Atch 21 APPENDIX 17 AF Form 103 Work Clearance Request Guidance.docx
DOCX document 34 KB Posted
- Attached to
- IDIQ Paving Federal contract opportunity
- Solicitation number
- FA486122R0011
- Issued by
- Department of the Air Force
View the file
Other files for this federal contract opportunity
Show all 43
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Please make sure to mention that the area in the map for the dig permit is covered by the dust permit and SWPPP (if applicable) Additional acreage will require additional permits.
Please include all environmental permit, Cultural resources, and Natural resources survey requirements with AF Form 103 dig permit submittals. (Dust permit, SWPPP, BSDW Water Line Connection, Cultural Survey results and SHPO Consultation Letter, Natural Resources Survey Reports) ENVIRONMENTAL AF Form 103 (DIG PERMIT) Requirements Guidance for CEN Projects
CONTRACTOR MUST SUBMIT ALL THE INFORMATION MENTIONED HERE WITH THE AF FORM 103
TO AVOID ANY DELAYS IN APPROVAL FROM ENVIRONMENTAL
Does your project involve:
- Trenching 100 linear ft or more? – Dust permit required (Including hydro-excavation). Time to obtain is at least 2 weeks.
- Disturbing unpaved soil .25 acre or more? – Dust permit required
- Disturbing unpaved soil 1 acre or more? Requires Storm water pollution prevention plan from NDEP (takes 1 week). Make sure to fill out all the SWPPP form questions as much as possible to avoid re-submittal.
- Demolishing 1000sqft or more? (This will require internal NEPA coordination and multiple permits– may take up to 12 months)
- Expanding a parking lot? (This will require internal NEPA coordination and multiple permits – may take up to 12 months)
- Tapping into main water line? Bureau of Safe Drinking Water (BSDW) Permit required. May take up to 90 days.
- Please make sure to follow up with cultural resources program managers about SHPO consultation from the beginning of your project. This process is the lengthiest of all, and may delay your project.
| - Natural Resources Surveys for Desert Tortoise, Migratory Birds, Burrowing Owl, Tree Removal require at least 2 weeks’ notice. | |
| Environmental Program Managers contact details can be found in Attachment 11. |