This document contains a Contract Data Requirements List (CDRL) and details for an Integrated Master Schedule (IMS) to be delivered under a U.S. Navy contract for maintenance and repair services of H-53E aircraft. The CDRL outlines requirements for the IMS, which is required to be submitted as a Microsoft Project file portraying the full schedule from contract start through completion of all option years. The IMS must demonstrate how the contractor will meet all contract requirements, include the Production Plan, and identify dependencies and resource constraints. The IMS is due for submission within one month of contract award and then must be revised and submitted monthly by the 5th of each month, and as needed for program reviews and significant meetings. The IMS will provide visibility to the government on the contractor's overall management plan and progress on contract activities and requirements.

This related federal contract opportunity notice is a draft pre-solicitation for H-53 aircraft maintenance and repair services currently performed under a previously awarded U.S. Navy contract. Interested parties can request the draft RFP and documents by completing a non-disclosure agreement to be sent to listed Navy contacts. Feedback is requested on the draft materials in advance of a formal solicitation. The services include depot-level maintenance, repair, and overhaul of H-53 aircraft to support the U.S. Navy and Marine Corps.

N6264920R0003 DRAFT CDRL F001

View the file

Other files

File Type Posted
Pre-Sol Conference Q&A_3.docx DOCX document
Pre-Solicitation Conference Q & A_2.docx DOCX document
H-53 Pre Solic Conf QAs.docx DOCX document
May 2019 HQMC_CNAF RESET Policy Message.pdf PDF
H-53E Att 09 Fac and AF Req 2019-12-13.docx DOCX document
CDRL A004 PRODUCTION PLAN H-53 12.13.19.pdf PDF
H-53E_Att_14_Price_Summary_Spreadsheet_DRAFT (2019-12-13).xlsx XLSX spreadsheet
04 - H-53E Att 01 PWS (2019-12-13) v1.docx DOCX document
H-53E_QUESTIONS_AND_ANSWERS_13DEC2019.xlsx XLSX spreadsheet
DRAFT RFP N6264920R0003 12.13.19.docx DOCX document
CDRL A007 SITUATION SUMMARY REPORT H-53 12.13.19.pdf PDF
Attachment_4_H-53_PRE_SOL_CONF_ACCEPTABLE_ID_FOR_NAFA_ACCESS.PPTX PPTX presentation
Attachment_2_H-53_PRE_SOLICITATION_CONFERENCE_Designated_Third_Country_Nationals.docx DOCX document
Attachment_1_H-53_PRE_SOLICITATION_CONFERENCE__Access_to_NAF_Atsugi.docx DOCX document
Attachment_3_H-53_PRE_SOL_CONF_Third_Designated_Country_List.pdf PDF
H-53E_Att_07_TEI_Process_at_Contarctor_Facilities_DRAFT.docx DOCX document
CDRL_B007_FINAL_MATERIAL_CONSUMPTION_REPORT_H-53.pdf PDF
CDRL_C001_MEETING_MINUTES_H-53.pdf PDF
CDRL_B002_AVDLR_TRACKER_H-53.pdf PDF
CDRL_A007_SITUATION_SUMMARY_REPORT_H-53.pdf PDF
CDRL_B009_EXCESS_MATERIAL_REPORT_H-53.pdf PDF
CDRL_A002_TECHNICAL_DIRECTIVES_REPORT__H-53.pdf PDF
CDRL_B010_ANNUAL_PHYSICAL_INVENTORY__H-53.pdf PDF
CDRL_G001_MONTHLY_MATERIAL_EXPENSE_REPORT_H-53.pdf PDF
CDRL_B014_DISCREPANT_PART_ON_INDUCTION_REPORT__H-53.pdf PDF
CDRL_B001_DAILY_REQUISITION_REPORT_(DRR)_H-53.pdf PDF
CDRL_A008_EXAMINATION_&_EVALUATION_(E&E)_DISCREPANCY_REPORT_H-53.pdf PDF
CDRL_A005_NOTIFICATION_OF_AIRCRAFT_DELAY_H-53.pdf PDF
CDRL_B004_RECEIPT_REPORT_H-53.pdf PDF
CDRL_A006_SCHEDULED_REMOVAL_CARDS_H-53.pdf PDF
CDRL_L001_TECHNICAL_DATA_INVENTORY_LIST_H-53.pdf PDF
CDRL_D004_CONTRACTOR_TRAINING_PLAN_H-53.pdf PDF
CDRL_C002_PRESENTATION_DOCUMENTATION_H-53.pdf PDF
CDRL_A001_TECHNICAL_DIRECTIVES_REPORT_10_DAY_REPORT__H-53.pdf PDF
CDRL_B008_SUPPORT_EQUIPMENT_(SE)_MAINTENANCE_HISTORY_REPORT_H-53.pdf PDF
CDRL_B011_SUPPORT_EQUIPMENT_MAINTENANCE_AND_CALIBRATION_REPORT_H-53.pdf PDF
CDRL_D002_TRANSITION_STATUS_REPORT_H-53.pdf PDF
CDRL_B013_PARTS_REQUIRED_REPORT_(PRR)_H-53.pdf PDF
CDRL_A004_PRODUCTION_PLAN.pdf PDF
CDRL_B006_ACTIVE_ITEM_REPORT__H-53.pdf PDF
CDRL_B012_COST_PER_BUNO_REPORT_H-53.pdf PDF
CDRL_A003_TDC_KIT_RECEIPT_AND_REPORTING_OF_PARTS_DISCREPANCY_REPORT__H-53.pdf PDF
CDRL_A010_MAINTENANCE_HISTORY_SUMMARY_REPORT_H-53.pdf PDF
CDRL_A009_NOTED_BUT_NOT_CORRECTED_(NBNC)_REPORT_H-53.pdf PDF
CDRL_D003_TRANSITION_INVENTORY_PLAN_(STAND-DOWN)_H-53.pdf PDF
CDRL_B005_SUPPLY_EFFECTIVENESS_REPORT_H-53.pdf PDF
CDRL_D001_PHASE-IN_TRANSITION_PLAN_H-53.pdf PDF
CDRL_B003_AIRCRAFT_AWAITING_PARTS_(AWP)_REPORT_H-53.pdf PDF
H-53E_Att_12_H-53E_PMID_Induction_Schedule_DRAFT.xlsx XLSX spreadsheet
DRAFT_RFP_N6264920R0003.docx DOCX document
Show 40 more

Latest 50 of 62 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 1 of 2 Pages Adobe Professional 8.0

18. ESTIMATED

TOTAL PRICE

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form

OMB

Approved No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

F

C. CATEGORY:

TDP TM OTHER X

D. SYSTEM/ITEM

H-53E PMID AIRCRAFT

E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO.

F001

2. TITLE OF DATA ITEM

INTEGRATED MASTER SCHEDULE (IMS) H-53E

3. SUBTITLE

N/A

4. AUTHORITY (Data Acquisition Document No.)

DI-MGMT-81650

5. CONTRACT REFERENCE

PWS

6. REQUIRING OFFICE

FRCWP Production

7. DD 250 REQ

NO

9. DIST STATEMENT

REQUIRED

NONE

10. FREQUENCY

BLOCK 16

12. DATE OF FIRST SUBMISSION

BLOCK 16

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

N/A

11. AS OF DATE

BLOCK 16

13. DATE OF SUBSEQUENT

SUBMISSION

BLOCK 16 Draft

Final

Reg Repro

16. REMARKS

(1) Applicability of Data Item Description DI-MGMT-81650: Integrated Master Plan (IMP), Earned Value Management System (EVMS) and Performance Measurement Baseline (PMB) do not apply. Replace SOW with PWS. Within Use/Relationship, delete paragraph b; reference paragraph d, the CPR is not required; reference paragraph e, only the note applies.

(2) Purpose: The Contractor’s Integrated Master Schedule (IMS) is the Contractor's schedule encompassing total program performance, and will provide the Government insight, awareness and understanding of the Contractor’s overall plan for management and scheduling of all contract activities and requirements. The Government will use the IMS to track progress, aid in understanding the Contractor's US Government dependencies and track changes throughout the contract period of performance. The IMS shall be the record of all contract activities documenting the planned and as completed work.

(3) Requirements:

(a) The IMS shall portray the schedule from contract start through completion of all exercised option years. The plan shall demonstrate how the contractor will meet all requirements of the contract, and shall include the Production Plan of CDRL A005. The IMS shall portray calendar and work days.

(b) The IMS shall include all contract phases and activities, including but not limited to: contract award; transition; all task orders, all inductions and drop-ins; non-concurrent In-Service Repair (ISR); non-concurrent aircraft modifications; contract milestones; CDRL due and delivery dates; all annual events; contract modifications; and similar planning and action dates.

(c) The IMS shall identify all dependencies and predecessor relationships,

(d) The IMS shall indicate major constrained resources and lay the schedule out chronologically avoiding any resource constraints.

(e) The IMS shall explicitly identify the contract level critical path.

FRCWP Production 1 FRCWP Business Ops 1

DCMA 1

15. TOTAL 0 3 0

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

17. PRICE GROUP

Reset

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

A. CONTRACT LINE ITEM NO.

B. EXHIBIT

F

C. CATEGORY: X

TDP TM OTHER

D. SYSTEM/ITEM

H-53E PMID AIRCRAFT

E. CONTRACT/PR NO. F. CONTRACTOR

16. REMARKS (Continued)

(4) Format: The IMS shall be submitted as a Microsoft Project document or Government approved equivalent. The IMS shall contain the Gantt chart and a minimum of the following fields: Task Name; % Complete; each aircraft Baseline Start and Finish, Current (Scheduled) Start and Finish, Actual Start and Finish, Duration, Predecessors and Resources for each induction, drop in repair, non-concurrent ISR, non-concurrent aircraft modification and other task orders as may be issued on the contract.

(5) Frequency:

(a) An initial IMS shall be submitted with the Contractor’s proposal. A formal post-award IMS shall be submitted within one month after contract award.

(b) A revised IMS shall be submitted monthly by the Contractor's close of business of the 5th working day of each month.

(c) The IMS shall be updated and available for review and/or discussion during all Program Management Reviews (PMR), and upon request for significant Contractor/Government meetings.

(6) After contract award all IMS submissions shall be emailed to FRCWP Business Office at:

[to be provided upon contract award]

Subject line of email shall include CDRL Number and Title

The Government shall have five working days for review and acceptance/rejection of each submission. No response will indicate acceptance.

DD FORM 1423-1, FEB 2001 Page 2 of 2 Pages