FA3047-10-R-0012 Atch 2C-Division 1

74 KB Posted

Attached to
Roofing Indefinite Delivery Indefinite Quantity (IDIQ) Federal contract opportunity
Solicitation number
FA3047-10-R-0012-ROOFING
Issued by
Department of the Air Force Air Education and Training Command

About this file

FA3047-10-R-0012 Atch 2C-Division 1 (Specs - 01 22 00) 8 Feb 10 Measurement and Payment

Text of this file

802 CONS/LGCA-3 FA3047-10-R-0012

Lackland AFB TX Roofing IDIQ

01 22 00.00 10

Section J – Attachment 2C Page 1 of 9 8 Feb 2010

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 PERFORMANCE OF WORK

This guide specification provides an example of the appropriate form to be used for lump sum schedule payment items and unit price schedule payment items. The following specification sections contain unit prices: 02 82 14.00 10, 05 30 00, 06 10 00, 07 22 00, 07 31 13, 07 41 20, 07 41 13, 07 41 60, 07 51 13, 07 60 00, 07 92 00 and 09 90 00

1.2 DEFINITIONS

CLIN - Acronym for Contract Line Item Number. The CLIN is a sequential number to differentiate between line items. For this project, these numbers follow the sequential industry standard CSI format for specifications. Lower value specification numbers have a lower value CLIN number. The first number in the CLIN represents the contract year, designated in this specification as "X". For example "0" is the basic year, "1" is the 1st option year, "2" is the 2nd option year, etc.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

No submittals required under this section.

1.4 INCIDENTAL ITEMS

Incidental items include items not specifically listed in the BID SCHEDULE as a separate unit price yet are incidental to the work. Such items include mobilization, demobilization, demolition, overhead (general, job, office), profit, transportation, delivery, disposal fees, as-built drawings, equipment usage/rental, contractor quality control, environmental protection, safety requirements, warranties, caulking/sealant, tools and utilities for performing all work required for which separate payment is not otherwise provided. Labor and material costs are included in the unit price line items. All costs for items of work, which are not specifically mentioned in a particular unit price item, must be included as a percentage either distributed across all line items or included in the unit price for the related item.

Section J – Attachment 2C Page 2 of 9 8 Feb 2010

1.5 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed must constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated

Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items. The unit price items for roof systems are relevant for full replacement or partial replacement.

All unit price items below are organized by CLIN (Contract Line Item Number) with a unique specification number cross referenced to the specification section. The relevant specification illustrates the details, materials and procedures for installation.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION

3.1 ROOF AREA CALCULATION

3.1.1 Gable Roof

For joint measurement of gable roofs, measure the projected "flat" roof area (building footprint + eaves) multiplied by a slope factor and a waste factor. The slope factor is included in the paragraph below titled "Slope Factor" and the waste factor is included in the respective unit price paragraph.

3.1.2 Hip Roof

For joint measurement of hip roofs (See FIG. I at the end of this specification). Hip roofs contain ends and sides. For the end, multiply the length of the end eave by 1/2 the length to the rafter. This is 1/2 of the end area. Multiply by 2 to calculate the whole end area.

To obtain the side area, add the length of the ridge to the length of the side eaves, divide this sum by 2 and multiply by the length of the rafter (calculates one side of the roof).

Multiply by 2 to calculate the whole roof (sides) Add the end area to the side area. To calculate length of hip tile (clay tile only), multiply the total roof run from eave to ridge, not the hip or valley run, by the slope factor. Convert the hip length to area (SQ), add the roof area to the hip area and multiply the sum by a waste factor.

3.1.3 Slope Factor

ROOF GABLE HIP

PITCH CONVERSION LENGTH

2:12 1.014 1.424

3:12 1.031 1.436

4:12 1.054 1.453

5:12 1.083 1.474

6:12 1.118 1.500

Section J – Attachment 2C Page 3 of 9 8 Feb 2010

8:12 1.202 1.564

12:12 1.413 1.732

3.2 SECTION 02 82 14.00 10 UNIT PRICE ITEMS

3.2.1 Asbestos Hazard Control Activities

Asbestos hazard control activities will be measured for payment by the square foot (SF).

