This is a Task Assignment (TA) document between the State of Florida Department of Environmental Protection (FDEP) and GHD Services, Inc. for groundwater monitoring services at the McNatt's Cleaners site located at 5227 Ehrlich Road, Tampa, Hillsborough County, Florida. The Task Assignment DC020A is entered pursuant to underlying Contract Number HW684 and was signed on June 14, 2022, with a completion date of November 25, 2022. Kevin Kane serves as the FDEP Department Project Manager, while Brian Moore represents GHD Services, Inc. as the contractor's Project Manager.

The contract encompasses two primary subtasks: (1) Project Management, calculated at 13% of direct labor costs, and (2) Groundwater Monitoring, which includes annual groundwater sampling at fifteen monitor wells during July 2022, depth-to-water measurements at all 33 available monitor wells, laboratory analysis for volatile organic halocarbons and various water quality parameters, investigation-derived waste (IDW) disposal, and preparation of a Groundwater Monitoring Report. The total Task Assignment value is $10,617.31 on a fixed unit rate basis, with the deliverable due date of August 22, 2022. Cost components include $5,541.56 in total labor costs (including overhead and fringe benefits), $240.00 in vehicle rental, $121.00 for IDW disposal services, $2,678.50 in laboratory analytical costs, and $1,482.10 in field equipment expenses. The work was to be conducted in accordance with the scope of work and cost proposal submitted by GHD on May 25, 2022, with documentation supporting the cost estimate included in the contractor's detailed Level-of-Effort worksheets and FDEP Cost Estimate forms.

View the file

Other files

File Type Posted
CN-370000-HW684-BIL02F.pdf PDF
CN-370000-HW684-BIL2CC03.pdf PDF
CN-370000-HW684-BIL2ECO1.pdf PDF
CN-370000-HW684-BIL2FCO1.pdf PDF
CN-370000-HW684-BIL2GCO1.pdf PDF
CN-370000-HW684-CSS02A.pdf PDF
CN-370000-HW684-CSS03B.pdf PDF
CN-370000-HW684-D033CCO1.pdf PDF
CN-370000-HW684-DC001A.pdf PDF
CN-370000-HW684-DC001F.pdf PDF
CN-370000-HW684-DC002B.pdf PDF
CN-370000-HW684-DC002C.pdf PDF
CN-370000-HW684-DC002D.pdf PDF
CN-370000-HW684-DC003D.pdf PDF
CN-370000-HW684-DC004D.pdf PDF
CN-370000-HW684-DC005A.pdf PDF
CN-370000-HW684-DC005D.pdf PDF
CN-370000-HW684-DC006B.pdf PDF
CN-370000-HW684-DC009C.pdf PDF
CN-370000-HW684-DC009D.pdf PDF
CN-370000-HW684-DC009E.pdf PDF
CN-370000-HW684-DC011A.pdf PDF
CN-370000-HW684-DC011C.pdf PDF
CN-370000-HW684-DC012D.pdf PDF
CN-370000-HW684-DC013B.pdf PDF
CN-370000-HW684-DC014D.pdf PDF
CN-370000-HW684-DC014F.pdf PDF
CN-370000-HW684-DC015A.pdf PDF
CN-370000-HW684-DC015C.pdf PDF
CN-370000-HW684-DC016B.pdf PDF
CN-370000-HW684-DC016C.pdf PDF
CN-370000-HW684-DC017C.pdf PDF
CN-370000-HW684-DC018C.pdf PDF
CN-370000-HW684-DC019C.pdf PDF
CN-370000-HW684-DC019D.pdf PDF
CN-370000-HW684-DC01ACO2.pdf PDF
CN-370000-HW684-DC020B.pdf PDF
CN-370000-HW684-DC025A.pdf PDF
CN-370000-HW684-DC026B.pdf PDF
CN-370000-HW684-DC026D.pdf PDF
CN-370000-HW684-DC027C.pdf PDF
CN-370000-HW684-DC028C.pdf PDF
CN-370000-HW684-DC029C.pdf PDF
CN-370000-HW684-DC031A.pdf PDF
CN-370000-HW684-DC034B.pdf PDF
CN-370000-HW684-DC03ACO1.pdf PDF
CN-370000-HW684-DC03CCO1.pdf PDF
CN-370000-HW684-DC03CCO2.pdf PDF
CN-370000-HW684-DC040A.pdf PDF
CN-370000-HW684-DC045B.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW684

DC020A Completion November 25, 2022

GHD Services, Inc. will conduct groundwater sampling at the McNatt's Cleaners site located in Tampa, Florida. All work will be conducted in accordance with the scope of work and cost proposal submitted on May 25, 2022.

