This is a construction drawing showing the fire suppression system plan for the first floor of Building HP505 (BEQ - Bachelor Enlisted Quarters) at Marine Corps Base Camp Lejeune, North Carolina. The drawing details sprinkler system requirements throughout the building, including sleeping rooms, mechanical rooms, plumbing chases, laundry facilities, and corridors.

The plan specifies key requirements including: sprinklers throughout all sleeping rooms per NFPA 13R standards, dry sidewall sprinklers for unconditioned spaces like the dryer chase and corridor, heat trace systems for wet pipe sprinkler piping crossing the corridor, backflow preventer test connections, fire department connections, RPZ backflow preventer assembly, and floor control assemblies for the first floor sprinkler system. The drawing was prepared by Jensen Hughes, approved by professional engineer Aaron P. Freid (VA License #044409), and includes construction contract number N40085-23-B-0034. A revision for PPI updates is noted as of January 17, 2025.

View the file

Other files

File Type Posted
Amend 0016.pdf PDF
Amend 0015.pdf PDF
Amend 0014.pdf PDF
Amend 0013.pdf PDF
60040360.pdf PDF
60040345.pdf PDF
60040454.pdf PDF
60040373.pdf PDF
60040328.pdf PDF
60040433.pdf PDF
60040414.pdf PDF
N4008523B0034 SpecsAsOne Addendum 01.pdf PDF
60040411.pdf PDF
60040407.pdf PDF
60040434.pdf PDF
60040420.pdf PDF
60040412.pdf PDF
60040343.pdf PDF
Amend 0012.pdf PDF
60040362.pdf PDF
60040342.pdf PDF
60040447.pdf PDF
60040408.pdf PDF
60040436.pdf PDF
60040424.pdf PDF
60040329.pdf PDF
60040422.pdf PDF
60040366.pdf PDF
60040376.pdf PDF
60040359.pdf PDF
Amend 0011.pdf PDF
Amend 0010.pdf PDF
Amend 0009.pdf PDF
Amend 0008.pdf PDF
Amend 0007.pdf PDF
Amend 0006.pdf PDF
Amend 0005.pdf PDF
Amend 0004.pdf PDF
Amend 0003.pdf PDF
Amend 0002.pdf PDF
Amend 0001.pdf PDF
23-0034 Asbestos and Lead Assessment.pdf PDF
23-0034 Appendix D.pdf PDF
N4008523B0034 DWGs.pdf PDF
RFP 230034.pdf PDF
N4008523B0034 SPECS.pdf PDF
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

101A

100A

107A

104A

109A

108A

113A

112A

117A

141 142

121A

120A

125A

FX101

B1

FX101

B2

FX101

B3

100 102

101 103

OH

RES RES

RESRES

MECHANICAL

2 2

2 2

MECHANICAL

F C

A

OH

OH

OH

STORAGE

STAIR

LAUNDRY

TOILET

ELECTRICAL

CORRIDOR

DUTY

LAUNDRY

OH

OH

OH

OH

LH

LH

LH

KEY NOTES

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

PROVIDE SPRINKLERS THROUGHOUT THE OUTLINED AREA.

HAZARD CLASSIFICATION IS TYPCIAL FOR SLEEPING ROOMS.

SPRINKLERS MUST BE PROVIDED THROUGHOUT THE

SLEEPING ROOMS AS REQUIRED BY NFPA 13R.

HAZARD CLASSIFICATION IS TYPCIAL FOR MECHANICAL

ROOMS.

HAZARD CLASSIFICATION IS TYPCIAL FOR PLUMBING CHASES.

PROVIDE BACKFLOW PREVENTER TEST CONNECTION.

PROVIDE FIRE DEPARTMENT CONNECTION.

PROVIDE RPZ BACKFLOW PREVENTER ASSEMBLY.

PROVIDE FLOOR CONTROL ASSEMBLIES FOR THE FIRST

FLOOR SPINKLER SYSTEM.

THE DRYER CHASE IS AN UNCONDITIONED SPACE. PROVIDE

DRY SIDEALL SPRINKLERS TO PROTECT THE DRYER CHASE.

WET PIPE SPRINKLER PIPING IS PROHIBITEDIN THE DRYER

CHASE.

THE CORRIDOR IS AN UNCONDITIONED SPACE. PROVIDE DRY

SIDEWALL SPRINKLERS TO PROTECT THE CORRIDOR. WET

PIPE SPRINKLER PIPING CROSSING THE CORRIDOR MUST BE

HEAT TRACED WITH AN APPROVED HEAT TRACE SYSTEM.

GENERAL SHEET NOTES:

1. FOR FIRE SUPPRESSION GENERAL NOTES AND LEGEND,

SEE SHEET FX001.

Lic. No. 044409

AARON P FREIDC

O M M O

N W

EA

LTHOF

V

IR

G

IN

I A

P R O F

E

SSIONAL EN

G

IN

E E R

29 MAY 2024

F ile

P ri n t

SYM. DESCRIPTION DATE APP.

REVISIONS

DR.

DES.

CHK.

SUBMITTED BY:

DESIGN DIR.

APPROVED: PWO OR OICC

SATISFACTORY TO:

DATE

DATE

DEPARTMENT OF THE NAVY NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND

CAMP LEJEUNE, NORTH CAROLINA

MARINE CORPS BASE

SIZE CODE IDENT. NO. NAVFAC DRAWING NO.

E1 80091

CONSTR. CONTR. NO.

AS NOTEDSCALE SHEET

M B

F A

N O

SPEC.

C U s e rs \a fr e id

\O n e

D ri v e

J e n s e n H u g h e s \D o c u m e n ts \2

F

IR

E a fr e id

.r v t

/1

/2

:4 :2

P

M

FX101

AHE

KEC

MORGAN HUNTER

APF

APF

REPAIR BEQ HP505

FIRE SUPPRESSION FIRST FLOOR PLAN - CONSTRUCTION

60040406 N40085-23-B-0034

SCALE: 3/32" = 1'-0"

D1

FIRE SUPPRESSION FIRST FLOOR PLAN - CONSTRUCTION

N

GRAPHIC SCALE: 1/8"=1'-0"

8' 0 4' 8' 16'

GRAPHIC SCALE: 3/32"=1'-0"

8' 0 4' 8' 16'

SCALE: 1/8" = 1'-0"

B1

FIRST FLOOR PARTIAL PLAN

SCALE: 1/8" = 1'-0"

B2

FIRST FLOOR PARTIAL PLAN

SCALE: 1/8" = 1'-0"

B3

FIRST FLOOR PARTIAL PLAN

1 PPI UPDATES 01/17/25 APF

File details come from the government source that posted it. Updated .