Measurement of this line item includes labor, bags, disposal, personnel protection, invoice and the incidentals identified in this section, paragraph 1.4. Count the number of full bags. Each bag is 3 cubic feet (Cu. Ft.). Round the quantity to the nearest 3 Cu. Ft.

(1 BAG).

3.3 SECTION 05 30 00 UNIT PRICE ITEMS

Roof Deck, Steel: Will be measured for payment by the square foot (SF). Measurement of this line item includes labor, steel deck, adjusting plates, closure plates, saddles, welding washers, cant strips, butt cover plates, under-lapping sleeves, and ridge and valley plates, sump pans, touch-up paint, spot welding and the incidentals identified in this section, paragraph 1.4. This item does not include insulation or collars. For sloped roofs, multiply the roof area by a slope factor. For flat roofs, measure the actual area.

Add actual measured quantity for closure plates, cover plates, column closures, and deck openings other than sump pans. When counting sump pans for roof drains, add 2 SF for

EA pan or round to the nearest 10 SF whichever is greater. For deck where concrete is installed, multiply the measured quantity (deck only, not accessories) by a shoring factor

(1.10). Round the measurement to the nearest square foot.

3.4 SECTION 06 10 00 UNIT PRICE ITEMS

3.4.1 Plywood Sheathing

Plywood sheathing will be measured for payment by the square foot (SF). Use this item to measure roof deck and wall sheathing of either wood or plywood. Measurement of this line item includes plywood, labor, joint clips, fasteners and the incidentals identified in this section, paragraph 1.4. This item does not include insulation or collars. For sloped roofs, multiply the roof area by a slope factor. For flat roofs and walls, measure the actual area. 3/4" nominal plywood is considered 1 unit. Initially, count all plywood as 3/4" units and apply the unit factors to adjust the quantities. For 3/8" nominal plywood, multiply the unit plywood measurement by 0.25. For 1/2" nominal plywood, multiply the unit plywood measurement by 0.5. For 1" nominal plywood, multiply the unit plywood measurement by 1.2. The joint measured quantity is the 3/4"-unit measurement times the unit factor. If two layers are required, multiply the quantity by 2.

If wood deck is desired in lieu of plywood, convert the deck by dividing the deck thickness by ¾" to determine the unit factor.

3.4.2 Structural Lumber

Section J – Attachment 2C Page 4 of 9 8 Feb 2010

Structural lumber will be measured for payment by the thousand board feet (MBF). The wood-framing member in this line item is defined as any dimensional lumber specifically used as a structural member used for floor, wall, ceiling or roof framing. The framing items include but are not limited to stud, column, rafter, ridge, joist, girder, beam, stringer, chord, lintel, sill and plate. Measurement of this line item includes wood members, labor, fasteners and the incidentals identified in this section, paragraph 1.4.

This item does not include insulation, stiffeners (considered part of the joist). 2x6 nominal wood members are considered 1 unit. Initially, count all wood members as 2x6 units and apply the unit factors to adjust the quantities. For 2x4 nominal members, multiply the unit board foot measurement by 0.67. For 2x8 nominal members, multiply the unit board foot measurement by 1.33. For 2x10 nominal members, multiply the unit board foot measurement by 1.66. For 2x12 nominal members, multiply the unit board foot measurement by 2.0. Likewise, for 1x nominal lumber the unit factors are halved and so on. The joint measured quantity is the 2x6-unit measurement times the unit factor.

To compensate for timber connectors (clip, hangar, plate, cap, angle, ring, grid, etc.)

count the number required and apply a percentage (determined during joint measurement) to increase BF quantity. After applying all factors (size, connector, and waste = 1.10), round the measured quantity to the nearest 1 BF.

3.4.3 Nailers/Blocking

Nailers/blocking will be measured for payment by the thousand board feet (MBF). The wood members in this line item include any dimensional lumber, used for support or non-structural purposes. The support items include but are not limited to the bridging, bracing, tie, strut, furring, nailing strips, purlin, blocking, gussets, plates, shims and fasteners. This measurement includes labor, wood members, cutting, fitting, and fasteners and the incidentals identified in this section, paragraph 1.4. 2x6 nominal wood members are considered 1 unit. Initially, count all wood members as 2x6 units and apply the unit factors to adjust the quantities. For 2x4 nominal members, multiply the unit board foot measurement by 0.67. For 2x8 nominal members, multiply the unit board foot measurement by 1.33. For 2x10 nominal members, multiply the unit board foot measurement by 1.66. For 2x12 nominal members, multiply the unit board foot measurement by 2.0. Likewise, for 1x nominal lumber the unit factors are halved and so

on. The joint measured quantity is the 2x6-unit measurement times the unit factor. After applying all factors (size, waste = 1.10), round the measured quantity to the nearest 1 BF.

3.4.4 Wood Soffit

Wood soffit will be measured for payment by the square foot (SF). The wood members in this line item include any dimensional lumber, used for closure purposes, labor, fasteners and the incidentals identified in this section, paragraph 1.4. This measurement includes wood members, cutting, fitting, and fasteners. The joint measured quantity is the actual measurement times a waste factor (1.1). Round the measured quantity to the nearest square foot.

Section J – Attachment 2C Page 5 of 9 8 Feb 2010

3.4.5 Wood Fascia

Wood fascia will be measured for payment by the thousand board feet (MBF). The wood members in this line item include any dimensional lumber used for trim, molding, fascia, cornice, stringers, treads, risers, base, chair/dado rail or millwork purposes, labor, fasteners and the incidentals identified in this section, paragraph 1.4. This measurement includes wood members, cutting, fitting, and fasteners. Round the measured quantity to the nearest board foot.

3.5 SECTION 07 22 00 UNIT PRICE ITEMS

3.5.1 Rigid Insulation

Rigid insulation will be measured for payment by the square foot (SF). The insulation in this line item is rigid wall or roof insulation. Measurement for this line item includes the insulation, vapor barrier/retarder, tape, adhesive, metal discs, fasteners, labor, and the incidentals identified in this section, paragraph 1.4. Use R5 as the standard unit. Initially measure all insulation as R5. To convert to R2, multiply the quantity by 0.4. For R3, multiply the quantity by 0.6. For R4, multiply the quantity by 0.8. For R8, multiply the quantity by 1.0. For R11, multiply the quantity by 1.3. For R15, multiply the quantity by

1.4. For R19, multiply the quantity by 1.7. For R23, multiply the quantity by 2. For multiple layers, multiply the quantity by the number of layers desired. After applying all factors (R-value, quantity), round the measured quantity to the nearest 1 SF.

3.6 SECTION 07 31 13 UNIT PRICE ITEMS

3.6.1 Strip Shingles/Roll Roofing

Strip shingles/roll roofing will be measured for payment by the square (SQ). The system in this line item includes the felt underlayment, leak barrier underlayment, labor, felt flashing, shingles, roll roofing/asphalt cap sheet, fasteners and the incidentals identified in this section, paragraph 1.4. Ventilators are measured separately. This item does not include insulation, metal flashing, drip edge, gutters, downspouts or wood trim. To compensate for ventilators, measure the ventilator area (SQ), and multiply by 2. After applying all factors (ventilator, waste for gable = 1.10, waste for hip = 1.15, waste for hip with dormer and valleys = 1.20), round the measured quantity to the nearest 0.1 SQ.

3.7 SECTION 07 32 14 UNIT PRICE ITEMS

3.7.1 Clay Tile Salvage

Clay tile salvage will be measured for payment as square foot (SF). Use this line item for partial or full roof replacement when instructed to reuse the existing clay tile.

