This is an architectural drawing showing reflected ceiling plans and details for the BEQ HP505 repair project at Marine Corps Base Camp Lejeune, North Carolina.

The drawing (A-106) includes detailed ceiling plans for first, second and third floor common areas, typical sleeping room ceiling plans, and construction details for bulkheads and sleeping room soffits. Key specifications include gypsum board ceilings at 7'-0" above finished floor in sleeping rooms, suspended acoustical tile ceilings at 7'-2" in other areas, and concrete plank ceilings. The plans show locations of lighting fixtures, diffusers, grilles, smoke detectors, sprinklers, and motion sensors. General construction notes require coordination with mechanical, electrical and fire protection drawings, and specify requirements for ceiling support systems and finishes. The drawing is part of Naval Facilities Engineering Systems Command (NAVFAC) construction contract N40085-23-B-0034.

View the file

Other files

File Type Posted
Amend 0016.pdf PDF
Amend 0015.pdf PDF
Amend 0014.pdf PDF
Amend 0013.pdf PDF
60040360.pdf PDF
60040406.pdf PDF
60040345.pdf PDF
60040454.pdf PDF
60040373.pdf PDF
60040328.pdf PDF
60040433.pdf PDF
60040414.pdf PDF
N4008523B0034 SpecsAsOne Addendum 01.pdf PDF
60040411.pdf PDF
60040407.pdf PDF
60040434.pdf PDF
60040420.pdf PDF
60040412.pdf PDF
60040343.pdf PDF
Amend 0012.pdf PDF
60040342.pdf PDF
60040447.pdf PDF
60040408.pdf PDF
60040436.pdf PDF
60040424.pdf PDF
60040329.pdf PDF
60040422.pdf PDF
60040366.pdf PDF
60040376.pdf PDF
60040359.pdf PDF
Amend 0011.pdf PDF
Amend 0010.pdf PDF
Amend 0009.pdf PDF
Amend 0008.pdf PDF
Amend 0007.pdf PDF
Amend 0006.pdf PDF
Amend 0005.pdf PDF
Amend 0004.pdf PDF
Amend 0003.pdf PDF
Amend 0002.pdf PDF
Amend 0001.pdf PDF
23-0034 Asbestos and Lead Assessment.pdf PDF
23-0034 Appendix D.pdf PDF
N4008523B0034 DWGs.pdf PDF
RFP 230034.pdf PDF
N4008523B0034 SPECS.pdf PDF
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MM

F M

C P

T R

N

L O

C

T

T

T

72"

72"

T

S3

S3

S1

S1

S1

S1

S3

S3

CONCRETE PLANK CEILING - PAINTED UNLESS NOTED

OTHERWISE

GYPSUM BOARD CEILING/SOFFIT AT 7'-0" ABOVE FINISHED FLOOR

UNLESS OTHERWISE NOTED. SEE ENLARGED PLANS FOR

SOFFITS AT COMMON AREAS

SUSPENDED ACOUSTICAL TILE CEILING AT 7'-2" ABOVE FINISHED

FLOOR. COORDINATE CEILING INSTALLATION WITH PLUMBING,

MECHANICAL, ELECTRICAL, AND FIRE PROTECTION DRAWINGS.

2' X 4' LIGHTING FIXTURE

1'x4' LIGHTING FIXTURE

UTILITY 4' LIGHTING FIXTURE

DOWNLIGHT OR PENDANT LIGHTING

EXIT LIGHT

COMBINATION EMERGENCY LIGHTING UNIT AND EXIT SIGN

WALL-MOUNTED LIGHTING FIXTURE

CEILING SUPPLY DIFFUSER

CEILING RETURN GRILLE

CEILING EXHAUST GRILLE

EMERGENCY LIGHTING UNIT

SMOKE DETECTOR

SPRINKLER HEAD

LOW-VOLTAGE 360° DUAL

TECHNOLOGY MOTION SENSOR FOR

EXTENDED COVERAGE.

S2

1. COORDINATE ALL CEILING WORK WITH MECHANICAL, ELECTRICAL, AND

FIRE PROTECTION DRAWINGS

2. PROVIDE NEW FINISHES FOR ALL SPACES AS DESCRIBED IN THE ROOM

FINISH SCHEDULE

3. UNDERSIDE OF EXISTING PRECAST CONCRETE BALCONY/ROOF TO

REMAIN UNFINISHED UNLESS NOTED OTHERWISE

4. ANY AND ALL FIRE PROTECTION, PLUMBING, MECHANICAL, AND/OR

ELECTRICAL ITEM SHOWN ARE FOR COORDINATION PURPOSES ONLY.

SEE RESPECTIVE PLANS AND LEGENDS FOR ADDITIONAL INFORMATION

5. CONTRACTOR TO COORDINATE SUSPENDED CEILING SUPPORT CABLE

LOCATIONS WITH MECHANICAL, PLUMBING, ELECTRICAL, AND FIRE

PROTECTION SYSTEMS

A3

A-106

B3

A-106

V E

R

IF

Y

2' -4

4'-0"

B3

A-106

A3

A-106

3 5/8" STEEL STUDS

EXISTING PRECAST

STRUCTURE ABOVE

6"

6'-10"

AFF

GYPSUM BOARD

SECURE TO EXISTING

CONCRETE PLANK

CEILING WITH (2)

FASTENERS AT 12"

ON CENTER

7'-2"

AFF

LIGHT GAUGE

BRACING TO

STRUCTURE ABOVE AT

32" ON CENTER (MAX)

ACOUSTICAL TILE

CEILING SYSTEM

4'-0"

B3

A-106

A3

A-106

B3

A-106

SLEEPING ROOM GYPSUM

BOARD CEILINGS TO BE AT

7'-0" ABOVE FINISHED

FLOOR (TYPICAL)

3 5/8" STEEL STUDS

EXISTING PRECAST

STRUCTURE ABOVE

SEE PLAN

AFF

GYPSUM BOARD

SECURE TO EXISTING

CONCRETE PLANK

CEILING WITH (2)

FASTENERS AT 12"

ON CENTER

LIGHT GAUGE

BRACING TO

STRUCTURE ABOVE AT

32" ON CENTER

CEILING TO REMAIN UNFINISHED

ATTIC ACCESS HATCH

VERIFY SOFFIT WIDTH DIMENSIONS WITH MECHANICAL DRAWINGS AND

EQUIPMENT REQUIREMENTS

ALIGN SOFFIT WITH FACE OF WALL

GYPSUM BOARD CEILING/SOFFIT AT 7'-0" ABOVE FINISHED FLOOR

GYPSUM BOARD CEILING/SOFFIT AT 6'-10" ABOVE FINISHED FLOOR

F ile

P ri n t

SYM. DESCRIPTION DATE APP.

REVISIONS

T

T C

E

TI

HCRAD

R E

G I S

ERE

A N

I

L

ORA

N O

R

T H

C

N

D A

R

N

DE

.J UE

ER

III

C

N

NRB E

E W

M

A

P.

STCETIHCRA

FB

BERN N.C

.NEW

CERT. NO.

UTCETIHCRA

DERET

SI

G E R

N

OI

TA

RO

PR

OC

LAR

CAROLINANORTH

50679

DR.

DES.

CHK.

SUBMITTED BY:

DESIGN DIR.

APPROVED: PWO OR OICC

SATISFACTORY TO:

DATE

DATE

DEPARTMENT OF THE NAVY NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND

CAMP LEJEUNE, NORTH CAROLINA

MARINE CORPS BASE

SIZE CODE IDENT. NO. NAVFAC DRAWING NO.

E1 80091

CONSTR. CONTR. NO.

AS NOTEDSCALE SHEET

M B

F A

N O

SPEC.

S p ro je c ts

\2

\2

C

L R e p a ir B

E Q

H P

\2

D e s ig n \2

D w g s \2

A

R C

H

.r v t

/1

/2

:0 :0

P

M

A-106

Approver

JAS

JAS

MORGAN HUNTER

JAS

REPAIR BEQ HP505

ENLARGED REFLECTED CEILING PLANS

60040362 N40085-23-B-0034

29 MAY 2024

GRAPHIC SCALE: 1/4"=1'-0"

4' 0 2' 4' 8'

REFLECTED CEILING PLAN LEGENDGENERAL CONSTRUCTION NOTES

SCALE: 1/4" = 1'-0"

C1

FIRST FLOOR COMMON AREA - CEILING

SCALE: 1/4" = 1'-0"

C3

SECOND FLOOR COMMON AREA - CEILING

N N

SCALE: 1 1/2" = 1'-0"

A3

BULKHEAD DETAIL

GRAPHIC SCALE: 1 1/2"=1'-0"

1' 6" 3" 0 1'

SCALE: 1/4" = 1'-0"

C5

THIRD FLOOR COMMON AREA - CEILING

N

SCALE: 1/4" = 1'-0"

A1

TYPICAL SLEEPING ROOM CEILING PLAN

N

SCALE: 1 1/2" = 1'-0"

B3

SLEEPING ROOM SOFFIT DETAIL

CONSTRUCTION KEYNOTES - CEILING

1 ADDENDUM 01 01.17.25

File details come from the government source that posted it. Updated .