Kevin Kane (850) 245-8971 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

GHD Services, Inc.

GHD Services, Inc.

Brian Moore (813) 257-0658

ERIC_4752

5227 Ehrlich Rd., Tampa, Hillsborough County

McNatt's Cleaners

✔ $ 10,617.31

$ 10,617.31

Scope of Work

Brian Moore

Project Manager

Brian Moore Digitally signed by Brian Moore Date: 2022.06.14 16:15:24 -04'00'

William E. Burns, Jr.

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2022.06.14 14:54:40 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Groundwater Monitoring Report + Project Management 08/22/2022

Subtasks 1 & 2: Upon submittal and FDEP approval of the Groundwater Monitoring Report + Project Management $ 10,617.31

$ 10,617.31

HW684

DC020A

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

TO: HW684 Contract File

FROM: Kevin Kane, Contract Manager

DATE: June 14, 2022

SUBJECT: Task Assignment DC020A

McNatt’s Cleaners

ERIC_4752

Monitoring

GHD Services, Inc. (GHD) will conduct annual groundwater sampling. Specific subtasks are detailed below:

Subtask 1: Project Management Project Management is calculated at 13% of the direct labor.

Subtask 2: Groundwater Monitoring GHD will conduct annual groundwater sampling in July 2022. Prior to groundwater sampling, depth to water measurements will be gathered at all available monitor wells (33 total). Groundwater sampling will be conducted at fifteen (15) monitor wells including: MW001, MW002, MW004, MW019, MW025, MW030, MW031, MW033, MW040, MW042, MW043, MW045, MW051, MW052, and MW053. Groundwater sampling will be conducted in accordance with FDEP SOPs. All groundwater samples will be analyzed for the presence of Volatile Organic Halocarbons. Select wells (MW025, MW039, MW040, MW042, MW043, MW045, MW051, and MW052) will also be analyzed for the presence of total dissolved solids, total recoverable petroleum hydrocarbons, sodium, ammonia, nitrite, and nitrate. In addition, monitor wells MW051 and MW052 will also be analyzed for chloride and dissolved gases (methane, ethane, ethene). The dissolved gas sampling will be conducted at MW051 and MW052 only and will include a duplicate and an equipment blank. Finally, the sample from monitor well MW051 will be analyzed for total organic carbon. Following receipt of analytical data, a Groundwater Monitoring Report will be prepared. The report will include a summary of groundwater sampling methods and analytical results and provide recommendations for additional remediation and/or testing.

Investigation derived waste (IDW) disposal is anticipated and has been accounted for under this subtask. Subcontractors for IDW disposal were chosen on a lowest-cost basis. The Florida Department of Environmental Protection (FDEP) has a current and valid site access agreement for this site, signed March 13, 1997.

This work will be conducted in line with the scope of work included with GHD’s proposal, received May 25, 2022. Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and proposal letter. The final deliverable due date is August 22, 2022, and the completion date for the Task Assignment is November 25, 2022.

The final cost total for Task Assignment DC020A is $10,617.31.

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 06/13/22

Task #: DC020A SubTask 1 Project Management SubTask 6

Site: McNatt Cleaners SubTask 2 Groundwater Monitoring SubTask 7

Activity/Phase: Monitoring SubTask 3 SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$40.12 Project Manager JM 5.90 5.9 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$46.33 Sr Professional Engineer JH 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$43.28 Professional Engineer/Sc GE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $39.82 Project Engineer/Scientis TC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.12 Project Manager/ Engine JM 17.00 17.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $33.17 Staff Engineer/Scientist DB 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.40 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.35 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.76 Senior Technician SA 18.00 18.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.65 Senior Technician SC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $23.69 Senior Technician WM 16.50 16.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.58 Junior Technician WO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.75 Junior Technician JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 6.00 6.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.44 Administrative Assistant DA 8.00 8.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Driller 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 HSEQ&R Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 72.40 5.90 66.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Direct Labor $2,070.84 $238.24 $1,832.60 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 129.80% $2,687.95 $309.24 $2,378.71 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $782.77 $90.05 $692.72 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $5,541.56 $637.53 $4,904.03 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $240.00 $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 Page 1

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 06/13/22

Task #: DC020A SubTask 1 Project Management SubTask 6

Site: McNatt Cleaners SubTask 2 Groundwater Monitoring SubTask 7

Activity/Phase: Monitoring SubTask 3 SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $240.00 $240.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $11.00 $11.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $121.00 $121.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $2,528.50 $2,528.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $150.00 $150.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $2,678.50 $2,678.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $1,442.10 $1,442.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,482.10 $1,482.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $10,063.16 $637.53 $9,425.63 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $554.15 $63.75 $490.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $10,617.31 $701.28 $9,916.03 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : McNatts Cleaners SUBTASK 2: Groundwater Monitoring

DATE: 06/13/22

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Sr Professional Engineer JH Conclusions/Recommendations 1

Project Manager JM Specify laboratory data deliverable/Sample Kit 1 Project Manager JM Field sampling SOW/coordinate site access 1 Project Manager JM QA/QC field and laboratory data 1 Project Manager JM Project Background 1 Project Manager JM Profile and coordinate IDW disposal 1 Project Manager JM Groundwater Sampling Methods 2 Project Manager JM Water Quality Parameter Summary 2 Project Manager JM Groundwater Analtycial Results (VOCs) 2.5 Project Manager JM Groundwater Analytical Results (UIC/performance) 2.5 Project Manager JM QA/QC Laboratory Data 2 Project Manager JM Conclusions/Recommendations 1

Senior Technician SA Mob/Demob (2 days) 2 Senior Technician SA Water levels (all wells - 33 total) 4 Senior Technician SA Groundwater Sampling (8 wells) 12

Senior Technician WM Mob/Demob (2 days) 2 Senior Technician WM Water levels (all wells - 33 total) 4 Senior Technician WM Groundwater Sampling (7 wells) 10.5

16.5

Drafting Technician PM Groundwater elevation figures (4 zones) 3 Drafting Technician PM Groundwater analytical figures (4 zones) 3

Staff Assistant DA Data Entry (15 monitor wells, 33 wls) 2 Staff Assistant DA Update summary tables 2 Staff Assistant DA Document Preparation/Publishing 2 Staff Assistant DA GIS/ADaPT 2

TOTAL LABOR 66.5

VEHICLE TYPE RATE UNIT USEAGE

Company Truck $120.00 day 2 $240.00

TOTAL VEHICLE $240.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Erwin Remediation IDW Drum Dispos 1 drum $110.00 $110.00

TOTAL $110.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOHs EPA Method 8260 $73.00 16 $1,168.00

TOC EPA 9060 $30.00 1 $30.00

TDS EPA 160.1 $16.00 3 $48.00

TRPH FL-PRO $88.00 3 $264.00

sodium EPA 6010 $13.50 3 $40.50 ammonia SM4500 $24.00 3 $72.00 chloride EPA 352.2 $24.00 2 $48.00 nitrate EPA 353.2 $23.00 3 $69.00 nitrite EPA 353.2 $23.00 3 $69.00 dissolved gases (methane, ethane, ethene) $180.00 4 $720.00 Sample Shipping Large Cooler (1 day) $150.00 1 $150.00

TOTAL LAB $2,678.50

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables

Expendables $40.00 day 1 $40.00

Equipment (Analytical Related)

Groundwater Sampling Kit $290.00 day 4 $1,160.00 Poly Tubing (HDPE) $0.30 ft 457 $137.10 Silicon Tubing $3.00 ft 15 $45.00 55-gallon drum $100.00 drum 1 $100.00

Equipment (Other) $0.00 $0.00

TOTAL EQUIPMENT $1,482.10

FINAL --7/24/96

COST PROPOSAL FOR TASK DC020A

McNatt’s Cleaners, 299502136/ERIC_4752

Groundwater Monitoring

1. INTRODUCTION:

GHD prepared a RAP Modification that was implemented in 2017. Following remedial injections and a period of SVE system operations, the system was recently shutdown. In order to continue to evaluate the performance of the remedial injections in accordance with the RAP Modification, groundwater monitoring is recommended. Task DC020A includes annual groundwater sampling in accordance with GHD’s recommendations from the previous annual RASR dated August 2022 and FDEP correspondence dated November 19, 2021.

Subtask 1: Project Management Includes all tasks associated with project management for annual groundwater sampling and reporting.

Subtask 2: Groundwater Monitoring Subtask 2 includes annual groundwater monitoring. Prior to groundwater sampling, depth to water measurements will be gathered at all available monitor wells (33 total). Groundwater sampling will be conducted at fifteen (15) monitor wells including: MW001, MW002, MW004, MW019, MW025, MW030, MW031, MW033, MW040, MW042, MW043, MW045, MW051, MW052, and MW053. Groundwater sampling will be conducted in accordance with FDEP SOPs. All groundwater samples will be analyzed for the presence of Volatile Organic Halocarbons. Select wells (MW025, MW039, MW040, MW042, MW043, MW045, MW051, and MW052) will also be analyzed for the presence of total dissolved solids, total recoverable petroleum hydrocarbons, sodium, ammonia, nitrite, and nitrate. In addition, monitor wells MW051 and MW052 will also be analyzed for chloride and dissolved gases (methane, ethane, ethene). The dissolved gas sampling will be conducted at MW051 and MW052 only, and will include a duplicate and an equipment blank. Finally, the sample from monitor well MW051 will be analyzed for total organic carbon.

Following receipt of analytical data, a Groundwater Monitoring Report (GMR) will be prepared. The GMR will include a summary of groundwater sampling methods and analytical results. The GMR will provide recommendations for additional remediation and/or testing.

Deliverables:

Deliverable Deliverable Due Date

Groundwater Monitoring Report 8/22/22

408 Ditmar Street

Pensacola, FL 32503

ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511

To: Mr. Brian Moore

GHD

5904 Hampton Oaks Parkway – Suite F

Tampa, FL 33610

May 23, 2022

Re: Transportation and Disposal of Non-Hazardous Soil and Water – Florida

Mr. Moore:

The price for disposal of drums of non-hazardous soil or groundwater located in the State of Florida will be $110.00 per drum, for both transportation and disposal.

This pricing is valid for all regions in the State of Florida except for the Florida Keys.

Pricing for sites located in the Florida Keys will be bid on a case-by-case basis dependent on the volume of drums and the location.

This quote is valid for 180 days.

Respectfully, Jonathan Erwin

Erwin Remediation, Inc.

Email: ErwinRemediation@Gmail.com

Office: (850) 292-6511 mailto:Remediation@Gmail.com

From: Jamie Infinger To: Brian Moore Subject: RE: IP Cleaners - Miami Date: Monday, March 16, 2020 8:39:32 AM Attachments: image001.png image002.png image003.png image004.png

$95.00 per drum plus $150.00 stop charge Have a great day

Thanks, Jamie Infinger A Nationwide Waste Disposal Company Clean Management Environmental Group, Inc.

P: (800)-538-8131 F: (843)-538-7845 C: (912)-674-6783 jinfinger@cleanmanagement.com www.cleanmanagement.com

From: Brian.Moore@ghd.com [mailto:Brian.Moore@ghd.com] Sent: Sunday, March 15, 2020 11:45 AM To: Jamie Infinger <jinfinger@cleanmanagement.com> Subject: IP Cleaners - Miami

Jamie, Can you provide quote for disposal of 2 drums of water from the above site. Low level solvents, assume non-haz thanks

Brian Moore, PE

GHD

Proudly employee owned T: 813 257 0658 | M: 813 335 2147 | E: Brian.Moore@ghd.com 5904 Hampton Oaks Parkway Suite F Tampa Florida 33610 USA | www.ghd.com Connect

WATER | ENERGY & RESOURCES | ENVIRONMENT | PROPERTY & BUILDINGS | TRANSPORTATION

mailto:jinfinger@cleanmanagement.com mailto:Brian.Moore@ghd.com mailto:jinfinger@cleanmanagement.com http://www.cleanmanagement.com/ mailto:Brian.Moore@ghd.com http://www.ghd.com/ https://www.linkedin.com/company/ghd https://www.facebook.com/GHDGroup https://twitter.com/GHD_Namerica https://www.youtube.com/channel/UCwUGfe6zgaddIXqA7entIwQ https://www.ghd.com/en/sectors/water.aspx https://www.ghd.com/en/sectors/energy---resources.aspx https://www.ghd.com/en/sectors/environment.aspx https://www.ghd.com/en/sectors/property---buildings.aspx https://www.ghd.com/en/sectors/transportation.aspx

Please consider our environment before printing this email

CONFIDENTIALITY NOTICE: This email, including any attachments, is confidential and may be privileged. If you are not the intended recipient please notify the sender immediately, and please delete it; you should not copy it or use it for any purpose or disclose its contents to any other person. GHD and its affiliates reserve the right to monitor and modify all email communications through their networks.

This e-mail has been scanned for viruses

ID Task Mode

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Wed 5/25/22Tue 6/7/22

2 Subtask 1: Project Management

54 days Wed 6/8/22 Mon 8/22/22

3 Subtask 2: Groundwater Monitoring

50 days Tue 6/14/22 Mon 8/22/22

4 Field Work Preparation 2 wks Tue 6/14/22 Mon 6/27/22

5 Groundwater Sampling 2 days Thu 6/30/22 Fri 7/1/22

6 Groundwater Monitoring Report

6 wks Tue 7/12/22 Mon 8/22/22

5/15 5/22 5/29 6/5 June

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC020A at the McNatts Cleaners site located in Tampa, Hillsborough County

Project: TA_020A Date: Wed 5/25/22

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Wed 5/25/22Tue 6/7/22

2 Subtask 1: Project Management

54 days Wed 6/8/22 Mon 8/22/22

3 Subtask 2: Groundwater Monitoring

50 days Tue 6/14/22 Mon 8/22/22

4 Field Work Preparation 2 wks Tue 6/14/22 Mon 6/27/22

5 Groundwater Sampling 2 days Thu 6/30/22 Fri 7/1/22

6 Groundwater Monitoring Report

6 wks Tue 7/12/22 Mon 8/22/22

Jenna Martin

Skylar Albritton,W

6/12 6/19 6/26 7/3 July

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC020A at the McNatts Cleaners site located in Tampa, Hillsborough County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Wed 5/25/22Tue 6/7/22

2 Subtask 1: Project Management

54 days Wed 6/8/22 Mon 8/22/22

3 Subtask 2: Groundwater Monitoring

50 days Tue 6/14/22 Mon 8/22/22

4 Field Work Preparation 2 wks Tue 6/14/22 Mon 6/27/22

5 Groundwater Sampling 2 days Thu 6/30/22 Fri 7/1/22

6 Groundwater Monitoring Report

6 wks Tue 7/12/22 Mon 8/22/22

William McKinney

7/10 7/17 7/24 7/31 August

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC020A at the McNatts Cleaners site located in Tampa, Hillsborough County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Wed 5/25/22Tue 6/7/22

2 Subtask 1: Project Management

54 days Wed 6/8/22 Mon 8/22/22

3 Subtask 2: Groundwater Monitoring

50 days Tue 6/14/22 Mon 8/22/22

4 Field Work Preparation 2 wks Tue 6/14/22 Mon 6/27/22

5 Groundwater Sampling 2 days Thu 6/30/22 Fri 7/1/22

6 Groundwater Monitoring Report

6 wks Tue 7/12/22 Mon 8/22/22

Jeremy Hess,Jenna Martin,P

8/7 8/14 8/21 8/28 Septemb

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC020A at the McNatts Cleaners site located in Tampa, Hillsboroough County