Measurement of this line item includes labor, clay tile, protection, fasteners, cement, sealant, mortar, and the incidentals identified in this section, paragraph 1.4.

Section J – Attachment 2C Page 6 of 9 8 Feb 2010

3.7.2 Clay Tile, Replacement

Clay tile, new will be measured for payment as square foot (SF). Use this line item to replace existing broken clay tiles or tiles that break during salvage operation. Tiles damaged during salvage operation as a result of carelessness are the contractor's responsibility and are not reimbursed under this line item. Measurement of this line item includes labor, clay tile, protection, fasteners, cement, sealant, mortar, and the incidentals identified in this section, paragraph 1.4.

3.8 SECTION 07 41 13 UNIT PRICE ITEMS

3.8.1 Steel Roofing Panels

Sheet metal roofing will be measured for payment by the square foot (SF). Measurement of this line item includes labor, metal roof panels, underlayment, fasteners, purlins, sub-purlins, accessories, trim, metal closure strips, caps, sealant, gaskets, insulating compounds and the incidentals identified in this section, paragraph 1.4. This item does not include metal flashing, insulation, gutters, downspouts, vents, curbs, or skylights.

When skylights and curbs are required, calculate a comparable area (SF) or percentage and apply this unit cost. If MET-TILE is desired, multiply the quantity by 2. Multiply the roof area by a slope factor and a waste factor (1.1) and round to the nearest 1 SF.

3.9 SECTION 07 41 60 UNIT PRICE ITEMS

3.9.1 Structural Standing Seam Metal Roof (SSSMR) System

SSSMR will be measured for payment by the square (SQ). Measurement of this line item includes labor, design, standing seam roof panels, fasteners, purlins, sub-purlins, connectors, clips, assemblies, panel finish, slip sheet, accessories, components, trim, roof panel connections, sealant, gaskets, insulating compounds and the incidentals identified in this section, paragraph 1.4. This item does not include roof penetration items such as vents, curbs, skylights; interior or exterior gutters and downspouts, and flashing. To compensate for roof penetration items, add an agreed percentage increase or use the appropriate CLIN during measurement. Multiply the roof area by a slope factor and round to the nearest 0.1 SQ.

3.10 SECTION 07 51 13 UNIT PRICE ITEMS

3.10.1 Asphalt Built-Up Roofing

Asphalt built-up roofing will be measured for payment by the square (SQ). Measurement of this line item includes labor, primer, bitumen, cement, cants, felt, glass fabric, bituminous fasteners, stops, cap sheet and the incidentals identified in this section, paragraph 1.4. This item does not include roof penetration items such as walkways, vents, curbs, skylights; interior or exterior gutters and downspouts, nailers, insulation and metal flashing. To compensate for roof penetration items, add an agreed percentage

Section J – Attachment 2C Page 7 of 9 8 Feb 2010 increase or use the appropriate CLIN during measurement. Round the quantity to the nearest 0.1 SQ.

3.10.2 Asphalt Flood Coat Built-Up Roof System

Asphalt flood coat built-up roof system will be measured for payment by the square (SQ).

Measurement of this line item includes labor, bitumen, aggregate and the incidentals identified in this section, paragraph 1.4. Round the quantity to the nearest 0.1 SQ.

3.11 SECTION 07 60 00 UNIT PRICE ITEMS

3.11.1 Copper Flashing

Copper flashing will be measured for payment by the square foot (SF). Measurement of this line item includes labor, material for flashing (i.e. base, counter, stepped, through wall, lintel, sill, valley, hip, gable, ridge roll, hip roll, cap, curb, reglet, drip edge, gravel stop, expansion joints), seams, cleats, gaskets, sealant, solder, fasteners and the incidentals identified in this section, paragraph 1.4. Round the quantity to the nearest 1

SF.

3.11.2 Galvanized Steel Flashing

Galvanized steel flashing will be measured for payment by the square foot (SF).

Measurement of this line item includes labor, material for flashing (i.e. base, counter, stepped, through wall, lintel, sill, valley, hip, gable, ridge roll, hip roll, cap, curb, reglet, drip edge, gravel stop, expansion joints), seams, cleats, gaskets, sealant, solder, fasteners and the incidentals identified in this section, paragraph 1.4. Round the quantity to the nearest 1 SF.

3.11.3 Aluminum Flashing

Aluminum flashing will be measured for payment by the square foot (SF). Measurement of this line item includes labor, material for flashing (i.e. base, counter, stepped, through wall, lintel, sill, valley, hip, gable, ridge roll, hip roll, cap, curb, reglet, drip edge, gravel stop, expansion joints), seams, cleats, gaskets, sealant, solder, fasteners and the incidentals identified in this section, paragraph 1.4. Round the quantity to the nearest 1

SF.

3.11.4 Copper Gutter

Copper gutter will be measured for payment by the linear foot (LF). Measurement of this line item includes labor, gutter, straps, cleats, elbows, strainer, and the incidentals identified in this section, paragraph 1.4. Initially, count all gutters as 4" units and apply the unit factors to adjust the quantities. For 2" gutters, multiply the unit measurement by

0.3. For 5" gutters, multiply the unit measurement by 1.5. For 6" gutters, multiply the

Section J – Attachment 2C Page 8 of 9 8 Feb 2010 unit measurement by 2.3. For alternative sizes, coordinate a suitable factor. Round the quantity to the nearest 1 LF.

3.11.5 Copper Downspout

Copper downspout will be measured for payment by the linear foot (LF). Measurement of this line item includes labor, downspout, straps, cleats, boots, elbows, and the incidentals identified in this section, paragraph 1.4. Initially, count all downspouts as 4" units and apply the unit factors to adjust the quantities. For 2", multiply the unit measurement by 0.3. For 5", multiply the unit measurement by 1.5. For 6", multiply the unit measurement by 2.3. For alternative sizes, coordinate a suitable factor. Round the quantity to the nearest 1 LF.

3.11.6 Aluminum Gutter

Aluminum gutter will be measured for payment by the linear foot (LF). Measurement of this line item includes labor, gutter, straps, cleats, elbows, strainer, factory finish and the incidentals identified in this section, paragraph 1.4. Initially, count all gutters as 4" units and apply the unit factors to adjust the quantities. For 2" gutters, multiply the unit measurement by 0.3. For 5" gutters, multiply the unit measurement by 1.5. For 6" gutters, multiply the unit measurement by 2.3. For alternative sizes, coordinate a suitable factor. Round the quantity to the nearest 1 LF.

3.11.7 Aluminum Downspout

Aluminum downspout will be measured for payment by the linear foot (LF).

Measurement of this line item includes labor, downspout, straps, cleats, boots, elbows, factory finish and the incidentals identified in this section, paragraph 1.4. Initially, count all downspouts as 4" units and apply the unit factors to adjust the quantities. For 2", multiply the unit measurement by 0.3. For 5", multiply the unit measurement by 1.5. For

6", multiply the unit measurement by 2.3. For alternative sizes, coordinate a suitable factor. Round the quantity to the nearest 1 LF.

3.12 SECTION 07 92 00 UNIT PRICE ITEMS

3.12.1 Caulking/Sealant

There will be no separate payment for caulking, sealant or the incidental items which include masking tape, backing, bond breaker, primer, the complementary items in the

JOINT SEALING specification. All caulking/sealant is considered incidental to the relevant line items. The specification section (07 92 00) is intended to qualify the materials and installation, and provide a scope for estimation. The estimation; however, is included in other line items and will not constitute separate payment.

3.13 SECTION 09 90 00 UNIT PRICE ITEMS

Section J – Attachment 2C Page 9 of 9 8 Feb 2010

3.13.1 Paints and Coatings

Paints and coatings will be measured for payment by the square foot (SF). Measurement of this line item includes labor, material, surface preparation, roller application and brushwork for interior or exterior surfaces (wood, metal, concrete, masonry, stucco/plaster, GWB) and the incidentals identified in this section, paragraph 1.4.

Initially, measure all paint as latex and apply the coating unit factors to adjust the quantity. For oil, multiply the unit measurement by 1.1. For enamel, multiply the unit measurement by 1.5. For elastomeric, multiply the unit measurement by 2.3. For textured coatings, multiply by 2. Double the quantity for successive coats including primer. Apply unit factors (coating, texture, layer) to the measurement and round the quantity to the nearest 1 SF.

--End of Section--

Other files for this federal contract opportunity

Other files attached to Roofing Indefinite Delivery Indefinite Quantity (IDIQ), newest first.
File Type Posted
FA3047-10-R-0012-0004 Amendment to RFP —
FA3047-10-R-0012-0003 Amendment to RFP Roofing IDIQ.pdf PDF
FA3047-10-R-0012-0002 Amendment to RFP Roofing IDIQ —
FA3047-10-R-0012 Attendance Record —
FA3047-10-R-0012 Atch 1 —
FA3047-10-R-0012 Atch 2N-Division 2 —
FA3047-10-R-0012 Atch 2AA-Division 7 —
FA3047-10-R-0012 Atch 2P-Division 2 —
FA3047-10-R-0012 Atch 2R-Division 2 —
FA3047-10-R-0012 Atch 2AD-Division 7 —
FA3047-10-R-0012 Atch 3 —
FA3047-10-R-0012 Atch 2Y-Division 7 —
FA3047-10-R-0012 RFP for Roofing IDIQ —
FA3047-10-R-0012 Atch 2AK —
FA3047-10-R-0012 Atch 2J-Division 1 —
FA3047-10-R-0012 Atch 2A - 8 Feb 10 Table of Contents.pdf PDF
FA3047-10-R-0012 Atch 2Q-Division 2 —
FA3047-10-R-0012 Atch 2AH-Division 8 —
FA3047-10-R-0012 Atch 2X-Division 7 —
FA3047-10-R-0012 Atch 2F-Division 1 —
FA3047-10-R-0012 Atch 2O-Division 2 —
FA3047-10-R-0012 Atch 2K-Division 1 —
FA3047-10-R-0012 Atch 2M-Division 2 —
FA3047-10-R-0012 Atch 2L-Division 1 —
FA3047-10-R-0012 Atch 2D-Division 1 —
FA3047-10-R-0012 Atch 2AJ-Division 26 —
FA3047-10-R-0012 Atch 2B-Division 0 —
FA3047-10-R-0012 Atch 2AC-Division 7 —
FA3047-10-R-0012 Atch 2I-Division 1 —
FA3047-10-R-0012 Atch 2G-Division 1 —
FA3047-10-R-0012 Atch 2W-Division 6 —
FA3047-10-R-0012 Atch 2E-Division 1 —
FA3047-10-R-0012 Atch 2S-Division 5 —
FA3047-10-R-0012 Atch 4 —
FA3047-10-R-0012_SBDC_Informational_Map.pdf PDF
FA3047-10-R-0012 Atch 2AF-Division 7 —
FA3047-10-R-0012 Atch 2H-Division 1 —
FA3047-10-R-0012 Atch 2V-Division 5 —
FA3047-10-R-0012 Atch 2Z-Division 7 —
FA3047-10-R-0012 Atch 2AB-Division 7 —
FA3047-10-R-0012 Atch 2AG-Division 7 —
FA3047-10-R-0012 Atch 2AI-Division 9 —
FA3047-10-R-0012 Atch 2U-Division 5 —
FA3047-10-R-0012 Atch 2AE-Division 7 —
FA3047-10-R-0012 Atch 1 —
FA3047-10-R-0012 Atch 2T-Division 5 —
Show all 46

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .