802 CONS/LGCA-3 FA3047-10-R-0012
Lackland AFB TX Roofing IDIQ
02 82 16.00 20
Section J – Attachment 2P Page 1 of 24 8 Feb 2010
SECTION 02 82 16.00 20
ENGINEERING CONTROL OF ASBESTOS CONTAINING MATERIALS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced.
The publications are referred to within the text by the basic designation only.
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI Z88.2(1992) Respiratory Protection
ANSI Z9.2(2001) Fundamentals Governing the Design and Operation of Local Exhaust
Ventilation Systems
ASTM INTERNATIONAL (ASTM)
ASTM C 732(2006) Aging Effects of Artificial Weathering on Latex Sealants
ASTM D 1331(1989; R 2001) Surface and Interfacial Tension of Solutions of Surface-
Active Agents
ASTM D 2794(1993; R 2004) Resistance of Organic Coatings to the Effects of Rapid
Deformation (Impact)
ASTM D 522(1993a; R 2008) Mandrel Bend Test of Attached Organic Coatings
ASTM E 119(2008a) Standard Test Methods for Fire Tests of Building Construction and
Materials
ASTM E 1368(2005e1) Visual Inspection of Asbestos Abatement Projects
ASTM E 1494(1992; R 2002) Encapsulants for Spray- or Trowel-Applied Friable
Asbestos-Containing Building Materials
ASTM E 736(2000; R 2006) Cohesion/Adhesion of Sprayed Fire-Resistive Materials
Applied to Structural Members
ASTM E 84(2009a) Standard Test Method for Surface Burning Characteristics of
Building Materials
02 82 16.00 20
Section J – Attachment 2P Page 2 of 24 8 Feb 2010
ASTM E 96/E 96M(2005) Standard Test Methods for Water Vapor Transmission of
Materials
TEXAS DEPARTMENT OF HEALTH ASBESTOS PROGRAMS BRANCH
PUBLICATION #18-10947Texas Asbestos Health Protection Rules
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA 560/5-85-024(1985) Guidance for Controlling Asbestos-Containing Materials in
Buildings (Purple Book)
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1926.103Respiratory Protection
29 CFR 1926.1101Asbestos
29 CFR 1926.200Accident Prevention Signs and Tags
29 CFR 1926.51Sanitation
29 CFR 1926.59Hazard Communication
40 CFR 61-SUBPART AGeneral Provisions
40 CFR 61-SUBPART MNational Emission Standard for Asbestos
40 CFR 763Asbestos
U.S. NAVAL FACILITIES ENGINEERING COMMAND (NAVFAC)
ND OPNAVINST 5100.23(Rev G) Navy Occupational Safety and Health (NAVOSH)
Program Manual
UNDERWRITERS LABORATORIES (UL)
UL 586(1996; Rev thru Aug 2008) Standard for High-Efficiency Particulate, Air Filter
Units
1.2 DEFINITIONS
1.2.1 ACM
Asbestos Containing Materials.
02 82 16.00 20
Section J – Attachment 2P Page 3 of 24 8 Feb 2010
1.2.2 Amended Water
Water containing a wetting agent or surfactant with a maximum surface tension of 29 dynes per centimeter when tested in accordance with ASTM D 1331.
1.2.3 Area Sampling
Sampling of asbestos fiber concentrations which approximates the concentrations of asbestos in the theoretical breathing zone but is not actually collected in the breathing zone of an employee.
1.2.4 Asbestos
The term asbestos includes chrysotile, amosite, crocidolite, tremolite asbestos, anthophyllite asbestos, and actinolite asbestos and any of these minerals that has been chemically treated or altered. Materials are considered to contain asbestos if the asbestos content of the material is determined to be greater than one percent.
1.2.5 Asbestos Control Area
That area where asbestos removal operations are performed which is isolated by physical boundaries which assist in the prevention of the uncontrolled release of asbestos dust, fibers, or debris.
1.2.6 Asbestos Fibers
Those fibers having an aspect ratio of at least 3:1 and longer than 5 micrometers as determined by National Institute for Occupational Safety and Health (NIOSH) Method
7400.
1.2.7 Asbestos Permissible Exposure Limit
0.1 fibers per cubic centimeter of air as an 8-hour time weighted average measured in the breathing zone as defined by 29 CFR 1926.1101 or other Federal legislation having legal jurisdiction for the protection of workers health.
1.2.8 Background
The ambient airborne asbestos concentration in an uncontaminated area as measured prior to any asbestos hazard abatement efforts. Background concentrations for other
(contaminated) areas are measured in similar but asbestos free locations.
1.2.9 Contractor
The Contractor is that individual, or entity under contract to the Government to perform the herein listed work.
Section J – Attachment 2P Page 4 of 24 8 Feb 2010
1.2.10 Competent Person
A person meeting the requirements for competent person as specified in 29 CFR
1926.1101 including a person capable of identifying existing asbestos hazards in the workplace and selecting the appropriate control strategy for asbestos exposure, who has the authority to take prompt corrective measures to eliminate them, and is specifically trained in a training course which meet the criteria of EPA's Model Accreditation Plan
(40 CFR 763) for project designer or supervisor, or its equivalent. The competent person shall have a current State of Texas asbestos contractors or supervisors license.
1.2.11 Encapsulation
The abatement of an asbestos hazard through the appropriate use of chemical encapsulants.
1.2.12 Encapsulants
Specific materials in various forms used to chemically or physically entrap asbestos fibers in various configurations to prevent these fibers from becoming airborne. There are four types of encapsulants as follows which must comply with performance requirements as specified herein.
a. Removal Encapsulant (can be used as a wetting agent)
b. Bridging Encapsulant (used to provide a tough, durable surface coating to asbestos containing material)
c. Penetrating Encapsulant (used to penetrate the asbestos containing material encapsulating all asbestos fibers and preventing fiber release due to routine mechanical damage)
d. Lock-Down Encapsulant (used to seal off or "lock-down" minute asbestos fibers left on surfaces from which asbestos containing material has been removed).
1.2.13 Friable Asbestos Material
Greater than one percent asbestos containing material that can be crumbled, pulverized, or reduced to powder by hand pressure when dry.
1.2.14 Glovebag Technique
Those asbestos removal and control techniques put forth in 29 CFR 1926.1101 Appendix
G.
1.2.15 HEPA Filter Equipment
Section J – Attachment 2P Page 5 of 24 8 Feb 2010
High efficiency particulate air (HEPA) filtered vacuum and/or exhaust ventilation equipment with a filter system capable of collecting and retaining asbestos fibers. Filters shall retain 99.97 percent of particles 0.3 microns or larger as indicated in UL 586.
1.2.16 Negative Pressure Enclosure (NPE)
That engineering control technique described as a negative pressure enclosure in 29 CFR
1926.1101.
1.2.17 Nonfriable Asbestos Material
Material that contains greater than one percent asbestos in which the fibers have been immobilized by a bonding agent, coating, binder, or other material so that the asbestos is well bound and will not normally release asbestos fibers during any appropriate use, handling, storage or transportation. It is understood that asbestos fibers may be released under other conditions such as demolition, removal, or mishap.
1.2.18 Personal Sampling
Air sampling which is performed to determine asbestos fiber concentrations within the breathing zone of a specific employee, as performed in accordance with 29 CFR
1926.1101.
1.2.19 Competent Person (CP)
That qualified person hired by the Contractor to perform the herein listed tasks.
1.2.20 Qualified Person (QP)
A Registered Architect, Professional Engineer, Certified Industrial Hygienist, consultant or other qualified person who has successfully completed training and is therefore accredited under a legitimate State Model Accreditation Plan as described in 40 CFR 763 as a Building Inspector, Contractor/Supervisor Abatement Worker, and Asbestos Project
Designer; and has successfully completed the National Institute of Occupational Safety and Health (NIOSH) 582 course "Sampling and Evaluating Airborne Asbestos Dust" or equivalent. The QP must be qualified to perform visual inspections as indicated in
ASTM E 1368. The QP shall be appropriately licensed in the State of Texas.
PUBLICATION #18-10947
1.2.21 TEM
Refers to Transmission Electron Microscopy.
1.2.22 Time Weighted Average (TWA)
02 82 16.00 20
Section J – Attachment 2P Page 6 of 24 8 Feb 2010
The TWA is an 8-hour time weighted average airborne concentration of asbestos fibers.
1.2.23 Wetting Agent
A chemical added to water to reduce the water's surface tension thereby increasing the water's ability to soak into the material to which it is applied. An equivalent wetting agent must have a surface tension of at most 29 dynes per centimeter when tested in accordance with ASTM D 1331.
1.3 REQUIREMENTS
1.3.1 Description of Work
The work covered by this section includes the handling and control of asbestos containing materials and describes some of the resultant procedures and equipment required to protect workers, the environment and occupants of the building or area, or both, from contact with airborne asbestos fibers. The work also includes the disposal of any asbestos containing materials generated by the work. More specific operational procedures shall be outlined in the Asbestos Hazard Abatement Plan called for elsewhere in this specification. Under normal conditions non-friable or chemically bound materials containing asbestos would not be considered hazardous; however, this material may release airborne asbestos fibers during demolition and removal and therefore must be handled in accordance with the removal and disposal procedures as specified herein.
Provide negative pressure enclosure techniques as outlined in this specification.
1.3.1.1 Wallboard/Joint Compound
Wallboard and joint compound have been tested and results are attached.
1.3.2 Medical Requirements
Provide medical requirements including but not limited to medical surveillance and medical record keeping as listed in 29 CFR 1926.1101.
1.3.2.1 Medical Examinations
Before exposure to airborne asbestos fibers, provide workers with a comprehensive medical examination as required by 29 CFR 1926.1101 or other pertinent State or local directives. This requirement must have been satisfied within the 12 months prior to the start of work on this contract. The same medical examination shall be given on an annual basis to employees engaged in an occupation involving asbestos and within 30 calendar days before or after the termination of employment in such occupation. Specifically identify x-ray films of asbestos workers to the consulting radiologist and mark medical record jackets with the word "ASBESTOS."
1.3.2.2 Medical Records
Section J – Attachment 2P Page 7 of 24 8 Feb 2010
Maintain complete and accurate records of employees' medical examinations, medical records, and exposure data for a period of 30 years after termination of employment and make records of the required medical examinations and exposure data available for inspection and copying to: The Assistant Secretary of Labor for Occupational Safety and
Health (OSHA), or authorized representatives of them, and an employee's physician upon the request of the employee or former employee.
1.3.3 Employee Training
Submit certificates, prior to the start of work but after the main abatement submittal, signed by each employee indicating that the employee has received training in the proper handling of materials and wastes that contain asbestos in accordance with 40 CFR 763;
understands the health implications and risks involved, including the illnesses possible from exposure to airborne asbestos fibers; understands the use and limits of the respiratory equipment to be used; and understands the results of monitoring of airborne quantities of asbestos as related to health and respiratory equipment as indicated in 29
CFR 1926.1101 on an initial and annual basis. Certificates shall be organized by individual worker, not grouped by type of certification. Train all personnel involved in the asbestos control work in accordance with United States Environmental Protection
Agency (USEPA) Asbestos Hazard Emergency Response Act (AHERA) training criteria or State training criteria whichever is more stringent. The Contractor shall document the training by providing: dates of training, training entity, course outline, names of instructors, and qualifications of instructors upon request by the Contracting Officer.
Furnish each employee with respirator training and fit testing administered by the CP as required by 29 CFR 1926.1101. Fully cover engineering and other hazard control techniques and procedures. All asbestos workers shall have a current State of Texas workers license.
1.3.4 Permits, Licenses, and Notifications
Obtain necessary permits and licenses in conjunction with asbestos removal, encapsulation, hauling, and disposition, and furnish notification of such actions required by Federal, State, regional, and local authorities prior to the start of work. Notify the
State's Department of Health and the Contracting Officer in writing 10 working days prior to commencement of work in accordance with 40 CFR 61-SUBPART M Notify the
Contracting Officer and other appropriate Government agencies in writing 10 working days prior to the start of asbestos work as indicated in applicable laws, ordinances, criteria, rules, and regulations. Submit copies of all Notifications to the Contracting
Officer. Notify the local fire department 3 days prior to removing fire-proofing material from the building including notice that the material contains asbestos.
1.3.5 Environment, Safety and Health Compliance
In addition to detailed requirements of this specification, comply with those applicable laws, ordinances, criteria, rules, and regulations of Federal, State, regional, and local
02 82 16.00 20
Section J – Attachment 2P Page 8 of 24 8 Feb 2010 authorities regarding handling, storing, transporting, and disposing of asbestos waste materials. Comply with the applicable requirements of the current issue of 29 CFR
1926.1101, 40 CFR 61-SUBPART A, 40 CFR 61-SUBPART M, and ND OPNAVINST
5100.23. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting the work. Where the requirements of this specification, applicable laws, rules, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirement as defined by the Government shall apply.
1.3.6 Respiratory Protection Program
Establish and implement a respirator program as required by ANSI Z88.2, 29 CFR
1926.1101, and 29 CFR 1926.103. Submit a written description of the program to the
Contracting Officer. Submit a written program manual or operating procedure including methods of compliance with regulatory statutes.
1.3.6.1 Respirator Program Records
Submit records of the respirator program as required by ANSI Z88.2, 29 CFR 1926.103, and 29 CFR 1926.1101.
1.3.7 Asbestos Hazard Control Supervisor
The Contractor shall be represented on site by a supervisor, trained using the model
Contractor accreditation plan as indicated in the Federal statutes for all portions of the herein listed work.
1.3.8 Hazard Communication
Adhere to all parts of 29 CFR 1926.59 and provide the Contracting Officer with a copy of the Material Safety Data Sheets (MSDS) for all materials brought to the site.
1.3.9 Asbestos Hazard Abatement Plan
Submit a detailed plan of the safety precautions such as lockout, tagout, tryout, fall protection, and confined space entry procedures and equipment and work procedures to be used in the encapsulation, removal, and demolition of materials containing asbestos.
The plan, not to be combined with other hazard abatement plans, shall be prepared, signed, and sealed by the CP. Provide a Table of Contents for each abatement submittal, which shall follow the sequence of requirements in the contract. Such plan shall include but not be limited to the precise personal protective equipment to be used including, but not limited to, respiratory protection, type of whole-body protection and if reusable coveralls are to be employed decontamination methods (operations and quality control plan), the location of asbestos control areas including clean and dirty areas, buffer zones, showers, storage areas, change rooms, removal, encapsulation method, interface of trades involved in the construction, sequencing of asbestos related work, disposal plan, type of
02 82 16.00 20
Section J – Attachment 2P Page 9 of 24 8 Feb 2010 wetting agent and asbestos sealer to be used, locations of local exhaust equipment, planned air monitoring strategies, and a detailed description of the method to be employed in order to control environmental pollution. The plan shall also include (both fire and medical emergency) response plans. The Asbestos Hazard Abatement Plan must be approved in writing prior to starting any asbestos work. The Contractor, Asbestos
Hazard Control Supervisor, and CP shall meet with the Contracting Officer prior to beginning work, to discuss in detail the Asbestos Hazard Abatement Plan, including work procedures and safety precautions. Once approved by the Contracting Officer, the plan will be enforced as if an addition to the specification. Any changes required in the specification as a result of the plan shall be identified specifically in the plan to allow for free discussion and approval by the Contracting Officer prior to starting work.
1.3.10 Testing Laboratory
Submit the name, address, and telephone number of each testing laboratory selected for the sampling, analysis, and reporting of airborne concentrations of asbestos fibers along with evidence that each laboratory selected holds the appropriate State license and/or permits and certification that each laboratory is American Industrial Hygiene Association
(AIHA) accredited and that persons counting the samples have been judged proficient by current inclusion on the AIHA Asbestos Analysis Registry (AAR) and successful participation of the laboratory in the Proficiency Analytical Testing (PAT) Program.
Where analysis to determine asbestos content in bulk materials or transmission electron microscopy is required, submit evidence that the laboratory is accredited by the National
Institute of Science and Technology (NIST) under National Voluntary Laboratory
Accreditation Program (NVLAP) for asbestos analysis. The testing laboratory firm shall be independent of the asbestos contractor and shall have no employee or employer relationship which could constitute a conflict of interest.
1.3.11 Landfill Approval
Submit written evidence that the landfill is for asbestos disposal by the U.S.
Environmental Protection Agency, Region 3, Air Enforcement Section (38W12), and local regulatory agencies. Within 3 working days after delivery, submit detailed delivery tickets, prepared, signed, and dated by an agent of the landfill, certifying the amount of asbestos materials delivered to the landfill. Submit a copy of the waste shipment records within 1 day of the shipment leaving the project site.
1.3.12 Medical Certification
Provide a written certification for each worker and supervisor, signed by a licensed physician indicating that the worker and supervisor has met or exceeded all of the medical prerequisites listed herein and in 29 CFR 1926.1101 and 29 CFR 1926.103 as prescribed by law. Submit certificates prior to the start of work but after the main abatement submittal.
1.4 SUBMITTALS
Section J – Attachment 2P Page 10 of 24 8 Feb 2010
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Local exhaust equipment; G
Vacuums; G
Respirators; G
Pressure differential automatic recording instrument; G
Amended water; G
Glovebags; G
Material Safety Data Sheets (MSDS) for all materials proposed for transport to the project site; G
Encapsulants; G
SD-06 Test Reports
Air sampling results; G
Pressure differential recordings for local exhaust system; G
Asbestos disposal quantity report; G
Encapsulation test patches; G
Clearance sampling; G
SD-07 Certificates
Asbestos hazard abatement plan; G
Testing laboratory; G
Competent person documentation; G
Contractor's license; G
02 82 16.00 20
Section J – Attachment 2P Page 11 of 24 8 Feb 2010
Competent person documentation; G
Worker's license; G
Landfill approval; G
Employee training; G
Medical certification requirements; G
Waste shipment records and if applicable exemption report; G
Respiratory Protection Program; G
Delivery tickets; G
Vacuums; G
Water filtration equipment; G
Ventilation systems; G
Other equipment used to contain airborne asbestos fibers; G
Chemical encapsulants sealers; G
Notifications
Show compliance with ANSI Z9.2 by providing manufacturers' certifications.
SD-11 Closeout Submittals
Notifications; G
Rental equipment; G
Respirator program records; G
Permits and licenses; G
1.5 QUALITY ASSURANCE
1.5.1 Competent Person Documentation
Submit the name, address, and telephone number of the Competent Person (CP) selected to prepare the Asbestos Hazard Abatement Plan, direct monitoring and training, and
02 82 16.00 20
Section J – Attachment 2P Page 12 of 24 8 Feb 2010 documented evidence that the CP has successfully completed training in and is accredited and where required is certified as, an asbestos consultant as described by 40 CFR 763 and has successfully completed the National Institute of Occupational Safety and Health
(NIOSH) 582 course "Sampling and Evaluating Airborne Asbestos Dust" or equivalent.
The CP and the asbestos contractor shall not have an employee/employer relationship or financial relationship which could constitute a conflict of interest. The CP shall be a first tier subcontractor.
1.5.2 Competent Person Documentation
Submit training certification and a current State of Texas Asbestos Contractor's and
Supervisor's License.
1.5.3 Worker's License
Submit documentation that requires all workers have a current State of Texas Asbestos
Workers License.
1.5.4 Contractor's License
Contractor shall have a current Texas asbestos contractor's license. Submit a copy of the asbestos contractor's license issued by the State of Texas.
1.5.5 Air Sampling Results
Complete fiber counting and provide results to the CP for review within 16 hours of the
"time off" of the sample pump. Notify the Contracting Officer immediately of any airborne levels of asbestos fibers in excess of the acceptable limits. Submit sampling results to the Contracting Officer and the affected Contractor employees where required by law within 3 working days, signed by the testing laboratory employee performing air sampling, the employee that analyzed the sample, and the CP. Notify the Contractor and the Contracting Officer immediately of any variance in the pressure differential which could cause adjacent unsealed areas to have asbestos fiber concentrations in excess of
0.01 fibers per cubic centimeter or background whichever is higher. In no circumstance shall levels exceed 0.1 fibers per cubic centimeter.
1.5.6 Pressure Differential Recordings for Local Exhaust System
Provide a local exhaust system that creates a negative pressure of at least 0.02 inches of water relative to the pressure external to the enclosure and operate it continuously, 24 hours a day, until the temporary enclosure of the asbestos control area is removed.
Submit pressure differential recordings for each work day to the CP for review and to the
Contracting Officer within 24 hours from the end of each work day.
1.5.7 Protective Clothing Decontamination Quality Control Records
02 82 16.00 20
Section J – Attachment 2P Page 13 of 24 8 Feb 2010
Provide all records that document quality control for the decontamination of reusable outer protective clothing.
1.5.8 Protective Clothing Decontamination Facility Notification
Submit written evidence that persons who decontaminate, store, or transport asbestos contaminated clothing used in the performance of this contract were duly notified in accordance with 29 CFR 1926.1101.
1.6 EQUIPMENT
1.6.1 Rental Equipment
Provide a copy of the written notification to the rental company concerning the intended use of the equipment and the possibility of asbestos contamination of the equipment.
PART 2 PRODUCTS
2.1 ENCAPSULANTS
Shall conform to current USEPA requirements, shall contain no toxic or hazardous substances as defined in 29 CFR 1926.59, and shall conform to the following performance requirements.
2.1.1 Removal Encapsulants
Requirement Test Standard
Flame Spread - 25, Smoke Emission - 50 ASTM E 84
Life Expectancy - 20 years ASTM C 732 Accelerated
Aging Test
Permeability - Minimum 0.4 perms ASTM E 96/E 96M
2.1.2 Bridging Encapsulant
02 82 16.00 20
Section J – Attachment 2P Page 14 of 24 8 Feb 2010
Fire Resistance - Negligible affect on ASTM E 119 fire resistance rating over 3 hour test
(Classified by UL for use over fibrous and cementitious sprayed fireproofing)
Impact Resistance - Minimum ASTM D 2794
43 in/lb Gardner Impact Test
Flexibility - no rupture or cracking ASTM D 522
Mandrel Bend Test
2.1.3 Penetrating Encapsulant
Cohesion/Adhesion Test - ASTM E 736
50 pounds of force/foot
Fire Resistance - Negligible affect on ASTM E 119 fire resistance rating over 3 hour test
(Classified by UL for use over fibrous and cementitious sprayed fireproofing)
Impact Resistance - Minimum ASTM D 2794
43 in/lb Gardner Impact Test
Flexibility - no rupture or cracking ASTM D 522
Mandrel Bend Test
2.1.4 Lock-down Encapsulant
Flame Spread: 25, Smoke Emission - 50 ASTM E 84
Life Expectancy: 20 years ASTM C 732 Accelerated
Permeability: Minimum 0.4 perms ASTM E 96/E 96M
Section J – Attachment 2P Page 15 of 24 8 Feb 2010
Fire Resistance: Negligible affect on ASTM E 119 fire resistance rating over 3 hour test
(Tested with fireproofing over encapsulant applied directly to steel member)
Bond Strength: 100 pounds of force/foot ASTM E 736
(Tests compatibility with cementitious and fibrous fireproofing)
PART 3 EXECUTION
3.1 EQUIPMENT
At all times, provide the Contracting Officer or the Contracting Officer's Representative, with at least three complete sets of personal protective equipment as required for entry to and inspection of the asbestos control area. Provide equivalent training to the
Contracting Officer or a designated representative as provided to Contractor employees in the use of the required personal protective equipment. Provide manufacturer's certificate of compliance for all equipment used to contain airborne asbestos fibers.
3.1.1 Respirators
Select respirators from those approved by the National Institute for Occupational Safety and Health (NIOSH), Department of Health and Human Services.
3.1.1.1 Respirators for Handling Asbestos
Provide personnel engaged in pre-cleaning, cleanup, handling, encapsulation, removal and/or demolition of asbestos materials with respiratory protection as indicated in 29
CFR 1926.1101 and 29 CFR 1926.103.
3.1.2 Exterior Whole Body Protection
3.1.2.1 Outer Protective Clothing
Provide personnel exposed to asbestos with disposable "non-breathable," whole body outer protective clothing, head coverings, gloves, and foot coverings. Provide disposable plastic or rubber gloves to protect hands. Cloth gloves may be worn inside the plastic or rubber gloves for comfort, but shall not be used alone. Make sleeves secure at the wrists, make foot coverings secure at the ankles, and make clothing secure at the neck by the use of tape.
3.1.2.2 Work Clothing
02 82 16.00 20
Section J – Attachment 2P Page 16 of 24 8 Feb 2010
Provide cloth work clothes for wear under the outer protective clothing and foot coverings and either dispose of or properly decontaminate them as recommended by the
CP after each use.
3.1.2.3 Personal Decontamination Unit
Provide a temporary, negative pressure unit with a separate decontamination locker room and clean locker room with a shower that complies with 29 CFR 1926.51(f)(4)(ii) through (V) in between for personnel required to wear whole body protective clothing.
Provide two separate lockers for each asbestos worker, one in each locker room. Keep street clothing and street shoes in the clean locker. HEPA vacuum and remove asbestos contaminated disposable protective clothing while still wearing respirators at the boundary of the asbestos work area and seal in impermeable bags or containers for disposal. Do not wear work clothing between home and work. Locate showers between the decontamination room and the clean room and require that all employees shower before changing into street clothes. Collect used shower water and filter with approved water filtration equipment to remove asbestos contamination. Dispose of filters and residue as asbestos waste. Discharge clean water to the sanitary system. Dispose of asbestos contaminated work clothing as asbestos contaminated waste. Decontamination units shall be physically attached to the asbestos control area. Build both a personnel decontamination unit and an equipment decontamination unit onto and integral with each asbestos control area.
3.1.2.4 Decontamination of Reusable Outer Protective Clothing
When reusable outer protective clothing is used, transport the double bagged clothing to a previously notified commercial/industrial decontamination facility for decontamination.
Perform non-destructive testing to determine the effectiveness of asbestos decontamination. If representative sampling is used, ensure the statistical validity of the sampling results. If representative sampling is used, reject any entire batch in which any of the pieces exceed 40 fibers per square millimeter. Inspect reusable protective clothing prior to use to ensure that it will provide adequate protection and is not or is not about to become ripped, torn, deteriorated, or damaged, and that it is not visibly contaminated.
Notify, in writing, all personnel involved in the decontamination of reusable outer protective clothing as indicated in 29 CFR 1926.1101.
3.1.2.5 Eye Protection
Provide goggles to personnel engaged in asbestos abatement operations when the use of a full face respirator is not required.
3.1.3 Warning Signs and Labels
Provide bilingual warning signs printed in English and in Spanish at all approaches to asbestos control areas. Locate signs at such a distance that personnel may read the sign and take the necessary protective steps required before entering the area. Provide labels
02 82 16.00 20
Section J – Attachment 2P Page 17 of 24 8 Feb 2010 and affix to all asbestos materials, scrap, waste, debris, and other products contaminated with asbestos.
3.1.3.1 Warning Sign
Provide vertical format conforming to 29 CFR 1926.200, and 29 CFR 1926.1101 minimum 20 by 14 inches displaying the following legend in the lower panel:
Legend Notation
Danger one inch Sans Serif
Gothic or Block
Asbestos one inch Sans Serif
Cancer and Lung Disease Hazard 1/4 inch Sans Serif
Authorized Personnel Only 1/4 inch Gothic
Respirators and Protective 1/4 inch Gothic
Clothing are Required in this Area
Spacing between lines shall be at least equal to the height of the upper of any two lines.
3.1.3.2 Warning Labels
Provide labels conforming to 29 CFR 1926.1101 of sufficient size to be clearly legible, displaying the following legend:
DANGER
CONTAINS ASBESTOS FIBERS
AVOID CREATING DUST
CANCER AND LUNG DISEASE HAZARD
BREATHING ASBESTOS DUST MAY
CAUSE SERIOUS BODILY HARM
3.1.4 Local Exhaust System
02 82 16.00 20
Section J – Attachment 2P Page 18 of 24 8 Feb 2010
Provide a local exhaust system in the asbestos control area in accordance with ANSI Z9.2 and 29 CFR 1926.1101 that will provide at least four air changes per hour inside of the negative pressure enclosure. Local exhaust equipment shall be operated 24 hours per day, until the asbestos control area is removed and shall be leak proof to the filter and equipped with HEPA filters. Maintain a minimum pressure differential in the control area of minus 0.02 inch of water column relative to adjacent, unsealed areas. Provide continuous 24-hour per day monitoring of the pressure differential with a pressure differential automatic recording instrument. In no case shall the building ventilation system be used as the local exhaust system for the asbestos control area. Filters on exhaust equipment shall conform to ANSI Z9.2 and UL 586. The local exhaust system shall terminate out of doors and remote from any public access or ventilation system intakes.
3.1.5 Tools
Vacuums shall be leak proof to the filter and equipped with HEPA filters. Filters on vacuums shall conform to ANSI Z9.2 and UL 586. Do not use power tools to remove asbestos containing materials unless the tool is equipped with effective, integral HEPA filtered exhaust ventilation systems. Remove all residual asbestos from reusable tools prior to storage or reuse.
3.1.6 Rental Equipment
If rental equipment is to be used, furnish written notification to the rental agency concerning the intended use of the equipment and the possibility of asbestos contamination of the equipment.
3.1.7 Glovebags
Submit written manufacturers proof that glovebags will not break down under expected temperatures and conditions.
3.2 WORK PROCEDURE
Perform asbestos related work in accordance with 29 CFR 1926.1101, 40 CFR 61-
SUBPART M, and as specified herein. Use wet or appropriate encapsulation procedures as listed in the asbestos hazard abatement plan and negative pressure enclosure techniques. Personnel shall wear and utilize protective clothing and equipment as specified herein. Eating, smoking, drinking, chewing gum, tobacco, or applying cosmetics shall not be permitted in the asbestos work or control areas. Personnel of other trades not engaged in the removal and demolition of asbestos containing material shall not be exposed at any time to airborne concentrations of asbestos unless all the personnel protection and training provisions of this specification are complied with by the trade personnel. Seal all roof top penetrations, except plumbing vents, prior to asbestos roofing work. Shut down the building heating, ventilating, and air conditioning system, cap the openings to the system, and provide temporary ventilation, prior to the commencement of
02 82 16.00 20
Section J – Attachment 2P Page 19 of 24 8 Feb 2010 asbestos work. Disconnect electrical service when encapsulation for wet removal is performed and provide temporary electrical service with verifiable ground fault circuit interrupter (GFCI) protection prior to the use of any water or encapsulant. If an asbestos fiber release or spill occurs outside of the asbestos control area, stop work immediately, correct the condition to the satisfaction of the Contracting Officer and CP including clearance sampling, prior to resumption of work.
3.2.1 Protection of Existing Work to Remain
Perform work without damage or contamination of adjacent work. Where such work is damaged or contaminated as verified by the Contracting Officer using visual inspection or sample analysis, it shall be restored to its original condition or decontaminated by the
Contractor at no expense to the Government as deemed appropriate by the Contracting
Officer. This includes inadvertent spill of dirt, dust, or debris in which it is reasonable to conclude that asbestos may exist. When these spills occur, stop work immediately. Then clean up the spill. When satisfactory visual inspection and air sampling results are obtained from the CP work may proceed at the discretion of the Contracting Officer.
3.2.2 Furnishings
Furniture and equipment will be removed from the area of work by the Government before asbestos work begins.
3.2.3 Precleaning
Wet wipe and HEPA vacuum all surfaces potentially contaminated with asbestos prior to establishment of an enclosure.
3.2.4 Asbestos Control Area Requirements
3.2.4.1 Negative Pressure Enclosure
Block and seal openings in areas where the release of airborne asbestos fibers can be expected. Establish an asbestos negative pressure enclosure with the use of curtains, portable partitions, or other enclosures in order to prevent the escape of asbestos fibers from the contaminated asbestos work area. Negative pressure enclosure development shall include protective covering of uncontaminated walls, and ceilings with a continuous membrane of two layers of minimum 6-mil plastic sheet sealed with tape to prevent water or other damage. Provide two layers of 6-mil plastic sheet over floors and extend a minimum of 12 inches up walls. Seal all joints with tape. Provide local exhaust system in the asbestos control area. Openings will be allowed in enclosures of asbestos control areas for personnel and equipment entry and exit, the supply and exhaust of air for the local exhaust system and the removal of properly containerized asbestos containing materials. Replace local exhaust system filters as required to maintain the efficiency of the system.
02 82 16.00 20
Section J – Attachment 2P Page 20 of 24 8 Feb 2010
3.2.4.2 Glovebag
The construction of a negative pressure enclosure is infeasible for the removal of TST material. Use alternate techniques as indicated in 29 CFR 1926.1101. Establish designated limits for the asbestos regulated area with the use of rope or other continuous barriers, and maintain all other requirements for asbestos control areas. The CP shall conduct personal samples of each worker engaged in asbestos handling (removal, disposal, transport and other associated work) throughout the duration of the project. If the quantity of airborne asbestos fibers monitored at the breathing zone of the workers at any time exceeds background or 0.01 fibers per cubic centimeter whichever is greater, stop work, evacuate personnel in adjacent areas or provide personnel with approved protective equipment at the discretion of the Contracting Officer. This sampling may be duplicated by the Government at the discretion of the Contracting Officer. If the air sampling results obtained by the Government differ from those obtained by the
Contractor, the Government will determine which results predominate. If adjacent areas are contaminated as determined by the Contracting Officer, clean the contaminated areas, monitor, and visually inspect the area as specified herein.
3.2.5 Removal Procedures
Wet asbestos material with a fine spray of amended water during removal, cutting, or other handling so as to reduce the emission of airborne fibers. Remove material and immediately place in 6 mil plastic disposal bags. Remove asbestos containing material in a gradual manner, with continuous application of the amended water or wetting agent in such a manner that no asbestos material is disturbed prior to being adequately wetted.
Where unusual circumstances prohibit the use of 6 mil plastic bags, submit an alternate proposal for containment of asbestos fibers to the Contracting Officer for approval. For example, in the case where both piping and insulation are to be removed, the Contractor may elect to wet the insulation, wrap the pipes and insulation in plastic and remove the pipe by sections. Asbestos containing material shall be containerized while wet. At no time shall asbestos material be allowed to accumulate or become dry. Lower and otherwise handle asbestos containing material as indicated in 40 CFR 61-SUBPART M.
3.2.5.1 Sealing Contaminated Items Designated for Disposal
Remove contaminated architectural, mechanical, and electrical appurtenances such as venetian blinds, full-height partitions, carpeting, duct work, pipes and fittings, radiators, light fixtures, conduit, panels, and other contaminated items designated for removal by completely coating the items with an asbestos lock-down encapsulant at the demolition site before removing the items from the asbestos control area. These items need not be vacuumed. The asbestos lock-down encapsulant shall be tinted a contrasting color. It shall be spray-applied by airless method. Thoroughness of sealing operation shall be visually gauged by the extent of colored coating on exposed surfaces. Lock-down encapsulants shall comply with the performance requirements specified herein.
3.2.5.2 Exposed Pipe Insulation Edges
Section J – Attachment 2P Page 21 of 24 8 Feb 2010
Contain edges of asbestos insulation to remain that are exposed by a removal operation.
Wet and cut the rough ends true and square with sharp tools and then encapsulate the edges with a 1/4 inch thick layer of non-asbestos containing insulating cement troweled to a smooth hard finish. When cement is dry, lag the end with a layer of non-asbestos lagging cloth, overlapping the existing ends by at least 4 inches. When insulating cement and cloth is an impractical method of sealing a raw edge of asbestos, take appropriate steps to seal the raw edges as approved by the Contracting Officer.
3.2.6 Encapsulation Procedures
3.2.6.1 Preparation of Test Patches
Install three test patches of encapsulant, as indicated. Use airless spray at the lowest pressure and as recommended by the encapsulant manufacturer. Follow exactly the manufacturer's instructions for thinning recommendations, application procedures and rates. Curing time shall be not less than five days or that recommended by the manufacturer, whichever is more. A test patch shall be 9 square feet in size.
3.2.6.2 Field Testing
Field test the encapsulation test patches in accordance with ASTM E 1494, paragraph
"Required Field Test," in the presence of the Contracting Officer. Keep a written record of the testing procedures and test results. Upon successful testing of the encapsulant, submit a signed statement to the Contracting Officer certifying that the encapsulant is suitable for installation on the particular asbestos containing material.
3.2.6.3 Large-Scale Application
Apply encapsulant using the same equipment and procedures as employed for the test patches. Keep the encapsulant material stirred to prevent settling. Keep a clean work area. Change pre-filters in the ventilation equipment as soon as they appear clogged by encapsulant aerosol or pressure differential drops below 0.02 inches of water.
3.2.7 Air Sampling
Sampling of airborne concentrations of asbestos fibers shall be performed in accordance with 29 CFR 1926.1101 and as specified herein. Sampling performed in accordance with
29 CFR 1926.1101 shall be performed by the CP. Sampling performed for environmental and quality control reasons shall be performed by the CP. Unless otherwise specified, use NIOSH Method 7400 for sampling and analysis. Monitoring may be duplicated by the Government at the discretion of the Contracting Officer. If the air sampling results obtained by the Government differ from those results obtained by the
Contractor, the Government will determine which results predominate.
3.2.7.1 Sampling Prior to Asbestos Work
Section J – Attachment 2P Page 22 of 24 8 Feb 2010
Provide area air sampling and establish the baseline one day prior to the masking and sealing operations for each demolition, removal or encapsulation site. Establish the background by performing area sampling in similar but uncontaminated sites in the building.
3.2.7.2 Sampling During Asbestos Work
The CP shall provide personal and area sampling as indicated in 29 CFR 1926.1101 and governing environmental regulations. In addition, provided the same type of work is being performed, provide area sampling at least once every work shift close to the work inside the enclosure, outside the clean room entrance to the enclosure, and at the exhaust opening of the local exhaust system. If sampling outside the enclosure shows airborne levels have exceeded background or 0.01 fibers per cubic centimeter, whichever is greater, stop all work, correct the condition(s) causing the increase, and notify the
Contracting Officer immediately. Where alternate methods are used, perform personal and area air sampling at locations and frequencies that will accurately characterize the evolving airborne asbestos levels.
The Contractor shall provide personal sampling as indicated in 29 CFR 1926.1101. At the same time the CP will provide area sampling close to the work inside the enclosure, outside the clean room entrance to the enclosure, and at the exhaust opening of the local exhaust system. In addition, provided the same type of work is being performed, the CP will provide area sampling once every work shift close to the work inside the enclosure, outside the clean room entrance to the enclosure, and at the exhaust opening of the local exhaust system. If sampling outside the enclosure shows airborne levels have exceeded background or 0.01 fibers per cubic centimeter, whichever is greater, stop all work, correct the condition(s) causing the increase, and notify the Contracting Officer immediately. Where alternate methods are used, perform personal and area air sampling at locations and frequencies that will accurately characterize the evolving airborne asbestos levels.
3.2.7.3 Sampling After Final Clean-Up (Clearance Sampling)
Provide area sampling of asbestos fibers using aggressive air sampling techniques as defined in the EPA 560/5-85-024 and establish an airborne asbestos concentration of less than 0.01 fibers per cubic centimeter after final clean-up but before removal of the enclosure or the asbestos work control area. After final cleanup and the asbestos control area is dry but prior to clearance sampling, the CP shall perform a visual inspection in accordance with ASTM E 1368 to ensure that the asbestos control and work area is free of any accumulations of dirt, dust, or debris. The asbestos fiber counts from these samples shall be less than 0.01 fibers per cubic centimeter or be not greater than the background, whichever is greater. Should any of the final samples indicate a higher value, the Contractor shall take appropriate actions to re-clean the area and shall repeat the sampling and analysis at the Contractor's expense.
02 82 16.00 20
Section J – Attachment 2P Page 23 of 24 8 Feb 2010
3.2.8 Lock-Down
Prior to removal of plastic barriers and after pre-clearance clean up of gross contamination, the CP shall conduct a visual inspection of all areas affected by the removal in accordance with ASTM E 1368. Inspect for any visible fibers, and to ensure that encapsulants were applied evenly and appropriately. A post removal (lock-down) encapsulant shall then be spray applied to ceiling, walls, floors and other areas exposed in the removal area. The exposed area shall include but not be limited to plastic barriers, furnishings and articles to be discarded as well as dirty change room, air locks for bag removal and decontamination chambers.
3.2.9 Site Inspection
While performing asbestos engineering control work, the Contractor shall be subject to on-site inspection by the Contracting Officer who may be assisted by or represented by safety or industrial hygiene personnel. If the work is found to be in violation of this specification, the Contracting Officer or his representative will issue a stop work order to be in effect immediately and until the violation is resolved. All related costs including standby time required to resolve the violation shall be at the Contractor's expense.
3.3 CLEAN-UP AND DISPOSAL
3.3.1 Housekeeping
Essential parts of asbestos dust control are housekeeping and clean-up procedures.
Maintain surfaces of the asbestos control area free of accumulations of asbestos fibers.
Give meticulous attention to restricting the spread of dust and debris; keep waste from being distributed over the general area. Use HEPA filtered vacuum cleaners. DO NOT
BLOW DOWN THE SPACE WITH COMPRESSED AIR. When asbestos removal is complete, all asbestos waste is removed from the work-site, and final clean-up is completed, the Contracting Officer will attest that the area is safe before the signs can be removed. After final clean-up and acceptable airborne concentrations are attained but before the HEPA unit is turned off and the enclosure removed, remove all pre-filters on the building HVAC system and provide new pre-filters. Dispose of filters as asbestos contaminated materials. Reestablish HVAC mechanical, and electrical systems in proper working order. The Contracting Officer will visually inspect all surfaces within the enclosure for residual material or accumulated dust or debris. The Contractor shall re-clean all areas showing dust or residual materials. If re-cleaning is required, air sample and establish an acceptable asbestos airborne concentration after re-cleaning. The
Contracting Officer must agree that the area is safe in writing before unrestricted entry will be permitted. The Government shall have the option to perform monitoring to determine if the areas are safe before entry is permitted.
3.3.2 Title to Materials
02 82 16.00 20
Section J – Attachment 2P Page 24 of 24 8 Feb 2010
All waste materials, except as specified otherwise, shall become the property of the
Contractor and shall be disposed of as specified in applicable local, State, and Federal regulations and herein.
3.3.3 Disposal of Asbestos
3.3.3.1 Procedure for Disposal
Collect asbestos waste, asbestos contaminated water, scrap, debris, bags, containers, equipment, and asbestos contaminated clothing which may produce airborne concentrations of asbestos fibers and place in sealed fiber-proof, waterproof, non-returnable containers (e.g. double plastic bags 6 mils thick, cartons, drums or cans).
Wastes within the containers must be adequately wet in accordance with 40 CFR 61-
SUBPART M. Affix a warning and Department of Transportation (DOT) label to each container including the bags or use at least 6 mils thick bags with the approved warnings and DOT labeling preprinted on the bag. The name of the waste generator and the location at which the waste was generated shall be clearly indicated on the outside of each container. Prevent contamination of the transport vehicle (especially if the transport vehicle is a rented truck likely to be used in the future for non-asbestos purposes).
This is the start of the file's text. The full file is on GovTribe.
Other files for this federal contract opportunity
Show all 46
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .