FA3047-10-R-0012 Atch 2AD-Division 7 (Specs - 07 54 19) 8 Feb 10 PVC Roofing

Text of this file

802 CONS/LGCA-3 FA3047-10-R-0012

Lackland AFB TX Roofing IDIQ

07 54 19

Section J – Attachment 2AD Page 1 of 20 8 Feb 2010

SECTION 07 54 19

POLYVINYL-CHLORIDE (PVC) ROOFING

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced.

The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D 4434(2009) Poly(Vinyl Chloride) Sheet Roofing

ASTM D 6754(2002) Standard Specification for Ketone Ethylene Ester Based Sheet

Roofing

ASTM E 108(2007a) Fire Tests of Roof Coverings

FM GLOBAL (FM)

FM 4470(1986; R 1992) Class I Roof Covers

FM P7825(2005) Approval Guide

NATIONAL ROOFING CONTRACTORS ASSOCIATION (NRCA)

NRCA 0405(2001; R 2003, 5th Ed) Roofing and Waterproofing Manual

UNDERWRITERS LABORATORIES (UL)

UL 790(2004; Rev thru Oct 2008) Test Methods for Fire Tests of Roof Coverings

UL RMSD(2009) Roofing Materials and Systems Directory

1.2 SYSTEM DESCRIPTION

Adhered or mechanically fastened PVC roof membrane system applied over insulation or

PVC membrane roofing manufacturer-accepted substrate. Provide adhered PVC roof membrane system only for repairs to existing fully adhered system. Incorporate air barrier in the roof assembly as specified in Section 07 22 00 ROOF AND DECK

INSULATION.

1.2.1 General

07 54 19

Section J – Attachment 2AD Page 2 of 20 8 Feb 2010

Roofing membrane sheet widths shall be consistent with membrane attachment methods and wind uplift requirements, and shall be as large as practical. In order to minimize joints and 3-way overlaps, prefabricated sheets are not accepted. Provide membrane which is free of defects and foreign material. Coordinate flashing work to permit continuous roof-surfacing operations. Insulation shall be applied and weatherproofed on the same day.

1.2.2 Fire Resistance

Complete roof system assembly shall be:

a. Class A rated in accordance with ASTM E 108, FM 4470, or UL 790.

b. Listed as part of Fire-Classified roof deck construction in the UL RMSD or Class I roof deck construction in the FM P7825 or FM RoofNav (www. roofnav.com).

FM or UL approved components of the roof covering assembly shall bear the appropriate

FM or UL label.

1.2.3 Wind Uplift Resistance

Complete roof covering assembly, including insulation, shall be rated Class 1 and configured in accordance with FM RoofNav (www. roofnav.com) or FM P7825 and capable of withstanding an uplift pressure determined in accordance with ASCE 7-05 for field, perimeter and corner zones and as outlined in FM Loss Prevention Data sheet 1-29 revised 2009. Wind uplift calculator is available at https://roofnav.fmglobal.com. Non-rated systems shall not be installed. Submit wind load, wind uplift calculations, and engineering calculations.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

Detail Drawings; G

Roof plan depicting wind loads and boundaries of enhanced perimeter and corner attachments of roof system components, location of perimeter half-sheets, spacing of perimeter, corner, and infield fasteners, as applicable. The drawing shall reflect the project roof plan of each roof level and conditions indicated.

SD-03 Product Data

Section J – Attachment 2AD Page 3 of 20 8 Feb 2010

PVC Roofing Membrane; G

Bonding Adhesive; G

Flashing; G

Membrane Fasteners and Plates; G

Roof Insulation; G

Pre-manufactured accessories; G

Water Cutoffs

Information Card; G

Submit data as required by Section 07 22 00 ROOF AND DECK INSULATION together with requirements of this section. Data shall include written acceptance by the roof membrane manufacturer of the insulation and other products and accessories to be provided by and warranted under the full system guarantee of the roof membrane manufacturer. Provide products as listed in the applicable wind uplift and fire rating classification listings.

SD-05 Design Data

Wind uplift calculations; G

Engineering calculations validating the wind resistance of roof system.

SD-07 Certificates

Qualification of ENERGY STAR-labeled PVC; G

Certificate from PVC membrane roofing manufacturer certifying that the roof membrane, meets specified requirements.

Qualifications of Applicator; G

Certificate stating that the applicator meets requirements specified.

Wind Uplift Resistance; G

Fire Resistance; G

Roof system assembly wind uplift and fire rating classification listings.

Section J – Attachment 2AD Page 4 of 20 8 Feb 2010

Minimum Polymer Thickness; G

Certification from PVC membrane manufacturer that the proposed PVC membrane roofing product meets the minimum polymer thickness specified.

Warranty; G

Sample certificate

SD-08 Manufacturer's Instructions

Application Method; G

Instructions including pattern and frequency of mechanical attachments required in the field for roof, corners, and perimeters to provide for the calculated wind resistance

Membrane Flashing; G

Perimeter Attachment

Auxiliary Fasteners

Pre-manufactured accessories

Cold weather; G

Detailed application instructions and standard manufacturer drawings altered as required by these specifications. Explicitly identify in writing, differences between manufacturer's instructions and the specified requirements.

SD-10 Operation and Maintenance Data

Instructions to Government Personnel

Copies of Material Safety Data Sheets for maintenance/repair materials.

1.4 QUALITY ASSURANCE

1.4.1 Qualification of ENERGY STAR-labeled PVC

ENERGY STAR labeled PVC membrane roofing product shall have at least 5 years of demonstrated performance experience.

1.4.2 Qualifications of Applicator

07 54 19

Section J – Attachment 2AD Page 5 of 20 8 Feb 2010

PVC membrane roofing system Applicator shall be approved, authorized, or licensed in writing by the PVC membrane roof manufacturer and shall have a minimum of three years experience as an approved, authorized, or licensed applicator with that manufacturer's PVC membrane roofing materials and be approved at a level capable of providing the specified warranty. The applicator shall supply the names, locations and client contact information of 5 projects of similar size and scope that the applicator has constructed using the manufacturer's roofing products submitted for this project within the previous three years.

1.4.3 Conformance and Compatibility

The entire roofing and flashing system (including edge metal) shall be in accordance with specified and indicated requirements, including fire and wind resistance requirements.

Work not specifically addressed and any deviation from specified requirements shall be in general accordance with recommendations of the NRCA 0405, membrane manufacturer published recommendations and details and shall be compatible with surrounding components and construction. Any deviation from specified or indicated requirements shall be submitted to the Contracting Officer and PVC roof membrane manufacturer for approval prior to installation.

1.4.4 Preroofing Conference

After approval of submittals and before performing roofing and insulation system installation work, hold a preroofing conference to review the following:

a. Drawings, specifications and submittals related to the roof work;

b. Roof system components installation;

c. Procedure for the roof manufacturer's technical representative's onsite inspection and acceptance of the roofing substrate, the name of the manufacturer's technical representatives, the frequency of the onsite visits, distribution of copies of the inspection reports from the manufacturer's technical representative;

d. Contractor's plan for coordination of the work of the various trades involved in providing the roofing system and other components secured to the roofing; and

e. Quality control plan for the roof system installation;

f. Safety requirements.

Preroofing conference scheduling shall be coordinated with the Contracting Officer. The conference shall be attended by the Contractor, the Contracting Officer's designated personnel, personnel directly responsible for the installation of roofing and insulation, flashing and sheet metal work, other trades interfacing with the roof work, and a representative of the roofing materials manufacturer. Before beginning roofing work, 07 54 19

Section J – Attachment 2AD Page 6 of 20 8 Feb 2010 provide a copy of meeting notes and action items to all attending parties. Note action items requiring resolution prior to start of roof work.

1.5 DELIVERY, STORAGE, AND HANDLING

1.5.1 Delivery

Deliver materials in their original, unopened containers or wrappings with labels intact and legible. Where materials are covered by a referenced specification number, the labels shall bear the specification number, type, class, and shelf life expiration date where applicable. Deliver materials in sufficient quantity to allow continuity of work.

1.5.2 Storage

Store and protect materials from damage and weather in accordance with manufacturer's instructions, except as specified otherwise. Keep materials clean and dry. Store and maintain adhesives, sealants, primers and other liquid materials above 60 degrees F.

Insulated hot boxes or other enclosed warming devices may be required in cold weather subject to PVC membrane roofing manufacturer's printed instruction. Mark and remove damaged materials from the site. Use pallets to support and canvas tarpaulins to completely cover material materials stored outdoors. Do not use polyethylene as a covering. Locate materials temporarily stored on the roof in approved areas, and distribute the load to stay within the live load limits of the roof construction. Remove unused materials from the roof at the end of each days work.

1.5.3 Handling

Prevent damage to roll materials. Damaged materials shall not be installed in the work.

Select and operate material handling equipment so as not to damage materials or applied roofing. Do not use materials contaminated by exposure, incompatible materials or moisture. Remove contaminated materials from the site. When hazardous materials are involved, conform with the special precautions of the manufacturer. Adhesives may contain petroleum distillates and may be extremely flammable; prevent personnel from breathing vapors, and do not use near sparks or open flame.

1.6 ENVIRONMENTAL REQUIREMENTS

Follow manufacturer's printed instructions for installation during cold weather conditions.

1.7 SEQUENCING

Coordinate the work with other trades to ensure that components which are to be secured to or stripped into the roofing system are available and that permanent flashing and counterflashing are installed as the work progresses. Ensure temporary protection measures are in place to preclude moisture intrusion or damage to installed materials.

07 54 19

Section J – Attachment 2AD Page 7 of 20 8 Feb 2010

Application of roofing shall immediately follow application of insulation as a continuous operation. Roofing operations shall be coordinated with insulation work so that all roof insulation applied each day is covered with roof membrane installation the same day.

1.8 WARRANTY

Provide a Full System Roof Warranty covering all PVC membrane roof system components as well as their installation workmanship and meeting all specified requirements. Revision or amendment to standard full system PVC membrane manufacturer warranty shall be provided as required to comply with the specified requirements.

1.8.1 PVC Membrane Manufacturer's Full Roof System Warranty

Furnish roof membrane manufacturer's 20-year, no dollar limit, full roof system materials and installation workmanship warranty, including all flashing, insulation, and accessory materials necessary to construct a complete, watertight roof system. The warranty shall run directly from the roof system manufacturer to the Government and commence at time of Government's acceptance of the roof work. The warranty shall state that:

a. If within the warranty period the roof system, as installed for its intended use in the normal climatic and environmental conditions of the facility, becomes non-watertight, shows evidence of moisture intrusion within the assembly, splits, tears, cracks, delaminates, separates at the seams, shrinks to the point of significant bridging or tenting membrane at transitions, or shows evidence of excessive weathering due to defective materials or installation workmanship, the repair or replacement of the defective and damaged materials of the roof system assembly and correction of defective workmanship shall be the responsibility of the roof membrane manufacturer. All costs associated with the repair or replacement work shall be the responsibility of the roof membrane manufacturer.

b. When the manufacturer and his approved applicator fail to perform the repairs within

72 hours of notification, emergency temporary repairs performed by others shall not void the warranty.

1.8.2 Roofing System Installer Warranty

The roof system installer shall warrant for a period of not less than five (5) years that the roof system, as installed, is free from defects in installation workmanship, to include the roof membrane, flashing, insulation, accessories, all attachments, including installation of all PVC membrane manufacturer-supplied edge metal which is always integral to a complete watertight roof system assembly. The warranty shall run directly to the

Government. Correction of defective workmanship and replacement of damaged or affected materials shall be the responsibility of the roof system installer. All costs associated with the repair or replacement work shall be the responsibility of the installer.

07 54 19

Section J – Attachment 2AD Page 8 of 20 8 Feb 2010

1.8.3 Continuance of Warranty

Any repair or replacement work that becomes necessary within the warranty period shall be approved by the roof membrane manufacturer and accomplished in a manner so as to restore the integrity of the roof system assembly and the validity of the roof membrane manufacturer warranty for the remainder of the manufacturer warranty period.

1.8.4 Single-Source Contract Liability Warranty

The specified, single-source contract liability warranty of a PVC membrane roofing system manufacturer shall be furnished to the Government upon project completion. The single-source contract liability warranty shall encompass all roof system components' warranty performance coverage's, including all performance guarantees for roof system materials, roof system design and all roof system installation labor and workmanship.

The single-source contract liability warranty shall be a Full Roof System Warranty that is issued by either the PVC membrane roof system manufacturer, or by a direct affiliate of the PVC membrane roof system manufacturer (100 percent owned affiliate), or by an agent of the PVC membrane roof system manufacturer possessing the authority to contractually bind the PVC membrane roof system manufacturer (manufacturer, affiliate and agent are collectively referred to as "Roofing System Supplier") and to, at said agent's discretion, underwrite and/or provide for insurance covering all of the respective warranty obligations of the PVC membrane manufacturer's Full Roof System Warranty.

a. The Government intends to sign a contract binding all warranty and associated roof system performance guarantees of the roofing system directly with the PVC membrane roofing manufacturer, or it's subsidiary, or an exclusive agent capable of enjoining said

PVC membrane manufacturer; and

b. This roofing system shall be applied only by a roofing system Applicator authorized by the PVC membrane roofing manufacturer prior to bid; and

c. The roofing system Applicator shall arrange with, and make arrangements to the satisfaction and discretion of the PVC Roofing System Supplier, to have the services of a

Technical Field Representative on site full time to observe the total roof application, including removal of pre-existing roofing (if applicable). The Technical Field

Representative shall provide written daily reports to the Roofing System Supplier and

Applicator. The roofing system Applicator shall include the cost of the full-time

Technical Field Representative in his/her bid price; and

d. Submit bids with approved detail drawings and specifications approved and furnished by the PVC membrane manufacturer, and

e. There shall be no deviation made from the contract specification or the approved shop/detail drawings without prior written approval by the both PVC membrane roofing material manufacturer/subsidiary and by the Government; and

07 54 19

Section J – Attachment 2AD Page 9 of 20 8 Feb 2010

f. Complete all work by personnel trained and authorized by the PVC membrane roof

PART 2 PRODUCTS

2.1 MATERIALS

a. Coordinate with other specification sections related to the roof work. Furnish a combination of specified materials that comprise a roof system acceptable to the roof membrane manufacturer and meeting specified requirements. Provide materials free of defects and suitable for the service and climatic conditions of the installation. All warranted guaranteed by components shall be PVC roof membrane manufacturer, including but not limited to all insulation, coverboards, accessories, adhesives and edge metal.

b. For each roof, furnish a typewritten information card for facility records and a card laminated in plastic and framed for interior display at roof access point, or a photoengraved 0.032 inch thick aluminum card for exterior display. Card shall be 8 1/2 by 11 inches minimum. Information card shall identify facility name and number;

location; contract number; approximate roof area; detailed roof system description, including deck type, membrane, number of plies, method of application, manufacturer, insulation and cover board system and thickness; presence of tapered insulation for primary drainage, presence of vapor retarder; date of completion; installing Contractor identification and contact information; membrane manufacturer warranty expiration, warranty reference number, and contact information. Install card at roof top or access location as directed by the Contracting Officer and provide a paper copy to the

Contracting Officer.

2.1.1 Bonding Adhesive

Provide PVC membrane manufacturer's standard membrane adhesive, as supplied by roof membrane manufacturer, and recommended by the manufacturer's printed data for bonding of PVC membrane materials to acceptable insulation, wood, metal, concrete or other acceptable substrate materials. Provide PVC membrane manufacturer's low volatile organic compound (VOC) membrane adhesive on occupied buildings. Bonding adhesive shall not be used to bond membrane materials to each other.

2.1.2 Water Cutoff Mastic/Water Block

As supplied by the roof membrane manufacturer and recommended by the manufacturer's printed data.

2.1.3 Membrane Flashing

Membrane flashing, including self-adhering membrane flashing, perimeter flashing, flashing around roof penetrations and prefabricated pipe seals, shall be minimum polymer

07 54 19

Section J – Attachment 2AD Page 10 of 20 8 Feb 2010 thickness 0.060 inch reinforced PVC, and shall be utilized as recommended and supplied by the roof membrane manufacturer for 20 year warranties.

2.1.4 Membrane Fasteners and Plates

Coated, corrosion-resistant fasteners as recommended and supplied by the PVC roof membrane manufacturer and meeting the requirements of FM 4470 and FM RoofNav

(www. roofnav.com) or FM P7825 for Class I roof deck construction and the wind uplift resistance calculated as described in 1.2.3 Wind Uplift Resistance. Fasteners and Plates to be supplied and warranted for the substrate type(s) by PVC membrane manufacturer and recommended by PVC membrane manufacturer's printed data.

2.1.4.1 Stress Plates, Bar or Rail for Fasteners

Corrosion-resistant stress plates as recommended by the roof membrane manufacturer's printed instructions and meeting the requirements of FM 4470 must be utilized and must be supplied by PVC roof membrane manufacturer. Stress plates shall be formed to prevent dishing or cupping. Manufacturer-supplied anchoring bar or rails may be utilized for high wind conditions.

2.1.4.2 Auxiliary Fasteners

Corrosion resistance screws, nails, or anchors must be suitable for intended attachment purpose and be recommended and supplied for use by the PVC roof membrane

2.1.5 Pre-manufactured Accessories

Pre-manufactured accessories shall be manufacturer's standard for intended purpose, must comply with applicable specification section, be compatible with the membrane roof system and approved for use and supplied by the PVC roof membrane manufacturer.

Pre-fabricated Curbs shall be heavy AZ55 galvalume with minimum 4 inch flange for attachment to roof nailers. Curbs shall provide minimum height of 10 inches above the finished roof membrane surface.

2.1.6 PVC Walk Tread and Precast Concrete Paver Block Walkways

Provide either of the following:

2.1.6.1 PVC Walk Tread

Scrim reinforced 0.096 inch thickness PVC membrane with a textured surface, compatible with and supplied by manufacturer of the PVC roof membrane.

2.1.6.2 Precast Concrete Paver Block

07 54 19

Section J – Attachment 2AD Page 11 of 20 8 Feb 2010

Precast concrete blocks (subject always to structutal capacity), 24 by 24 inch, without sharp edges and projections, and with weight in accordance with structural capacity and wind uplift calculations.

2.1.7 Elevated Metal Walkways and Platforms

As specified in Section 05 50 13 MISCELLANEOUS METAL FABRICATIONS, and as approved by the roof membrane manufacturer.

2.1.8 Roof Insulation

Insulation system and facer material shall be compatible with membrane application specified and be approved and supplied by the PVC membrane roof manufacturer and as specified in Section 07 22 00 ROOF AND DECK INSULATION. PVC roof membrane shall be installed on perlite, polystyrene, or standard wood fiber insulation board substrates.

2.1.9 Wood Products

As specified in Section 06 10 00 ROUGH CARPENTRY, except that fire retardant treated materials shall not be in contact with PVC membrane or PVC accessory products, unless approved by the membrane manufacturer and the Contracting Officer.

2.2 ENERGY STAR-Labeled, Reinforced, PVC Membrane

Reinforced polyvinyl chloride (PVC) membrane shall contain fibers or scrim, and shall comply with ASTM D 4434, Type II, Grade I, Type III, Type IV or Type II, Grade I or

Type III or Type IV, fleece backed, or ASTM D 6754, and in all cases shall provide

0.060 inch minimum thickness for adhered or mechanically fastened application. Not withstanding the ASTM standards referenced, reinforced PVC roof membranes provided under this section shall have the minimum, labeled thickness specified. PVC membrane thickness specified herein is exclusive of backing material on the bottom of fleece-backed membrane. Principal polymer used in manufacture of the membrane sheet shall be PVC.

Width and length of PVC membrane roofing sheet shall be consistent with membrane attachment methods and wind uplift requirements, and shall be as large as practical. In order to minimize joints and 3-way overlaps, prefabricated sheets are not accepted.

Maximum reinforced PVC membrane roofing sheet dimensions to be the maximum width obtainable from PVC membrane roof manufacturer in order to minimize seams in the field of the roof.

PART 3 EXECUTION

3.1 EXAMINATION

Ensure that the following conditions exist prior to application of the roofing materials:

07 54 19

Section J – Attachment 2AD Page 12 of 20 8 Feb 2010

a. Drains, curbs, control joints, expansion joints, perimeter walls, roof penetrating components, and equipment supports are in place.

b. Surfaces are rigid, clean, dry, smooth, and free from cracks, holes, and sharp changes in elevation.

c. Substrate is sloped to provide positive drainage.

d. Walls and vertical surfaces are constructed to receive counterflashing, and will permit mechanical fastening of the base flashing materials.

e. Treated wood nailers are in place on non-nailable surfaces, to permit nailing of base flashing at minimum height of 8 inches above finished roofing surface.

f. Pressure-preservative treated wood nailers are fastened in place at eaves, gable ends, openings, and intersections with vertical surfaces for securing of membrane, edging strips, attachment flanges of sheet metal, and roof fixtures. Embedded nailers are flush with deck surfaces. Surface-applied nailers are the same thickness as the roof insulation.

g. PVC materials are not in contact with fire retardant treated wood, except as approved by the PVC membrane roof manufacturer and Contracting Officer.

h. Venting shall be provided if required by, and in accordance with the cellular lightweight concrete manufacturer's requirements and recommendations.

i. Exposed nail heads in wood substrates are properly set. Warped and split boards and sheets have been replaced. There are no cracks or end joints 1/4 inch in width or greater.

Joints in plywood substrates are taped or otherwise sealed to prevent air leakage from the underside.

j. Insulation boards are installed smoothly and evenly, and are not broken, cracked, or curled. There are no gaps in insulation board joints exceeding 1/4 inch in width.

Insulation is attached as specified in Section 07 22 00 ROOF AND DECK

INSULATION. Insulation is being roofed over on the same day the insulation is installed.

3.2 APPLICATION METHOD

Apply entire PVC membrane roofing utilizing mechanically fastened application method.

Apply adhered PVC root membrane system only for repairs to existing fully adhered system. Apply roofing materials as specified herein unless approved otherwise by the

Contracting Officer.

3.2.1 Special Precautions

07 54 19

Section J – Attachment 2AD Page 13 of 20 8 Feb 2010

a. Do not dilute coatings or sealants unless specifically recommended by the material manufacturer's printed application instructions. Do not thin liquid materials or cleaners used for cleaning PVC sheet.

b. Keep liquids in airtight containers, and keep containers closed except when removing materials.

c. Use liquid components, including adhesives, within their shelf life period. Store adhesives at 60 to 80 degrees F prior to use. Avoid excessive adhesive application and adhesive spills, as they can be destructive to some thermoplastic sheets and insulations;

follow adhesive manufacturer's printed application instructions. Mix and use liquid components in accordance with label directions and manufacturer's printed instructions.

d. Provide clean, dry cloths or pads for applying membrane cleaners and cleaning of membrane.

e. Do not use heat guns or open flame to expedite drying of adhesives or primers.

f. Require workmen and others who walk on the membrane to wear clean, soft-soled shoes to avoid damage to roofing materials.

g. Do not use equipment with sharp edges which could puncture the PVC membrane roofing sheet.

h. Shut down air intakes and any related mechanical systems and seal open vents and air intakes when applying solvent-based materials in the area of the opening or intake.

Coordinate shutdowns with the Contracting Officer.

3.2.2 PVC Roofing Membrane

Only felt-backed membrane shall be placed directly on concrete deck or other hard surface which may otherwise damage the membrane, absent the felt backing. Non-felt-backed PVC membrane roofing sheet shall not be placed directly on concrete deck or other hard surface which may damage the membrane. Membrane shall be overlapped a minimum of 3 inches at sides for adhered applications and 5.5-7 inches for mechanically fastened applications and minimum 4 inches at ends. Where possible, direction of laps shall allow water to flow over and not into the lap. Membrane joints shall be free of wrinkles and fishmouths. The entire length of hot-air-welded seams shall be probe-tested and corrected during the day of installation. Defective areas shall be re-welded.

Wrinkles, fishmouths, or damaged areas shall be cut out and the area covered with membrane using a continuous hot-air-welded seam on all sides. Repairs shall be probe-tested for continuity. Hot-air-welded seams are to be accomplished in accordance with the PVC membrane roofing manufacturer's published requirements.

3.2.2.1 Nailing

07 54 19

Section J – Attachment 2AD Page 14 of 20 8 Feb 2010

Membrane shall be fastened to nailers in accordance with the membrane manufacturer's approved instructions. Unless otherwise specified, nails shall be staggered on 4 inch centers maximum; screws for sheet metal shall be staggered on 8 inch centers maximum;

and a row of fasteners shall be at least 1/2 inch from edges of sheet metal.

3.2.2.2 Flashing

Roof edges, projections through the roof and changes in roof planes shall be flashed. The seam shall be sealed a minimum of 3 inches beyond the fasteners which attach the membrane to nailers. The installed flashing's shall be secured at the top of the flashing a maximum of 12 inches on centers under the counterflashing or cap. Where possible, prefabricated components shall be used for pipe seals and flashing accessories.

3.2.2.3 Expansion Joints

Expansion joints shall be covered using Prefabricated covers or elastomeric flashing in accordance with the recommendations of the manufacturer.

3.2.2.4 Cutoffs

If work is terminated prior to weatherproofing the entire roof, the membrane shall be sealed to the roof deck. Flutes in metal decking shall be sealed off along the cutoff edge.

Membrane shall be pulled free or cut to expose the insulation when resuming work and cut insulation sheets used for fill-in shall be removed. Asphalt or coal-tar products shall not be used for sealing.

3.2.2.5 Walkways

Walkways shall be installed on a loose-laid pad of the membrane material extending at least 1 inch beyond the walkway material, and as specified by the manufacturer. Stone ballast shall not be placed below or above walkways.

3.2.3 Adhered Membrane Application

Layout membrane and side lap adjoining sheets in accordance with membrane manufacturer's printed installation instructions. Allow for sufficient membrane to form proper membrane terminations. Remove dusting agents and dirt from membrane and substrate areas where bonding adhesives are to be applied. Apply specified adhesive evenly and continuously to substrate and underside of sheets at rates recommended by the roof membrane manufacturer's printed application instructions. When adhesive is spray applied, roll with a paint roller to ensure proper contact and coverage. Do not apply bonding adhesive to surfaces of membrane in seam or lap areas. Allow adhesive to flash off or dry to consistency prescribed by manufacturer before adhering sheets to the substrate. When adhesive is peel & stick release paper-activated, follow manufacturer's printed instructions. Roll each sheet into adhesive slowly and evenly to avoid wrinkles;

broom or roll the membrane to remove air pockets and fishmouths and to ensure

07 54 19

Section J – Attachment 2AD Page 15 of 20 8 Feb 2010 adequately uniform bonding of sheet to substrate. Form field hot-air-welded laps or seams as specified and ensure that hot-air welded dimension is at width required by the membrane manufacturer's installation instructions. Check all seams and continuous hot-air-weld of all seams and lap seals.

3.2.4 Mechanically Fastened Membrane Application

Layout membrane and lap adjoining sheets in accordance with membrane manufacturer's printed instructions such that the minimum recommended seam width is maintained and to ensure that seam width is as required by tested assembly meeting specified wind resistance requirements. Account for additional overlap required for placement of fasteners and plates or battens beyond the closed seam. Allow for sufficient membrane to form proper membrane terminations. Ensure membrane is free of wrinkles and ridges in the installation. Mechanically secure the membrane sheet with specified fasteners in the lap area. Space fasteners as required to provide the wind uplift resistance specified and in accordance with submitted fastener patterns for the field, corner, and perimeter roof areas. Set fasteners firm to plate or batten. Form field hot-air-welded seams and laps and/or coverstrips, as specified. Check all seams and ensure full/continuous lap seal.

3.2.5 Perimeter Attachment

Adhesive bond or mechanically secure roof membrane sheet at roof perimeter in a manner to comply with wind resistance requirements and in accordance with membrane manufacturer's printed application instructions. When adhesively bonding a mechanically fastened system in perimeter areas, the perimeter boundary of the adhesive bond shall be the same as the boundary required for additional perimeter mechanical fastening to meet wind resistance requirements.

3.2.6 Securement at Base Tie-In Conditions

Mechanically fasten the roof membrane at penetrations, at base of curbs and walls, and at all locations where the membrane turns and angles greater than 4 degrees (1:12). Space fasteners a maximum of 12 inches on center, except where more frequent attachment is required to meet specified wind resistance or where recommended by the roof membrane manufacturer. Cover over fasteners with a layer of flashing material. Hot-air-weld all seams of flashing material as recommended by the roof membrane manufacturer's printed data.

3.2.7 Membrane Flashing

a. Install flashing and flashing accessories as the roof membrane is installed. Apply flashing to cleaned surfaces and as recommended by the roof membrane manufacturer and as specified. Utilize reinforced PVC membrane flashing and prefabricated accessory flashing's as recommended by the roof membrane manufacturer.

07 54 19

Section J – Attachment 2AD Page 16 of 20 8 Feb 2010

b. Completely adhere flashing sheets in place. Hot-air-weld the seams of flashing membrane in the same manner as roof membrane, except as otherwise recommended by the membrane manufacturer's printed instructions and approved by the Contracting

Officer. Mechanically fasten top edge of base flashing with manufacturer recommended termination bar fastened at maximum 12 inches on center. Sheet metal counter-flashing shall be installed over the termination bar in the completed work. Mechanically fasten top edge of base flashing for all other terminations in a manner recommended by the roof membrane manufacturer. Apply reinforced PVC flashing membrane over top of exposed nailers and blocking and to overlap top edge of base flashing installation at curbs, parapet walls, expansion joints and as otherwise indicated. Metal flashing's are specified under

Section 07 60 00 FLASHING AND SHEET METAL.

c. Flashing for roof drains, are specified in Section 07 60 00 FLASHING AND SHEET

METAL. Provide a tapered insulation sump into the drain bowl area. Tapered slope shall not exceed 15 degrees (3:12) for fiberglass reinforced PVC membrane. Tapered insulation shall have surface suitable for adhering membrane in the drain sump area.

Avoid field seams running through or within 24 inches of roof drain, or as otherwise recommended by the roof membrane manufacturer.

d. Adhere the membrane to the tapered insulation in the drain sump area. Apply PVC membrane manufacturer's compatible sealant and extend membrane sheets over edge of drain bowl opening at the roof drain deck flange in accordance with membrane manufacturer's printed application instructions. Membrane shall be free of wrinkles and folds in the drain area. Securely clamp membrane in the flashing clamping ring. Ensure membrane is cut to within 3/4 inch of inside rim of clamping ring to maintain drainage capacity. Do not cut back to bolt holes.

3.2.8 Pre-fabricated Curbs

Prefabricated curbs shall be securely anchored to nailer or other base substrate and flashed with PVC membrane flashing materials.

3.2.8.1 Set-On Accessories

Where pipe or conduit blocking, supports and similar roof accessories, or isolated paver block, are set on the membrane, adhere reinforced membrane or walkpad material, as recommended by the roof membrane manufacturer, to bottom of accessories prior to setting on roofing membrane. Specific method of installing set-on accessories must permit normal movement due to expansion, contraction, vibration, and similar occurrences without damaging roofing membrane. Do not mechanically secure set-on accessories through roofing membrane into roof deck substrate.

3.2.8.2 Lightning Protection

07 54 19

Section J – Attachment 2AD Page 17 of 20 8 Feb 2010

Lightning protection system components shall be flashed or attached to the roof membrane in a manner acceptable to the PVC membrane roof manufacturer and compliant with Code requirements.

3.2.9 Roof Walkways

Install walkways at roof access points and where otherwise indicated for traffic areas and for access to mechanical equipment, in accordance with the PVC membrane roof manufacturer's printed instructions.

3.2.10 Elevated Metal Walkways and Platforms

Install over completed roof system in accordance with Section 05 50 13

MISCELLANEOUS METAL FABRICATIONS. Provide for protection of roof membrane by placing reinforced membrane or walkpad material, or other material approved by the PVC membrane roof manufacturer and Contracting Officer, at all surface bearing support locations.

3.2.11 Isolated Paver Blocks

Install paver blocks where indicated and as necessary to support surface bearing items traversing the roof area. Paver block shall be set on a layer of reinforced PVC membrane or walkway applied over the completed PVC roof membrane.

3.2.12 Correction of Deficiencies

Where any form of deficiency is found, additional measures shall be taken as deemed necessary by the Contracting Officer to determine the extent of the deficiency and corrective actions shall be as directed by the Contracting Officer.

3.2.13 Clean Up

Remove debris, scraps, containers and other rubbish and trash resulting from installation of the roofing system from job site each day.

3.3 PROTECTION OF APPLIED ROOFING

At the end of the day's work and when precipitation is imminent, protect applied membrane roofing system from water intrusion.

3.3.1 Water Cutoffs

Straighten insulation line using loose-laid cut insulation sheets and seal the terminated edge of the roof membrane system in an effective manner. Seal off flutes in metal decking along the cutoff edge. Remove the water cut-offs to expose the insulation when resuming work, and remove the insulation sheets used for fill-in.

Section J – Attachment 2AD Page 18 of 20 8 Feb 2010

3.3.2 Temporary Flashing for Permanent Roofing

Provide temporary flashing at drains, curbs, walls and other penetrations and terminations of roofing sheets until permanent flashings can be applied. Remove temporary flashing before applying permanent flashing.

3.3.3 Temporary Walkways, Runways, and Platforms

Do not permit storing, walking, wheeling, and trucking directly on applied roofing system. Provide temporary walkways, runways, and platforms of smooth clean boards, mats or planks as necessary to avoid damage to applied roofing materials, and to distribute weight to conform to live load limits of roof construction. Use rubber-tired equipment for roofing work.

3.4 FIELD QUALITY CONTROL

3.4.1 Construction Monitoring

During progress of the roof work, make visual inspections as necessary to ensure compliance with specified parameters. Additionally, verify the following:

a. Equipment is in working order. Metering devices are accurate.

b. Materials are not installed in adverse weather conditions.

c. Substrates are in acceptable condition, in compliance with specification, prior to application of subsequent materials.

(1) Nailers and blocking are provided where and as needed.

(2) Insulation substrate is smooth, properly secured to its substrate, and without excessive gaps prior to membrane application.

(3) The proper number, type, and spacing of fasteners are installed.

(4) Materials comply with the specified requirements.

(5) All materials are properly stored, handled and protected from moisture or other damages. Liquid components are properly mixed prior to application.

(6) Adhesives are applied uniformly to both mating surfaces and checked for proper set prior to bonding mating materials. Mechanical attachments are spaced as required, including additional fastening of membrane in corner and perimeter areas as required.

07 54 19

Section J – Attachment 2AD Page 19 of 20 8 Feb 2010

(7) Membrane is properly overlapped.

(8) Membrane seaming is as specified by PVC membrane manufacturer. All seams are checked at the end of each work day.

(9) Applied membrane is inspected and repaired as necessary prior to paver installation.

(10) Membrane is adhered without ridges, wrinkles, kinks, fishmouths.

(11) Installer adheres to specified and detailed application parameters.

(12) Associated flashing's and sheet metal are installed in a timely manner in accord with the specified requirements.

(13) Temporary protection measures are in place at the end of each work shift.

3.4.2 Manufacturer's Inspection

Manufacturer's technical representative shall be present full time when Single Source

Contract Liability Warranty is desired during the installation for purposes of reviewing materials installation practices and adequacy of work in place. After each inspection, a report, signed by the manufacturer's technical representative shall be submitted by the roofing Contractor to the Contracting Officer within 3 working days. The report shall note overall quality of work, deficiencies and any other concerns, and recommended corrective action.

3.5 INSTRUCTIONS TO GOVERNMENT PERSONNEL

Furnish written and verbal instructions on proper maintenance procedures to designated

Government personnel. Furnish instructions by a competent representative of the roof membrane manufacturer and include a minimum of 4 hours on maintenance and emergency repair of the membrane. Include a demonstration of membrane repair, and give sources of required special tools. Furnish information on safety requirements during maintenance and emergency repair operations.

3.6 ROOF DRAIN TEST

After completing roofing but prior to Government acceptance, perform the following test for watertightness. Plug roof drains and fill with water to edge of drain sump for 8 hours.

Do not plug secondary overflow drains at the same time as adjacent primary drain. To ensure some drainage from roof, do not test all drains at same time. Measure water at beginning and end of the test period. When precipitation occurs during test period, repeat test. When water level falls, remove water, thoroughly dry, and inspect installation;

repair or replace roofing at drain to provide for a properly installed watertight flashing seal. Repeat test until there is no water leakage.

Section J – Attachment 2AD Page 20 of 20 8 Feb 2010

--End of Section--

Other files for this federal contract opportunity

Other files attached to Roofing Indefinite Delivery Indefinite Quantity (IDIQ), newest first.
File Type Posted
FA3047-10-R-0012-0004 Amendment to RFP —
FA3047-10-R-0012-0003 Amendment to RFP Roofing IDIQ.pdf PDF
FA3047-10-R-0012-0002 Amendment to RFP Roofing IDIQ —
FA3047-10-R-0012 Attendance Record —
FA3047-10-R-0012 Atch 1 —
FA3047-10-R-0012 Atch 2N-Division 2 —
FA3047-10-R-0012 Atch 2AA-Division 7 —
FA3047-10-R-0012 Atch 2P-Division 2 —
FA3047-10-R-0012 Atch 2R-Division 2 —
FA3047-10-R-0012 Atch 3 —
FA3047-10-R-0012 Atch 2Y-Division 7 —
FA3047-10-R-0012 RFP for Roofing IDIQ —
FA3047-10-R-0012 Atch 2AK —
FA3047-10-R-0012 Atch 2J-Division 1 —
FA3047-10-R-0012 Atch 2A - 8 Feb 10 Table of Contents.pdf PDF
FA3047-10-R-0012 Atch 2Q-Division 2 —
FA3047-10-R-0012 Atch 2AH-Division 8 —
FA3047-10-R-0012 Atch 2X-Division 7 —
FA3047-10-R-0012 Atch 2F-Division 1 —
FA3047-10-R-0012 Atch 2O-Division 2 —
FA3047-10-R-0012 Atch 2K-Division 1 —
FA3047-10-R-0012 Atch 2M-Division 2 —
FA3047-10-R-0012 Atch 2L-Division 1 —
FA3047-10-R-0012 Atch 2D-Division 1 —
FA3047-10-R-0012 Atch 2AJ-Division 26 —
FA3047-10-R-0012 Atch 2B-Division 0 —
FA3047-10-R-0012 Atch 2AC-Division 7 —
FA3047-10-R-0012 Atch 2I-Division 1 —
FA3047-10-R-0012 Atch 2G-Division 1 —
FA3047-10-R-0012 Atch 2W-Division 6 —
FA3047-10-R-0012 Atch 2E-Division 1 —
FA3047-10-R-0012 Atch 2S-Division 5 —
FA3047-10-R-0012 Atch 4 —
FA3047-10-R-0012_SBDC_Informational_Map.pdf PDF
FA3047-10-R-0012 Atch 2AF-Division 7 —
FA3047-10-R-0012 Atch 2H-Division 1 —
FA3047-10-R-0012 Atch 2V-Division 5 —
FA3047-10-R-0012 Atch 2Z-Division 7 —
FA3047-10-R-0012 Atch 2AB-Division 7 —
FA3047-10-R-0012 Atch 2AG-Division 7 —
FA3047-10-R-0012 Atch 2AI-Division 9 —
FA3047-10-R-0012 Atch 2U-Division 5 —
FA3047-10-R-0012 Atch 2AE-Division 7 —
FA3047-10-R-0012 Atch 1 —
FA3047-10-R-0012 Atch 2T-Division 5 —
FA3047-10-R-0012 Atch 2C-Division 1 —
Show all 46

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .