CN-370000-HW684-DC020B.pdf

PDF 3 MB Posted

Attached to
Master Agreement FL|HW684|68b160b8827755ddf560142dd2a41e53
Contract number
HW684
Issued by
Florida

About this file

This Task Assignment (TA) is a contract document between the State of Florida Department of Environmental Protection (FDEP) and GHD Services, Inc. for groundwater monitoring activities at McNatt's Cleaners (formerly Ehrlich Road Cleaners) located at 5227 Ehrlich Road, Tampa, Hillsborough County, Florida. The project is identified as ERIC_4752 under the parent contract number HW684. Nicole Knutson serves as the FDEP Project Manager, while Brian Moore represents GHD Services, Inc. as the contractor's project manager. The task assignment was signed on November 29, 2023 (FDEP) and December 1, 2023 (Contractor), with a task completion date of April 15, 2024.

The contract involves two subtasks: Subtask 1 covers project management for annual groundwater sampling and reporting, while Subtask 2 encompasses the actual groundwater monitoring activities. Services include depth-to-water measurements at 33 monitor wells and groundwater sampling at 15 specific wells with analysis for volatile organic compounds and additional parameters including total dissolved solids, total recoverable petroleum hydrocarbons, sodium, ammonia, nitrite, nitrate, chloride, and dissolved gases. The total task value is $11,969.46 on a fixed unit rate basis. This amount covers direct labor costs ($2,527.98), overhead at 129.80% ($3,281.32), fringe benefits at 37.80% ($955.57), travel ($240.00), subcontractor costs including IDW disposal through Erwin Remediation ($121.00), laboratory analytical services ($2,685.00), field equipment and expenses ($1,482.10), and a completion fee ($676.49). The primary deliverable is a Groundwater Monitoring Report due February 13, 2024, with invoice payment contingent upon FDEP approval of this report.

View the file

Other files

File Type Posted
CN-370000-HW684-BIL02F.pdf PDF
CN-370000-HW684-BIL2CC03.pdf PDF
CN-370000-HW684-BIL2ECO1.pdf PDF
CN-370000-HW684-BIL2FCO1.pdf PDF
CN-370000-HW684-BIL2GCO1.pdf PDF
CN-370000-HW684-CSS02A.pdf PDF
CN-370000-HW684-CSS03B.pdf PDF
CN-370000-HW684-D033CCO1.pdf PDF
CN-370000-HW684-DC001A.pdf PDF
CN-370000-HW684-DC001F.pdf PDF
CN-370000-HW684-DC002B.pdf PDF
CN-370000-HW684-DC002C.pdf PDF
CN-370000-HW684-DC002D.pdf PDF
CN-370000-HW684-DC003D.pdf PDF
CN-370000-HW684-DC004D.pdf PDF
CN-370000-HW684-DC005A.pdf PDF
CN-370000-HW684-DC005D.pdf PDF
CN-370000-HW684-DC006B.pdf PDF
CN-370000-HW684-DC009C.pdf PDF
CN-370000-HW684-DC009D.pdf PDF
CN-370000-HW684-DC009E.pdf PDF
CN-370000-HW684-DC011A.pdf PDF
CN-370000-HW684-DC011C.pdf PDF
CN-370000-HW684-DC012D.pdf PDF
CN-370000-HW684-DC013B.pdf PDF
CN-370000-HW684-DC014D.pdf PDF
CN-370000-HW684-DC014F.pdf PDF
CN-370000-HW684-DC015A.pdf PDF
CN-370000-HW684-DC015C.pdf PDF
CN-370000-HW684-DC016B.pdf PDF
CN-370000-HW684-DC016C.pdf PDF
CN-370000-HW684-DC017C.pdf PDF
CN-370000-HW684-DC018C.pdf PDF
CN-370000-HW684-DC019C.pdf PDF
CN-370000-HW684-DC019D.pdf PDF
CN-370000-HW684-DC01ACO2.pdf PDF
CN-370000-HW684-DC025A.pdf PDF
CN-370000-HW684-DC026B.pdf PDF
CN-370000-HW684-DC026D.pdf PDF
CN-370000-HW684-DC027C.pdf PDF
CN-370000-HW684-DC028C.pdf PDF
CN-370000-HW684-DC029C.pdf PDF
CN-370000-HW684-DC031A.pdf PDF
CN-370000-HW684-DC034B.pdf PDF
CN-370000-HW684-DC03ACO1.pdf PDF
CN-370000-HW684-DC03CCO1.pdf PDF
CN-370000-HW684-DC03CCO2.pdf PDF
CN-370000-HW684-DC040A.pdf PDF
CN-370000-HW684-DC045B.pdf PDF
CN-370000-HW684-DC046B.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW684

DC020B Completion April 15, 2024

GHD will perform groundwater monitoring activities at McNatt's Cleaners.

Nicole Knutson 850-245-8763 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

GHD Services, Inc.

GHD Services, Inc.

Brian Moore 813 257 0658

ERIC_4752

5227 Ehrlich Rd, Tampa, Hillsborough County

McNatt's Cleaners (Former Ehrlich Road Cleaners)

✔ $ 11,969.46

$ 11,969.46

Scope of Work

Brian Moore Digitally signed by Brian Moore Date: 2023.12.01 08:42:10 -05'00' Kelly Crain Digitally signed by Kelly Crain

Date: 2023.11.29 12:02:27 -05'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Groundwater Monitoring Report & PM - Subtasks 1 & 2 02/13/2024

FDEP Approval of Groundwater Monitoring Report & PM - Subtasks 1 & 2 $ 11,969.46

$ 11,969.46

HW684

DC020B

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

Memorandum

TO: ERIC_4752

McNatt’s Cleaners

FROM: Nicole Knutson, Project Manager

SUBJECT: Negotiation Summary

HW684 DC020B

DATE: November 27, 2023

GHD will perform groundwater monitoring activities at McNatt's Cleaners, as detailed in the November 15, 2023 proposal. Erwin Remediation will complete IDW transportation and disposal.

Total task amount is $11,969.46. GHD’s time, labor, and subcontractor costs for these activities have been reviewed and are appropriate. The level-of-effort and cost estimate are reasonable for the scope of services. Final deliverable due date is February 13, 2024. Task completion date is April 15, 2024.

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 11/27/2023

Task #: DC020B SubTask 1 Project Management SubTask 6

Site: McNatts Ehrlich SubTask 2 Groundwater Monitoring SubTask 7

Activity/Phase: Monitoring SubTask 3 SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$49.53 Project Manager JM 5.87 5.87 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$56.19 Sr Professional Engineer JH 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$45.07 Professional Engineer/Sc GE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $39.28 Project Engineer/Scientis CH 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $49.53 Project Manager/ Enginee JM 20.00 20.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $31.78 Staff Engineer/Scientist JW 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.40 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.35 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.21 Senior Technician SA 18.00 18.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $26.63 Senior Technician WM 16.50 16.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $24.55 Senior Technician DC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $20.21 Junior Technician WO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.00 Junior Technician JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 6.00 6.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $21.63 Administrative Assistant JJ 8.00 8.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total Hours 75.37 5.87 69.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Direct Labor $2,527.98 $290.83 $2,237.15 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 129.80% $3,281.32 $377.50 $2,903.82 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $955.57 $109.93 $845.64 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $6,764.87 $778.26 $5,986.61 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 11/27/2023

Task #: DC020B SubTask 1 Project Management SubTask 6

Site: McNatts Ehrlich SubTask 2 Groundwater Monitoring SubTask 7

Activity/Phase: Monitoring SubTask 3 SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $240.00 $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $240.00 $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Location $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $11.00 $11.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $121.00 $121.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $2,528.50 $2,528.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $156.50 $156.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $2,685.00 $2,685.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $1,342.10 $1,342.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,482.10 $1,482.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $11,292.97 $778.26 $10,514.71 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $676.49 $77.83 $598.66 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $11,969.46 $856.09 $11,113.37 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Cost from Prior CEF: Manual Entry Cost from Delta CEF; Manual Entry

Cost (Prior + Delta): $0.00 Auto-Calculated Rounding Error: $11,969.46 Auto-Calculated

Final Total Cost: $11,969.46 Auto-Calculated

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : McNatts Cleaners (Ehrlich) SUBTASK 2: Groundwater Monitoring

DATE: 11/27/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Sr Professional Engineer JH Conclusions/Recommendations 1

Project Manager JM Field Work Preparation 1 Project Manager JM Update HASP 1 Project Manager JM Owner Coordination 1 Project Manager JM Project Background 1 Project Manager JM Profile and coordinate IDW disposal 1 Project Manager JM Groundwater Sampling Methods 3 Project Manager JM Water Quality Parameter Summary 3 Project Manager JM Groundwater Analtycial Results (VOCs) 3 Project Manager JM Groundwater Analytical Results (UIC/performance) 3 Project Manager JM Laboratory Data Validation 2 Project Manager JM Conclusions/Recommendations 1

Senior Technician SA Mob/Demob (2 days) 2 Senior Technician SA Water levels (all wells - 33 total) 4 Senior Technician SA Groundwater Sampling (8 wells) 12

Senior Technician WM Mob/Demob (2 days) 2 Senior Technician WM Water levels (all wells - 33 total) 4 Senior Technician WM Groundwater Sampling (7 wells) 10.5

16.5

Drafting Technician PM Groundwater elevation figures (4 zones) 3 Drafting Technician PM Groundwater analytical figures (4 zones) 3

Staff Assistant JJ Data Entry (15 monitor wells, 33 wls) 2 Staff Assistant JJ Update summary tables 2 Staff Assistant JJ Document Preparation/Publishing 2 Staff Assistant JJ GIS/ADaPT 2

TOTAL LABOR 69.5

VEHICLE TYPE RATE UNIT USEAGE

Company Truck $120.00 day 2 $240.00

TOTAL VEHICLE $240.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Erwin Remediation IDW Drum Dispos 1 drum $110.00 $110.00

TOTAL $110.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOHs EPA Method 8260 $73.00 16 $1,168.00 MW001, 2, 4, 19, 25, 30, 31, 33, 40, 42, 43, 45, 51, 52, 53 & IDW

TOC EPA 9060 $30.00 1 $30.00 MW051

TDS EPA 160.1 $16.00 3 $48.00 MW040, 42, 51

TRPH FL-PRO $88.00 3 $264.00 MW040, 42, 51

sodium EPA 6010 $13.50 3 $40.50 MW040, 42, 51 ammonia SM4500 $24.00 3 $72.00 MW040, 42, 51 chloride EPA 352.2 $24.00 2 $48.00 MW051, 52 nitrate EPA 353.2 $23.00 3 $69.00 MW040, 42, 51 nitrite EPA 353.2 $23.00 3 $69.00 MW040, 42, 51 dissolved gases (methane, ethane, ethene) RSK175 $180.00 4 $720.00 MW051 and 52 and 2 QA/QC Sample Shipping Large Cooler (1 day) $150.00 1 $150.00

Ice $6.50 1 $6.50

TOTAL LAB $2,685.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 day 1 $40.00

Groundwater Sampling Kit $290.00 day 4 $1,160.00 Poly Tubing (HDPE) $0.30 ft 457 $137.10 Silicon Tubing $3.00 ft 15 $45.00

55-gallon drum $100.00 drum 1 $100.00

TOTAL EQUIPMENT $1,482.10

FINAL --7/24/96

COST PROPOSAL FOR TASK DC020B

McNatt’s Cleaners, 299502136/ERIC_4752

Groundwater Monitoring

1. INTRODUCTION:

GHD prepared a RAP Modification that was implemented in 2017. Following remedial injections and a period of SVE system operations, the system was recently shutdown. In order to continue to evaluate the performance of the remedial injections in accordance with the RAP Modification, groundwater monitoring is recommended. Task DC020B includes annual groundwater sampling in accordance with GHD’s recommendations from the previous annual groundwater monitoring report dated September 2023 and FDEP correspondence dated November 15, 2022.

Subtask 1: Project Management Includes all tasks associated with project management for annual groundwater sampling and reporting.

Subtask 2: Groundwater Monitoring Subtask 2 includes annual groundwater monitoring. Prior to groundwater sampling, depth to water measurements will be gathered at all available monitor wells (33 total). Groundwater sampling will be conducted at fifteen (15) monitor wells including: MW001, MW002, MW004, MW019, MW025, MW030, MW031, MW033, MW040, MW042, MW043, MW045, MW051, MW052, and MW053. Groundwater sampling will be conducted in accordance with FDEP SOPs. All groundwater samples will be analyzed for the presence of Volatile Organic Halocarbons. Select wells (MW025, MW039, MW040, MW042, MW043, MW045, MW051, and MW052) will also be analyzed for the presence of total dissolved solids, total recoverable petroleum hydrocarbons, sodium, ammonia, nitrite, and nitrate. In addition, monitor wells MW051 and MW052 will also be analyzed for chloride and dissolved gases (methane, ethane, ethene). The dissolved gas sampling will be conducted at MW051 and MW052 only, and will include a duplicate and an equipment blank. Finally, the sample from monitor well MW051 will be analyzed for total organic carbon.

