FA3047-10-R-0012 Atch 2F-Division 1 (Specst - 01 35 26) 8 Feb 10 Governmental Safety Requirements
Text of this file
802 CONS/LGCA-3 FA3047-10-R-0012
Lackland AFB TX Roofing IDIQ
01 35 26
Section J – Attachment 2F Page 1 of 20 8 Feb 2010
SECTION 01 35 26
GOVERNMENTAL SAFETY REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced.
The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)
ASSE/SAFE A10.32(2004) Fall Protection
ASSE/SAFE A10.34(2001; R 2005) Protection of the Public on or Adjacent to
Construction Sites
ASSE/SAFE Z359.1(2007) Safety Requirements for Personal Fall Arrest Systems, Subsystems and Components
ASME INTERNATIONAL (ASME)
ASME B30.22(2005) Articulating Boom Cranes
ASME B30.3(2004) Construction Tower Cranes
ASME B30.5(2007) Mobile and Locomotive Cranes
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION (NASA)
NASA NSS 1740.12(1993) NASA Safety Standard For Explosives, Propellants and
Pyrotechnics
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 10(2007; Errata 2007; AMD 1 2007) Standard for Portable Fire Extinguishers
NFPA 241(2009) Standard for Safeguarding Construction, Alteration, and Demolition
Operations
NFPA 51B(2009) Standard for Fire Prevention During Welding, Cutting, and Other Hot
Work
NFPA 70E(2009; Errata 2009) Standard for Electrical Safety in the Workplace
01 35 26
Section J – Attachment 2F Page 2 of 20 8 Feb 2010
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1(2008) Safety and Health Requirements Manual
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1926Safety and Health Regulations for Construction
29 CFR 1926.500Fall Protection
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Accident Prevention Plan (APP); G
Activity Hazard Analysis (AHA); G
Crane Critical Lift Plan; G
Proof of qualification for Crane Operators
SD-06 Test Reports
Reports
Submit reports as their incidence occurs, in accordance with the requirements of the paragraph entitled, "Reports."
Accident Reports
Crane Reports
SD-07 Certificates
Hot work permit
Contractor Safety Self-Evaluation Checklist; G
Certificate of Compliance (Crane)
01 35 26
Section J – Attachment 2F Page 3 of 20 8 Feb 2010
Submit one copy of each permit/certificate attached to each Daily Quality Control
Report.
1.3 DEFINITIONS
a. Competent Person for Fall Protection. A person who is capable of identifying hazardous or dangerous conditions in the personal fall arrest system or any component thereof, as well as their application and use with related equipment, and has the authority to take prompt corrective measures to eliminate the hazards of falling.
b. High Visibility Accident. Any mishap which may generate publicity and/or high visibility.
c. Medical Treatment. Treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by a physician or registered personnel.
d. Operating Envelope. The area surrounding any crane. Inside this "envelope" is the crane, the operator, riggers and crane walkers, rigging gear between the hook and the load, the load and the crane's supporting structure (ground, rail, etc.).
e. Qualified Person for Fall Protection. A person with a recognized degree or professional certificate, and with extensive knowledge, training and experience in the field of fall protection; who is capable of performing design, analysis, and evaluation of fall protection systems and equipment.
f. Recordable Injuries or Illnesses. Any work-related injury or illness that results in:
(1) Death, regardless of the time between the injury and death, or the length of the illness;
(2) Days away from work (any time lost after day of injury/illness onset);
(3) Restricted work;
(4) Transfer to another job;
(5) Medical treatment beyond first aid;
(6) Loss of consciousness; or
(7) A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in (1) through (6) above.
01 35 26
Section J – Attachment 2F Page 4 of 20 8 Feb 2010
d. "USACE" property and equipment specified in USACE EM 385-1-1 should be interpreted as Government property and equipment.
e. Weight Handling Equipment (WHE) Accident. A WHE accident occurs when any one or more of the six elements in the operating envelope fails to perform correctly during operation, including operation during maintenance or testing resulting in personnel injury or death; material or equipment damage; dropped load; derailment; two-blocking; overload; and/or collision, including unplanned contact between the load, crane, and/or other objects. A dropped load, derailment, two-blocking, overload and collision are considered accidents even though no material damage or injury occurs. A component failure (e.g., motor burnout, gear tooth failure, bearing failure) is not considered an accident solely due to material or equipment damage unless the component failure results in damage to other components (e.g., dropped boom, dropped load, roll over, etc.) Any mishap meeting the criteria described above shall be documented in the
Contractor Significant Incident Report (CSIR) and submitted within five days to the
Contracting Officer.
1.4 CONTRACTOR SAFETY SELF-EVALUATION CHECKLIST
Contracting Officer will provide a "Contractor Safety Self-Evaluation checklist" to the
Contractor at the pre-construction conference. The checklist will be completed monthly by the Contractor and submitted with each request for payment voucher. Additionally, monthly exposure reporting to the Contracting Officer is required to be attached to the monthly billing request. This report is a compilation of employee-hours worked each month for all site workers, both prime and subcontractor. The Contracting Officer will provide copies of any special forms. An acceptable score of 90 or greater is required.
Failure to submit the completed safety self-evaluation checklist or achieve a score of at least 90, will result in a retention of up to 10 percent of the voucher.
1.5 REGULATORY REQUIREMENTS
In addition to the detailed requirements included in the provisions of this contract, comply with the most recent addition of USACE EM 385-1-1, and the following federal, state, and local, laws, ordinances, criteria, rules and regulations. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work. Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements govern.
1.6 SITE QUALIFICATIONS, DUTIES AND MEETINGS
1.6.1 Personnel Qualifications
1.6.1.1 Site Safety and Health Officer (SSHO)
01 35 26
Section J – Attachment 2F Page 5 of 20 8 Feb 2010
The contractor shall provide a Safety oversight team that includes a minimum of one (1)
Competent Person at each project site to function as the Safety and Health Officer
(SSHO). The SSHO shall be at the work site at all times, unless specified differently in the contract, to perform safety and occupational health management, surveillance, inspections, and safety enforcement for the Contractor, and their training, experience, and qualifications shall be as required by EM 385-1-1 paragraph 01.A.17 and all associated sub-paragraphs. A Competent Personal shall be provided for all of the hazards identified in the Contractor's Safety and Health Program in accordance with the accepted Accident
Prevention Plan, and shall be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. The credentials of the
Competent Persons(s) shall be approved by the Contracting Officer in consultation with the Safety Office.
The Contractor Quality Control (QC) person can be the SSHO on this project.
1.6.1.2 Crane Operators
Meet the crane operators requirements in USACE EM 385-1-1, Section 16 and Appendix
I. In addition, for mobile cranes with Original Equipment Manufacturer (OEM) rated capacitates of 50,000 pounds or greater, designate crane operators as qualified by a source that qualifies crane operators (i.e., union, a government agency, or and organization that tests and qualifies crane operators). Provide proof of current qualification.
1.6.2 Personnel Duties
1.6.2.1 Site Safety and Health Officer (SSHO)
a. Conduct daily safety and health inspections and maintain a written log which includes area/operation inspected, date of inspection, identified hazards, recommended corrective actions, estimated and actual dates of corrections. Attach safety inspection logs to the
Contractors' daily quality control report.
b. Conduct mishap investigations and complete required reports. Maintain the OSHA
Form 300 and Daily Production reports for prime and sub-contractors.
c. Maintain applicable safety reference material on the job site.
d. Attend the pre-construction conference, pre-work meetings including preparatory inspection meeting, and periodic in-progress meetings.
e. Implement and enforce accepted APPS and AHAs.
f. Maintain a safety and health deficiency tracking system that monitors outstanding deficiencies until resolution. Post a list of unresolved safety and health deficiencies on the safety bulletin board.
Section J – Attachment 2F Page 6 of 20 8 Feb 2010
g. Ensure sub-contractor compliance with safety and health requirements.
Failure to perform the above duties will result in dismissal of the superintendent, QC
Manager, and/or SSHO, and a project work stoppage. The project work stoppage will remain in effect pending approval of a suitable replacement.
h. Maintain a list of hazardous chemicals on site and their material safety data sheets.
1.6.2.2 Certified Safety Professional (CSP) and/or Certified Industrial Hygienist (CIH)
a. Perform safety and occupational health management, surveillance, inspections, and safety enforcement for the project.
b. Perform as the safety and occupational health "competent person" as defined by
USACE EM 385-1-1.
c. Be on-site at least weekly whenever work or testing is being performed.
d. Conduct and document safety inspections.
e. shall have no other duties other than safety and occupational health management, inspections, and enforcement on this contract.
If the CSP or CIH is appointed as the SSHO all duties of that position shall also be performed.
1.6.3 Meetings
1.6.3.1 Preconstruction Conference
a. Contractor representatives who have a responsibility or significant role in accident prevention on the project shall attend the preconstruction conference. This includes the project superintendent, site safety and health officer, quality control supervisor, or any other assigned safety and health professionals who participated in the development of the
APP (including the Activity Hazard Analyses (AHAs) and special plans, program and procedures associated with it).
b. Discuss the details of the submitted APP to include incorporated plans, programs, procedures and a listing of anticipated AHAs that will be developed and implemented during the performance of the contract. This list of proposed AHAs will be reviewed at the conference and an agreement will be reached between the Contractor and the
Contracting Officer's Representative as to which phases will require an analysis. In addition, establish a schedule for the preparation, submittal, review, and acceptance of
AHAs to preclude project delays.
01 35 26
Section J – Attachment 2F Page 7 of 20 8 Feb 2010
c. Deficiencies in the submitted APP will be brought to the attention of the Contractor at the preconstruction conference, and the Contractor shall revise the plan to correct deficiencies and re-submit it for acceptance. Do not begin work until there is an accepted
APP.
d. The functions of a Preconstruction conference may take place at the Post-Award
Kickoff meeting for Design Build Contracts.
1.6.3.2 Safety Meetings
Conduct and document meetings as required by EM 385-1-1. Attach minutes showing contract title, signatures of attendees and a list of topics discussed to the Contractors' daily quality control report.
1.7 ACCIDENT PREVENTION PLAN (APP)
Use a qualified person to prepare the written site-specific APP. Prepare the APP in accordance with the format and requirements of USACE EM 385-1-1 and as supplemented herein. Cover all paragraph and subparagraph elements in USACE EM
385-1-1, Appendix A, "Minimum Basic Outline for Accident Prevention Plan". Specific requirements for some of the APP elements are described below. The APP shall be job-specific and address any unusual or unique aspects of the project or activity for which it is written. The APP shall interface with the Contractor's overall safety and health program. Include any portions of the Contractor's overall safety and health program referenced in the APP in the applicable APP element and made site-specific. The
Government considers the Prime Contractor to be the "controlling authority" for all work site safety and health of the subcontractors. Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out. The APP shall be signed by the person and firm (senior person) preparing the APP, the Contractor, the on-site superintendent, the designated site safety and health officer, the Contractor Quality Control Manager, and any designated CSP and/or CIH.
Submit the APP to the Contracting Officer 15 calendar days prior to the date of the preconstruction conference for acceptance. Work cannot proceed without an accepted
APP.
Once accepted by the Contracting Officer, the APP and attachments will be enforced as part of the contract. Disregarding the provisions of this contract or the accepted APP will be cause for stopping of work, at the discretion of the Contracting Officer, until the matter has been rectified.
Once work begins, changes to the accepted APP shall be made with the knowledge and concurrence of the Contracting Officer, project superintendent, SSHO and quality control
01 35 26
Section J – Attachment 2F Page 8 of 20 8 Feb 2010 manager. Should any severe hazard exposure, i.e. imminent danger, become evident, stop work in the area, secure the area, and develop a plan to remove the exposure and control the hazard. Notify the Contracting Officer within 24 hours of discovery.
Eliminate/remove the hazard. In the interim, take all necessary action to restore and maintain safe working conditions in order to safeguard onsite personnel, visitors, the public (as defined by ASSE/SAFE A10.34,) and the environment.
Copies of the accepted plan will be maintained at the Contracting Officer's office and at the job site.
Continuously reviewed and amended the APP, as necessary, throughout the life of the contract. Incorporate unusual or high-hazard activities not identified in the original APP as they are discovered.
1.7.1 EM 385-1-1 Contents
In addition to the requirements outlines in Appendix A of USACE EM 385-1-1, the following is required:
a. Names and qualifications (resumes including education, training, experience and certifications) of all site safety and health personnel designated to perform work on this project to include the designated site safety and health officer and other competent and qualified personnel to be used such as CSPs, CIHs, STSs, CHSTs. Specify the duties of each position.
b. Qualifications of competent and of qualified persons. As a minimum, designate and submit qualifications of competent persons for each of the following major areas:
excavation; scaffolding; fall protection; hazardous energy; confined space; health hazard recognition, evaluation and control of chemical, physical and biological agents; personal protective equipment and clothing to include selection, use and maintenance.
c. Crane Critical Lift Plan (when crane is required). Prepare and sign weight handling critical lift plans for lifts over 75 percent of the capacity of the crane or hoist at any radius of lift; lifts involving more than one crane or hoist; lifts of personnel; and lifts involving non-routine rigging or operation, sensitive equipment, or unusual safety risks. Submit 15 calendar days prior to on-site work and include the requirements of USACE EM 385-1-1, paragraph 16.H. and for lifts of personnel, demonstrate compliance with the requirements of 29 CFR 1926.550(g).
d. Fall Protection and Prevention (FP&P) Program Documentation. The program documentation shall be site specific and address all fall hazards in the work place and during different phases of construction. Address how to protect and prevent workers from falling to lower levels when they are exposed to fall hazards above 6 feet. A qualified person for fall protection shall prepare and sign the program documentation.
Include fall protection and prevention systems, equipment and methods employed for every phase of work, responsibilities, assisted rescue, self-rescue and evacuation procedures, training requirements, and monitoring methods. Revise the Fall Protection
01 35 26
Section J – Attachment 2F Page 9 of 20 8 Feb 2010 and Prevention Program documentation every three months for lengthy projects, reflecting any changes during the course of construction due to changes in personnel, equipment, systems or work habits. Keep and maintain the accepted Fall Protection and
Prevention Program documentation the job site for the duration of the project. Include the Fall Protection and Prevention Program documentation in the Accident Prevention
Plan (APP).
e. Lead Compliance Plan. The safety and health aspects of lead work, prepared in accordance with Section 02 83 13.00 20 LEAD IN CONSTRUCTION.
f. Asbestos Hazard Abatement Plan. The safety and health aspects of asbestos work, prepared in accordance with Section 02 82 14.00 10 ASBESTOS ABATEMENT.
g. PCB Plan. The safety and health aspects of Polychlorinated Biphenyls work, prepared in accordance with Sections 02 84 33 REMOVAL AND DISPOSAL OF
POLYCHLORINATED BIPHENALS.
h. Site Demolition Plan. The safety and health aspects prepared in accordance with
Section 02 41 00 DEMOLITION and referenced sources. Include engineering survey as applicable.
1.8 ACTIVITY HAZARD ANALYSIS (AHA)
The Activity Hazard Analysis (AHA) format shall be in accordance with USACE EM
385-1-1, Section 1. Submit the AHA for review at least 15 calendar days prior to the start of each phase. Format subsequent AHAs as amendments to the APP. The analysis should be used during daily inspections to ensure the implementation and effectiveness of the activity's safety and health controls.
The AHA list will be reviewed periodically (at least monthly) at the Contractor's supervisory safety meeting and updated as necessary when procedures, scheduling, or hazards change.
Develop the activity hazard analyses using the project schedule as the basis for the activities performed. Any activities listed on the project schedule will require an AHA.
The AHAs will be developed by the contractor, supplier or subcontractor and provided to the prime contractor for submittal to the Contracting Officer.
1.9 DISPLAY OF SAFETY INFORMATION
Within 1 calendar day after commencement of work, erect a safety bulletin board at the job site. Where size, duration, or logistics of project do not facilitate a bulletin board, an alternative method, acceptable to the Contracting Officer, that is accessible and includes all mandatory information for employee and visitor review, shall be deemed as meeting the requirement for a bulletin board. Include and maintain information on safety bulletin board as required by EM 385-1-1, section 01.A.06.
Section J – Attachment 2F Page 10 of 20 8 Feb 2010
1.10 SITE SAFETY REFERENCE MATERIALS
Maintain safety-related references applicable to the project, including those listed in the article "References." Maintain applicable equipment manufacturer's manuals.
1.11 EMERGENCY MEDICAL TREATMENT
Contractors will arrange for their own emergency medical treatment. Government has no responsibility to provide emergency medical treatment.
1.12 REPORTS
1.12.1 Accident Reports
a. Conduct an accident investigation for recordable injuries and illnesses, as defined in
1.3.h and property damage accidents resulting in at least $2,000 in damages, to establish the root cause(s) of the accident, complete the USACE Accident Report Form 3394 and provide the report to the Contracting Officer within 5 calendar day(s) of the accident.
The Contracting Officer will provide copies of any required or special forms.
b. Conduct an accident investigation for any weight handling equipment accident
(including rigging gear accidents) to establish the root cause(s) of the accident, complete the WHE Accident Report (Crane and Rigging Gear) form and provide the report to the
Contracting Officer within 30 calendar days of the accident. Do not proceed with crane operations until cause is determined and corrective actions have been implemented to the satisfaction of the Contracting Officer. The Contracting Officer will provide a blank copy of the accident report form.
1.12.2 Accident Notification
Notify the Contracting Officer as soon as practical, but not later than four hours, after any accident meeting the definition of Recordable Injuries or Illnesses or High Visibility
Accidents, property damage equal to or greater than $2,000, or any weight handling equipment accident. Within notification include Contractor name; Contract title; type of contract; name of activity, installation or location where accident occurred; date and time of accident; names of personnel injured; extent of property damage, if any; extent of injury, if known, and brief description of accident (to include type of construction equipment used, PPE used, etc.). Preserve the conditions and evidence on the accident site until the Government investigation team arrives on-site and Government investigation is conducted.
1.12.3 Crane Reports
Submit crane inspection reports required in accordance with USACE EM 385-1-1, Appendix I and as specified herein with Daily Reports of Inspections.
Section J – Attachment 2F Page 11 of 20 8 Feb 2010
1.12.4 Certificate of Compliance
Provide a Certificate of Compliance for each crane entering an activity under this contract (see Contracting Officer for a blank certificate). State within the certificate that the crane and rigging gear meet applicable OSHA regulations (with the Contractor citing which OSHA regulations are applicable, e.g., cranes used in construction, demolition, or maintenance comply with 29 CFR 1926 and USACE EM 385-1-1 Section 16 and
Appendix I. Certify on the Certificate of Compliance that the crane operator(s) is qualified and trained in the operation of the crane to be used. Also certify that all of its crane operators working on the DOD activity have been trained in the proper use of all safety devices (e.g., anti-two block devices). Post certifications on the crane.
1.13 HOT WORK
Coordinate with Contracting Officer for a written permit prior to performing "Hot Work"
(welding, cutting, etc.) or operating other flame-producing/spark producing devices. A permit is required from the Explosives Safety Office for work in and around where explosives are processed, stored, or handled. CONTRACTORS ARE REQUIRED TO
MEET ALL CRITERIA BEFORE A PERMIT IS ISSUED. The Contractor will provide at least two (2) twenty (20) pound 4A:20 BC rated extinguishers for normal "Hot Work".
All extinguishers shall be current inspection tagged, approved safety pin and tamper resistant seal. It is also mandatory to have a designated FIRE WATCH for any "Hot
Work" done at this activity. The Fire Watch shall be trained in accordance with NFPA
51B and remain on-site for a minimum of 30 minutes after completion of the task or as specified on the hot work permit.
When starting work in the facility, require personnel to familiarize themselves with the location of the nearest fire alarm boxes and place in memory the emergency Fire Division phone number. ANY FIRE, NO MATTER HOW SMALL, SHALL BE REPORTED TO
THE RESPONSIBLE FIRE DIVISION IMMEDIATELY.
1.14 FACILITY OCCUPANCY CLOSURE
Streets, walks, and other facilities occupied and used by the Government shall not be closed or obstructed without written permission from the Contracting Officer.
1.15 HIGH NOISE LEVEL PROTECTION
Operations performed by the Contractor that involve the use of equipment with output of high noise levels (jackhammers, air compressors, and explosive-actuated devices) shall be scheduled with the Contracting Officer prior to commencement of work.
1.16 SEVERE STORM PLAN
In the event of a severe storm warning, the Contractor must:
Section J – Attachment 2F Page 12 of 20 8 Feb 2010
a. Secure outside equipment and materials and place materials that could be damaged in protected areas.
b. Check surrounding area, including roof, for loose material, equipment, debris, and other objects that could be blown away or against existing facilities.
c. Ensure that temporary erosion controls are adequate.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
3.1 CONSTRUCTION AND/OR OTHER WORK
Comply with USACE EM 385-1-1, NFPA 241, the APP, the AHA, Federal and/or State
OSHA regulations, and other related submittals and activity fire and safety regulations.
The most stringent standard prevails.
3.1.1 Hazardous Material Exclusions
Notwithstanding any other hazardous material used in this contract, radioactive materials or instruments capable of producing ionizing/non-ionizing radiation (with the exception of radioactive material and devices used in accordance with USACE EM 385-1-1 such as nuclear density meters for compaction testing and laboratory equipment with radioactive sources) as well as materials which contain asbestos, mercury or polychlorinated biphenyls, di-isocynates, lead-based paint are prohibited. The Contracting Officer, upon written request by the Contractor, may consider exceptions to the use of any of the above excluded materials. The Radiation Safety Officer (RSO) must be notified prior to excepted items of radioactive material and devices being brought on base.
3.1.2 Unforeseen Hazardous Material
The design should have identified materials such as PCB, lead paint, and friable and non-friable asbestos and other OSHA regulated chemicals (i.e. 29 CFR Part 1910.1000). If additional material, not indicated, that may be hazardous to human health upon disturbance during construction operations is encountered, stop that portion of work and notify the Contracting Officer immediately. Within 14 calendar days the Government will determine if the material is hazardous. If material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If material is hazardous and handling of the material is necessary to accomplish the work, the
Government will issue a modification pursuant to "FAR 52.243-4, Changes" and "FAR
52.236-2, Differing Site Conditions."
01 35 26
Section J – Attachment 2F Page 13 of 20 8 Feb 2010
3.2 PRE-OUTAGE COORDINATION MEETING
Contractors are required to apply for utility outages at least 5 days in advance. As a minimum, the request should include the location of the outage, utilities being affected, duration of outage and any necessary sketches. Special requirements for electrical outage requests are contained elsewhere in this specification section. Once approved, and prior to beginning work on the utility system requiring shut down, attend a pre-outage coordination meeting with the Contracting Officer and the other representatives effected by outage to review the scope of work and the lock-out/tag-out procedures for worker protection. No work will be performed on energized electrical circuits unless proof is provided that no other means exist.
3.3 CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT)
Contractor shall ensure that each employee is familiar with and complies with these procedures and USACE EM 385-1-1, Section 12, Control of Hazardous Energy.
Contracting Officer will, at the Contractor's request, apply lockout/tagout tags and take other actions that, because of experience and knowledge, are known to be necessary to make the particular equipment safe to work on for Government owned and operated systems.
No person, regardless of position or authority, shall operate any switch, valve, or equipment that has an official lockout/tagout tag attached to it, nor shall such tag be removed except as provided in this section. No person shall work on any energized equipment including, but not limited to activities such as erecting, installing, constructing, repairing, adjusting, inspecting, un-jamming, setting up, trouble shooting, testing, cleaning, dismantling, servicing and maintaining machines equipment of processes until an evaluation has been conducted identifying the energy source and the procedures which will be taken to ensure the safety of personnel.
When work is to be performed on electrical circuits, only qualified personnel shall perform work on electrical circuits.
A supervisor who is required to enter an area protected by a lockout/tagout tag will be considered a member of the protected group provided he notifies the holder of the tag stub each time he enters and departs from the protected area.
Identification markings on building light and power distribution circuits shall not be relied on for established safe work conditions.
Before clearance will be given on any equipment other than electrical (generally referred to as mechanical apparatus), the apparatus, valves, or systems shall be secured in a passive condition with the appropriate vents, pins, and locks.
Pressurized or vacuum systems shall be vented to relieve differential pressure completely.
Section J – Attachment 2F Page 14 of 20 8 Feb 2010
Vent valves shall be tagged open during the course of the work.
Where dangerous gas or fluid systems are involved, or in areas where the environment may be oxygen deficient, system or areas shall be purged, ventilated, or otherwise made safe prior to entry.
3.3.1 Tag Placement
Lockout/tagout tags shall be completed in accordance with the regulations printed on the back thereof and attached to any device which, if operated, could cause an unsafe condition to exist.
If more than one group is to work on any circuit or equipment, the employee in charge of each group shall have a separate set of lockout/tagout tags completed and properly attached.
When it is required that certain equipment be tagged, the Government will review the characteristics of the various systems involved that affect the safety of the operations and the work to be done; take the necessary actions, including voltage and pressure checks, grounding, and venting, to make the system and equipment safe to work on; and apply such lockout/tagout tags to those switches, valves, vents, or other mechanical devices needed to preserve the safety provided. This operation is referred to as "Providing Safety
Clearance."
3.3.2 Tag Removal
When any individual or group has completed its part of the work and is clear of the circuits or equipment, the supervisor, project leader, or individual for whom the equipment was tagged shall turn in his signed lockout/tagout tag stub to the Contracting
Officer. That group's or individual's lockout/tagout tags on equipment may then be removed on authorization by the Contracting Officer.
3.4 FALL HAZARD PROTECTION AND PREVENTION PROGRAM
Establish a fall protection and prevention program, for the protection of all employees exposed to fall hazards. Within the program include company policy, identify responsibilities, education and training requirements, fall hazard identification, prevention and control measures, inspection, storage, care and maintenance of fall protection equipment and rescue and evacuation procedures.
3.4.1 Training
Institute a fall protection training program. As part of the Fall Hazard Protection and
Prevention Program, provide training for each employee who might be exposed to fall
01 35 26
Section J – Attachment 2F Page 15 of 20 8 Feb 2010 hazards. Provide training by a competent person for fall protection in accordance with
USACE EM 385-1-1, Section 21.B.
3.4.2 Fall Protection Equipment and Systems
Enforce use of the fall protection equipment and systems designated for each specific work activity in the Fall Protection and Prevention Plan and/or AHA at all times when an employee is exposed to a fall hazard. Protect employees from fall hazards as specified in
EM 385-1-1, Section 21. In addition to the required fall protection systems, safety skiff, personal floatation devices, life rings etc., are required when working above or next to water in accordance with USACE EM 385-1-1, Paragraphs 21.N through 21.N.04.
Personal fall arrest systems are required when working from an articulating or extendible boom, swing stages, or suspended platform. In addition, personal fall arrest systems are required when operating other equipment such as scissor lifts if the work platform is capable of being positioned outside the wheelbase. The need for tying-off in such equipment is to prevent ejection of the employee from the equipment during raising, lowering, or travel. Fall protection must comply with 29 CFR 1926.500, Subpart M, USACE EM 385-1-1 and ASSE/SAFE A10.32.
3.4.2.1 Personal Fall Arrest Equipment
Personal fall arrest equipment, systems, subsystems, and components shall meet
ASSE/SAFE Z359.1. Only a full-body harness with a shock-absorbing lanyard or self-retracting lanyard is an acceptable personal fall arrest body support device. Body belts may only be used as a positioning device system (for uses such as steel reinforcing assembly and in addition to an approved fall arrest system). Harnesses shall have a fall arrest attachment affixed to the body support (usually a Dorsal D-ring) and specifically designated for attachment to the rest of the system. Only locking snap hooks and carabiners shall be used. Webbing, straps, and ropes shall be made of synthetic fiber. The maximum free fall distance when using fall arrest equipment shall not exceed 6 feet. The total fall distance and any swinging of the worker (pendulum-like motion) that can occur during a fall shall always be taken into consideration when attaching a person to a fall arrest system.
3.4.3 Fall Protection for Roofing Work
Implement fall protection controls based on the type of roof being constructed and work being performed. Evaluate the roof area to be accessed for its structural integrity including weight-bearing capabilities for the projected loading.
a. Low Sloped Roofs:
(1) For work within 6 feet of an edge, on low-slope roofs, Protect personnel from falling by use of personal fall arrest systems, guardrails, or safety nets.
01 35 26
Section J – Attachment 2F Page 16 of 20 8 Feb 2010
(2) For work greater than 6 feet from an edge, erect and install warning lines in accordance with 29 CFR 1926.500 and USACE EM 385-1-1.
b. Steep-Sloped Roofs: Work on steep-sloped roofs requires a personal fall arrest system, guardrails with toe-boards, or safety nets. This requirement also includes residential or housing type construction.
3.4.4 Existing Anchorage
Certified (or re-certified) by a qualified person for fall protection existing anchorages, to be used for attachment of personal fall arrest equipment in accordance with ASSE/SAFE
Z359.1. Exiting horizontal lifeline anchorages must be certified (or re-certified) by a registered professional engineer with experience in designing horizontal lifeline systems.
3.4.5 Horizontal Lifelines
Design, install, certify and use under the supervision of a qualified person horizontal lifelines for fall protection as part of a complete fall arrest system which maintains a safety factor of 2 (29 CFR 1926.500).
3.4.6 Guardrails and Safety Nets
Design, install and use guardrails and safety nets in accordance with EM 385-1-1 and 29
CFR 1926 Subpart M.
3.4.7 Rescue and Evacuation Procedures
When personal fall arrest systems are used, the Contractor must ensure that the mishap victim can self-rescue or can be rescued promptly should a fall occur. Prepare a Rescue and Evacuation Plan and include a detailed discussion of the following: methods of rescue; methods of self-rescue; equipment used; training requirement; specialized training for the rescuers; procedures for requesting rescue and medical assistance; and transportation routes to a medical facility. Include the Rescue and Evacuation Plan within the Activity Hazard Analysis (AHA) for the phase of work, in the Fall Protection and Prevention (FP&P) Plan, and the Accident Prevention Plan (APP).
3.5 OTHER PERSONNEL SAFETY EQUIPMENT
a. Hard Hat
b. Safety Glasses
c. Appropriate Safety Shoes
d. Reflective Vests
01 35 26
Section J – Attachment 2F Page 17 of 20 8 Feb 2010
3.6 SCAFFOLDING
Provide employees with a safe means of access to the work area on the scaffold.
Climbing of any scaffold braces or supports not specifically designed for access is prohibited. Access scaffold platforms greater than 20 feet maximum in height by use of a scaffold stair system. Do not use vertical ladders commonly provided by scaffold system manufacturers for accessing scaffold platforms greater than 20 feet maximum in height.
The use of an adequate gate is required. Ensure that employees are qualified to perform scaffold erection and dismantling. Do not use scaffold without the capability of supporting at least four times the maximum intended load or without appropriate fall protection as delineated in the accepted fall protection and prevention plan. Stationary scaffolds must be attached to structural building components to safeguard against tipping forward or backward. Give special care to ensure scaffold systems are not overloaded.
Side brackets used to extend scaffold platforms on self-supported scaffold systems for the storage of material is prohibited. The first tie-in shall be at the height equal to 4 times the width of the smallest dimension of the scaffold base. Place work platforms on mud sills.
Scaffold or work platform erectors shall have fall protection during the erection and dismantling of scaffolding or work platforms that are more than six feet. Delineate fall protection requirements when working above six feet or above dangerous operations in the Fall Protection and Prevention (FP&P) Plan and Activity Hazard Analysis (AHA) for the phase of work.
3.7 EQUIPMENT
3.7.1 Material Handling Equipment
a. Material handling equipment such as forklifts shall not be modified with work platform attachments for supporting employees unless specifically delineated in the manufacturer's printed operating instructions.
b. The use of hooks on equipment for lifting of material must be in accordance with manufacturer's printed instructions.
c. Operators of forklifts or power industrial trucks shall be licensed in accordance with
OSHA.
3.7.2 Weight Handling Equipment
a. Equip cranes and derricks as specified in EM 385-1-1, section 16.
b. Notify the Contracting Officer 15 days in advance of any cranes entering the activity so that necessary quality assurance spot checks can be coordinated. Prior to cranes entering federal activities, a Crane Access Permit must be obtained from the Contracting
Officer. A copy of the permitting process will be provided at the Preconstruction
Conference. Contractor's operator shall remain with the crane during the spot check.
01 35 26
Section J – Attachment 2F Page 18 of 20 8 Feb 2010
c. Comply with the crane manufacturer's specifications and limitations for erection and operation of cranes and hoists used in support of the work. Perform erection under the supervision of a designated person (as defined in ASME B30.5). Perform all testing in accordance with the manufacturer's recommended procedures.
d. Comply with ASME B30.5 for mobile and locomotive cranes, ASME B30.22 for articulating boom cranes, ASME B30.3 and for construction tower cranes.
e. Under no circumstance shall a Contractor make a lift at or above 90 percent of the cranes rated capacity in any configuration.
f. When operating in the vicinity of overhead transmission lines, operators and riggers shall be alert to this special hazard and follow the requirements of USACE EM 385-1-1
Section 11 and ASME B30.5 or ASME B30.22 as applicable.
g. Do not crane suspended personnel work platforms (baskets) unless the Contractor proves that using any other access to the work location would provide a greater hazard to the workers or is impossible. Do not lift personnel with a line hoist or friction crane.
h. Inspect, maintain, and recharge portable fire extinguishers as specified in NFPA 10, Standard for Portable Fire Extinguishers.
i. All employees must keep clear of loads about to be lifted and of suspended loads.
j. Use cribbing when performing lifts on outriggers.
k. The crane hook/block must be positioned directly over the load. Side loading of the crane is prohibited.
l. A physical barricade must be positioned to prevent personnel from entering the counterweight swing (tail swing) area of the crane.
m. Certification records which include the date of inspection, signature of the person performing the inspection, and the serial number or other identifier of the crane that was inspected shall always be available for review by Contracting Officer personnel.
n. Written reports listing the load test procedures used along with any repairs or alterations performed on the crane shall be available for review by Contracting Officer personnel.
o. Certify that all crane operators have been trained in proper use of all safety devices
(e.g. anti-two block devices).
p. Take steps to ensure that wind speed does not contribute to loss of control of the load during lifting operations. Prior to conducting lifting operations set a maximum wind speed at which a crane can be safely operated based on the equipment being used, the
01 35 26
Section J – Attachment 2F Page 19 of 20 8 Feb 2010 load being lifted, experience of operators and riggers, and hazards on the work site. This maximum wind speed determination shall be included as part of the activity hazard analysis plan for that operation.
3.7.3 Equipment and Mechanized Equipment
a. Proof of qualifications for operator shall be kept on the project site for review.
b. Manufacture specifications or owner's manual for the equipment shall be on-site and reviewed for additional safety precautions or requirements that are sometimes not identified by OSHA or USACE EM 385-1-1. Incorporate such additional safety precautions or requirements into the AHAs.
3.7.4 USE OF EXPLOSIVES
Explosives shall not be used or brought to the project site without prior written approval from the Contracting Officer. Such approval shall not relieve the Contractor of responsibility for injury to persons or for damage to property due to blasting operations.
Storage of explosives, when permitted on Government property, shall be only where directed and in approved storage facilities. These facilities shall be kept locked at all times except for inspection, delivery, and withdrawal of explosives.
Explosive work shall be performed in accordance with NASA NSS 1740.12. This document is available at:
http://www.hq.nasa.gov/office/codeq/doctree/871912.htm
3.8 UTILITIES WITHIN CONCRETE SLABS
Utilities located within concrete slabs or pier structures, bridges, and the like, are extremely difficult to identify due to the reinforcing steel used in the construction of these structures. Whenever contract work involves concrete chipping, saw cutting, or core drilling, the existing utility location must be coordinated with station utility departments in addition to a private locating service. Outages to isolate utility systems must be used in circumstances where utilities are unable to be positively identified. The use of historical drawings does not alleviate the Contractor from meeting this requirement.
3.9 ELECTRICAL
3.9.1 Portable Extension Cords
Size portable extension cords in accordance with manufacturer ratings for the tool to be powered and protected from damage. Immediately removed from service all damaged extension cords. Portable extension cords shall meet the requirements of NFPA 70E and
OSHA electrical standards.
Section J – Attachment 2F Page 20 of 20 8 Feb 2010
--End of Section--
Other files for this federal contract opportunity
Show all 46
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .