CZQZ_13-1090_Renovate_Community_Center_SOO.docx

DOCX document 44 KB Posted

Attached to
CANNON AFB, NM SABER
Solicitation number
FA4855-13-R-0009
Issued by

About this file

Attachment TO1 - Statement of Objectives

View the file

Other files

File Type Posted
Amendment_5.pdf PDF
Attachment__01_-_SABER_2013_General_Requirements_update_7_Aug_2013_with_header.doc DOC document
Q_and_A_-_Revised.pdf PDF
Amendment_4.pdf PDF
Attachment_S4_-_Coefficient_Spreadsheet.xls XLS spreadsheet
Q_and_A.pdf PDF
CZQZ_13-1090_Renovate_Community_Center_SOO 1 .docx DOCX document
Amendment_3_(SF_30).pdf PDF
Amendment_2.pdf PDF
Attachment_25a.docx DOCX document
Attachment_TO3.pdf PDF
Attachment_25f.docx DOCX document
Amendment_1.doc DOC document
Attachment_25e.docx DOCX document
Attachment_25c.docx DOCX document
Attachment_25d.docx DOCX document
Attachment_25b.docx DOCX document
SABER_Pre-Proposal_Conference_and_Site_Visit.pptx PPTX presentation
Pre-Proposal_Minutes_and_Sign-In.pdf PDF
Second_Floor_Project_Drawings_11X17.pdf PDF
(15_Dec_2012)_CZQZ131090_2nd_Floor_Comm_Call-out.docx DOCX document
1208_2nd_floor_as-built_Floor_Plan_Plans_(1).pdf PDF
SABER_Solicitation.doc DOC document
Attachment_23_-_CAFB_and_MAFR_Civilian_Contractor_Environmental_Guide_Appendix_A_Forms_(2)_with_header.doc DOC document
Attachment_05_-_CAFB_Hardware_Specifications_Guideline-_2011_with_header.pdf PDF
Attachment_21_-_Contractor_handbook_23_Mar_2012_with_header.doc DOC document
Attachment_S2_-_Past_Performance_Project_Data_(REVISED).doc DOC document
Attachment_12__-AF_Form_3064__Contract_Progress_Scheule.xfdl XFDL file
Attachment_03_-_CAFB_Architectural_Compatibility_Guide-2013_with_header.pdf PDF
Attachment_S4_-_Coefficient_Spreadsheet.xls XLS spreadsheet
Attachment_18_-_Building_Construction_1354_Checklist__with_header.xls XLS spreadsheet
Attachment_02_-_SABER_Specifications.pdf PDF
Attachment_24_-_SOW_Example_2013.doc DOC document
Attachment__01_-_SABER_General_Requirements_update_29_Jan_13_with_header.doc DOC document
Attachment_09_-_GeoBase_Initial_Operating_Capability_Implemen_with_header.pdf PDF
Attachment_S3_-_Past_Performance_Questionaire_1.docx DOCX document
Attachment_07_-_CAFB_CAD_Standards_with_header.pdf PDF
Attachment_14_-_Schedule_of_Material_Submittals_(AF66)_with_header.xls XLS spreadsheet
Attachment_S4A_Coefficient_Spreadsheet_(Example).xls XLS spreadsheet
Attachment_08_-_Facility_Excellence_Guide_with_header.pdf PDF
Attachment_S5_-_Question_and_Answer_Template.docx DOCX document
Attachment_04_-_CAFB_Electrical_Standards-March_13 _2012_with_header.pdf PDF
Attachment_13_-_AF_Form_3065_Progrees_Report.xfdl XFDL file
Attachment_06_-_CAFB_Sustainable_Landscape_Development_Plan_-_2012_with_header.pdf PDF
Attachment_19_-_CAFB_Labeling_Standards_for_Communications_with_header.pdf PDF
Attachment_11_-_UFC_1-300-8 _Real_Property_Transfer_with_header.pdf PDF
Attachment_20_-_Base_Contractor_Storage_Lot_Agreement_with_header.doc DOC document
Attachment_17_-_USAF_Hot_Work_Permit.xfdl XFDL file
Attachment_22_-_Cannon_AFB_and_Melrose_AFR_Civilian_Contractor_Environmental_Guide_with_header.doc DOC document
Attachment_16_-_AF_Form_103v5_Work_Clearance_Request_with_header.pdf PDF
Show 40 more

Latest 50 of 53 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF OBJECTIVES

Renovate Community Center Bldg 1208 Contract # FA4855-xx-x-xxxx Project # CZQZ 13-1090 11 Feb 2013

1. OBJECTIVE: Renovate the second floor of bldg. 1208 to facilitate the Community Center. Restructure the existing facility and upgrade the HVAC and Electrical systems to meet the requirements as outlined below. Provide restructured Theater Room, Game Room, Video Gaming Room, Community Room, Bathroom, Offices, and Storage spaces.

2. WORK LOCATION: Bldg 1208, Cannon AFB, NM.

3. PRINCIPAL FEATURES: The work required is to include but is not limited to the furnishing of materials, equipment, facilities, transportation, labor, and supervision required to accomplish the following:

SITE DEMO (Refer to Attached Drawing A101)

1. Game room

a. Demo all wainscoating/baseboard/trim and remove all existing drywall.

b. Remove all electrical and components back to existing panel,

c. Demo single door to include frames between game room and theater room.

d. Demo double doors to include frames leading to hallway

e. Demo flooring (carpet) down to concrete subfloor

f. Demo suspended ceiling system

2. Theater Room

a. Demo all wainscoating/baseboard/trim and remove all existing drywall.

b. Remove all electrical and components back to existing panel,

c. Demo double doors to include frames leading to hallway

d. Demo storage room E door and frame.

e. Demo flooring (carpet) down to concrete subfloor

f. Demo suspended ceiling system

3. Video Gaming Room

a. Demo all wainscoating/baseboard/trim and remove all existing drywall.

b. Remove all electrical and components back to existing panel,

c. Demo storage room D (southwest storage room). Remove only non-load bearing wall structure (studs, floor plate & top plate)

d. Remove wall between storage rooms A &B (West corner storage rooms). Remove only non-load bearing wall structure (studs, floor plate & top plate)

e. Demo single doors on storage rooms A, B, C, and Comm room, to include frames

f. Demo double doors, to include frames, leading to hallway

g. Demo flooring (carpet) down to concrete subfloor

h. Demo suspended ceiling system

4. Restroom

a. Completely demo bathroom to include all fixtures, plumbing, electrical, flooring, door, and walls. Remove only non-load bearing wall structure (studs, floor plate & top plate)

b. Demo ceiling system

5. Janitor room

a. Remove door wall, door and frame. Remove only non-load bearing wall structure (studs, floor plate & top plate)

b. Remove Shelving

c. Remove all electrical and components back to existing panel as necessary to relocate door wall

d. Retain ladder and mop sink and associated plumbing

6. Storage room F, H, office 1 and 2

a. Completely demo both storage rooms and both offices to include flooring , electrical, comm, walls, doors, and ceiling.

7. Storage room G

a. Demo door and frame

8. Sound room

a. Completely demo to include flooring , electrical, comm, walls, doors, and ceiling as a minimum

9. Hall way and Community Room

a. Remove all electrical and components back to existing panel,

b. Remove wall between community room and hallway; starting at storage room G and going west/southwest to existing stairway. Remove only non-load bearing wall structure (studs, floor plate & top plate)

c. Demo flooring (carpet) down to concrete subfloor

d. Demo suspended ceiling system

e. Demo existing power panel and components back to primary panel (downstairs)

10. Stair wells A&B

a. Remove VCT and covebase from each level

b. Remove stair treads

c. Remove/Strip paint from hand rail system NEW INSTALLATION (Refer to Attached Drawing 102)

1. Community Room

a. Construct Storage Room apprx 17 ft x 6 ft in S. corner of room (refer to Drawing A102),

i. Install solid core wood door and frame door to open into the storage room; stain and finish. Stain will be determined by the government

ii. Install light switch and electrical receptacle

iii. Install hard ceiling with two ceiling mounted two lamp 2 ft x 4 ft T8 florescent fixtures

b. Frame in wall on Northeast wall where door was removed

c. Install new solid core wood double door and frame with half glass, where old double door was removed. Panic bars are required for double door and hold open door closure for both doors. Use ADA industrial type door handles with a 7 pin best lock system or government approved equal.

d. Install new 5/8 inch gypsum board throughout room at 10 foot height. Mud and tape to a level 4 finish.

e. Texture, prime and paint all walls – colors to be chosen by government

f. Install duplex receptacles and voice/data on SW wall at 6 ft on center intervals along wall at 42 inches above the finished floor

g. On all other walls install duplex receptacles and voice/data at 6 ft on center intervals along wall at standard height above the finished floor

h. Install new hard wood floor and baseboard, selection to be made by the government

i. Install new suspended ceiling system with 2 ft x 2 ft tegular, fire rated ceiling tiles

j. Install two single receptacles in ceiling, refer to drawing A102

k. Install motion sensor light switches at entrance into the room

2. Video Gaming Room

a. Construct 48 inch high wall, splitting the room. Recommend Columns on each end and two evenly spaced along the length of the wall and tie into deck above for stability. North end column needs to be 9 ‘ from North wall and South end column needs to be minimum 42 inches from South wall

i. Place fourplex receptacles, voice and data outlets at 6 ft on center intervals along Southwest side of wall

ii. Place fourplex receptacles, voice and data outlets at 3 ft on center intervals along Northeast side of wall

b. Construct new wall between Video Game Room and Theater/AV Room. Install 2 layers of 5/8 sheetrock with joints offset on Video Game Room side. Install 1 layer on Theater/AV Room side.

c. Install fourplex receptacles and voice/data receptacles along Southwest, North, South, and North corner of Northeast wall at 6 foot on center intervals – refer to drawing A-102

d. Install fourplex receptacles and voice/data receptacles along Northeast wall at 3 foot on center intervals going north to the HVAC Duct bank area

e. Install 4 way light switches at each entrance into the room. Switch at main door also shall be a dimmer

f. Install 3 single receptacles on North wall evenly distributed at 6 feet high

g. Install new Audio/Visual Fire Alarms as per code utilize existing drops

h. Install Cable outlets on Northwest wall of room

i. Install new 5/8 inch gypsum board throughout room at 10 foot height. Mud and tape to a level 4 finish.

j. Texture, prime and paint all walls – colors to be chosen by government

k. Install new suspended ceiling system with 2 ft x 2 ft tegular, fire rated ceiling panels

l. Install new 2 ft x 4 ft T8 fluorescent lights

m. Install emergency ballist into T8 lighting as required to meet emergency lighting requirements

n. Install new hard wood floor and baseboard, selection to be made by the government

o. Install new solid core wood double door and frame with half glass, where old double door was removed

p. Install new solid core door and frame on the Southwest wall and the Northeast wall along with new hardware, refer to drawing A102 for approximate locations. Panic bars are required for double door and hold open door closure for all three doors. Use ADA industrial type door handles with a 7 pin best lock system or government approved equal.

q. Install new solid core wood door and frame along with new hardware on mechanical room door, stain and finish. Stain will be determined by the government

3. Theater/AV Room

a. Install duplex receptacles and voice/data receptacles along walls at 6 foot on center intervals – refer to drawing A-102

b. Install duplex receptacle at 6’ above finished floor in center of south wall and mounting structure to facilitate video screen equipment (requirements will be determined by product data)

c. Install single receptacle in ceiling and mounting structure to facilitate video equipment (distance from wall will be determined by product data)

d. Install 3 way light switches at each entrance into the room. Switch at main door shall also be a dimmer

e. Install new Audio/Visual Fire Alarms as per code utilize existing drops

f. Install Cable outlets on South wall of room

g. Restructure storage rooms and comm. room as identified on drawing A102. Re-use door frames that were removed from these rooms.

h. Frame in walls where doors are to be removed and not reset.

i. Install new 5/8 inch gypsum board throughout room at 10 foot height. Mud and tape to a level 4 finish.

j. Texture, prime and paint all walls – colors to be chosen by government

k. Install new suspended ceiling system with 2 ft x 2 ft tegular, fire rated ceiling panels. Storage Room Electrical Room and Comm room will have a hard ceiling

l. Install new 2 ft x 4 ft T8 fluorescent lights

m. Install emergency ballast into T8 lighting as required to meet emergency lighting requirements

n. Install carpet and vinyl covebase – colors to be chosen by government

o. Install new solid core wood double door and frame with half glass, where old double door was removed

p. Install new solid core door and frame on the Southwest wall and the Northeast wall along with new hardware, refer to drawing A102 for approximate locations. Panic bars are required for double door and hold open door closure for all three doors. Use ADA industrial type door handles with a 7 pin best lock system or government approved equal.

q. Install new solid core wood door and frame along with new hardware on mechanical room door, stain and finish. Stain will be determined by the government

4. Bathrooms

a. Construct Male and Female bathroom in southwest area of second floor. (Refer to Drawing A102) Both bathrooms shall be constructed with a hard ceiling and as a minimum meet the requirements listed below:

i. Womens bathroom

1. Install two waterclosets, one standard and one to meet Disability Standards

2. Install 2 lavoratories into a wall hung countertop

3. Install dual toilet paper roll holders – industrial

4. Install Paper towel/trash receptacle, inset wall unit

5. Install mirror above each sink

6. Install lighting at sinks

7. Install 12 in x 12 in ceramic tile with ceramic covebase

8. Install 2 duplex Ground Fault Circuit Indicators (GFCI) at sink counter

9. Install booster fans for exhaust system, dampered to prevent backflow and tie into existing exhaust system.

ii. Mens Bathroom

1. Install one urinal and one watercloset (to meet Disability Standards)

2. Install 2 lavoratories into a wall hung countertop

3. Install dual toilet paper roll holder – industrial

4. Install Paper towel/trash receptacle, inset wall unit

5. Install mirror above each sink

6. Install lighting at sinks

7. Install 12 in x 12 in ceramic tile with ceramic covebase

8. Install 2 duplex Ground Fault Circuit Indicators (GFCI) at sink counter

9. Install booster fans for exhaust system, dampered to prevent backflow and tie into existing exhaust system.

5. Office

a. Construct an office apprx 13 ft x 12 ft in next to bathrooms (refer to Drawing A102),

b. Install new solid core wood double door and frame with half glass; stain and finish. Stain will be determined by the government. Use ADA industrial type door handles with a 7 pin best lock system or government approved equal.

c. Install new 5/8 inch gypsum board throughout room at 10 ft height. Mud and tape to a level 4 finish.

d. Texture, prime and paint all walls – colors to be chosen by government

e. Install duplex receptacles and voice/data on all walls at 6 ft on center intervals along wall. All voice and data receptacles will be ran back to communications room. One set as determined by the user will be patched in, all others will be prepped accordingly and the dead ended in the communications room

f. Install new suspended ceiling system with 2 ft x 2 ft tegular, fire rated ceiling tiles

g. Install new 2 ft x 4 ft T8 fluorescent lights.

h. Install motion sensor light switches at entrance into the room

i. Install carpet and vinyl covebase, colors to be chosen by government.

6. Table Top Game Room, Recption Area, and Main Hallway (refer to Drawing A102)

a. Install new 5/8 inch gypsum board throughout room at 10 ft height. Mud and tape to a level 4 finish.

b. Texture, prime and paint all walls – colors to be chosen by government

c. Install duplex receptacles and voice/data on all walls at 6 ft on center intervals along wall, with the exception of the main hallway. Voice and data receptacles at Reception area will be ran back to communications room. One set as determined by the user will be patched in, all others will be prepped accordingly and dead ended in the communications room

d. Place two duplex receptacles in main hallway between video game room door and Theater/AV Room door

e. Install new water fountain

f. Install new solid core wood double door and frame to storage room; stain and finish. Stain will be determined by the government.

g. Install new suspended ceiling system at 9 ft height with 2 ft x 2 ft tegular, fire rated ceiling tiles

h. Install new 2 ft x 4 ft T8 fluorescent lights.

i. Install motion sensor light switches in the room

j. Install new hard wood floor and baseboard, selection to be made by the government

k. Flooring at the reception area shall be carpet and transition into the wood flooring area

l. Install lower and upper cabinetry in reception area along office and exterior wall, approx 13 ft 6 in x 10 ft. Install countertop on base cabinets

7. Sound Studio

a. Construct a studio sound room and sound control room in lower Northeast corner of second floor area (refer to drawing A102)

b. Construct counter below new window for sound control equipment/computer; approx 5 ft long.

c. Install 2 fourplex receptacles above counter

d. Install new solid core wood door and frame with half glass in Sound Control Room; stain and finish. Stain will be determined by the government. Use ADA industrial type door handles with a 7 pin best lock system or government approved equal. Use sound sealed door.

e. Install new solid core wood door and frame between Sound Control Room and Sound Studio; stain and finish. Stain will be determined by the government. Use ADA industrial type door handles with a 7 pin best lock system or government approved equal. Use sound sealed door.

f. Install Sound proof window between Sound Control Room and Sound Studio; approx 5 ft long and 3ft high above counter in Sound Control room

g. Install 2 layers of new 5/8 inch gypsum board (or sound reducing material) on both sides of interior and exterior walls and wall between control room and studio at 10 ft height. Mud and tape to a level 4 finish.

h. Texture, prime and paint all walls – colors to be chosen by government

i. Install duplex receptacles and voice/data on all walls at 6 ft on center intervals along wall of Sound Studio. All voice and data receptacles will be ran back to communications room. One set as determined by the user will be patched in, all others will be prepped accordingly and the dead ended in the communications room.

j. Install new suspended ceiling system with 2 ft x 2 ft tegular, fire rated ceiling tiles at 9 ft high

k. Install new 2 ft x 4 ft T8 fluorescent lights.

l. Install motion sensor light switches at entrance into both rooms

m. Install carpet and vinyl covebase, colors to be chosen by government.

8. Stairwells A & B

a. Install new suspended ceiling system with 2 ft x 2 ft tegular, fire rated ceiling tiles

b. Install new 2 ft x 4 ft T8 fluorescent lights.

c. Install motion sensor light switches at top and bottom of both stairwells

d. Repair walls as needed and repaint entire stairwell – color to be chosen by the Government

e. Install VCT and vinyl covebase, colors to be chosen by government.

f. Install Rubber stair tread

g. Refinish handrails

h. Install Fire Alarm pull station at both stairwell doorways.

9. General

a. All comm. Conduit to be stubbed out above roof with no cabling unless previously stated

b. Install new Audio/Visual Fire Alarms as per code utilize existing drops

c. Reinstall all EMCS Controls

d. Connect all ductwork to new diffusers in each room/are. Install returns in ceiling to allow for open plenum return system

e. Install 4 new fire extinguisher boxes

f. Inset pull stations into block wall

4. PERFORMANCE PERIOD:

Submittal------------------------- 14 Calendar days Material Procurement---------- 30 Calendar days Construction--------------------- 120 Calendar days TOTAL--------------- 164 Calendar Days

5. RELATED PROJECTS: None

6. SAFETY: All OSHA, AFOSH and other applicable DOD Standards apply as stated in SABER contract FA4855-xx-x-xxxx.

7. SPECIFICATIONS: All materials and construction criteria used in SABER contract FA4855-xx-x-xxxx, will be strictly adhered to.

8. SPECIAL REQUIREMENTS: Materials must be commercial/industrial quality and meet the “Buy American Act”. In the event of strong wind and monsoon conditions, contractor will secure all materials at no cost to the government.

9. POINT OF CONTACT: Kirk Reader/PM 784-7076.

KIRK L. READER, GS-11, DAF
SABER Chief