Following receipt of analytical data, a Groundwater Monitoring Report (GMR) will be prepared. The GMR will include a summary of groundwater sampling methods and analytical results. The GMR will provide recommendations for additional remediation and/or testing.

Deliverables:

Deliverable Deliverable Due Date

Groundwater Monitoring Report 2/13/24

COT FTF (ERIC_ 7413)_HW683 SOW_Supplemental Assessment_2022-12_v2.pdf
Subtask 1 – Project Management
Subtask 2 – Site Assessment Work Plan, Health and Safety Plan, Access Agreements, and Source Water Sampling
Subtask 3 –Monitoring Well Installation
Right-of-Way Permitting
Utility Locate and Drilling Subcontractors
Monitoring Well Installation
Subtask 4 – Monitoring Well Sampling and Surveying
Laboratory Analysis
Trip Report
Subtask 5 – Investigation Derived Waste
Trip Report
Subtask 6 – Supplemental Site Assessment Report
Invoice and Deliverable Schedule:
ATTACHMENT A
ATTACHMENT B
ATTACHMENT C
ATTACHMENT D
ATTACHMENT E
ATTACHMENT F
Attachment A -COT FTF (ERIC_7413)_HW683 CEF-LOE_Supplemental Assessment_2022-12_v1.pdf
Cost Estimate
Subtask 2
Subtask 3
Subtask 4
Subtask 5
Subtask 6
2022-11_COT FTF Groundwater Assessment Rationale Table_Drilling_Rev1_12-12-22.pdf
Table 1 for SAWP
Monitoring Well Locations
Utility Locate Bids_Compiled.pdf
Geosyntec Utility-272_Geotek_1500
Geoview Utility Quote_2000_COT FTF SIS
Tallahassee Fire Training Division_V1_Bloodhound_3700
Drilling Bids_Compiled.pdf
PDS_Geosyntec, Tallahassee Fire Training Division, Tallahassee, FL (sonic)
Direct Push
City of Tallahassee Fire Training Site_GW Protection PFAS Free Water Estimate Email
Cascade_Geosyntec Consultants, Inc. - City of Tallahassee Fire Training Facility - PN221026-118844
GW Protection_Geosyntec (T) 1022060 S.pdf
Invoice
Geosyntec, Tallahassee Fire Training Division, Tallahassee, FL (MOT).xlsx.pdf
Sheet1
COT FTF (ERIC_ 7413)_HW683 SOW_Supplemental Assessment_2022-12_txt_v1.pdf
Subtask 1 – Project Management
Subtask 2 – Site Assessment Work Plan, Health and Safety Plan, Access Agreements, and Source Water Sampling
Subtask 3 –Monitoring Well Installation
Right-of-Way Permitting
Utility Locate and Drilling Subcontractors
Monitoring Well Installation
Subtask 4 – Monitoring Well Sampling and Surveying
Laboratory Analysis
Trip Report
Subtask 5 – Investigation Derived Waste
Trip Report
Subtask 6 – Supplemental Site Assessment Report
Invoice and Deliverable Schedule:
ATTACHMENT A
ATTACHMENT B
ATTACHMENT C
ATTACHMENT D
ATTACHMENT E
ATTACHMENT F
COT FTF (ERIC_ 7413)_HW683 SOW_Supplemental Assessment_2022-12_txt_v2.pdf
Subtask 1 – Project Management
Subtask 2 – Site Assessment Work Plan, Health and Safety Plan, Access Agreements, and Source Water Sampling
Subtask 3 –Monitoring Well Installation
Right-of-Way Permitting
Utility Locate and Drilling Subcontractors
Monitoring Well Installation
Subtask 4 – Monitoring Well Sampling and Surveying
Laboratory Analysis
Trip Report
Subtask 5 – Investigation Derived Waste
Trip Report
Subtask 6 – Supplemental Site Assessment Report
Invoice and Deliverable Schedule:
ATTACHMENT A
ATTACHMENT B
ATTACHMENT C
ATTACHMENT D
ATTACHMENT E
ATTACHMENT F
Attachment A -COT FTF (ERIC_7413)_HW683 CEF-LOE_Supplemental Assessment_2022-12_v2.pdf
Cost Estimate
Subtask 2
Subtask 3
Subtask 4
Subtask 5
Subtask 6
2022-11_COT FTF Groundwater Assessment Rationale Table_Drilling_Rev2.pdf
Table 1 for SAWP
Monitoring Well Locations

File details come from the government source that posted it. Updated .