FA3047-10-R-0012 Atch 2D-Division 1 (Specs - 01 30 00) 8 Feb 10 Submittal Descriptions
Text of this file
802 CONS/LGCA-3 FA3047-10-R-0012
Lackland AFB TX Roofing IDIQ
01 30 00-1
Section J – Attachment 2D Page 1 of 3 8 Feb 2010
SECTION 01 30 00
SUBMITTAL DESCRIPTIONS
PART 1 GENERAL
1.1 SUMMARY (Not Applicable)
1.2 REFERENCES (Not Applicable)
1.3 SUBMITTALS
The submittals described below are those required and further described in other sections of the specifications. Other requirements pertaining to submittals are included in Specification Section
01305 SUBMITTAL PROCEDURES. Submittals required by the CONTRACT CLAUSES and other non-technical parts of the contract are not included in this section.
SD-01 Data
Submittals which provide calculations, descriptions, or documentation regarding the work.
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Drawings
Submittals which graphically show relationship of various components of the work, schematic diagrams of systems, details of fabrication, layouts of particular elements, connections, and other relational aspects of the work.
SD-06 Instructions
Submittals containing preprinted material describing installation of a product, system or material, including special notices and material safety data sheets (MSDS), if any, concerning impedances, hazards, and safety precautions.
SD-07 Schedules
Tabular lists showing location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.
01 30 00-2
Section J – Attachment 2D Page 2 of 3 8 Feb 2010
SD-08 Statements
A document, required of the Contractor, or through the Contractor, from a supplier, installer, manufacturer, or other lower tier Contractor, the purpose of which is to confirm the quality or orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel, qualifications, or other verifications of quality.
SD-09 Reports
Reports of inspections or tests, including analysis and interpretation of test results. Each report shall be properly identified. Test methods used shall be identified and test results shall be recorded.
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-13 Certificates
Statement signed by responsible official of a manufacturer of a product, system or material, attesting that the product, system or material meets specified requirements. The statement must be dated after the award of this contract, must name the project, and must list the specific requirements that are being certified.
SD-14 Samples
Samples, including both fabricated and unfabricated physical examples of materials, products, and units of work as complete units or as portions of units of work.
01 30 00-3
Section J – Attachment 2D Page 3 of 3 8 Feb 2010
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-18 Records
Submittals containing documentation to record compliance with technical or administrative requirements.
SD-19 Operation and Maintenance Manuals
Submittals containing data that forms a part of an operation and maintenance manual.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section --
Other files for this federal contract opportunity
Show all 46
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .