Repair_Replace Liner, Wastewater Lagoon One

Closed Solicitation Posted

Solicitation number
FA309923R0002
Agency
Air Education and Training Command Air Force, Department of Defense
Responses due
Set-aside
Woman-Owned Small Business

Opportunity facts

NAICS code
237110 Water and Sewer Line and Related Structures Construction
PSC
Z2ND Repair Or Alteration Of Sewage And Waste Facilities
Place of performance
Laughlin AFB, Texas 78843, United States

Notice details come from SAM.gov. Updated .

Notice text

5 versions

Update #5 · Latest ·

Amendment 0003-RFI additional Gov responses ,time extension, and inclusion of additional clause

Time exstension is for 2 days changing the proposal due date from 12 June 2023@1400 CST, to 14 June 2023@1400 CST

Ammendment 0003 is posted

Amendment 0002 - RFI Gov responses

Amendment 0001 - Site Visit and RFI dates

The purpose of the project is to repair the eroded lagoon clay liner, replace with a geomembrane liner, and install a leak detection system in the Wastewater Lagoon 1.

This project is a design-build contract. The Contractor shall be responsible for completing a 100% design. The Contractor shall also be responsible for the construction of the approved design as described herein. The 100% design shall be approved by the Government prior to the beginning of construction.

The Contractor shall furnish all labor, equipment, material, transportation, administration, supervision, and all else necessary to obtain all information and engineering design data through on-site investigation, reconnaissance, and surveys, as required to complete the scope of work described within this Statement of Objectives (SOO).

Update #4 ·

Amendment 0003-RFI additional Gov responses ,time extension, and inclusion of additional clause

Time exstension is for 2 days changing the proposal due date from 12 June 2023@1400 CST, to 14 June 2023@1400 CST

Ammendment 0003 is forthcoming, the additional attachments are able to be provided at this time.

Amendment 0002 - RFI Gov responses

Amendment 0001 - Site Visit and RFI dates

The purpose of the project is to repair the eroded lagoon clay liner, replace with a geomembrane liner, and install a leak detection system in the Wastewater Lagoon 1.

This project is a design-build contract. The Contractor shall be responsible for completing a 100% design. The Contractor shall also be responsible for the construction of the approved design as described herein. The 100% design shall be approved by the Government prior to the beginning of construction.

The Contractor shall furnish all labor, equipment, material, transportation, administration, supervision, and all else necessary to obtain all information and engineering design data through on-site investigation, reconnaissance, and surveys, as required to complete the scope of work described within this Statement of Objectives (SOO).

Update #3 ·

Amendment 0002 - RFI Gov responses

Amendment 0001 - Site Visit and RFI dates

The purpose of the project is to repair the eroded lagoon clay liner, replace with a geomembrane liner, and install a leak detection system in the Wastewater Lagoon 1.

This project is a design-build contract. The Contractor shall be responsible for completing a 100% design. The Contractor shall also be responsible for the construction of the approved design as described herein. The 100% design shall be approved by the Government prior to the beginning of construction.

The Contractor shall furnish all labor, equipment, material, transportation, administration, supervision, and all else necessary to obtain all information and engineering design data through on-site investigation, reconnaissance, and surveys, as required to complete the scope of work described within this Statement of Objectives (SOO).

Update #2 ·

Amendment 0001 - Site Visit and RFI dates

The purpose of the project is to repair the eroded lagoon clay liner, replace with a geomembrane liner, and install a leak detection system in the Wastewater Lagoon 1.

This project is a design-build contract. The Contractor shall be responsible for completing a 100% design. The Contractor shall also be responsible for the construction of the approved design as described herein. The 100% design shall be approved by the Government prior to the beginning of construction.

The Contractor shall furnish all labor, equipment, material, transportation, administration, supervision, and all else necessary to obtain all information and engineering design data through on-site investigation, reconnaissance, and surveys, as required to complete the scope of work described within this Statement of Objectives (SOO).

Update #1 ·

The purpose of the project is to repair the eroded lagoon clay liner, replace with a geomembrane liner, and install a leak detection system in the Wastewater Lagoon 1.

This project is a design-build contract. The Contractor shall be responsible for completing a 100% design. The Contractor shall also be responsible for the construction of the approved design as described herein. The 100% design shall be approved by the Government prior to the beginning of construction.

The Contractor shall furnish all labor, equipment, material, transportation, administration, supervision, and all else necessary to obtain all information and engineering design data through on-site investigation, reconnaissance, and surveys, as required to complete the scope of work described within this Statement of Objectives (SOO).

Attachments

Show all 23

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
Repair_Replace Liner, Wastewater Lagoon One This notice · Latest solicitation Solicitation
Repair_Replace Liner, Wastewater Lagoon One Original Pre-Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity