Repair_Replace Liner, Wastewater Lagoon One
Closed Solicitation Posted
- Solicitation number
- FA309923R0002
- Agency
- Air Education and Training Command Air Force, Department of Defense
- Responses due
- Set-aside
- Woman-Owned Small Business
Opportunity facts
- NAICS code
- 237110 Water and Sewer Line and Related Structures Construction
- Place of performance
- Laughlin AFB, Texas 78843, United States
Notice details come from SAM.gov. Updated .
Notice text
5 versions
Update #5 · Latest ·
Amendment 0003-RFI additional Gov responses ,time extension, and inclusion of additional clause
Time exstension is for 2 days changing the proposal due date from 12 June 2023@1400 CST, to 14 June 2023@1400 CST
Ammendment 0003 is posted
Amendment 0002 - RFI Gov responses
Amendment 0001 - Site Visit and RFI dates
The purpose of the project is to repair the eroded lagoon clay liner, replace with a geomembrane liner, and install a leak detection system in the Wastewater Lagoon 1.
This project is a design-build contract. The Contractor shall be responsible for completing a 100% design. The Contractor shall also be responsible for the construction of the approved design as described herein. The 100% design shall be approved by the Government prior to the beginning of construction.
The Contractor shall furnish all labor, equipment, material, transportation, administration, supervision, and all else necessary to obtain all information and engineering design data through on-site investigation, reconnaissance, and surveys, as required to complete the scope of work described within this Statement of Objectives (SOO).
Update #4 ·
Amendment 0003-RFI additional Gov responses ,time extension, and inclusion of additional clause
Time exstension is for 2 days changing the proposal due date from 12 June 2023@1400 CST, to 14 June 2023@1400 CST
Ammendment 0003 is forthcoming, the additional attachments are able to be provided at this time.
Amendment 0002 - RFI Gov responses
Amendment 0001 - Site Visit and RFI dates
The purpose of the project is to repair the eroded lagoon clay liner, replace with a geomembrane liner, and install a leak detection system in the Wastewater Lagoon 1.
This project is a design-build contract. The Contractor shall be responsible for completing a 100% design. The Contractor shall also be responsible for the construction of the approved design as described herein. The 100% design shall be approved by the Government prior to the beginning of construction.
The Contractor shall furnish all labor, equipment, material, transportation, administration, supervision, and all else necessary to obtain all information and engineering design data through on-site investigation, reconnaissance, and surveys, as required to complete the scope of work described within this Statement of Objectives (SOO).
Update #3 ·
Amendment 0002 - RFI Gov responses
Amendment 0001 - Site Visit and RFI dates
The purpose of the project is to repair the eroded lagoon clay liner, replace with a geomembrane liner, and install a leak detection system in the Wastewater Lagoon 1.
This project is a design-build contract. The Contractor shall be responsible for completing a 100% design. The Contractor shall also be responsible for the construction of the approved design as described herein. The 100% design shall be approved by the Government prior to the beginning of construction.
The Contractor shall furnish all labor, equipment, material, transportation, administration, supervision, and all else necessary to obtain all information and engineering design data through on-site investigation, reconnaissance, and surveys, as required to complete the scope of work described within this Statement of Objectives (SOO).
Update #2 ·
Amendment 0001 - Site Visit and RFI dates
The purpose of the project is to repair the eroded lagoon clay liner, replace with a geomembrane liner, and install a leak detection system in the Wastewater Lagoon 1.
This project is a design-build contract. The Contractor shall be responsible for completing a 100% design. The Contractor shall also be responsible for the construction of the approved design as described herein. The 100% design shall be approved by the Government prior to the beginning of construction.
The Contractor shall furnish all labor, equipment, material, transportation, administration, supervision, and all else necessary to obtain all information and engineering design data through on-site investigation, reconnaissance, and surveys, as required to complete the scope of work described within this Statement of Objectives (SOO).
Update #1 ·
The purpose of the project is to repair the eroded lagoon clay liner, replace with a geomembrane liner, and install a leak detection system in the Wastewater Lagoon 1.
This project is a design-build contract. The Contractor shall be responsible for completing a 100% design. The Contractor shall also be responsible for the construction of the approved design as described herein. The 100% design shall be approved by the Government prior to the beginning of construction.
The Contractor shall furnish all labor, equipment, material, transportation, administration, supervision, and all else necessary to obtain all information and engineering design data through on-site investigation, reconnaissance, and surveys, as required to complete the scope of work described within this Statement of Objectives (SOO).
Attachments
Show all 23
Notice history
| Notice | Type | Posted |
|---|---|---|
| Repair_Replace Liner, Wastewater Lagoon One | Solicitation | |
| Repair_Replace Liner, Wastewater Lagoon One | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity