Attachment_S3_-_Past_Performance_Questionaire_1.docx

DOCX document 34 KB Posted

Attached to
CANNON AFB, NM SABER Federal contract opportunity
Solicitation number
FA4855-13-R-0009
Issued by
Department of the Air Force Special Operations Command

About this file

Attachment S3

View the file

Other files for this federal contract opportunity

Other files attached to CANNON AFB, NM SABER, newest first.
File Type Posted
Amendment_5.pdf PDF
Attachment__01_-_SABER_2013_General_Requirements_update_7_Aug_2013_with_header.doc DOC document
Amendment_4.pdf PDF
Q_and_A_-_Revised.pdf PDF
Attachment_S4_-_Coefficient_Spreadsheet.xls XLS spreadsheet
Q_and_A.pdf PDF
CZQZ_13-1090_Renovate_Community_Center_SOO 1 .docx DOCX document
Amendment_3_(SF_30).pdf PDF
Amendment_2.pdf PDF
Attachment_25b.docx DOCX document
Attachment_25d.docx DOCX document
Amendment_1.doc DOC document
Attachment_25e.docx DOCX document
Attachment_TO3.pdf PDF
Attachment_25a.docx DOCX document
Attachment_25f.docx DOCX document
SABER_Pre-Proposal_Conference_and_Site_Visit.pptx PPTX presentation
Pre-Proposal_Minutes_and_Sign-In.pdf PDF
1208_2nd_floor_as-built_Floor_Plan_Plans_(1).pdf PDF
Second_Floor_Project_Drawings_11X17.pdf PDF
(15_Dec_2012)_CZQZ131090_2nd_Floor_Comm_Call-out.docx DOCX document
CZQZ_13-1090_Renovate_Community_Center_SOO.docx DOCX document
Attachment_S1_-_Letter_of_Instruction_to_Reference_for_PPQ_-_REVISED.doc DOC document
Attachment_10_-_US_Army_Corps_Of_Engineer_Mobile_District_Des_with_header.pdf PDF
Attachment_16_-_AF_Form_103v5_Work_Clearance_Request_with_header.pdf PDF
Attachment_15_-_AF_Form_3000_Material_Approval_Submittal.xfdl XFDL file
Attachment_17_-_USAF_Hot_Work_Permit.xfdl XFDL file
Attachment_11_-_UFC_1-300-8 _Real_Property_Transfer_with_header.pdf PDF
Attachment_20_-_Base_Contractor_Storage_Lot_Agreement_with_header.doc DOC document
Attachment_22_-_Cannon_AFB_and_Melrose_AFR_Civilian_Contractor_Environmental_Guide_with_header.doc DOC document
SABER_Solicitation.doc DOC document
Attachment_S4_-_Coefficient_Spreadsheet.xls XLS spreadsheet
Attachment_08_-_Facility_Excellence_Guide_with_header.pdf PDF
Attachment_S5_-_Question_and_Answer_Template.docx DOCX document
Attachment_04_-_CAFB_Electrical_Standards-March_13 _2012_with_header.pdf PDF
Attachment_S2_-_Past_Performance_Project_Data_(REVISED).doc DOC document
Attachment_21_-_Contractor_handbook_23_Mar_2012_with_header.doc DOC document
Attachment_05_-_CAFB_Hardware_Specifications_Guideline-_2011_with_header.pdf PDF
Attachment_12__-AF_Form_3064__Contract_Progress_Scheule.xfdl XFDL file
Attachment_18_-_Building_Construction_1354_Checklist__with_header.xls XLS spreadsheet
Attachment_02_-_SABER_Specifications.pdf PDF
Attachment__01_-_SABER_General_Requirements_update_29_Jan_13_with_header.doc DOC document
Attachment_24_-_SOW_Example_2013.doc DOC document
Attachment_14_-_Schedule_of_Material_Submittals_(AF66)_with_header.xls XLS spreadsheet
Attachment_S4A_Coefficient_Spreadsheet_(Example).xls XLS spreadsheet
Attachment_13_-_AF_Form_3065_Progrees_Report.xfdl XFDL file
Attachment_06_-_CAFB_Sustainable_Landscape_Development_Plan_-_2012_with_header.pdf PDF
Attachment_19_-_CAFB_Labeling_Standards_for_Communications_with_header.pdf PDF
Attachment_09_-_GeoBase_Initial_Operating_Capability_Implemen_with_header.pdf PDF
Attachment_07_-_CAFB_CAD_Standards_with_header.pdf PDF
Show all 50

CANNON AFB, NM SABER has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Past Performance Questionnaire Cover Sheet

WHEN FILLED IN THIS DOCUMENT IS SOURCE SELECTION SENSITIVE INFORMATION IAW FAR 3.104

SECTION A: Contractor Information (to be completed by the offeror prior to mailing to the reference):

A. Contractor’s name and address:

B. Point of Contact: C. Phone/Fax/Email Address:

D. Contract Number:

E. Project Title/Description of Work:

E(1) |_| Design |_| Design-Build |_| Build F. Contract Type: |_| Firm-Fixed Price |_| Indefinite-Delivery/Indefinite-Quantity |_| Cost-Reimbursement |_| Other, specify

G. Project Award Date:Scheduled Completion Date: Current/Final Completion Date:
H. Project Award Amount:Current/Final Project Amount:
I. Contractor being evaluated performed as the: |_| Prime Contractor|_|Subcontractor |_| Key Personnel |_| Supplier

J. Authorization is hereby granted to provide the information requested in SECTION B of this Questionnaire

(Name and Title of Authorizing Official) (Signature) (Date)

SECTION B: To be completed by the Reference/Evaluator: Please complete the information below and the Past Performance Questionnaire and return by fax, email, or mail to contacts listed in Section C NO LATER THAN 26 July 2013.

Using the following definitions, Evaluator please rate the relevancy of this contract: [VR] or [R] or [SR] or [NR]

PAST PERFORMANCE

Very Relevant [VR]
Relevant [R]
Somewhat Relevant [SR]
Not Relevant [NR]
Present/past performance multiple task order effort involved managing at least five (5) projects simultaneously with a combined value of $750K and each project was similar in terms of scope, magnitude and complexities and included all the Relevancy Elements listed OR Present/past performance multiple task order effort involved managing at least two (2) projects simultaneously with a combined value of $1.5M and the combined efforts of the projects were similar in terms of scope, magnitude and complexities and included all Relevancy Elements listed.
Present/past performance effort involved managing at least three (3) projects simultaneously with a combined value of $750K and each project was similar in terms of scope, magnitude and complexities and included all the Relevancy Elements listed OR Present/past performance effort involved managing at least two (2) projects simultaneously with a combined value of $1M and the combined efforts of the projects were similar in terms of scope, magnitude and complexities and included all Relevancy Elements listed.
Present/past performance effort involved managing a similar project in terms of scope, magnitude and complexities. Project must have been above $100K and included three (3) or more of the Relevancy Elements listed.
Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
Relevancy Elements: Design; Carpentry, Electrical, Plumbing, HVAC, Masonry, Painting
Relevancy Elements: Design; Carpentry, Electrical, Plumbing, HVAC, Masonry, Painting
Relevancy Elements: Carpentry, Electrical, Plumbing, HVAC, Masonry, Painting

*EVALUATED BY: RELEVANCY RATING: VR or R or SR or NR

______________________________________________________________________________________
(Signature)(Date)
____________________________________________________________________________
(Typed or Printed Name)(Title)

(Address, City, State and Zip)

(Phone) (Fax) (/Email) *NOTE: The identity of individual(s) providing reference information SHALL NOT/WILL NOT be disclosed.

Attachment S3
FA4855-13-R-0009
20 June 2013

URGENT! PLEASE RESPOND PROMPTLY

Past Performance Questionnaire

E
VG
S
M
U
N/A
EXCEPTIONAL
VERY GOOD
SATISFACTORY
MARGINAL
UNSATISFACTORY
NOT APPLICABLE
Performance meets contractual requirements with many exceeded to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with no more than a few minor problems for which corrective actions taken by the contractor were highly effective.
Performance meets contractual requirements with some exceeded to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with no more than some minor problems for which corrective actions taken by the contractor were effective.
Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor were satisfactory.
Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions or the contractor’s proposed actions appear only marginally effective or were not fully implemented.
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
Performance was not observed or not applicable to the current effort being reported.

EVALUATION AREAS

I. Quality / Technical Performance
E
VG
S
M
U
N/A
Descripted Comments are appreciated!
1.
Contractor provided effective quality control and inspection procedures that resulted in a quality-finished project.
|_|
|_|
|_|
|_|
|_|
|_|
2.
Contractor developed and submitted realistic progress schedules.
|_|
|_|
|_|
|_|
|_|
|_|
3.
Contractor provided well researched and clearly identified submittals that matched contract requirements.
|_|
|_|
|_|
|_|
|_|
|_|
4.
Contractor completed all work with good workmanship and in conformance with specifications, resulting in minor, if any, punchlist items.
|_|
|_|
|_|
|_|
|_|
|_|
5.
Contractor thoroughly reviewed correspondence for accuracy, completeness, and compliance with contract requirements.
|_|
|_|
|_|
|_|
|_|
|_|
6.
Adequacy/effectiveness of environmental / safety procedures.
|_|
|_|
|_|
|_|
|_|
|_|
7.
Proposals were complete and accurate. Cooperative in negotiations
|_|
|_|
|_|
|_|
|_|
|_|
8.
Responses to changes
|_|
|_|
|_|
|_|
|_|
|_|
II. Timely Performance
E
VG
S
M
U
N/A
1.
Contractor met established project schedules to complete project on time.
|_|
|_|
|_|
|_|
|_|
|_|
2.
Contractor proposed alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the customer
|_|
|_|
|_|
|_|
|_|
|_|
3.
Contractor submitted the progress schedule and interim progress reports as required in a timely manner and the schedule was approved prior to actual construction.
|_|
|_|
|_|
|_|
|_|
|_|
4.
Contractor provided submittals on time as required.
|_|
|_|
|_|
|_|
|_|
|_|
5.
Contractor provided payrolls for both its employees and its subcontractor’s employees as required and scheduled
|_|
|_|
|_|
|_|
|_|
|_|
6.
Provided timely resolution of deficiencies, punchlist items and warranty calls.
|_|
|_|
|_|
|_|
|_|
|_|
7.
Responsive to changes
III. Management Effectiveness
E
VG
S
M
U
N/A
1.
Contractor provided experienced qualified managers and supervisors with the technical and administrative abilities needed to meet contract requirements.
|_|
|_|
|_|
|_|
|_|
|_|
2.
Contractor hired quality subcontractors and effectively managed and coordinated their work.
|_|
|_|
|_|
|_|
|_|
|_|
3.
Contractor understood/complied with customer objectives and technical requirements.
|_|
|_|
|_|
|_|
|_|
|_|
4.
Contractor hired, maintained, and replaced as necessary, qualified personnel and subcontractors/suppliers.
|_|
|_|
|_|
|_|
|_|
|_|
5.
Contractor ensured the site manager had sufficient authority to make decisions and take actions during project performance to keep the project on schedule.
|_|
|_|
|_|
|_|
|_|
|_|
6.
Contractor provided timely and satisfactory response to warranty issues after project completion.
|_|
|_|
|_|
|_|
|_|
|_|
7.
Contractor paid employees/subcontractors/suppliers as required.
|_|
|_|
|_|
|_|
|_|
|_|
8.
Provided timely/effective contract problem resolution without extensive customer guidance.
|_|
|_|
|_|
|_|
|_|
|_|
9.
Contractor proposed alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the customer
|_|
|_|
|_|
|_|
|_|
|_|
IV. Compliance with Labor Standards
E
VG
S
M
U
N/A
1.
Contractor facilitated labor inspections for determination of compliance with wage determinations and labor standards.
|_|
|_|
|_|
|_|
|_|
|_|
2.
Labor posters and wage determinations were displayed as required.
|_|
|_|
|_|
|_|
|_|
|_|
3.
Subcontractor acceptance of labor standard clauses submitted as required.
|_|
|_|
|_|
|_|
|_|
|_|
4.
Statement of Compliance for payroll reports was submitted as required.
|_|
|_|
|_|
|_|
|_|
|_|
V. Compliance with Safety Standards
E
VG
S
M
U
N/A
1.
Adequacy of Safety Plan
|_|
|_|
|_|
|_|
|_|
|_|
2.
Implementation of Safety Plan
|_|
|_|
|_|
|_|
|_|
|_|
VI. Design
E
VG
S
M
U
N/A
1.
Timely submittal of design documents
|_|
|_|
|_|
|_|
|_|
|_|
2.
Specifications and drawings accurate and complete?
|_|
|_|
|_|
|_|
|_|
|_|
3.
Proper engineering to applicable standards?
|_|
|_|
|_|
|_|
|_|
|_|
VII. Overall Performance
E
VG
S
M
U
N/A
1.
Please rate the contractor’s overall performance
|_|
|_|
|_|
|_|
|_|
|_|

In order to understand the basis for the rating in the NARRATIVE SUMMARY section, please discuss and describe each response for which you indicated E (Exceptional), M (Marginal) or U (Unsatisfactory) in response to the questions above (use additional sheets, if necessary).

Government Contracts Only: Has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations?

No ___ or Yes___. If yes was it for: |_|Default |_|Convenience |_|Pending Termination

If yes, please explain (e.g., inability to meet cost, performance, or delivery schedules, etc):

NARRATIVE SUMMARY:

What were the contractor’s most positive aspects in the performance of the contract?

What were the contractor’s most negative aspects in the performance of the contract?

Would you have any reservations about soliciting this contractor in the future or having them perform one of your critical and demanding programs?

Please provide any additional comments concerning this contractor’s performance, as desired.

SECTION C. Return COMPLETED Questionnaire Form to:

Attn:27SOCONS/BFLT Source Selection
110 E. Sextant Ave, Bldg 600, Cannon AFB, NM 88103-5214
Fax:575-784-1148 (DSN 681-1148) or
Email to:shannon.hochmuth@cannon.af.mil and richard.morris@cannon.af.mil

Thank you for your prompt response and assistance!

File details come from the government source that posted it. Updated .