Attachment_16_-_AF_Form_103v5_Work_Clearance_Request_with_header.pdf

PDF 485 KB Posted

Attached to
CANNON AFB, NM SABER Federal contract opportunity
Solicitation number
FA4855-13-R-0009
Issued by
Department of the Air Force Special Operations Command

About this file

Attachment 16

View the file

Other files for this federal contract opportunity

Other files attached to CANNON AFB, NM SABER, newest first.
File Type Posted
Amendment_5.pdf PDF
Attachment__01_-_SABER_2013_General_Requirements_update_7_Aug_2013_with_header.doc DOC document
Q_and_A_-_Revised.pdf PDF
Amendment_4.pdf PDF
Attachment_S4_-_Coefficient_Spreadsheet.xls XLS spreadsheet
Amendment_3_(SF_30).pdf PDF
Q_and_A.pdf PDF
CZQZ_13-1090_Renovate_Community_Center_SOO 1 .docx DOCX document
Amendment_2.pdf PDF
Attachment_TO3.pdf PDF
Amendment_1.doc DOC document
Attachment_25e.docx DOCX document
Attachment_25a.docx DOCX document
Attachment_25f.docx DOCX document
Attachment_25c.docx DOCX document
Attachment_25b.docx DOCX document
Attachment_25d.docx DOCX document
SABER_Pre-Proposal_Conference_and_Site_Visit.pptx PPTX presentation
Pre-Proposal_Minutes_and_Sign-In.pdf PDF
Second_Floor_Project_Drawings_11X17.pdf PDF
(15_Dec_2012)_CZQZ131090_2nd_Floor_Comm_Call-out.docx DOCX document
CZQZ_13-1090_Renovate_Community_Center_SOO.docx DOCX document
1208_2nd_floor_as-built_Floor_Plan_Plans_(1).pdf PDF
Attachment_18_-_Building_Construction_1354_Checklist__with_header.xls XLS spreadsheet
Attachment_02_-_SABER_Specifications.pdf PDF
Attachment__01_-_SABER_General_Requirements_update_29_Jan_13_with_header.doc DOC document
Attachment_24_-_SOW_Example_2013.doc DOC document
Attachment_14_-_Schedule_of_Material_Submittals_(AF66)_with_header.xls XLS spreadsheet
Attachment_S4A_Coefficient_Spreadsheet_(Example).xls XLS spreadsheet
Attachment_13_-_AF_Form_3065_Progrees_Report.xfdl XFDL file
Attachment_06_-_CAFB_Sustainable_Landscape_Development_Plan_-_2012_with_header.pdf PDF
Attachment_19_-_CAFB_Labeling_Standards_for_Communications_with_header.pdf PDF
Attachment_S3_-_Past_Performance_Questionaire_1.docx DOCX document
Attachment_08_-_Facility_Excellence_Guide_with_header.pdf PDF
Attachment_S5_-_Question_and_Answer_Template.docx DOCX document
Attachment_04_-_CAFB_Electrical_Standards-March_13 _2012_with_header.pdf PDF
Attachment_S2_-_Past_Performance_Project_Data_(REVISED).doc DOC document
Attachment_21_-_Contractor_handbook_23_Mar_2012_with_header.doc DOC document
Attachment_05_-_CAFB_Hardware_Specifications_Guideline-_2011_with_header.pdf PDF
Attachment_12__-AF_Form_3064__Contract_Progress_Scheule.xfdl XFDL file
Attachment_09_-_GeoBase_Initial_Operating_Capability_Implemen_with_header.pdf PDF
Attachment_07_-_CAFB_CAD_Standards_with_header.pdf PDF
Attachment_23_-_CAFB_and_MAFR_Civilian_Contractor_Environmental_Guide_Appendix_A_Forms_(2)_with_header.doc DOC document
Attachment_03_-_CAFB_Architectural_Compatibility_Guide-2013_with_header.pdf PDF
Attachment_S1_-_Letter_of_Instruction_to_Reference_for_PPQ_-_REVISED.doc DOC document
Attachment_10_-_US_Army_Corps_Of_Engineer_Mobile_District_Des_with_header.pdf PDF
Attachment_15_-_AF_Form_3000_Material_Approval_Submittal.xfdl XFDL file
Attachment_17_-_USAF_Hot_Work_Permit.xfdl XFDL file
Attachment_11_-_UFC_1-300-8 _Real_Property_Transfer_with_header.pdf PDF
Attachment_20_-_Base_Contractor_Storage_Lot_Agreement_with_header.doc DOC document
Show all 50

CANNON AFB, NM SABER has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AF FORM 103v5, ------ Modified for Cannon AFB NM Page 1 of 4 PREVIOUS EDITIONS ARE OBSOLETE

BASE CIVIL ENGINEERING WORK CLEARANCE REQUEST DATE PREPARED

(ddmmyy)

(See Instructions on Reverse)

1. Clearance is requested to proceed with work at: _________________________ __________________________________________

On Work Order No ____ _________________ Contract No.____________________________________involving excavation or utility disturbance per attached sketch. This area: has has not been staked or clearly marked.

2. TYPE OF FACILITY/ WORK INVOLVED

A. PAVEMENT D. FIRE DETECTION & PROTECTION SYSTEM

G. AIRCRAFT OR VEHICULAR

TRAFFIC FLOW

B. DRAINAGE SYSTEM E. UTILITY OVERHEAD UNDERGROUND H. SECURITY

C. RAILROAD TRACKS F. COMM OVERHEAD UNDERGROUND I. OTHER

3. DATE CLEARANCE REQUIRED

4. DATE OF CLEARANCE

5. SIGNATURE OF REQUESTING OFFICIAL 6. TELEPHONE NO. 7. ORGANIZATION

ORGANIZATION REMARKS (Use Reverse for additional comments} REVIEWER'S NAME & INITIALS

8. BASE OPERATIONS Bldg 135 Contact 48 hrs prior to clearance requirement 575-784-2801 - Call for clearance

9. MAINTENANCE OPERATIONS CENTER Bldg 164

Contact 48 hrs prior to clearance requirement 575-784-2135

10. SAFETY Bldg 1 Contact 48 hrs prior to clearance requirement 575-784-2811

11. COMMUNICATIONS Bldg 10 Contact 48 hrs prior to clearance requirement 575-784-6622 - Call for clearance and utility location

12. SCX Bldg 10

575-784-6103 - Call for clearance and utility location

13. SECURITY FORCES Bldg 575

575-784-4111

14. COMMERCIAL UTILITY COMPANIES

New Mexico 811

1- 800 -321-2537 - Note date & request number.

Date ____________________

Request # ________________

X TELEPHONE

X CABLE

. B

A

SE

C

IV

IL

E

N G

IN

EE

R

IN

G , B ld g

A. ELECTRICAL DISTRIBUTION Contact 48 hrs prior to clearance requirement 575-784-4371 - Call for clearance and utility location

B. GAS DISTRIBUTION Contact 48 hrs prior to clearance requirement 575-693-2565 - Call for clearance and utility location

C. WATER DISTRIBUTION Contact 48 hrs prior to clearance requirement 575-693-2565 - Call for clearance and utility location

D. SEWER DISTRIBUTION Contact 48 hrs prior to clearance requirement 575-693-2565 - Call for clearance and utility location

E. IRRIGATION SYSTEMS

HAND DIG ONLY (Unless waived by CEO) CEO Approved ________________________

F. POL DISTRIBUTION Contact 48 hrs prior to clearance requirement 575-784-6742 - Call for clearance and utility location

G. ENVIRONMENTAL Contact 48 hrs prior to clearance requirement 575-784-1092

H. PAVEMENTS / GROUNDS Contact 48 hrs prior to clearance requirement 575-784-4383 - Call for clearance and utility location

I. FIRE PROTECTION Contact 48 hrs prior to clearance requirement 575-784-2578 - Call for clearance and utility location

J. EMCS / HVAC Contact 48 hrs prior to clearance requirement 575-784-1195 - Call for clearance and utility location

K. GEOBASE OFFICE Contact 48 hrs prior to clearance requirement 575-784-1610 - Call to update maps or utility tabs

16. OTHER (Specify)

17. REQUESTED CLEARANCE

APPROVED DISAPPROVED

18. TYPED NAME AND SIGNATURE OF APPROVING OFFICER (Chief of Operations Flight} 18a. DATE SIGNED (ddmmyy)

Milton.Mahon Typewritten Text Attachment 16

Milton.Mahon Typewritten Text

FA4855-13-R-0009

AF FORM 103v5, ------ Modified for Cannon AFB NM Page 2 of 4 PREVIOUS EDITIONS ARE OBSOLETE

19. Remarks. (This section describes specific precautionary measures to be taken before and during work accomplishment. Specific comments concerning the approved method of excavation, hand or powered equipment should be listed)

Equipment being used: ______________________________________________________________________________

1. Contractor will not proceed with any work until clearance has been coordinated as indicated by remarks that have been provided.

2. Any drawings provided indicate the APPROXIMATE location of the work area.

3. Contractor shall contact and give notice to all listed organizations by calling the phone numbers as listed in the remarks section next to each organization.

a. It is very important all clearance requests are made and understood by the contractor. The contractor shall log all calls and activities made to each organization as listed on the AF 103. The log information will be placed on page 3 of the AF 103. Each entry will be kept in a numbered, sequential order by date and organization. Note: If additional pages are required for the clearance log, record is to be attached to the original AF103.

b. If clearance is not required in the location of this request, the contractor will note the reviewer’s name and date/time the organization was contacted and indicate “No Action Required”.

c. If clearance is required by the organization, the contractor will coordinate a site meeting with the reviewer(s) representing that organization. The reviewer will physically spot the clearance issue and/or mark the location.

The contractor will then have the reviewer fill in his name and initials in the Reviewers Name and Initials column on page 1 for that organization. The contractor will also log on page 3 of the AF103, the meeting, date/time, person(s) name, and action taken.

4. As-builts for irrigation systems are not available. The contractor will ensure restoration of landscaping and repair of irrigation systems are completed, at no cost to the government, during the course of work.

5. The contractor will notify the Contracting Officer Representative (COR) or Project Manager (Box 5) if there are any questions or concerns to ensure proper coordination of this Work Clearance Request.

6. The contractor or his agent will maintain this clearance request on the site and make it available for review by any

Government representative upon request.

7. Notify Fire Department Control Center @ 575-784-2578 if any utilities are damaged after normal work hours.

Contractor Representative (Print Name) _______________________________ Telephone No. ____________

Signature_______________________________ Date_______________ (NOTE: Work cannot begin until signed by Contractor Representative)

Project Manager/COR (Print Name) __________________________________ Telephone No. ____________

Signature _______________________________ Date ______________

INSTRUCTIONS

The BCE work clearance request is used for any work (contract or in-house) that may disrupt aircraft or vehicular flow, base utility services, protection provided by fire and intrusion alarm system, or routine activities of the installation. This form is used to coordinate the required work with key base activities and keep customer inconvenience to a minimum. It is also used to identify potentially hazardous work conditions in an attempt to prevent accidents. The work clearance request is processed just prior to the start of work. If delays are encountered and the conditions at the job site change (or may have changed) this work clearance request must be re-processed.

Action Log

AF FORM 103v5, ------ Modified for Cannon AFB NM Page 3 of 4 PREVIOUS EDITIONS ARE OBSOLETE

Base Utility Locater Action Taken Contractor Date/Time Electrical Distribution EMCS / Alarms / HVAC Gas Distribution

Water Distribution Sewer Distribution Irrigation / Landscaping Comm / Americom

GEO Base

New Mexico 811 Locater Action Taken Contractor Date/Time SuddenLink CenturyLink Plateau

Organization Name Action Taken Contractor Date/Time 1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

16.

17.

18.

370335

Chindit B lvd

Chindit B lvd

Air C ommando Way

Air C ommando Way

D.L. Ingram Ave

D.L. Ingram Ave

Unnam ed

Unnam ed

Alison Avenue

Alison Avenue Albright Avenue

Albright Avenue

En gin ee rs

W ay

En gin ee rs

W ay

Eureka Avenue

Eureka Avenue

Cochran Avenue

Cochran Avenue

Kermit Evans Avenue

Kermit Evans Avenue

Libera tor A ven ue

Libera tor A ven ue

Eagle C law

Blvd

Eagle C law

Blvd

Unnamed

Unnamed

103°19'24"W

103°19'24"W

°23 '39

"N

°23

'39 "N

1 inch = 443 feet 0 50 100 150 20025 Meters 0 210 420 630 840105

Feet

REV DATE INITIAL

SCALE: 1 IN = 2000 FT DATE: Aug 2012 PLAN

MAP: C-1AFI 32-7062, COMPREHENSIVE PLANNING

DRAWN BY: 27SOCES/CEPT

DESCRIPTION

DEPARTMENT OF THE AIR FORCE

AIR FORCE SPECIAL OPERATIONS COMMAND

BASE COMPREHENSIVE PLAN

INSTALLATION LAYOUT

FILE: S:\ CEPT\ 3_Base_Comprehensive_Plans\ C-Tabs Layout and Vicinit y Maps\ C-1 Inst allat ion Layout

CANNON AIR FORCE BASE, NEW MEXICO

CAD/GIS FORMAT: ESRI ArcMap 10

CANNON AIR FORCE BASE, NEW MEXICOCANNON AIR FORCE BASE, NEW MEXICO

DIG PERMIT BUILDING STOPSDIG PERMIT BUILDING STOPSThis map is for reference only . Although every effort has been made to ensure the accuracy of information, errors and conditions originating from physical sources used to develop the database may be reflec ted on this map. GeoBase shall not be liable for any errors , omiss ions, or damages that result from inappropriate use of this document.

This material is For Off ic ial Use Only (FOUO). Unauthorized reproduct ion, distribut ion, publication, or of this material is STRICTLY PROHIBITED. Des troy as "FOUO".

Prepared By:

Geospat ial Inform ation Off ice

27 Civil Engineering Off ice Cannon AFB, N M 88103×$

Date: 01/23/2013 Path: S:\CEPT\2_Work_Request\4_27MSG-MDG\SOCES\CEP Misc\Dig Permits\Dig Permit Building Stops.mxd

MAGNETIC DECLINATION:

AS OF DATE:

ANNUAL CHANGE:

AIRFIELD ELEVATION:

7° 54' 00"

SEP 2008

00° 07' W 4294.00ft

COORDINATE SYSTEM:

DATUM:

UNITS:

UTM Zone 13N

WGS 84

Meters

AF103v5 1
Dig Permit Building Stops