be communicated to the offerors.